Manchester Chiller 100_CD_R1 Narrative.pdf
PDF 7 MB Posted
- Attached to
- 4130--608-20-110 - Bldg. 1 Chiller Replacement Federal contract opportunity
- Solicitation number
- 36C24124B0019
About this file
This federal contract opportunity notice is for the replacement of two chillers at the Manchester VA Medical Center in Manchester, New Hampshire. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1 is soliciting bids under solicitation number 36C24124B0019 for the replacement of the existing 100-ton chillers with two new 175-ton air-cooled chillers. The project scope includes removing the existing chillers and support structure, installing new structural supports, installing the two new chillers, upgrading primary and secondary chilled water pumps, and modifying existing chilled water piping. Bids are due by the response date listed in the solicitation notice. The awarded contractor will be required to utilize temporary chillers during construction to maintain chilled water supply to the facility.
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
100% Design Narrative
Chiller Replacement
Manchester VA Medical Center
Submitted to:
U.S. DEPARTMENT OF VETERAN AFFAIRS
Attn: Matthew Welch, General Engineer
Manchester VA Hospital
718 Smyth Road, Manchester, NH 03104
Submitted by:
Alares LLC
248 Copeland Street
Quincy, MA 02169
May 2022
Chiller Replacement Design
May 2022
Table of Contents Section Page
1.0 Executive Summary
2.0 Existing Conditions
3.0 Architectural Narrative
3.1 Applicable Codes/References
3.2 Scope
4.0 Mechanical Design Narrative
4.1 Applicable Codes/References
4.2 Design
4.3 Recommended Phasing
4.4 DDC Controls
5.0 Structural Design Narrative
5.1 Design Criteria
5.2 Proposed Structural Work
6.0 Electrical Design Narrative
6.1 Applicable Codes/References
6.2 Design Recommendation
6.3 Electrical for Temporary Chiller
7.0 Estimated Costs
APPENDICES
APPENDIX A – Cost Estimate
APPENDIX B – Structural Calculations
APPENDIX C – Equipment Cut Sheets
APPENDIX D – Cooling Demand Calculations
APPENDIX E – Design Coordination Log
May 2022 3
1 .0 EX EC U TIV E S U MMA RY
The Manchester VA Medical Center is located at 718 Smyth Road, Manchester, NH 03104.
Building 1 was constructed in 1948. The primary goal of this design project is to replace the two air-cooled chillers outside of the Building 1 penthouse. The chillers were previously replaced in
2004 and new 6” Ø chilled water risers were installed recently.
After receiving feedback from the VA from the 90% design development package, Alares
Engineering (Alares) and NV5 prepared the 100% Basis of Design (BOD) narrative to describe the final design intent. The proposed design will replace the existing chillers with two 175-ton
York YLAA200 Chillers. Larger chillers require upsizing electrical, structural, and existing primary chilled water pumps P-1 and P-2. This report documents the detailed replacement design with a proposed piping layout, temporary chiller location, and phasing plan.
The new chilled water primary loop will connect to the existing buffer tank on the roof. A new bypass with valves will be installed to isolate the tank if required. In addition to replacing the chillers, the secondary chilled water loop will be upgraded. The existing pumps P-4, P-5, P-6, and
P-7 will be demolished and replaced with two larger pumps. The proposed phasing plan is described in the Design Approach section below.
2 .0 EX IS TIN G C O N D ITIO N S
The chilled water system is currently serving part of Building 1, from Floor 1 to Floor 6. Some other spaces are served by dedicated DX systems. The building layout is broken down below:
• Floor 1: Mostly offices, common rooms, lobby, and kitchen.
• Floor 2: West wing is dental area, East wing is laboratory area, North is SPS.
• Floor 3: Half of the floor is ophthalmology and half is audiology.
• Floor 4: West wing is pre-operation, East wing is offices, and North is operation.
• Floor 5: Mental health entire floor, many group rooms + offices.
• Floor 6: Mostly offices.
According to the VA Manchester staff, the chilled water system serves Floors 2, 3, 5, and part of
Floor 4 which totals 80 tons capacity cooling demand.
The Building 1 existing chilled water system consists of:
- Two (2) 100-ton Trane air-cooled chillers, model number RTAA100 in an n+1 configuration.
- Existing chiller physical data:
o Overall footprint: 194.5” x 88.2” (LxW) o Total Operating weight: 8,465 lbs.
- Two primary loop pumps (P-1 and P-2) serve chiller primary loop with n+1 configuration.
- Two secondary loop pumps (P-6 and P-7) dedicated to serve operating rooms with n+1 configuration.
- One secondary loop pump (P5) dedicatedly serves 6” Ø chilled water riser.
May 2022 4
- One secondary loop pump (P4) dedicatedly serves 4” Ø chilled water riser.
3 .0 A R C H ITEC TUR A L N A R R AT IV E
The architectural work includes roof modifications and limited floor and wall demolition and patching. A new wall penetration will be made for temporary chilled water hoses connection to the temporary chiller. This penetration will be patched after construction is completed and the permanent chillers are brought online. Details for areas of work are included in the design drawings.
3 . 1 A P P L I C A B L E C O D E S / R E F E R E N C E S
• VA Directives, Design Manuals, Master Specifications, VA National CAD
Standard Application Guide, and other Guidance on the Technical Information
Library (TIL) (http://www.cfm.va.gov/til/).
• International Building Code (IBC)
• NFPA 101 Life Safety Code
• NFPA National Fire Codes with the exception of NFPA 5000 and NFPA 900
• Occupational, Safety and Health Administration (OSHA) Standards.
3 . 2 S C O P E
The architectural scope includes:
1. New roofing for the area of the former chillers.
2. Roof opening and repair for installing new structural supports for new chiller locations.
3. New roof penetration details for the curb supports.
4. Roof repair for the areas of the condenser relocations
5. New roofing for relocated condenser pads.
6. Patching wall penetrations
7. Installing new wall penetrations.
4 .0 MEC H A N IC AL D ES IG N N A R R ATIV E
The goal of the project is to design a chilled water system that complies with current VA Design
Guidelines, Local Code and Standards, and meets the following requirements:
- Air-cooled chillers.
http://www.cfm.va.gov/til/
May 2022 5
- All pump systems (primary loop, secondary loop) shall have n+1 configuration.
- Construction of the new system will avoid interrupting the current system.
- Construction phasing will be incorporated to avoid unfavorable weather conditions.
- Temporary chillers will be used to facilitate the chiller replacements.
4 . 1 A P P L I C A B L E C O D E S / R E F E R E N C E S
- Ventilation for Acceptable Indoor Air Quality ASHRAE 62.1 2007
- Ventilation of Health Care Facilities ASHRAE 170
- VA Mechanical Design Guide
- VA Seismic Design Requirements H-18-8
- VA Master Specifications
4 . 2 D E S I G N
As requested by the VA, the existing chillers are being upsized to accommodate more cooling capacity for future demand. Areas in Building 1 currently being served by standalone DX systems will be tied into the central chilled water loop at a later date. The future cooling load calculations are included in Appendix D.
The basis of design for the air cooled chillers are York scroll chillers (Appendix C):
a. High efficiency
b. Multiple scroll compressors
c. Dual circuit
d. Overall footprint: 275.6” x 88.7” (LxW)
e. Total Operating weight: 10,443 lbs
The recommended design will provide 175 tons of cooling with an n+1 configuration. Each new chiller is 7 ft longer and 2,000 lbs heavier than existing chillers. The structural support frame shall be modified to accommodate both new chillers. The roof structure will need to be re-enforced. See structural section below.
Additional isolation valves and bypass will be installed for the existing buffer tank. Pumps P-1, P-2 shall be replaced to meet new water flow and n+1 configuration. P-4, P-5, P-6 and P-7 shall be consolidated to meet new water flow and n+1 configuration. Piping serving Operating Rooms, 4” Ø riser and 6” Ø riser shall be modified, as shown on the design drawings. A new circuit setter will be installed on each riser to control flow. Temporary chillers are needed to facilitate the chiller replacement work. During the site investigation, Alares found that the 48’x 36’ area in front of
Ambulatory Care is large enough for the temporary chillers, and that 150’ of temporary piping will be required to connect to the pumping system on the roof. The recommended temporary chiller location are shown on the drawings under separate attachment.
4 . 3 R E C O M M E N D E D P H A S I N G
Phase 1: Install Temporary Chillers
May 2022 6
- Phase 1 shall require a short-term system shutdown. The shutdown shall be coordinated with the VA COR in advance.
- Provide temporary chillers and pumps. Two 100-ton temporary chillers shall have n+1 configuration to maintain continuous chilled water supply for building during construction.
Two (2) 40 feet temporary chiller trailers shall be located in the courtyard behind Building 1 near the Ambulatory Care Entrance.
- Contractor shall provide temporary power for chiller trailers. Refer to electrical drawings for more info.
- Contractor shall provide temporary fence around chillers. The fence shall include a lockable gate.
- Contractor shall install temporary 4” chilled water supply + return piping from chillers to the building roof. Holes in the wall will be required to allow piping to enter the building mechanical room. Temporary piping shall be removed after completion of the project.
- Contractor shall install an isolation valve on the existing chilled water supply at the penthouse wall penetration.
- Contractor shall provide approximately 150 ft of chilled water flexible hoses to connect temporary pipes on roof to existing chilled water system in the penthouse mechanical room.
- Provide 6" butterfly isolation valve on chilled water supply before hooking up temporary chiller to existing chilled water system.
The photo below shows the location of the proposed temporary chiller location.
Figure 1: Temporary Chiller and Piping Layout
May 2022 7
Figure 2: Temporary Chilled Water Hose Connection
Phase 2: Replace Chillers and Primary Pumps
- Phase 2 shall commence once temporary chillers/piping are installed, connected to system and ready to operate.
- Demolish & remove existing chillers CH-1 and CH-2 entirely, including all accessories.
- Demolish chiller supporting structure I-beams and patch the roof according to VA specifications.
- Demolish existing 4” Ø branch pipes connected to each chiller back to 6” Ø main pipe.
- Demolish & remove primary loop pumps P-1 and P-2 including all accessories.
- Provide new structural frame to support new chillers.
- Install new chillers CH-1 and CH-2 with accessories. Chiller model is YVAA0200 or equal.
- Install new primary loop pumps P-1 and P-2 with all accessories.
- Install new 6” Ø branch pipes and accessories as indicated on drawings; connect main pipe to new chillers.
- Install butterfly valves to bypass buffer tank.
- Relocate three split system condensing units. Provide new roof curb at new locations. Remove existing Roof curbs and patch the roof according to VA specifications.
Since the new chillers are 2,000 lbs heavier and 7 feet longer than existing chiller, the VA decided on the following new configuration: the new chillers will be placed on top of 4 existing concrete columns and 2 existing concrete beams.
The chillers will avoid the columns and consequently will only be supported by 2 existing concrete beams. Refer to structural design section below for more information.
Proposed Crane Location
May 2022 8
The proposed location for rigging, shown below and is to the right of the main entrance, bordering the new Community Living Center.
Figure 5: Rigging Plan
Install New Pumps 1 and 2
During Phase 2, Pumps 1 and 2 will be replaced. See location below.
Figure 6: Primary Pump P-1 and P-2 Replacement
Phase 3: Replace Secondary Pump P-4, P-5, P-6 & P-7 and modify secondary loop piping.
May 2022 9
- Phase 3 shall commence once new chillers/piping and primary pumps are installed, connected to system and ready to operate.
- Phase 3 shall require a short-term system shutdown. The shutdown shall be coordinated with the VA COR in advance.
- Remove all temporary chillers and piping from the system. Alternatively, temporary chillers and accessories can be kept until the project until the new chiller system is commissioned. It is recommended the Contractor operates the chiller for a 30-day performance period to demonstrate the chiller system is operating as designed.
- Demolish & remove secondary pump P-4, P-5, P-6 & P-7 and all accessories.
- Demolish 3”, 4”, and 6” chilled water piping as indicated on drawings.
- Install new larger pumps P-4 and P-5.
- Modify piping so new P-4 & P-5 can serve the existing 3” Ø OR riser, 4” Ø riser, and 6” Ø riser serving Building 1. See drawings for connection to main header.
- Provide seismic bracing for piping in mechanical room.
Figure 7: Secondary Pump P-4, P-5, P-6 & P-7 Replacement
4 . 4 D D C C O N T R O L S
The existing DDC control system will remain. However, a new control sequence was developed to operate the new chillers and pumps. New programming and control points for the new chillers and pumps are required and will be connected to the existing building automation control system.
5 .0 S TR U C TU R AL D ES IG N N A R R ATIV E
5 . 1 D E S I G N C R I T E R I A
Structural support will be designed in accordance with the 2015 International Building Code (IBC) as adopted and amended by the State of New Hampshire, and Specification for Structural Steel
May 2022 10
Buildings (ANSI/AISC 360-10) and Bridges (ANSI/AISC 303-10). All structural codes are included on drawing SF-001.
1. Building Risk Category IV – Essential Facility
2. Dead Loads
a) Actual weight of the chiller and its accessories.
3. Live Loads
a) Roof: 20 psf
4. Snow Loads
a) Ground Snow Load, Pg – 70 psf
b) Minimum Flat Roof Snow Load, Pf min. – 58.8 psf
c) Snow Importance Factor, Is – 1.2
5. Wind Loads
a) Basic Wind Speed, Vult – 95 mph
b) Wind Exposure Category – C
6. Seismic Loads
a) Spectral Response Acceleration Parameter, SS – 0.351
b) Spectral Response Acceleration Parameter, S1 – 0.080
c) Seismic Importance Factor, Ie – 1.5
5 . 2 P R O P O S E D S T R U C T U R A L W O R K
The conceptual design for support of the new chillers that will be installed on the existing roof framing and building structure columns is described below:
- Remove the existing steel beams which underlies the existing chillers.
- Remove existing membraned beams (W12x40) on the top of roof slab.
- Provide three new membraned beams (W12x40) that run on top of 2 existing concrete beam.
- Provide twelve structural stub columns (Round HSS 6 x0.5”) that are placed on top of three new membraned beams to support longitudinal structural beams (W10x33).
- Provide longitudinal structural beams (W10x33) which placed along the perimeter of each chiller and connect to structural column (Round HSS 6 x0.5”).
The chiller loads will be transferred to the new membraned beams which are supported by the building concrete beams and columns. The advantage of this configuration is that the existing roof slab does not take the weight of the chillers and no concrete reinforcement is needed. The disadvantage is that more equipment coordination and roofing work is needed to accommodate the new chillers.
May 2022 11
In regarding to support temporary pipe, a steel rack will be installed at the parapet of the building to support the steel pipes from the temporary chillers on the ground to the roof. Some masonry anchors may be required to provide the lateral support of the pipes during the construction.
Also metal stairs and platform will be installed in front of the chillers for accessing control panel and chiller equipment.
In addition, seismic bracing for the new equipment and piping is required. Seismic calculations are included in Appendix B.
6 .0 ELEC TR IC A L D ES IG N N A RR ATIV E
Chillers No.1 is fed from normal distribution board “DP-1L” via a 300kVA dry-type transformer
(208V-delta to 480V-delta) located in the main electric room. Distribution board ‘DP-1L’ is fed via existing main switchboard “SG20-T3’ and emergency equipment branch switchboard
‘20_ESG_GEN OUTPUT 1’ via a 1200A automatic transfer switch ‘ATS-5-2’. The feeder serving Chiller No. 1 appears to be tapped off to power panel ‘P7-N’ located in penthouse mechanical room E701. Panel P7-N powers the associated primary and secondary loop pumps.
Chiller No.2 is fed from the existing normal main switchboard ‘SG20-T4 via a 225kVA dry-type transformer (208V-delta to 480V-delta). Chiller No.2 is also powered from the emergency equipment branch switchboard ‘20_ESG_GEN OUTPUT 1 ‘via a 600A manual transfer switch
‘MTS-1-2’ located in the main electric room. The transfer switch is manufactured by Square D.
The existing chillers are rated at approximately186kVA based on Trane model RTA100 equipment data. The existing chillers are connected to the lightning protection system at the roof level.
Main switchboards ‘SG20-T3’ and ‘SG-20T4’ are fed from 1000kVA pad-mounted transformers
(4160V primary-208/120V secondary).
Emergency double-ended switchboard ‘20_ESG-GEN OUTPUT 1/20_ESG-GEN OUTPUT 2’ is fed from (3)-500kW-480V standby emergency generators via 750kVA pad-mounted transformers rated 480V primary/208V secondary. The upstream disconnect switches FD-1 and FD-2 are rated at 2500A however the emergency switchboards and tie breaker are rated at 1600A. The reduced capacity of the downstream distribution equipment needs to be addressed in order to provide adequate capacity for the proposed chiller upgrades.
The majority of the loads fed from ‘SG20-T3’ and “SG20-T4’ are also fed from the emergency distribution system via automatic transfer switches.
6 . 1 A P P L I C A B L E C O D E S / R E F E R E N C E S
Materials, installation of systems and equipment provided under this section shall be done in strict accordance with the Department of Public Safety, Department of Environmental Protection, State
Building Code and any other Codes and Regulations having jurisdiction including but not limited to:
May 2022 12
1. All Applicable NFPA Standards
2. National Electrical Code (NEC).
3. Occupational Safety and Health Administration (OSHA)
4. State and Local Building Codes
5. Underwriters' Laboratories, Inc (UL)
6 . 2 D E S I G N R E C O M M E N D A T I O N
Existing 100-ton chillers shall be disconnected/removed and replaced with new 175 ton scroll chillers. The new chillers are rated at approximately 228kW/285kVA at 480V, three phases.
1. The existing 300kVA dry-type transformer powering Chiller No.1 shall be retained for reuse. A new 800A automatic transfer switch shall be provided. The transfer switch shall be fed from new 800A circuit breakers in existing main switchboard SG20-T3 and emergency distribution board EQDP1.
2. The existing 225kVA dry-type transformer powering Chiller No.2 shall be upgraded to
300kVA. The related circuit breaker in emergency distribution board EQDP1 and main switchboard ‘SG20-T4’ shall be upgraded to 800A. The existing manual transfer switch powering Chiller No. 2 shall be replaced with a new 800A automatic transfer switch.
3. The new feeders shall be run from Building 20 main electric room to Building 1 penthouse mechanical room via the abandoned dumbwaiter chase.
4. Provide air terminals mounted on chiller roof and reconnect to existing lightning protection system.
Existing panel P7-N shall be upgraded to 400A to power the upgraded pumps and existing loads.
A new 400A circuit breaker in panel DP-1L and 112.5kVA dry-type transformer shall be provided.
Primary pumps (P-1 and P-2) shall be disconnected/removed and replaced with new pumps 1-P-
1/1-P-2 (n+1). Related VFDs shall be replaced with new.
Existing secondary loop pumps (P-4 and P-5) shall be disconnected/removed and replaced with new pumps 1-P-5/1-P-6(n+1). Pumps shall be fed from the new 800A distribution board located in the penthouse mechanical room. Related VFDs shall be disconnected/removed and replaced with new.
Existing double-ended emergency switchboard shall be upgraded to 2500A, 208V-3ph. The new switchboard shall be located adjacent to the existing upstream disconnect switches FD-1 and FD-
2. New incoming feeders shall be provided from disconnect switches FD-1 and FD-2. Existing active branch loads shall be extended to the new switchboard.
Lastly, installation of recording meters for a minimum period of 30 days are recommended for the emergency generators, switchboard ’20_SG_SWBD_T3” and 20_SG_SWBD_T4’ to determine if
May 2022 13 there is ample spare capacity on the existing distribution system to accommodate the proposed upgrades.
6 . 3 E L E C T R I C A L F O R T E M P O R A R Y C H I L L E R
The following is required:
Provide a temporary chiller to facilitate the proposed replacement work. It appears that temporary power can be provided from existing panel D2X located in Building 20 main electric room. A bus tap with disconnect switch shall be provided to power the temporary chillers. The disconnect switches shall be located within 10’-0” of panel D2X.
7 .0 ES TIMATED C O S TS
The table below summarizes the anticipated construction costs for installing two new 175-ton chillers.
Cost Estimate Summary
Description Estimated
Implementation Cost
Replace chillers with (2) 175-ton chillers
Replace connection piping for each chiller
Replace primary pumps P-1&2 & VFD
Replace secondary pumps P-4, P-5, P-6, P-7 & VFD
Modify piping to cross connect 3” Ø, 4”Ø and 6”Ø risers
Provide temporary chillers and piping
USD 1,946,478
Refer to Appendix A for the cost estimate breakdown.
100% Construction Documents
Manchester VA Medical Center Alares Engineering
Achieving swift results
Appendix A
Construction Cost Estimate
Project Scope
The 100% Construction Drawings are the basis for the final construction cost estimate. This project consists of the removal of two 100 ton air cooled chillers (to include their platforms, roof supports, access decking, and immediate piping) on the 7th floor roof of the Manchester, NH VAMC. Work also includes the providing of temporary chilled water (supplied by vendor from ground-based chillers on trailers) to the rooftop while two
175-ton chillers are installed. Ancillary work includes roof repair, piping modifications, relocation of a few existing equipment items on the roof, and pump and valve work inside the adjacent mechanical room.
Methodology
The projected cost is based on materials, current pricing, labor practices, local prevailing
(Davis Bacon) wages and vendor costs for all associated work items with an expected accuracy of +/- 10%.
General Assumptions
1. Project is bid to pre-approved, non- set-aside Contractors.
2. The on-site construction period is 20 weeks.
3. There are no asbestos or lead conditions that will impact this project.
4. The 175-ton replacement chillers are York units with an expected lead time for delivery on site of 12 weeks.
5. Material unit costs are based on multiple sources including in-house, trade references, RS Means 2020 and, BNi 2020 Construction Data.
6. Craft rates and crew mixes have been applied from the same sources and comply with
Davis Bacon Wage Rate requirements for the Manchester market.
7. Likewise, equipment rates conform to the same references.
8. Estimate preparation is based upon a Prime Contractor managing sub-contractors and trades as a construction manager. The Prime Contractor is working under a fixed
Price agreement.
9. This project is tax-exempt for materials and labor.
10. Temporary trailer mounted chillers will supply cooling from surface parking behind the main hospital building. The vendor will design and install the means by which pipe supply and return lines are installed without damage to the existing building facades. These units will be powered from a VA panel identified. There will be higher level of noise in this area, but it is not expected to be detrimental to the use of any facilities. Assumed that temporary chiller will operate for 3 months.
11. Crane for rigging can be placed in front of Building 1. Space behind Building 1 will be taken by temporary chillers.
12. There will be no structural work required inside the facility.
13. There will be short duration cross-over work requirements that will interfere with normal HVAC operations but nothing noticeable to occupants and all such work will be scheduled for weekends when the hospital is not open for services.
14. No project escalation or contingency is included in this estimate.
CONSTRUCTION COST ESTIMATE DATE PREPARED 2/12/2021
PROJECT BASIS FOR ESTIMATE 100% CD
Manchester Chiller Upgrade
LOCATION Two / 175-ton Chillers w/ Temp Chiller
Manchester NH VAHC
ARCHITECT/ENGINEER
Alares Engineering
Estimator RAF Reviewer DJM
MATERIALS LABOR EQUIPMENT SUBCONTRACTOR TOTAL
Division 1 - General Requirements 1,000.00$ 139,400.00$ -$ 96,500.00$ 236,900.00$
Division 2 - Existing Conditions 22,500.00$ 15,985.68$ -$ 57,500.00$ 95,985.68$
Division 3 - Concrete 8,400.00$ 18,304.64$ -$ -$ 26,704.64$
Division 4 - Masonry -$ -$ -$ -$ not used
Division 5 - Metals 64,200.00$ 25,612.80$ -$ 5,500.00$ 95,312.80$
Division 6 - Wood and Plastic -$ -$ -$ -$ not used
Division 7 - Thermal and Moisture Protection 40,800.00$ 12,615.36$ -$ 4,000.00$ 57,415.36$
Division 8 - Doors and Windows -$ -$ -$ -$ not used
Division 9 - Finishes 950.00$ 5,007.60$ -$ -$ 5,957.60$
Division 10 - Specialties -$ -$ -$ -$ not used
Division 11 - Equipment -$ -$ -$ -$ not used
Division 12 - Furnishings -$ -$ -$ -$ not used
Division 13 - Special Construction (Temp Chiller Option / Req't) 107,000.00$ 106,854.40$ 10,000.00$ -$ 223,854.40$
Division 14 - Conveying Equipment -$ -$ -$ -$ not used
Division 21 - Fire Suppression -$ -$ -$ -$ not used
Division 22 - Plumbing -$ -$ -$ -$ not used
Division 23 - Heat, Ventilating, and Air Conditioning 83,300.00$ 108,823.52$ 326,000.00$ 130,000.00$ 648,123.52$
Division 26 - Electrical 79,200.00$ 85,705.80$ -$ 28,500.00$ 193,405.80$
Division 27 - Communications -$ -$ -$ -$ not used
Division 28 - Electronic Safety and Security -$ -$ -$ -$ not used
Division 31 - Earthwork -$ -$ -$ -$ not used
Division 32 - Exterior Improvements-rigging and temp chiller space -$ -$ -$ -$ 25,000.00$
Division 33 - Utilities -$ -$ -$ -$ not used
SUBTOTAL 1,608,659.80$
Allowance for Phasing 0.00% -$
Overhead 10.00% 160,865.98$
Profit 10.00% 176,952.58$
Bond 1.50% 29,197.18$
PROJECT TOTAL 1,946,478.36$
Division 01 General Requirements PROJECT BASIS FOR ESTIMATE 100% CD Date Prepared: 2/12/2021
Manchester Chiller Upgrade
LOCATION
Manchester NH VAHC
ARCHITECT/ENGINEER
Alares Engineering
DRAWING NO. Estimator RAF Reviewer DJM
QUANTITY SUBCONTRACTOR
NO. UNIT PER TOTAL Hours Rate TOTAL PER TOTAL TOTAL TOTAL
UNITS MEAS. UNIT UNIT COST
General Conditions
Project Manager 120 150.00$ 18,000.00$ 18,000.00$
Asst PM 80 95.00$ 7,600.00$ 7,600.00$
Superintendent (20 weeks) 800 110.00$ 88,000.00$ 88,000.00$
Admin 40 55.00$ 2,200.00$ 2,200.00$
Constr Coord - Admin 80 95.00$ 7,600.00$ 7,600.00$
Gas / Fuel - Superintendent -$
Print Plans and distribute - per trade -$
Dumpster (allowance) 5,000.00$ 5,000.00$
Storage Containers - each/month -$
Storage Containers - deliver and remove -$
Temporary Toilets - 1 x /week servicing 20 week 50.00$ 1,000.00$ 1,000.00$
Temporary Toilets - deliver and remove -$
Small Tools (allowance) 5,000.00$ 5,000.00$
Equipment (allowance) 5,000.00$ 5,000.00$ photocopying, office supplies for trailer 2,000.00$ 2,000.00$
Safety Items 15,000.00$ 15,000.00$
Surveying, layout -$
Screening, drug testing, security Badging 10,000.00$ 10,000.00$
Cell Phone Useage -$
Trucks -$
Office Trailer -$
Equipment Rentals 20,000.00$ 20,000.00$
Common Laborer 400 40.00$ 16,000.00$ 4,000.00$ 20,000.00$
Cleanup Labor - hourly -$
Final Cleaning - Rough and Final SUB QUOTE 5,000.00$ 5,000.00$
Comm Tools - Hardware, Software, Computers, OPM -$
Client Specific Training Costs 5,000.00$ 5,000.00$
Project Documentation - Startup 5,000.00$ 5,000.00$
Project Documentation - Closeout 5,000.00$ 5,000.00$
Barricade - build, relocate, remove 10,000.00$ 10,000.00$
Testing - Xray Slabs ($350 minimum set up) -$
Testing - Moisture testing of floor slab -$
Temporary utilities - Electric -$
Temporary fencing and gates -$
Security Services -$
Temporary Construction Signs and Signage 500.00$ 500.00$
Permits (if assigned by Owner) -$
Bonds -$
SUBTOTAL -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------1,000.00$ 139,400.00$ -$ 96,500.00$ 236,900.00$
MATERIALS & ASSUMPTIONS EQUIPMENTLABOR
Division 02 Existing Conditions PROJECT BASIS FOR ESTIMATE 100% CD Date Prepared: 2/12/2021
Manchester Chiller Upgrade
LOCATION
Manchester NH VAHC
ARCHITECT/ENGINEER
Alares Engineering
DRAWING NO. Estimator RAF Reviewer DJM
QUANTITY SUBCONTRACTOR
NO. UNIT PER TOTAL Hours Rate TOTAL PER TOTAL TOTAL TOTAL
SOURCE UNITS MEAS. UNIT UNIT COST
Crane to demo towers, lift components 2 lifts 2,000.00$ 4,000.00$ 40.00 30.92$ 1,236.80$ 20,000.00$ 25,236.80$
Access work and repair 2 ea 2,000.00$ 4,000.00$ 16.00 30.92$ 494.72$ 5,000.00$ 9,494.72$ Remove and dispose of chiller units (disposal inc. in subcontractor fee) 2 ea 2,000.00$ 4,000.00$ 32.00 30.92$ 989.44$ 25,000.00$ 29,989.44$
Relocation of Existing Roof Equipment 3 ea 2,000.00$ 6,000.00$ 96.00 37.04$ 3,555.84$ 9,555.84$
Demolition of Existing Roofing and Curbs 4000 SF 1.00$ 4,000.00$ 260.00 30.92$ 8,039.20$ 4,000.00$ 16,039.20$
Demolition of Existing raised platform 1 ea 200.00$ 200.00$ 30 30.92$ 927.60$ 3,000.00$ 4,127.60$
Demolition of Existing pump sets 3 ea 100.00$ 300.00$ 24 30.92$ 742.08$ 500.00$ 1,542.08$
SUBTOTAL -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------22,500.00$ 15,985.68$ -$ 57,500.00$ 95,985.68$
MATERIALS & ASSUMPTIONS LABOR EQUIPMENT
Division 03 Concrete PROJECT BASIS FOR ESTIMATE 100% CD Date Prepared: 2/12/2021
Manchester Chiller Upgrade
LOCATION
Manchester NH VAHC
ARCHITECT/ENGINEER
Alares Engineering
DRAWING NO. Estimator RAF Reviewer DJM
QUANTITY SUBCONTRACTOR
NO. UNIT PER TOTAL Hours Rate TOTAL PER TOTAL TOTAL TOTAL
SOURCE UNITS MEAS. UNIT or per unit UNIT COST
Penetrations allow 1,000.00$ 1,000.00$
Seal Penetrations RSM 6 ea 100.00$ 600.00$ 24.00 30.92$ 4,452.48$ 5,052.48$
Raised Machinery Platform allow 2 ea 300.00$ 600.00$ 24.00 30.92$ 1,484.16$ 2,084.16$
Platform work at Expanded Tower Pad allow 4 ea 1,500.00$ 6,000.00$ 60.00 30.92$ 7,420.80$ 13,420.80$
Pump concrete pads allow 4 ea 300.00$ 1,200.00$ 40.00 30.92$ 4,947.20$ 6,147.20$
SUBTOTAL -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------8,400.00$ 18,304.64$ -$ -$ 27,704.64$
Division 05 Metals PROJECT BASIS FOR ESTIMATE 100% CD Date Prepared: 2/12/2012
Manchester Chiller Upgrade
LOCATION
Manchester NH VAHC
ARCHITECT/ENGINEER
Alares Engineering
DRAWING NO. Estimator RAF Reviewer DJM
QUANTITY SUBCONTRACTOR
NO. UNIT PER TOTAL Hours Rate TOTAL PER TOTAL TOTAL TOTAL
SOURCE UNITS MEAS. UNIT or per unit UNIT COST
RTU Platform Extension 2 ea 20,000.00$ 40,000.00$ 200 $36.80 7,360.00$ 5,500.00$ 52,860.00$
Pipe Supports (Roof) 18 ea 400.00$ 7,200.00$ 240 $36.80 8,832.00$ 16,032.00$
Seismic Bracing 40 ea 300.00$ 12,000.00$ 160 $36.80 5,888.00$ 17,888.00$
Interior support work 1 ea 5,000.00$ 5,000.00$ 96 $36.80 3,532.80$ 8,532.80$
SUBTOTAL -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------64,200.00$ 25,612.80$ -$ 5,500.00$ 95,312.80$
Division 7 - Thermal and Moisture Protection PROJECT BASIS FOR ESTIMATE 100% CD Date Prepared: 2/12/2021
Manchester Chiller Upgrade
LOCATION
Manchester NH VAHC
ARCHITECT/ENGINEER
Alares Engineering
DRAWING NO. Estimator RAF Reviewer DJM
QUANTITY SUBCONTRACTOR
NO. UNIT PER TOTAL Hours Rate TOTAL PER TOTAL TOTAL TOTAL
SOURCE UNITS MEAS. UNIT or per unit UNIT COST
Wall and Ceiling Penetrations 6 ea 800.00$ 4,800.00$ 3 30.92$ 556.56$ 5,356.56$
Wall waterproofing 10 ea 800.00$ 8,000.00$ 3 30.92$ 927.60$ 8,927.60$
Install new roofing, flashing, and curb enclosures 4000 sf 7.00$ 28,000.00$ 360 30.92$ 11,131.20$ -$ 4,000.00$ 43,131.20$
SUBTOTAL -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------40,800.00$ 12,615.36$ -$ 4,000.00$ 57,415.36$
Division 9 - Finishes PROJECT BASIS FOR ESTIMATE 100% CD Date Prepared: 2/12/2021
Manchester Chiller Upgrade
LOCATION
Manchester NH VAHC
ARCHITECT/ENGINEER
Alares Engineering
DRAWING NO. Estimator RAF Reviewer DJM
QUANTITY SUBCONTRACTOR
NO. UNIT PER TOTAL Hours Rate TOTAL PER TOTAL TOTAL TOTAL
SOURCE UNITS MEAS. UNIT or per unit UNIT COST
Misc Patching 30 ea 10.00$ 300.00$ 2.00 $30.92 1,855.20$ 2,155.20$
Paint Allowance 30 ea 5.00$ 150.00$ 2.00 26.27$ 1,576.20$ 1,726.20$
Pipe Painting and Marking 1 ea 500.00$ 500.00$ 60 26.27$ 1,576.20$ 2,076.20$
SUBTOTAL -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------950.00$ 5,007.60$ -$ -$ 5,957.60$
Division 13 - Special Construction PROJECT BASIS FOR ESTIMATE 100% CD Date Prepared: 2/12/2021
Manchester Chiller Upgrade
LOCATION Temporary Chiller Costs Manchester NH VAHC
ARCHITECT/ENGINEER
Alares Engineering
DRAWING NO. Estimator RAF Reviewer DJM
QUANTITY SUBCONTRACTOR
NO. UNIT PER TOTAL Hours Rate TOTAL PER TOTAL TOTAL TOTAL
SOURCE UNITS MEAS. UNIT or per unit UNIT COST
Temporary Chiller Service
Truck Mounted Chiller (3 months) quote 3 ea 16,000.00$ 48,000.00$ 48,000.00$
Allowance for Temporary Power allow 1 ls 7,000.00$ 7,000.00$ 80.00 37.04$ 2,963.20$ -$ 9,963.20$
Piping / Hoses RSM 600 lf 60.00$ 36,000.00$ 0.30 37.04$ 6,667.20$ -$ 42,667.20$
Vertical Pipe Support System allow 80 lf 100.00$ 8,000.00$ 2.00 37.04$ 5,926.40$ 10,000.00$ 23,926.40$
Connection Work and Glycol Ballancing allow 200 gal 15.00$ 3,000.00$ 0.20 37.04$ 1,481.60$ -$ 4,481.60$
Dissambley and Repair allow 1 ls 5,000.00$ 5,000.00$ 400.00 37.04$ 14,816.00$ -$ 19,816.00$
Added General Conditions for 30-day Project Extension 75,000.00$ -$ 75,000.00$
SUBTOTAL -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------107,000.00$ 106,854.40$ 10,000.00$ -$ 223,854.40$
Division 23 - Heat, Ventilating, and Air Conditioning PROJECT BASIS FOR ESTIMATE 100% CD Date Prepared: 2/12/2021
Manchester Chiller Upgrade
LOCATION
Manchester NH VAHC
ARCHITECT/ENGINEER
Alares Engineering
DRAWING NO. Estimator RAF Reviewer DJM
QUANTITY SUBCONTRACTOR
NO. UNIT PER TOTAL Hours Rate TOTAL PER TOTAL TOTAL TOTAL
SOURCE UNITS MEAS. UNIT or per unit UNIT COST
Air Cooled Chillers quote 2 ea 5,000.00$ 10,000.00$ 600.00 $37.04 44,448.00$ 115,000.00$ 230,000.00$ 284,448.00$
Pump, HP quote 2 ea 100.00$ 200.00$ 40 $37.04 2,963.20$ 20,000.00$ 40,000.00$ 43,163.20$
Pump, HP quote 2 ea 100.00$ 200.00$ 40 $37.04 2,963.20$ 16,000.00$ 32,000.00$ 35,163.20$
Pump, HP quote 2 ea 100.00$ 200.00$ 40 $37.04 2,963.20$ 12,000.00$ 24,000.00$ 27,163.20$
6" Pipe with hangers & insulation BNi 100 lf 130.00$ 13,000.00$ 2 $37.04 7,408.00$ -$ 20,408.00$
4" Pipe with hangers & insulation BNi 140 lf 85.00$ 11,900.00$ 2 $37.04 7,778.40$ -$ 19,678.40$ small pipe with hangers & insulation BNi 80 lf 40.00$ 3,200.00$ 4 $37.04 11,852.80$ -$ 15,052.80$
8" fittings BNi 30 ea 400.00$ 12,000.00$ 4 $37.04 4,444.80$ -$ 16,444.80$
6" fittings BNi 16 ea 200.00$ 3,200.00$ 4 $37.04 2,370.56$ -$ 5,570.56$
4" fittings BNi 40 ea 100.00$ 4,000.00$ 4 $37.04 5,926.40$ -$ 9,926.40$ other fitting allowance BNi 8 ea 1,500.00$ 12,000.00$ 3 $37.04 888.96$ -$ 12,888.96$
Glycol quote 40 gal 110.00$ 4,400.00$ 4 $37.04 5,926.40$ -$ 10,326.40$
Sensors allow 1 ea 5,000.00$ 5,000.00$ 40 $37.04 1,481.60$ -$ 6,481.60$
Control Wiring allow 200 lf 20.00$ 4,000.00$ 1 $37.04 7,408.00$ -$ 11,408.00$
Controls contractor allow -$ 100,000.00$ 100,000.00$
Commissioning allow -$ 30,000.00$ 30,000.00$
SUBTOTAL -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------83,300.00$ 108,823.52$ 326,000.00$ 130,000.00$ 648,123.52$
Division 26 - Electrical PROJECT BASIS FOR ESTIMATE 100% CD Date Prepared: 2/12/2021
Manchester Chiller Upgrade
LOCATION
Manchester NH VAHC
ARCHITECT/ENGINEER
Alares Engineering
DRAWING NO. Estimator RAF Reviewer DJM
QUANTITY SUBCONTRACTOR
NO. UNIT PER TOTAL Hours Rate TOTAL PER TOTAL TOTAL TOTAL
SOURCE UNITS MEAS. UNIT or per unit UNIT COST
Power to Chillers BNi 2 ea 5,000.00$ 10,000.00$ 200.00 $51.63 20,652.00$ 30,652.00$
Power to Pumps Bni 5 ea 1,500.00$ 7,500.00$ 40.00 $51.63 10,326.00$ 17,826.00$
Panel Work BNi 3 ea 3,000.00$ 9,000.00$ 120.00 $51.63 18,586.80$ 27,586.80$
VFDs inc manufacturer rep startup BNi 5 ea 6,500.00$ 32,500.00$ 60.00 $51.63 15,489.00$ 3,500.00$ 51,489.00$
Temporary Work / Phasing allow 2 ea 100.00$ 200.00$ 80.00 $51.63 8,260.80$ 8,460.80$
ATS inc. testing allow 1 ea 20,000.00$ 20,000.00$ 240.00 $51.63 12,391.20$ 15,000.00$ 47,391.20$
Startup and commissioning support allow 1 ea -$ 10,000.00$ 10,000.00$
SUBTOTAL -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------79,200.00$ 85,705.80$ -$ 28,500.00$ 193,405.80$
Appendix B
Structural Calculations
STRUCTURAL CALCULTION
Design Summary
The option 2 layout was adopted by the client. The new chillers are oriented perpendicular to the existing chillers and supported on the newly installed the steel beams (W10X33). The supporting frame layout is shown below:
The design loads
Structural support will be designed in accordance with the 2015 International Building Code (IBC) as adopted and amended by the State of New Hampshire, and Specification for Structural Steel
Buildings (ANSI/AISC 360-16).
1. Building Risk Category IV – Essential Facility
2. Dead Loads
a) Actual weight of the chiller 10443 lbs/each) and its accessories.
3. Live Loads
a) Roof: 20 psf
4. Snow Loads
a) Ground Snow Load, Pg – 70 psf
b) Minimum Flat Roof Snow Load, Pf min. – 58.8 psf
c) Snow Importance Factor, Is – 1.2
5. Wind Loads
a) Basic Wind Speed, Vult – 95 mph
b) Wind Exposure Category – C
6. Seismic Loads
a) Spectral Response Acceleration Parameter, SS – 0.351
b) Spectral Response Acceleration Parameter, S1 – 0.080
c) Seismic Importance Factor, Ie – 1.5
The loads of the equipment were converted to a line load shown as follows in the calculation:
Steel Beam Calculation:
The roof concrete beam evaluation
Roof concrete Column Evaluation
Appendix C
Equipment Cutsheets www.mobileair.com 1-800-596-0800
Resolute Industrial’s York® brand Air Cooled Scroll Compressor Chiller package is self-contained and engineered to provide flexible, temporary chilled fluid for commercial and industrial air conditioning and process cooling applications.
The chiller package is permanently mounted on a rugged steel tubular frame with fork-pockets for easy maneuvering, and features a single-point power connection and integral pump package.
TECHNICAL DATA
General Model Number YLAA100 Dimensions, L x W x H 12’ 8” x 7’ 6” x 8’ Shipping Weight, approximate lbs 6,800 Refrigerant R-410A Refrigerant Circuits 2 Equipment Insurance Value $150,000
Electrical Single Point Power Supply 460/3/60 Connections, 1 per phase plus ground Series 16, cam type
RLA* 225
MCA* 280
*Includes 10 HP pump
Evaporator Flow Minimum GPM 100 Nominal GPM 228 Maximum GPM 385 Fluid Connections 4” Victaulic Maximum Water Side Connections 150 PSIG Evaporator Volume, gallons 51
RENTAL AIR COOLED
SCROLL COMPRESSOR
CHILLER
YLAA100
Hly Text Box
TEMPORARY CHILLERS
www.mobileair.com 1-800-596-0800
YLAA100
COOLING CAPACITY, TONS
Actual capacity subject to leaving temperature, fluid utilized and ambient conditions.
LCWT (°F) LBT (°F)
Outdoor Ambient (°F)
85 90
50 117 111 108 105
44 107 101 98 95
40 101 95 92 89
Brine Required
35 92 87 85 82
30 84 80 87 75
25 76 72 70 68
PUMP PERFORMANCE
Design Conditions Datasheet
MLP Effective Date:10/8/2020 (ALARES) VA Manchester
Generated on2020-11-02 E.20.4.24348.0-D.87.0014(REV. v8_22.idd) Datasheet Spec
Unit Folder: CH-2 Software Version: YW20.04a Page_1_of_2
Unit Tag Qty Model No Net Cooling
Capacity (ton.R) Nominal Voltage Refrigerant Type
CH-2 1 YLAA0200HE46XFBBCTX 184.3 460-3-60.0 R410A
PIN:
YLAA0200HE 46XFBBCTXB SXBLXCXX41 SE1XXXHXXX YAXGXXX7BX XMXSBXXXXX
....5...10 ....5...20 ....5...30 ....5...40 ....5...50 ....5...60 ....5...70 ....5...80 ....5...90
Evaporator Data Evaporator Data (Cont.) Performance Data EWT (°F) 56.00 Fluid Volume (USGAL) 12.68 EER (Btu/W∙h) 9.678
LWT (°F) 41.00 Min. Flow Rate (USGPM) 229.8 IPLV.IP (Btu/W∙h) 17.61
NPLV.IP (Btu/W∙h) 17.06
Design Flow Rate (USGPM) 310.2 Max. Flow Rate (USGPM) 624.5
Evap. Press. Drop (ft H2O) 11.5
Fluid Propylene
Glycol (%) 35 Condenser Data Physical Data
Strainer Press. Drop (ft H2O) 2.47 Ambient Temp. Design (°F) 95.0 Rigging Wt. (lb) 10313
Ext. Kit Press. Drop (ft H2O) 0.696 Altitude (ft) 0.000 Operating Wt. (lb) 10443
Total Press. Drop (ft H2O) 14.7 Compressor Type Scroll - Hermetic Refrigerant Charge (lb) 190.9
Fouling Factor (h.ft².F/Btu) 0.000100
Electrical Data Circuit 1 2 3 4
Compressor RLA 51 / 51 / 51 51 / 51 / 51
Fan QTY/FLA (each) 6 / 4 6 / 4
High LRA Current 316 / 316 / 316 316 / 316 / 316
Single Point Min. Circuit Ampacity 374
Recommended Fuse/CB Rating 400
Max. Inverse Time CB Rating 400
Max. Dual Element Fuse Size (A) 400 Operating Condition Electrical Data Unit Short Circuit Withstand (STD) 65 [kA] Compressor kW 208.4
Wires Per Phase 2 + 1 Total Fan kW 20.16
Wire Range (Lug Size) #3/0 AWG - 250 kcmil +
250 - 500 kcmil Total kW 228.6
Starter Type Across The Line
Notes:
This unit does not have a coil coating selected.
Certified in accordance with the AHRI Air-Cooled Water-Chilling Packages Certification Program, which is based on AHRI Standard 550/590 (I-P) and AHRI Standard 551/591 (SI). Certified units may be found in the AHRI Directory at www.ahridirectory.org.
Unit contains freeze protection fluids in the evaporator with a leaving chilled fluid temperature above 32 DEG F [0 DEG C] and is certified when rated per the Standard with water. Auxiliary components included in total KW - Oil heaters, Chiller controls. Auxiliary power is already included in the compressor and fan power
ASHRAE Standard 90.1-2010 Compliant.
Compliant with the requirements of the LEED Energy and Atmosphere Enhanced Refrigerant Management Credit (EAc4).
Hly
Selected 175 Ton Chillers CH-1, CH-2
Design Conditions Datasheet
MLP Effective Date:10/8/2020 (ALARES) VA Manchester
Generated on2020-11-02 E.20.4.24348.0-D.87.0014(REV. v8_22.idd) Datasheet Spec
Unit Folder: CH-2 Software Version: YW20.04a Page_2_of_2
Part Load Rating Data
Stage Ambient (°F) Capacity (ton.R) Total kW Unit Efficiency
(Btu/W∙h) 1 95.0 184.3 228.6 9.678
2 88.2 163.3 172.5 11.36
3 80.7 140.2 122.7 13.71
4 71.4 111.5 81.34 16.46
5 61.2 79.99 46.56 20.62
6 55.0 39.53 21.84 21.72
Sound Power Levels (In Accordance with AHRI 370)
Stage Ambient
(°F)
63 Hz
(dB)
125 Hz
(dB)
250 Hz
(dB)
500 Hz
(dB)
1 kHz
(dB)
2 kHz
(dB)
4 kHz
(dB)
8 kHz
(dB)
LWA
1 95.0 97 96 92 92 88 85 81 78 94
2 88.2 95 94 90 90 87 84 80 76 92
3 80.7 93 92 88 88 84 82 78 74 90
4 71.4 90 89 85 86 82 80 76 72 88
5 61.2 85 84 80 80 77 76 72 67 83
6 55.0 82 81 77 77 74 73 69 64 80
Note: Unit is equipped with Acoustic Sound Blanket and Ultra Quiet Fans with VSD Control.
Performance at AHRI Conditions
Evaporator Data Condenser Data Performance Data EWT (°F) 54.00 Ambient Temp. (°F) 95.0 EER (Btu/W∙h) 10.15
LWT (°F) 44.00 Altitude (ft) 0.000 IPLV.IP (Btu/W∙h) 17.61
Flow Rate (USGPM) 467.3 Net Cooling Capacity
(ton.R) 195.8
Pressure Drop (ft H2O) 18.9
Fluid Water
Fouling Factor (h.ft².F/Btu) 0.000100
Fluid Volume (USGAL) 12.68
Note: Unit rated at design condition capacity.
PRODUCT DATA
ITEM NO. DOE BASIC MODEL NO.
MODEL NO. PEI
VL
IMPELLER DIA.
GPM
HEAD/FT
WEIGHT
PUMP/MOTOR
FREQUENCY
PHASEHPRPM
VOLTAGE HI ENERGY RATING
JOB:
ENGINEER:
REPRESENTATIVE:
CONTRACTOR:
SFI Series Pump - NEMA 1 | Submittal Data Submittal No: 301-S311 | Model: SFI3011D | RPM: 1760 | HP: 20HP | ODP | Effective: April 3, 2020 | Supersedes: NEW
OPERATING SPECIFICATIONS
FLANGE PRESSURE TEMPERATURE
STANDARD
ANSI Class
175 PSIG*
(1210 KPA)
250°F
(120°C)
OPTIONAL
ANSI Class
300 PSIG**
(2070 KPA)
250°F
(120°C)
Motors: All NEMA Standard (T Frame)
* In accordance with ANSI Standard B16.1 Class 125
** In accordance with ANSI Standard B16.1 Class 250
DIMENSIONS
English dimensions are in inches. Metric dimensions are in millimeters.
Metric data is presented in ( ).
Do not use for construction purposes unless certified.
(Dimensions are for NEMA ODP)
50 Cycle Performance Curves attached when applicable
Model No. | 3011D
Flange Size (Suction x Discharge) | 4 x 3 (102 x 76)
NSF 61 CERTIFIED YES NO
SFI3011D-A-4P-PD
0.46 54
201760
HORSEPOWER 20
O D
P
MOTOR FRAME 256T
G MAX 22.57 (573)
MAXIMUM ASSEMBLY
WEIGHT LBS. (KG)
750 (340)
A
ANSI Class 125: 4.72 (120)
ANSI Class 250: 5.03 (128)
B
ANSI Class 125: 11.00 (279)
ANSI Class 250: 11.38 (289)
C 19.17 (487)
D 52.0 (1321)
E
ANSI Class 125: 1.54 (39)
ANSI Class 250: 1.23 (31)
F 14.03 (356)
J
ANSI Class 125: 23.77 (604)
ANSI Class 250: 24.08 (630)
K 17.67 (449)
N 2.00 (50)
P 48.0 (1219)
Hly
1-P-1 & 1-P-2
N/A - Not Available
DRIVE DATA
DRIVE DIMENSIONS
PROTOCOLS
(Standard) BACnet, Modbus RTU, N2 Metasys, FLN Apogee, FC Protocol
PROTOCOLS
(Optional) LonWorks® DeviceNet Profibus
ENCLOSURE NEMA Type 1 / IP21
I/O (Standard)
6 Digital Inputs / 2 Digital Outputs
1 Analog Current Output / 2 Analog Inputs
2 Pulse Inputs
2 Form C Relays
ADDITIONAL
CONTROL
OPTIONS
None General Purpose I/O Relay Card
24VDC Supply Analog I/O
ELECTRICAL
CONFIGURATION
Basic (no disconnect) Mechanical disconnect Fused disconnect
2 Contactor Bypass - Drive Fusing & Main Disconnect (5kA SCCR)
2 Contactor Bypass - Main Fusing & Disconnect (100kA SCCR)
3 Contactor Bypass - Drive Fusing & Main Disconnect (5kA SCCR)
3 Contactor Bypass - Main Fusing & Disconnect (100kA SCCR)
EMC/RFI
CONTROL
Intergated filter designed to meet EN61800-3
HARMONIC
SUPPRESSION
Dual DC-link chokes (Equivalent: 5% AC line reactor)
Supporting IEEE 519-1992 requirements
COOLING Fan-cooled through back channel
AMBIENT
TEMPERATURE
-10°C to 45°C up to 1000 meters above sea level
-14°F to 113°F up to 3300 feet above sea level
HP RANGE
FRAME
DIMENSIONS - IN (MM)
208V 460V 575V T U V
4 (3.0) -
5 (4.0)
7.5 (5.5) -
10 (7.5)
1.5 (1.1) -
10 (7.5)
WITHOUT
BYPASS (A3)
19.1 (485) 5.1 (130) 9.6 (245)
WITH
BYPASS (A3)
31.7 (806) 7.6 (194) 9.7 (247)
7.5 (5.5) -
15 (11) 15 (11) - 25 (18)
WITHOUT
BYPASS (B1)
18.9 (480) 9.5 (242) 12.1 (308)
WITH
BYPASS (B1)
41.8 (1061) 9.1 (231) 15.9 (405)
20 (15) -
20 (15) 30 (22) - 40 (30)
WITHOUT
BYPASS (B2)
25.6 (650) 9.5 (242) 12.1 (308)
WITH
BYPASS (B2)
43.2 (1098) 9.6 (243) 17.7 (450)
COMMENTS
Submittal No: 301-S311 | Model: SFI3011D | RPM: 1760 | HP: 20HP | ODP Page: 2
U
T
V Drive with optional disconnect
V U
T
Basic drive
U
T
V Drive with bypass
U
T
V Drive with optional disconnect
U V
T
Basic drive
U
T
V Drive with bypass
TEFC
ODP
953-6596
U
T
V Drive with optional disconnect
V U
T
Basic drive
U
T
V Drive with bypass
U
T
V Drive with optional disconnect
U V
T
Basic drive
U
T
V Drive with bypass
TEFC
ODP
953-6596
Drive with optional disconnect
Basic Drive
U
T
V Drive with optional disconnect
V U
T
Basic drive
U
T
V Drive with bypass
U
T
V Drive with optional disconnect
U V
T
Basic drive
U
T
V Drive with bypass
TEFC
ODP
953-6596
Drive with bypass
MATERIALS OF
CONSTRUCTION
CASING COVER IMPELLER WEAR RING SHAFT
SHAFT
SLEEVE
MECHANICAL
SEAL
SEAL
FLUSH LINE
ASSEMBLY
STANDARD
CONSTRUCTION
BRONZE
FITTED
125#
FLANGE
Cast Iron ASTM
A48/A48M-03
Class 30A
Cast Iron ASTM
A48/A48M-03
Class 30A
Bronze ASTM
B584 ALLOY
C83600 or C84400
N/A
Stainless Steel
TYPE 416”T
ASTM A582
Bronze ASTM
B584-98A C92200 Ceramic/EPT N/A
250#
FLANGE
Ductile Iron ASTM
A536-84
Grade 65-45-12
Cast Iron ASTM
A48/A48M-03
Class 30A
Bronze ASTM
B584 ALLOY
C83600 or C84400
N/A
Stainless Steel
TYPE 416”T
ASTM A582
Bronze ASTM
B584-98A C92200 Ceramic/EPT N/A
OPTIONAL
125# OR
250# N/A N/A
Stainless Steel
ASTM A351/A
351M-08
Bronze ASTM
B584-98A C92200 N/A
Stainless Steel
TYPE 303 ASTM
A276
Tyngsten Carbide
/EPT or Silicon-
Carbide/EPT
Copper & Brass
C3600
STANDARD
CONSTRUCTION
NSF 61
125#
FLANGE
Cast Iron ASTM
A48/A48M-03
Class 30A
Cast Iron ASTM
A48/A48M-03
Class 30A
Stainless Steel
ASTM A351/A
351M-08
N/A
Stainless Steel
TYPE 416”T”
ASTM A582
Bronze ASTM
B584-98A
C92200
Ceramic/EPT Copper & Brass
C3600
250#
FLANGE
Ductile Iron
ASTM A536-84
Grade: 65-45-12
Cast Iron ASTM
A48/A48M-03
Class 30A
Stainless Steel
ASTM A351/A
351M-08
N/A
Stainless Steel
TYPE 416”T”
ASTM A582
Bronze ASTM
B584-98A
C92200
Ceramic/EPT Copper & Brass
C3600
OPTIONAL
125# OR
250# N/A N/A N/A
Bronze
ASTM B584-98A
C92200
N/A N/A N/A N/A
Taco, Inc., 1160 Cranston Street, Cranston, RI 02920 | Tel: (401) 942-8000 | FAX: (401) 942-2360 | Taco (Canada), Ltd., 8450 Lawson Road, Suite #3, Milton, Ontario L9T 0J8 | Tel: (905) 564-9422 | FAX: (905) 564-9436
Visit our website: www.TacoComfort.com | Printed in USA | ©2020 Taco, Inc.
Page: 3Submittal No: 301-S311 | Model: SFI3011D | RPM: 1760 | HP: 20HP | ODP
0 75 150 225 300 375 450 525 600 675 750
FLOW IN GALLONS PER MINUTE
L/SEC 5 10 15 20 25 30 35 40 45
0 0
5 50
10 100
15 150
20 200
25 250
30 300
35 350
40 400
H
EA
D
IN
M
ET
ER
S
H
EA
D
IN
K
IL
O
PA
SC
AL
S
H
EA
D
IN
F
EE
T
60Hz
20Hz
Model SFI3011D-1760-20 SFI Series
1760 RPM
March 15, 2020
Size 4 x 3 x 11 Motor/Drive 20 HP
Curves based on Clear Water @ 60F with a Specific Gravity of 1.0
Base-mounted end suction Pumps Model: SFI3011D
0 75 150 225 300 375 450 525 600 675 750
FLOW IN GALLONS PER MINUTE
L/SEC 5 10 15 20 25 30 35 40 45
0 0
5 50
10 100
15 150
20 200
25 250
30 300
H E
A D
IN
M
E T
E R
S
H E
A D
IN
K
IL
O
P A
S C
A
LS
H E
A D
IN
F
E E
T
120Hz
40Hz
114.50Hz
34.94Hz
Model SFI3011D-1760-20 SFI Series (Oe)
1760 RPM
March 15, 2020
Size: 4 x 3 x 11.00 Motor/Drive: 20 HP Design Power: 11.71 HP
Design Point: 310.00 gpm @ 110.00 ft Curves based on Water @ 60F with Specific Gravity of 1.0000.
Tag: Primary
310Flow Rate (GPM):
110Head (FT):
Water @ 60 FWorking Fluid:
74%Efficiency (%):
IronConstruction:
11.71Design Hp:
20.00Nol Hp:
20 hpMotor Hp:
6Npsh (Ft):
1760RPM:
11.00Imp Dia:
208/3/60Volt/Ph/Hz:
Notes:
301-2753-JSubmittal Data Information
SFI Series Pumps MODEL SFI3013-1760-25SUPERSEDES: NewEFFECTIVE: May 14, 2015
ENGINEER: ________________________________________________JOB: _______________________________________________________
REP: ______________________________________________________CONTRACTOR: ______________________________________________
ELEC. CHAR.H.P.HEAD/FTG.P.M.IMPELLER DIA.MODEL NO.ITEM NO.
PUMP/MOTOR _______________WEIGHT ________________
Dimensions - Inches (mm) Frame
HP Range
VUT575V460V208V
12.1 (308)9.5 (242)18.9 (480) Without bypass
B1 15 (11.0) - 25 (18.0)15 (11.0) - 25 (18.0)7.5 (5.5) - 15 (11.0)
15.9 (405)9.1 (231)41.8 (1061) With bypass
B1 15 (11.0) - 25 (18.0)15 (11.0) - 25 (18.0)7.5 (5.5) - 15 (11.0)
14.1 (359)12.1(308)26.9 (680) Without bypass
C1 50 (37.0) - 75 (55.0)50 (37.0) - 75 (55.0)25 (18.0) -…