This document is a set of Utility and Security Shut Down Standards from the State of Michigan Department of Corrections (MDOC). The standards outline the requirements for the shutdown of various building systems during construction, including perimeter detection, video management, boiler and heating, electrical and generator, and life safety systems. The standards require the submission of detailed hour-by-hour schedules for each system shutdown, as well as the deployment of redundant backup generators if the electrical shutdown exceeds two hours, to ensure the continued operation of critical security and life safety systems. The standards also specify that boiler and heating system shutdowns must be scheduled between May and October.
The related state and local contract opportunity is for the upgrades to the cell door controls and locks at the Gus Harrison Correctional Facility in Lenawee County, Michigan. The contract is administered by the Michigan Department of Logistics (DPL) and the jurisdiction is Lenawee County.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of Michigan
Department of Corrections
Utility and Security Shut Down Standards
Utility and Security Shut Down Standards Page -1
MDOC – UTILITY AND SECURITY SHUT DOWN STANDARDS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. This section includes instructions for the shutdown of the following Systems:
1. Perimeter Detections.
2. Video Management.
3. Boiler and Heating System.
4. Electrical, Generator and Back Up Supply
5. Life Safety
PART 2 - PRODUCTS
Not used.
PART 3 - EXECUTION
3.01 PERIMETER DETECTION SYSTEM
A. An Hour by Hour Schedule MUST be submitted to MDOC leadership and the Facility for review 2 weeks prior to implementing the construction. In this the document submitted to leadership the following must be included for leadership:
1. ALL building systems, perimeter detection, video management and life safety systems affected.
2. ALL additional security measures that will be in place, will be defined in detail by the
Warden or designated custody staff, during the construction period.
3. Example of schedule:
Technicians scheduled are Andy Frazine and Rob Schutt.
Will need 1 escort, working hours 7:00am to 6:00pm each day.
Monday, January13th 7:00am– 11:00am Tower #1 Ultra-Link (move alarms from transponder to new ultra-link) Tower 1 points:
12:00pm – 2:00pm Tower #6 Ultra-Link (move alarms from transponder to new ultra-link)
2:00pm - 6:00pm Programs Building (move alarms from transponder to new ultra-link)
Zone 49A
Zone 49B
Zone 49C
Zone 50
Zone 51
Zone 49/51 Supervisory
Utility and Security Shut Down Standards Page -2
Programs Points:
B. If a window of MORE THAN TWO HOURS is required for electrical shut down, then a redundant back up Generator MUST BE ON SITE during the construction, to provide power to ALL PERIMETER DETECTION, VIDEO MANAGEMENT, AND LIFE SAFETY SYSTEMS during the construction period.
3.02 VIDEO MANAGEEMENT SYSTEM
A. An Hour by Hour Schedule MUST be submitted to MDOC leadership and the Facility for review 2 weeks prior to implementing the construction. In this the document submitted to leadership the following must be included for leadership:
1. ALL building systems, perimeter detection, video management and life safety systems affected.
2. ALL additional security measures that will be in place, will be defined in detail by the
Warden or designated custody staff, during the construction period.
B. If a window of MORE THAN TWO HOURS is required for electrical shut down, then a redundant back up Generator MUST BE ON SITE during the construction, to provide power to ALL PERIMETER DETECTION, VIDEO MANAGEMENT, AND LIFE SAFETY SYSTEMS during the construction period.
3.03 BOILER AND HEATING SYSTEM
A. An Hour by Hour Schedule MUST be submitted to MDOC leadership and the Facility for review 2 weeks prior to implementing the construction. In this the document submitted to leadership the following must be included for leadership:
1. ALL building systems, perimeter detection, video management and life safety systems affected.
2. ALL additional security measures that will be in place, will be defined in detail by the
Warden or designated custody staff, during the construction period.
B. If a window of MORE THAN TWO HOURS is required for electrical shut down, then a redundant back up Generator MUST BE ON SITE during the construction, to provide power to ALL PERIMETER DETECTION, VIDEO MANAGEMENT, AND LIFE SAFETY SYSTEMS during the construction period.
C. THIS HAS BEEN DETERMINED BY LEADERSHIP TO BE A SEASONAL REPAIR, AND
MUST BE SCHEDULED BETWEEN THE MONTHS OF MAY AND OCTOBER.
3.04 ELECTRICAL, GENERATOR AND BACK UP SUPPLY
A. An Hour by Hour Schedule MUST be submitted to MDOC leadership and the Facility for review 2 weeks prior to implementing the construction. In this the document submitted to leadership the following must be included for leadership:
1. ALL building systems, perimeter detection, video management and life safety systems affected.
2. ALL additional security measures that will be in place, will be defined in detail by the
Warden or designated custody staff, during the construction period.
Programs Cabinet Tamper
Programs Mechanical Room
Door
Programs Electrical Room Door
Utility and Security Shut Down Standards Page -3
3. Schedule shall look like the following:
1/21/2020
• 8am – 10am Facility run on generator #2 during utility shut down for installation of temporary wires for temporary switch gear.
1/22/2020
• 7am - 12pm Transfer Food Service to single feed, disconnect deenergized feed either A6 or B6 and connect into temporary switch gear, once this is complete shift Food service to new temp feed and perform same operation on other feed. If all gear operates and transfers, no power interruption would be seen in Food Service.
• 1pm – 3pm Power plant service disconnected and transferred to temporary switch gear. During this time no steam will be produced for Food service, Laundry, Heat, and Hot water. If Temperatures are to low this will be postponed. Owner may have temporary generator available to back up steam boiler.
1/27/2020
• 8am – 10am Complete power shut down for Administration and I Block.
• 1pm – 3pm Complete power shut down for Warehouse and J Block.
1/28/2020
• 8am – 10am Complete power shut down of Aerial lines. This will affect the Bar Screen, Maintenance South, and 4 post which feeds all Wall Lighting.
• 12pm – 3pm Contingency Time slot for Food Service or Power Plant.
1/29/2020
• 8am – 10am Complete facility shut down to remove parallel 750KCM.
• 11am – 3pm Contingency Time slot
B. If a window of MORE THAN TWO HOURS is required for electrical shut down, then a redundant back up power supply MUST BE ON SITE during the construction, to provide power to ALL PERIMETER DETECTION, VIDEO MANAGEMENT, AND LIFE SAFETY during the construction period.
3.05 LIFE SAFETY
A. An Hour by Hour Schedule MUST be submitted to MDOC leadership and the Facility for review 2 weeks prior to implementing the construction. In this the document submitted to leadership the following must be included for leadership:
1. ALL building systems, perimeter detection, video management and life safety systems affected.
2. ALL additional security measures that will be in place, will be defined in detail by the
Warden or designated custody staff, during the construction period.
B. If a window of MORE THAN TWO HOURS is required for electrical shut down, then a redundant back up power supply MUST BE ON SITE during the construction, to provide power to ALL PERIMETER DETECTION, VIDEO MANAGEMENT, AND LIFE SAFETY SYSTEMS during the construction period.
C. GIVEN THE NATURE OF THESE REPAIRS, A TIME LIMIT REQUIREMENT, MUST BE
IMPLIMENTED.
END OF SECTION