MDAH COMMISSIONING SERVICES RFQ_FINAL.pdf

PDF 567 KB Posted

Attached to
1475-27-R-RFQI-00001
Solicitation number
3140004733
Issued by
Hinds County, Jackson City, Mississippi

About this file

Summary

This is a Request for Qualifications (RFQ) issued by the Mississippi Department of Archives and History (MDAH) for professional building commissioning services to be provided on an ongoing basis from January 1, 2027, through December 31, 2029. The commissioning professional will be retained directly by MDAH and must remain independent of the primary architect/engineer and all associated consultants. Commissioning services will be required for all major facility projects administered by MDAH, defined as new construction projects exceeding 5,000 gross square feet or repair and renovation projects involving greater than 50 percent of facility replacement value. Systems subject to commissioning include HVAC, plumbing, electrical, data/communication, life-safety, conveying, building envelope, and other specialty systems depending on project complexity. The scope of work spans from pre-design through the one-year warranty period and includes developing commissioning plans, reviewing design and construction documents, conducting functional performance tests, and performing two off-season tests within eleven months following project completion. Qualifications submissions in duplicate (including electronic copies) must be received by 5:00 p.m. on Thursday, November 19, 2026, with the selected commissioning professional to be notified by December 31, 2026. MDAH makes no guarantee regarding the specific number or dollar value of assignments.

Compensation for commissioning services will be structured as a percentage of construction cost, calculated using a logarithmic fee formula that varies based on six project classifications (CxA through CxF) ranging from ordinary to high complexity, with or without building envelope commissioning. Professional firms must be registered with the Mississippi Engineering Board, and the selected commissioning professional must be registered to do business in Mississippi. Preferred qualifications include a minimum of five years of commissioning experience with all systems, current certification by the Building Commissioning Association as a certified commissioning professional, or accreditation by the University of Wisconsin-Madison as a commissioning process provider. Evaluation criteria for short-list selection include past performance with MDAH (up to 10 points), site presence and geographic location (up to 10 points), project team qualifications (up to 50 points), relevant experience (up to 20 points), and fresh perspective or additional resources (up to 10 points). Final selection from the short list will be based on project vision (up to 20 points), relationship management capabilities (up to 10 points), and quality assurance in both design and construction phases (up to 70 points combined). All submissions must include a letter of interest, completed Form M54 and Form M55, and a statement of qualifications demonstrating firm history, commissioning expertise, local experience, reference contacts, key personnel resumes, and professional liability insurance documentation.

View the file

Other files

File Type Posted
MDAH COMMISSIONING SERVICES RFQ AD.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF MISSISSIPPI

MISSISSIPPI DEPARTMENT OF ARCHIVES AND HISTORY

200 North Street Jackson, Mississippi 39201

Phone: 601-576-6850

REQUEST FOR QUALIFICATIONS

FOR

COMMISSIONING PROFESSIONAL SERVICES

RFQ# 3140004733

1. GENERAL: The Mississippi Department of Archives and History (MDAH) will contract for professional commissioning services as described in this Request for Qualifications (RFQ). Contracts for Commissioning Authority Professional will be a standard Commissioning Professional Contract, Percentage Fee, based on project complexity, between the Mississippi Department of Archives and History (Owner), and the Professional firm (Commissioning Authority Professional). The Commissioning Authority Professional will be retained directly by MDAH and shall be independent of the primary architect/engineer and all consultants engaged by the primary architect/engineer. One commissioning Professional will be selected via this RFQ for subsequent appointment by MDAH to ongoing projects where a commissioning professional is required and to new projects initiated between January 1, 2027, and December 31, 2029. MDAH makes no guarantee of a specific number or dollar value of assignments.

Project assignments will vary greatly in size and complexity. All major facility projects administered by MDAH will be commissioned. A major facility project is generally defined as all new construction projects over five thousand (5,000) gross square feet and all repair and renovation projects which involve greater than fifty percent (50%) of the facility replacement value. (Miss. Code Ann. §31-11-35 ) Systems that will be commissioned include HVAC systems, plumbing systems, electrical systems, data/communication systems, life-safety systems, conveying systems, building envelope, and other specialty systems depending upon project complexity. The form of the contract to be used for this engagement is attached as Exhibit “A.” MDAH must utilize template contracts provided by the Department of Finance and Administration (DFA), and certain contract provisions are mandatory pursuant to 12 Miss. Admin. Code Pt. 13, R.4.1. See Exhibit “B.”

2. SELECTION PROCESS: Professional selection will be in accordance with the State of Mississippi Bureau of Building Professional Selection Policy as identified in 12 Miss. Admin. Code Pt.13, R. 2.2-2.5.

Evaluation criteria for short list selection for this RFQ shall be as follows (100-point scale):

2.1.1 Past Performance: If a firm has done prior work for MDAH, award up to 10 points depending on past performance.

2.1.2 Site Presence: Geographic location and/or proven track record of maintaining presence on site, award up to 10 points.

2.1.3 Project Team: General qualifications of Commissioning Professional and Consultant firms as well as specific abilities of identified team members, award up to 50 points.

2.1.4 Relevant Experience: Commissioning experience of Project Team with projects of similar type, scale and/or complexity of projects, award up to 20 points.

2.1.5 Fresh Perspective: Project Team offers new perspective or additional resources, award up to 10 points.

Evaluation criteria for selection of the best and final firm from the short list for this RFQ shall be as follows (100-point scale):

2.2.1 Project Vision: Commissioning Professional has a clear vision/strategy for the project which complements the vision of MDAH, award up to 20 points.

2.2.2 Relationship Management: Commissioning Professional balances goals and requirements of multiple governmental entities and user groups, award up to 10 points.

2.2.3 Quality Assurance (Design Phase): Project Team provides clear, useful, timely design reviews and comments, and planning phase documents, award up to 30 points.

2.2.4 Quality Assurance (Construction Phase): Project Team provides construction phase service, which assures proper execution of contract documents, timely identification of issues, and facilitates resolution of same, award up to 40 points.

3. SUBMISSIONS: Any individual, firm, or corporation desiring to provide services for commissioning should submit the following to the Mississippi Department of Archives and History in DUPLICATE, accompanied by an electronic submittal exactly like your hard copy submittals (in color, blue signature, etc.)

3.1 Letter of interest: Each submission must be accompanied by an individual letter.

3.2 Form M54: Each submission must be accompanied by a completed and current Form M54, Architect-Engineer Related Services Questionnaire.

3.3 Form M55: Each submission must be accompanied by a completed and current Form M55, Architect-Engineer Related Services for Commissioning Authority Professional. M55 Item 7 must include entries for key personnel for the following Project assignments:

3.3.1 KEY PRINCIPAL - will be totally responsible for the commissioning project.

3.3.2 PLANNING PHASE - will be responsible for all commissioning specifications.

3.3.3 CONSTRUCTION PHASE – will be responsible for site inspections for project.

3.4 Statement of Qualifications: In addition to the M54 and M55 forms, each submission must be accompanied by a statement of qualifications including the following information:

3.4.1 History of the firm;

3.4.2 Evidence that commissioning is a principal enterprise of the firm;

3.4.3 Commissioning expertise and capability, including experience with building envelope commissioning;

3.4.4 Local experience over the last five (5) years on projects of similar size and scope;

3.4.5 Prior commissioning reference contacts with telephone numbers;

3.4.6 Resumes of key (commissioning) management personnel and their positions; and

3.4.7 Professional liability insurance.

4. PROPRIETARY INFORMATION: Any page(s) of proposal that proposer considers to contain “trade secrets” or confidential commercial or financial information shall be submitted on different color paper than non-confidential pages and be marked in the upper right-hand corner with the word “CONFIDENTIAL”. Failure to clearly identify will result in that information being released subject to a public records request.

5. DELIVERY: All submissions must be received in the Mississippi Department of Archives and History’s Finance Office by 5:00 p.m., on Thursday, November 19, 2026. The selected Commissioning Professional should be notified [at least by] December 31, 2026. Address all submissions to:

Attn: Joey Roberts Finance Office Mississippi Department of Archives and History 200 North Street Jackson, Mississippi 39201

6. QUALIFICATIONS: Professional Engineering firms with experience in commissioning are invited to respond to this Request for Qualification. The individual Engineer AND the Engineering Firm must both be registered at the Mississippi Engineering Board. The approved Commissioning Professional will need to be registered to do business in the State of Mississippi at the

Mississippi Secretary of State’s Office before executing a Contract with the State of Mississippi. The selected Commissioning Professional must be independent of the primary architect/engineer and their consultants and will be retained directly by MDAH. Testing, Adjusting and Balancing agents (TAB) will be secured by, and reported to, the Commissioning Agent. Preferred qualifications include a minimum of five (5) years of commissioning experience with all systems, including building envelope. The Commissioning Professional must meet the certification requirements established by the State of Mississippi Bureau of Building, including certification by the Building Commissioning Association (BCA) as a certified commissioning Professional and/or accreditation by the University of Wisconsin–Madison as a commissioning process provider.

7. SCOPE OF WORK: Commissioning is a systematic process of quality assurance for buildings and their systems. The Process will span the entire project from Pre-Design through the one-year warranty period.

The intent of commissioning is to result in facilities with increased energy efficiency, improved occupant comfort, shorter project turnover times, less post-occupancy corrective work, improved indoor air quality, greater equipment life, and less changes during the construction process. A scope of services for the Commissioning Agent for a typical project provides some insight to the detailed technical effort required to ensure that the systems are designed, installed, programmed, started, and operated properly. The following list, not all-inclusive, of expected services describes the general scope of work for each project:

7.1 Assist in development of Owner’s Project Requirement Document

7.2 Assist in development of a Basis of Design Document.

7.3 Develop Draft Commissioning Plan.

7.4 Review Design Development Documents.

7.5 Develop project specific Commissioning Specifications, with review by the design team, for inclusion in the Construction Documents.

7.6 Review final Construction Documents.

7.7 Develop Commissioning Plan.

7.8 Develop System Verification /Installation Checklists.

7.9 Chair an orientation meeting with contractors to explain the Commissioning Plan & Installation

Checklists at the second regularly scheduled monthly progress meeting.

7.10 Review applicable product/equipment submittals.

7.11 Develop Functional Performance Documents.

7.12 Monitor Contractor system startup.

7.13 Oversee Testing, Adjusting and Balancing (TAB) effort and review TAB Report.

7.14 Confirm Installation Verification.

7.15 Conduct Functional Performance Tests.

7.16 Track problem issues to resolution.

7.17 Participate in identifying Owner training needs and assist in coordinating training.

7.18 Prepare and submit final Commissioning Report including System Manual to the Owner.

7.19 Perform two (2) off-season Functional Performance Tests within the eleven months immediately following project completion.

7.20 Attend warranty meetings and assist in resolving any issues regarding commissioned systems.

7.21 Chair or attend Commissioning meetings as required and provide Commissioning reports to the

Owner and Prime Professional during the project. The Commissioning meetings will coincide with regularly scheduled project meetings and commence at a mutually agreeable time as set by the Commissioning Authority Professional and Construction Administrator.

Commissioning Percentage Contract 1

STANDARD FORM OF AGREEMENT BETWEEN

THE OWNER AND THE COMMISSIONING AUTHORITY PROFESSIONAL

This Agreement made effective the day of , 20 between the Owner:

and acting for the State of Mississippi; and the Professional:

Business Name Mailing Address City/State/Zip E-mail address:

The Professional is a (Check and complete one of the following):

( ) CORPORATION (includes PA, LLC, or PLLC) solely organized and existing under the laws of the State of ____________ and having its principal office in _______________, ______________, ________________.

(City) (County) (State)

( ) PARTNERSHIP of the following (List all partners): _____ JOINT VENTURE (list all joint venture firms)

( ) SOLE PROPRIETORSHIP

For the following Project:

And limited as described in Paragraph 4.1.2 to the amount of $ as authorized by an action of the Owner.

PROFESSIONAL:

By:

(Signature)

(Name and Title)

OWNER:

By:

(Signature)

(Name and Title)

APPROVED AS TO FORM:

By:

(Signature of Attorney)

The Owner and the Commissioning Authority Professional agree as set forth in pages one through thirteen, Articles one through nine, as follows:

EXHIBIT A

Commissioning Percentage Contract 2

TERMS AND CONDITIONS OF AGREEMENT BETWEEN OWNER AND COMMISSIONING

AUTHORITY PROFESSIONAL

ARTICLE 1: COMMISSIONING AUTHORITY PROFESSIONAL COMPENSATION

1.1 FEE

1.1.1 For the Commissioning Authority Professional's basic services as described in Subparagraph 2.1.1, the fee shall be a percentage of the construction cost.

1.1.2 The Commissioning Authority Professional may provide additional services beyond the basic services and those additional services and their compensation are indicated in Paragraph 1.3.

1.1.3 When the Commissioning Authority Professional is called upon to provide extra services as described in Paragraph 7.3, the compensation shall be fixed at the fee indicated in Paragraph 1.4.

1.2 BASIC SERVICES - PERCENTAGE OF CONSTRUCTION COST

1.2.1 Compensation for basic services shall be a percentage of construction cost based on each awarded Project Construction

Contract for which the Commissioning Authority Professional provides services and in accordance with Article 6.

1.2.2 The project classification as defined in Subparagraph 6.2.1 for the Project shall be:

Cx A Cx B Cx C Cx D Cx E Cx F

1.2.3 The fees for the Project will include a credit in the amount of $ for fees earned on previous Project # entitled .

1.2.4 The fees for the Project will include a credit in the amount of $ for fees earned and paid by the Using

Agency.

1.3 ADDITIONAL SERVICES

1.3.1 The Project does not include any additional services which will require an additional fee.

1.3.2 The Project includes additional services listed in Subparagraph 2.1.2. In addition to the basic services fee, an additional fee for each service shall be indicated as follows:

1.3.3 ___ Pre-Design Phase

Lump Sum Fee: $ described in Paragraph 2.3.

1.3.4 ___

Lump Sum Fee: $ described in Paragraph .

1.4 EXTRA SERVICES

1.4.1 In special cases, fees shall be paid to the Commissioning Authority Professional for extra services as described in

Paragraph 7.3 and shall be in addition to the basic services fee as follows:

.1 Principal's time at a fixed rate of Seventy-Five Dollars ($75.00) per hour. For the purposes of this Agreement, the principals are:

.2 Employee's time computed at a multiple of two and one half (2 1/2) times the employee's direct personnel expense as defined in Paragraph 7.5.

.3 Additional services performed by Commissioning Authority Professional Consultants engaged for the normal mechanical systems commissioning, controls commissioning, electrical systems commissioning, life safety systems commissioning, conveying systems commissioning or building envelope commissioning services, at the amount billed to the Professional computed in accordance with Subparagraphs .1 and .2 above.

Commissioning Percentage Contract 3

1.5 REIMBURSEMENTS

1.5.1 As approved by the Owner, reimbursements to the Commissioning Authority Professional shall be made for testing, adjusting and balancing services during the course of the Project and in accordance with Paragraph 7.4.

ARTICLE 2: COMMISSIONING AUTHORITY PROFESSIONAL'S SERVICES AND RESPONSIBILITIES

2.1 SERVICES

2.1.1 The Professional's basic services shall consist of Paragraphs 2.2 and the phases listed and marked below. Any phase listed but not marked shall not be part of the basic services.

Pre-Design Phase described in Paragraph 2.3

X Schematic Design Phase described in Paragraph 2.4

X Design Development Phase described in Paragraph 2.5

X Construction Document Phase described in Paragraph 2.6

X Construction Phase described in Paragraph 2.7

2.1.2 The Commissioning Authority Professional shall provide additional services as listed and marked below. Any phase listed but not marked shall not be an additional service to this Agreement.

2.1.3 The Commissioning Authority Professional's basic services listed in Subparagraph 2.1.1 shall include consulting services listed below and comply with 300.4 of Owner Procedure Manual. Any consultant listed but not marked shall not be a consultant to this Agreement

Consulting Service: Services to be Performed by:

Mechanical

Controls

Electrical

Life Safety System

Conveying Systems

Building Envelopes

2.2 TIME

2.2.1 The Commissioning Authority Professional shall perform services as expeditiously as is consistent with professional skill and care and the orderly progress of the Work. The Commissioning Authority Professional shall submit for the Owner's approval, an estimated Schedule of Performance of services in 2.2.2. This Schedule may be adjusted as the Project proceeds and shall include allowances for periods of time required for the Owner's review and approval of submissions and for approvals of authorities having jurisdiction over the Project. This Schedule, when approved by the Owner, shall not, except for reasonable cause, be exceeded by the Commissioning Authority Professional. The Initial Meeting Date referenced below is the latter of the Pre-Design Conference or the OPR Workshop for the Commissioning Agent, if required, as scheduled by the Owner. The Initial Meeting Date referenced below is the latter of the Pre-Design Conference or the OPR Workshop for the Commissioning Agent, if required, as scheduled by the Owner.

Commissioning Percentage Contract 4

2.2.2 The estimated Schedule of Performance described in Subparagraph 2.2.1 shall be in the following format:

.1 Professional services beginning date will be the Initial Meeting Date described above.

.2 Pre-Design Phase described Paragraph 2.3: n/a days from the Initial Meeting Date.

.3 Schematic Design Phase described Paragraph 2.4: days from approval by Owner of the Pre- Design Phase, if required, or from the Initial Meeting Date.

.4 Design Development Phase described Paragraph 2.5: days from approval by Owner of SD’s.

.5 Construction Document Phase described Paragraph 2.6: days from approval by Owner of DD’s.

.6 Total planning: days

2.2.3 The dates for receipt of phases shall be the date the Documents are stamped into the Owner's office if they are in an approval condition. If submittals are rejected, then the clock will continue to run without charge for that time being reviewed by the Owner.

2.2.4 The date for approval and beginning of the next phase shall be the date of receipt, by the Commissioning Authority

Professional, of the letter of approval from the Owner.

2.2.5 All time for review of documents by the Owner, which result in an approval with instructions to move to the next phase, shall not be charged to the Commissioning Authority Professional's days for performing services.

2.3 PRE-DESIGN PHASE

2.3.1 The Commissioning Authority Professional shall meet with the Owner to establish the initial Commissioning Team for the

Project. Once team members are identified, the Commissioning Authority Professional shall schedule, chair, facilitate and document the Owner’s Project Requirements Workshop. The Commissioning Authority Professional shall utilize the information obtained in the Workshop to develop the Owner’s Project Requirements Document.

2.3.2 Upon approval by the Owner of the Owner’s Project Requirements Document, the Commissioning Authority Professional shall prepare and submit to the Owner four (4) copies of the Pre-Design Phase Documents. The Pre-Design Phase Documents shall include, but shall not be limited to, the following:

.1 Commissioning Team Contact List .2 Owner’s Project Requirements Document .3 Preliminary Commissioning Plan

2.3.3 The Commissioning Authority Professional shall show progress to date, confirm the remainder of the Schedule of

Performance, and obtain the Owner's written approval of the Pre-Design Phase before proceeding with the Schematic Design Phase.

2.4 SCHEMATIC DESIGN PHASE

2.4.1 The Commissioning Authority Professional shall confirm the Owner’s Project Requirements. If a Preliminary

Commissioning Plan has not been provided either within this Agreement or other sources, the Commissioning Authority Professional shall prepare and submit to the Owner four (4) copies of a Preliminary Commissioning Plan.

2.4.2 The Commissioning Authority Professional shall facilitate the development of the Design Professional’s Basis of Design

Document. The Basis of Design Document shall include, but shall not be limited to, the following:

.1 System and Assembly Options and Selection Reasoning

.2 Facility, System and Assembly Performance Assumptions

.3 Narrative System and Assembly Descriptions

.4 Codes, Standards, Guidelines, Regulations and Other References

.5 Specific Descriptions of Systems and Assemblies

2.4.3 The Commissioning Authority shall review and verify that Project Schematic Design Documents produced by the Design Professional meet and properly convey the Owner’s Project Requirements. Review shall include, but shall not be limited to, the following:

.1 General quality review of the documents, including legibility, consistency and level of completeness .2 Coordination between disciplines .3 Discipline-specific review for achieving the Owner’s Project Requirements .4 Specification applicability and consistency with Owner’s Project Requirements and Basis of Design

Commissioning Percentage Contract 5

2.4.4 Throughout the Schematic Design Phase, the Commissioning Authority Professional shall:

.1 Schedule, chair, facilitate and document Commissioning Team meetings

.2 Update the Owner’s Project Requirements Document

.3 Update the Commissioning Plan

.4 Track/document all issues relating to the Owner’s Project Requirements and document resolutions in the Issues Log.

2.4.5 Upon completion of the Schematic Design Phase, the Commissioning Authority Professional shall prepare and submit to the Owner four (4) copies of the Schematic Design Phase Commissioning Documents. The Schematic Design Phase Commissioning Documents shall include, but shall not be limited to, the following:

.1 Review Comments for Design Professional’s Schematic Design Submittal .2 Updated Owner’s Project Requirements Document .3 Updated Commissioning Plan .4 Review Comments for Design Professional’s Basis of Design Document .5 Issues Log .6 Commissioning Process Progress Reports

2.4.6 The Professional shall show progress to date, confirm the remainder of the Schedule of Performance, and obtain the

Owner's written approval of the Schematic Design Phase before proceeding with the Design Development Phase, unless Owner waives the Design Development Phase, directing Professional to proceed to the Contract Document Phase.

2.5 DESIGN DEVELOPMENT PHASE

2.5.1 The Commissioning Authority shall review and verify that Project Design Development Documents produced by the Design

Professional meet and properly convey the Owner’s Project Requirements. Review shall include, but shall not be limited to, the following:

.1 General quality review of the documents, including legibility, consistency and level of completeness .2 Coordination between disciplines

2.5.2 Throughout the Design Development Phase, the Commissioning Authority Professional shall:

.3 Update the Commissioning Plan

.4 Track/document all issues relating to the Owner’s Project Requirements and document resolutions in the Issues Log.

2.5.3 Upon completion of the Design Development Phase, the Commissioning Authority Professional shall prepare and submit to the Owner four (4) copies of the Design Development Phase Commissioning Documents. The Design Development Phase Commissioning Documents shall include, but shall not be limited to, the following:

.1 Review Comments for Design Professional’s Design Development Submittal

.3 Updated Commissioning Plan .4 Review Comments for Design Professional’s Updated Basis of Design Document .5 Updated Issues Log

2.6 CONSTRUCTION DOCUMENT PHASE

2.6.1 The Commissioning Authority shall review and verify that Project Construction Documents produced by the Design

Professional meet and properly convey the Owner’s Project Requirements. Review shall include, but shall not be limited to, the following:

.1 General quality review of the documents, including legibility, consistency and level of completeness .2 Coordination between disciplines

Commissioning Percentage Contract 6

2.6.2 The Commissioning Authority Professional shall develop Construction Specifications for Commissioning to be included in the Contract Documents. The Commissioning Authority Professional’s submission of Specifications shall be sufficiently in advance of completion of Construction Document Phase to allow for inclusion in Design Professional’s Construction Document Phase submission. Specifications to be provided shall include General Requirements for the Commissioning Process, Sample Test Procedures and Component Commissioning Process Specifications, as well as language/requirements to be included in individual Specification Sections in other Divisions to address the following:

.1 Commissioning Process Activities .2 Installation and Start-up .3 Testing, Adjusting and Balancing .4 Demonstration and Training .5 Operation and Maintenance Data

2.6.3 Throughout the Construction Document Phase, the Commissioning Authority Professional shall:

.3 Update the Commissioning Plan

.4 Track/document all issues relating to the Owner’s Project Requirements and document resolutions in the Issues Log

2.6.4 Upon completion of the Construction Document Phase, the Commissioning Authority Professional shall prepare and submit to the Owner four (4) copies of the Construction Document Phase Commissioning Documents. The Construction Document Phase Commissioning Documents shall include, but shall not be limited to, the following:

.1 Review Comments for Design Professional’s Construction Document Submittal

.3 Updated Commissioning Plan .4 Review Comments for Design Professional’s Basis of Design Document .5 Updated Issues Log

.7 Construction Specifications for Commissioning

2.7 CONSTRUCTION PHASE

2.7.1 The Construction Phase for the Commissioning Authority Professional shall begin at the Pre-Bid Conference for the

Construction Contract. The Commissioning Authority Professional shall attend this Conference to alert bidders to Commissioning Process requirements with which they may not be familiar.

2.7.2 The Commissioning Authority Professional shall schedule participation of Owner’s representatives in Commissioning

Process activities.

2.7.3 The Commissioning Authority Professional shall conduct a Pre-Construction Commissioning Process Meeting which shall be coordinated to coincide with the Owner’s Pre-Construction Conference, scheduled by the Owner. Subject matter to be discussed shall include the Owner’s Project Requirements, Basis of Design and unique contract document requirements as well as specific roles of the contractor relative to the Commissioning Process activities.

2.7.4 Concurrent with Design Team and Owner review, the Commissioning Authority Professional shall review coordination drawings, shop drawings and other project submittals for compliance with the Owner’s Project Requirements. Comments shall be distributed to Owner and Design Professional.

2.7.5 The Commissioning Authority Professional shall provide assistance in identifying commissioning process activities to be included in the Contractor’s Construction Schedule.

2.7.6 The Commissioning Authority Professional shall be responsible for developing component, system/assembly and inter-system test procedures, checklists and test data record format for execution by the Contractor. The Commissioning Authority Professional shall be responsible for witnessing of tests, verification of tests or verification of test data reports throughout the Construction Phase.

2.7.7 The Commissioning Authority Professional shall be responsible for witnessing and assisting in the execution of Owner

Training conducted by Contractor.

Commissioning Percentage Contract 7

2.7.8 Throughout the Construction Phase, the Commissioning Authority Professional shall:

.3 Update the Commissioning Plan

.4 Make and document periodic site visits to verify compliance with Owner’s Project Requirements

.5 Update Issues Log

2.7.9 The Commissioning Authority Professional shall develop and distribute a Draft Construction Phase Commissioning

Process Report to the Commissioning Team for review and comments. A Final Construction Phase Commissioning Process Report shall be submitted to the Commissioning Team which incorporates review comments from the Owner.

2.7.10 The Commissioning Authority Professional shall review the testing, adjusting and balancing report and perform quality control sampling to ensure reliability. Furnish a summary report and distribute to the Commissioning Team.

2.7.11 The Commissioning Authority Professional shall verify that the Systems Manual, developed by the Contractor, is updated to incorporate materials generated during the Construction Phase. The Commissioning Authority Professional shall be responsible for furnishing to the Contractor only those items produced by the Commissioning Authority Professional.

Materials to be added shall include, but shall not be limited to, the following:

.1 Test Procedures and Test Data Records .2 Training Plans .3 Training Records .4 Submittal Review Reports .5 Updated Owner’s Project Requirements .6 Updated Commissioning Plan .7 Updated Basis of Design .8 Updated Issues Log .9 Commissioning Process Progress Reports

2.7.12 During the period of time between Substantial Completion and the end of the Warranty period of the Construction

Contract, the Commissioning Authority Professional shall work with the Design Professional and a Representative of the Owner in securing remedy of defects that become apparent. The Commissioning Authority Professional shall attend, with the Design Professional and a Representative of the Owner present, the Warranty inspection of the Project prior to the expiration of the Warranty period and report observed discrepancies to the Owner and Design Professional.

2.7.13 During the period of time between Substantial Completion and the end of the Warranty period of the Construction

Contract, the Commissioning Authority Professional shall perform two off-season Functional Performance Tests.

2.7.14 The Construction Phase shall terminate upon expiration of the Warranty period or settlement of all Warranty claims, whichever occurs last.

ARTICLE 3: OWNER'S RESPONSIBILITY

3.1 PROJECT INFORMATION AND BUDGET

3.1.1 The Owner shall provide information regarding requirements for Project program and budget.

3.1.2 The Owner shall furnish information required in Subparagraph 3.1.1 as expeditiously as necessary for the orderly progress of work.

3.2 PRINTING COSTS

3.2.1 Reimbursement shall not be made for any printing, photocopying or photographic methods used as an aid in the development of documents, reports or other instruments of service.

ARTICLE 4: CONSTRUCTION COST

4.1 DEFINITION

4.1.1 The construction cost means the cost of all Contracts to the Owner, but such cost shall not include the Commissioning

Authority Professional's fee and/or reimbursements and shall not include loose equipment. Built-in or attached equipment shall be considered a part of the building construction cost.

Commissioning Percentage Contract 8

4.1.2 The total Project Budget includes the Contract(s) for construction, including information technology, furnishing and equipping, if applicable, all fees, special Consultants and Contracts, advertising costs, code compliance expenses, a reasonable contingency, and any other expenses necessary to complete the Project and deliver a useful facility to the Using Agency. Where project services as defined in Paragraph 2.1.1 do not include any phase beyond Construction Document Phase, the total Project and budget shall include only the fees based on a percentage of estimated construction cost, special Consultants and Contracts, and any other expenses needed to complete the planning of the Project through completion of the last designated planning phase.

ARTICLE 5: MISCELLANEOUS PROVISIONS

5.1 OWNERSHIP OF DOCUMENTS

5.1.1 Documents and Specifications as instruments of service are the property of the Owner whether the work for which they are intended is executed or not. Upon payment of the fees accrued for the services performed through the latest completed phase as provided in Article 6, the Owner shall have full and unrestricted use of the Documents and Specifications for execution of the Project. Original documents and specifications may remain in the files of the Commissioning Authority Professional until the Owner requests delivery.

5.2 REFERENCE STANDARDS

5.2.1 The Commissioning Authority Professional shall prepare Documents and Specifications in conformance with the following

Reference Standards in effect as of the date of this Agreement, unless a different edition is so noted.

.1 ASHRAE Guideline 0-200X The Commissioning Process

.2 ASHRAE Guideline 1-200X The HVAC&R Commissioning Process

.3 NIBS Guidelines 2-200X through 14-200X

5.3 CONSULTING PROFESSIONALS

5.3.1 The Consulting Professionals retained or otherwise employed by the Commissioning Authority Professional must be approved by the Owner. The Commissioning Authority Professional shall not employ or otherwise retain consulting Professionals with proprietary interests.

5.3.2 The Commissioning Authority Professional agrees to employ the Consultants for complete services, including inspection.

5.4 SUCCESSORS AND ASSIGNMENTS

5.4.1 The Commissioning Authority Professional shall not assign, subcontract or otherwise transfer in whole or in part, its right or obligations under this agreement without prior written consent of the Owner. Any attempted assignment or transfer without said consent shall be void and of no effect.

5.5 LAWS

5.5.1 This Agreement shall be governed by and construed in accordance with the Laws of the State of Mississippi, excluding its conflicts of laws provisions, and any litigation with respect thereto shall be brought in the courts of the state. The Commissioning Authority Professional shall comply with applicable federal, state and local laws and regulations.

5.5.2 E-Verify – Employee Status Verification System. If applicable, the Contractor represents and warrants that it will ensure its compliance with the Mississippi Employment Protection Act, Section 71-11-1, et seq of the Mississippi Code Annotated (Supp 2008) and will register and participate in the status verification system for all newly hired employees. The term “employee” as used herein means any person that is hired to perform work within the State of Mississippi. As used herein, “status verification system” means the Illegal Immigration Reform and Immigration Responsibility Act of 1996 that is operated by the United States Department of Homeland Security, also known as the E-Verify Program, or any other successor electronic verification system replacing the E-Verify Program. The Contractor agrees to maintain records of such compliance, and upon request of the State and approval of the Social Security Administration or Department of Homeland Security, where required, to provide a copy of each such verification to the State. The Contractor further represents and warrants that any person assigned to perform services hereunder meets the employment eligibility requirements of all immigration laws of the State of Mississippi. The Contractor understands and agrees that any breach of these warranties may subject the Contractor to the following: (a) termination of this Agreement and ineligibility for any state or public contract in Mississippi for up to three (3) years, with notice of such cancellation/termination being made public, or (b) the loss of any license, permit, certification or other document granted to the Contractor by an agency, department or governmental entity for the right to do business in Mississippi for up to one (1) year, or (c) both. In the event of such

Commissioning Percentage Contract 9 termination/cancellation, the Contractor would also be liable for any additional costs incurred by the State due to the contract cancellation or loss of license or permit.”

5.6.3 Transparency. In accordance with the Mississippi Accountability and Transparency Act of 2008, §27-104-151, et seq., of the Mississippi Code of 1972, as Amended, the American Accountability and Transparency Act of 2009 (P.L. 111-5), where applicable, and §31-7-13 of the Mississippi Code of 1972, as amended, where applicable, a fully executed copy of this agreement shall be posted to the State of Mississippi’s accountability website at: https://www.transparency.mississippi.gov

ARTICLE 6: FEES AND PAYMENTS TO THE COMMISSIONING AUTHORITY PROFESSIONAL

6.1 GENERAL

6.1.1 The fee for the Project shall be a percentage of construction cost based on each construction contract awarded.

6.2 PERCENTAGE OF CONSTRUCTION COST

6.2.1 When the Project fee is based on a percentage of construction cost, the basic project shall be classified as one (1) of six

(6) types. Only the Owner shall be responsible for deciding in which classification the Project falls as indicated in Subparagraph 1.2.2. The project classifications are:

Type CxA: Projects of ordinary complexity for which commissioning will be limited to mechanical, controls, electrical, life safety and conveying systems.

Type CxB: Projects of moderate complexity for which commissioning will be limited to mechanical, controls, electrical, life safety and conveying systems. Projects of this type include one or more non-standard system to be commissioned or include one standard system of higher than ordinary complexity.

Type CxC: Projects of high complexity for which commissioning will be limited to mechanical, controls, electrical, life safety and conveying systems. Projects of this type include multiple non-standard systems to be commissioned or include several systems of high complexity.

Type CxD: Projects of ordinary complexity for which commissioning will be “total building type” including mechanical, controls, electrical, life safety and conveying systems as well as building envelope.

Type CxE: Projects of moderate complexity for which commissioning will be “total building type” including mechanical, controls, electrical, life safety and conveying systems as well as building envelope.

Projects of this type include one or more non-standard system to be commissioned or include one standard system of higher than ordinary complexity.

Type CxF: Projects of high complexity for which commissioning will be “total building type” including mechanical, controls, electrical, life safety and conveying systems as well as building envelope. Projects of this type include multiple non-standard systems to be commissioned or include several systems of high complexity.

6.2.2 The Owner shall pay the Commissioning Authority Professional a fee calculated as a percentage of construction cost derived from a basic fee formula of a fixed number (X) divided by the common logarithm of the actual construction cost (C). The formulas for each project classification are as follows:

CxA Fee percentage formula = 5 CxA Fee amount formula = C (5)_ Log C (Log C)

CxB Fee percentage formula = 6 CxB Fee amount formula = C (6)_ Log C (Log C)

CxC Fee percentage formula = 7 CxC Fee amount formula = C (7)_ Log C (Log C)

CxD Fee percentage formula = 9 CxD Fee amount formula = C (9)_ Log C (Log C)

CxE Fee percentage formula = 10 CxE Fee amount formula = C (10)_ https://www.transparency.mississippi.gov/

Commissioning Percentage Contract 10

CxF Fee percentage formula = 11 CxF Fee amount formula = C (11)_

6.2.3 When Change Orders occur, the fee shall be increased or decreased accordingly if the Construction Contract amount is increased or decreased.

ARTICLE 7: PAYMENTS TO THE COMMISSIONING AUTHORITY PROFESSIONAL

7.1 PAYMENTS FOR BASIC FEE

7.1.1 Payments to the Commissioning Authority Professional on account of his basic fee under Article 6 shall be made as indicated in the following paragraphs.

7.1.2 Upon completion of the Schematic Design Phase and written approval of the Owner, a sum equal to five percent (5%) of the basic fee computed upon the approved estimate of construction cost shall be due.

7.1.3 Upon completion of the Design Development Phase and written approval of the Owner, a sum equal to fifteen percent

(15%) of the basic fee, less any previous payments, computed upon the approved estimate of construction cost shall be due.

7.1.4 Upon completion of the Construction Document Phase and written approval of the Owner, a sum equal to thirty-five percent (35%) of the basic fee, less any previous payments, computed upon the approved estimate of construction cost shall be due.

7.1.5 Upon award of the Contract for Construction and written approval of the Owner, a sum equal to thirty-five percent (35%), less any previous payments, computed upon the actual awarded construction amount shall be due.

7.1.6 Payment of fees to the Commissioning Authority Professional during the Construction Phase shall be made monthly in proportion to the current percentage requested by the Contractor and approved by the Owner.

7.1.7 The Owner reserves the right to determine when and who provides the Professional service items needed for this Project.

Any pay request submitted by the Commissioning Authority Professional which contains service items not authorized by the Owner to be performed by the Commissioning Authority Professional may be disapproved in part, or total.

7.2 PAYMENTS FOR ADDITIONAL SERVICES

7.2.1 Upon completion of any additional services indicated in Paragraphs 1.3 and 2.1.2 and written approval of the Owner, payment in full shall be due, minus any offsets.

7.2.2 Partial payments may be made upon written request by the Commissioning Authority Professional and the Owner's written approval, minus any offsets.

7.3 PAYMENTS FOR EXTRA SERVICES AND SPECIAL SITUATIONS

7.3.1 If the Commissioning Authority Professional is caused extra documentation, review or other expense because of major changes ordered by the Owner, the delinquency or insolvency of the Contractor, or as a result of damage to work in progress by fire or other cause, the Commissioning Authority Professional may request to be paid for such extra services and expenses.

7.3.2 Any Commissioning Authority Professional having a claim under this Paragraph shall prepare a complete and documented explanation and submit it to the Owner for consideration. Only upon written Owner approval shall extra compensation be made.

7.3.3 At the Owner's discretion, and only after receiving the Owner’s written approval, the Commissioning Authority Professional may be compensated for extra services in special situations according to the fees indicated in Paragraph 1.4, or negotiated a lump sum payment.

Commissioning Percentage Contract 11

7.4 REIMBURSEMENTS

7.4.1 The Owner shall reimburse the Commissioning Authority Professional for expenses listed in Paragraph 1.5 and previously approved by Owner. The Commissioning Authority Professional shall submit separate invoices for each item for which reimbursement is requested.

7.4.2 The Commissioning Authority Professional shall not be reimbursed for any traveling or living expenses incurred personally, by Associates or by Consultants identified in Paragraph 2.1.3.

7.4.3 All requests for reimbursement must be received with or before the final request for payment. Payment of the

Commissioning Authority Professional's retainage constitutes waiver by the Commissioning Authority Professional of any future claims for reimbursement.

7.5 DIRECT PERSONNEL EXPENSE

7.5.1 When applicable to the Agreement, direct personnel expense shall include that of employees engaged on the Project by the Commissioning Authority Professional including Architects, Engineers, Professionals, Specification Writers, Inspectors and Secretaries involved in consultation, research, design, production of Reports, Specifications and other Documents pertaining to the Project and inspection of construction of the Project.

7.5.2 Direct personnel expense shall include the cost of salaries and mandatory and customary benefits, such as statutory employee benefits, insurance, sick leave, holidays, vacations, pensions and similar benefits.

7.6 COMMISSIONING AUTHORITY PROFESSIONAL'S ACCOUNTING RECORDS

7.6.1 Records of the Commissioning Authority Professional's direct personnel expense, Consultant expense, and reimbursable expenses pertaining to the Project and records of accounts between the Owner and the Commissioning Authority Professional shall be maintained in conformity with generally accepted accounting principles for a period of three (3) full years from the date of final payment and shall be subject to audit at any reasonable time and upon reasonable notice by the Owner, the Owner's duly appointed Representative or a licensed independent public accountant.

7.7 DEDUCTIONS

7.7.1 No deductions shall be made from the Commissioning Authority Professional's fee on account of penalty or liquidated damage sums withheld from payment to Contractors through no fault of the Commissioning Authority Professional.

7.8 PAYMENT LIMITATIONS

7.8.1 It is expressly understood and agreed that the obligation of the Owner, to proceed under this agreement is conditioned upon the appropriation of funds by the Mississippi State Legislature and the receipt of state and/or federal funds. If the funds anticipated for the continuing fulfillment of the Agreement are, at any time, not forthcoming or insufficient, either through the failure of the federal government to provide funds or of the State of Mississippi to appropriate funds or the discontinuance or material alteration of the program under which funds were provided or if funds are not otherwise available to the Owner, the Owner shall have the right upon ten (10) working days written notice to the Professional, to terminate this agreement without damage, penalty, cost or expenses to the Owner, of any kind whatsoever. The effective date of termination shall be as specified in the notice of termination.

7.9 PAYMENT REQUESTS

7.9.1 All requests for payment by the Commissioning Authority Professional shall be submitted with an ORIGINAL and one (1) copy.

7.10 E-Payment and E-Invoice: The word “contractor” herein shall mean Professional, Vendor, Architect, Engineer, Lessor, etc.

(Currently – July 2009 – the BoB is exempt from E-Invoice.)

The State agrees to make payment in accordance with Mississippi law on “Timely Payments for Purchases by Public Bodies”, Section 31-7-301, et seq. of the Mississippi Code of 1972, as amended, which generally provides for payment of undisputed amounts within forty-five (45) days of receipt of the invoice.

Commissioning Percentage Contract 12

Payments by state agencies using the statewide electronic payment and remittance vehicle shall be made and remittance information provided electronically as directed by the State. These payments shall be deposited into the bank account of the Contractor’s choice. The State may, at its sole discretion, require the Contractor to submit invoices and supporting documentation electronically at any time during the term of this Agreement. Contractor understands and agrees that the State is exempt from the payment of taxes. All payments shall be in United States currency.

No payment, including final payment, shall be construed as acceptance of defective or incomplete work, and the Contractor shall remain responsible and liable for full performance.

ARTICLE 8: LIABILITY INSURANCE, ET AL

8.1 ERRORS AND OMISSIONS / WORKERS COMP

8.1.1 The Commissioning Authority Professional shall purchase and maintain with a company, or companies, licensed to do business in the State of Mississippi, such insurance as will provide protection from claims resulting from errors and omissions, or negligent acts arising out of the performance of professional services and operations under this Agreement.

8.1.2 The errors and omissions insurance required in Subparagraph 8.1.1 shall be written for not less than:

Total Project Funds (Amount Listed on Page One) Minimum Limit of Insurance

$ 0 - $ 999,999 $ 250,000.00 $ 1,000,000 - $ 7,499,999 $ 500,000.00 $ 7,500,000 - $ 14,999,999 $ 750,000.00 $ 15,000,000 - Up $ 1,000,000.00

8.1.3 If by the terms of this insurance any mandatory deductibles are required, or if the Commissioning Authority Professional should elect with the written concurrence of the Owner, to increase the mandatory deductible amounts or purchase this insurance with voluntary deductible amounts, the Commissioning Authority Professional shall be responsible for payment of the amount of the deductible in the event a claim is paid. In the event of a claim against the policy, the Commissioning Authority Professional shall arrange for the restoration of the limit of liability so that full coverage is maintained at all times.

8.1.4 The Commissioning Authority Professional shall be fully responsible to the Owner for work performed by Associates and/or Consultants. In the case of joint ventures, joint venture errors and omissions insurance coverage shall be required in accordance with the limits stated in Subparagraph 8.1.2.

8.1.5 Workers Comp Insurance when and if there are five or more workers in the Professional’s firm.

8.1.6 The errors and omissions insurance and workers comp coverages shall remain in effect for the period of time the

Commissioning Authority Professional is responsible for the Project.

8.1.7 The Professional, on signing this Agreement, shall provide the Owner two (2) copies of a Certificate of Insurance. The Insurance Coverage may not be canceled or not renewed during the term of subject Contract. Professional’s contractual obligation is to procure and maintain the requisite coverage(s) throughout the life of subject Project/Contract, when applicable.

ARTICLE 9: TERMINATION AND EXTENT OF AGREEMENT

9.1 TERMINATION OF AGREEMENT FOR CAUSE

9.1.1 If, through any cause, the Commissioning Authority Professional shall fail to fulfill, in a timely and proper manner, obligations under this Agreement, the Owner shall thereupon have the right to terminate this Agreement at any Phase by giving seven (7) days written notice to the Commissioning Authority Professional of such termination and specifying the effective date of termination. At the option of the Owner, all finished or unfinished Documents and Specifications prepared by the Commissioning Authority Professional shall be the property of the Owner, and the Commissioning Authority Professional shall not be entitled to any compensation beyond the last approved design phase as listed in Subparagraph 2.1.1.

9.1.2 Notwithstanding the above, the Commissioning Authority Professional shall not be relieved of liability to the Owner for damages sustained by the Owner by virtue of any breach of this Agreement by the Commissioning Authority Professional, and the Owner may withhold any payments to the Commissioning Authority Professional for the purpose of offset until…