Mascot_PowerUpgrade_AnnotatedPictures_Drawings.pdf
PDF 571 KB Posted
- Attached to
- Electrical upgrade at Mascot Saloon located within Federal contract opportunity
- Solicitation number
- 140P9721Q0057
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Scope_7-12-2021_0002.pdf | ||
| Sol_140P9721Q0057_Amd_0002.pdf | ||
| Scope_6-28-2021_0001.pdf | ||
| Sol_140P9721Q0057_Amd_0001.pdf | ||
| Combined_synopsis-solicitation.pdf | ||
| Service_Contract_Labor_Wages.pdf | ||
| Sol_140P9721Q0057.pdf | ||
| General_specifications.pdf | ||
| Scope.pdf | ||
| Submittal_Register_Mascot_PowerUpgrades.pdf | ||
| Submittal_Form.pdf | ||
| Past_performance_questionnaire.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Other Notes: Electrical service will enter the building through the crawls space above grade, but under boardwalk. Then enter Mascot Mechanical Room through the floor. If a crawl space vent is not available a 4” hole will be drilled through the stem wall.
Constructed Valve Pit
Shed and Fuel tank
Fence
H-Frame (red) to extend 108” from the existing power pole (blue) to mount the new 400 am CT meter and Main Disconnect (green rectangles) for the Upgraded Mascot Electrical
Service. Protected by bollards (yellow). Dumpster pad (grey) will be re-established after
Electrical Service installation. Bollards and H-Frame posts to be buried 4’ below grade.
Approx. Privy Location.
New electrical service (red line) will be one 4” conduit. Top of conduit is 24” below grade until under the boardwalk when it is raised and
“daylighted” above grade before entering the crawlspace.
Approx. Privy Location.
Code allows for exemptions to disconnect or shunt trip attached to building when the building is operated by a single owner. Engineer recommends placard, identifying disconnect on H-Frame by the power pole be attached to wall by back door.
Representation of H-Frame and Gear is not to scale (actual dimensions listed on page 4). Location of the post on the left side of the picture is in the correct location relative to the distance from the south side of the power pole and Westmark
Building. Bollards (yellow) will be placed to protect electrical service from vehicular damage. Dumpster pad will be replaced after installation.
400 Amp
Main
Disconnect
For Building
400 Amp
Current
Transformer
(CT) Meter
Existing Disconnect for 6 meter pack attached to the
Verb Cribs to be replaced with new.
Location of H-Frame post (brown) is 108” north of the side of the power pole (just out of view of the picture. Area inside of green oval is where new conduit follows trenching that occurred in 2019.
New electrical service
(red line) will be one 4” conduit and one 1” conduit. Top of conduit is 24” below grade until under the boardwalk when it is raised and
“daylighted” above grade before entering the crawlspace.
Electrical gear sketch and dimensions to be mounted to H-Frame connected to power pole.
Panel M to be surface mounted. Services enters room through crawlspace. 150 amp connection from Panel M to Panel A will also be routed through the crawlspace. Fiber Optic ONT, hydrant and conjunction box to be relocated, removed, or abandoned prior to Panel M installation.
Panel M
Location
Panel A