M67001-20-Q-0010-00003 Amendment .pdf
PDF 120 KB Posted
- Attached to
- Parachute Loft and Boat Locker Support Services Federal contract opportunity
- Solicitation number
- M67001-20-Q-0010
- Issued by
- United States Marine Corps
About this file
This amendment to a solicitation provides answers to questions from offerors. The Marine Corps is soliciting proposals for parachute loft and boat locker support services at Camp Lejeune, as described in the attached performance work statement. The amendment clarifies that key functions refer to those tasks already listed in the PWS, and instructs offerors to use the instructions in FAR 52.212-2 when generating the required document outlining key functions. While certifications are no longer required to be submitted, offerors may submit them to demonstrate qualifications under the technical evaluation factor. Resumes do not need to be signed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| M67001-20-Q-0010-00004 Paraloft and Boat Locker Support Services Question and Answer Amendment 4.pdf | ||
| M67001-20-Q-0010-00002 Paraloft and Boat Locker Support Services.pdf | ||
| M67001-20-Q-0010 Paraloft and Boat Locker Amendment.pdf | ||
| DD254 DoD Contract Security Classification Specification Form .pdf | ||
| PAST PERFORMANCE QUESTIONNAIRE.doc | DOC document | |
| M67001-20-Q-0010 Paraloft and Boat Locker Support Services RFP.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTING DEPARTMENT
ATTN: TONY BENSON
P.O. BOX 8368 MCB
CAMP LEJEUNE NC 28547
M1200920SUYZCQP
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Reason for this amendment is to provide answ ers to questions from previous amendment.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 02-Apr-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X M6700120Q0010
X 9B. DATED (SEE ITEM 11)
11-Mar-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
02-Apr-2020
CODE
M67001
CONTRACTING DEPARTMENT
PO BOX 8368 (BLDG 1116)
CAMP LEJEUNE NC 28547-8368
M67001 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE M67001
FACILITY CODECODE
EMAIL:TEL:
M6700120Q0010
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been added by full text:
QUESTIONS AND ANSWERS
Questions and Answers clarifying from previous amendment.
1. Can you please provide additional details and explanation as to what a “key function” is? Are key functions not those tasks that are already listed in the PWS? Are you asking offerors to propose additional tasks that their personnel will perform, which are not currently listed in PWS?
Please refer to paragraph 7.0 of Performance Work Statement (PWS)
2. What are the instructions offeror are to utilize in generating this new document that outlines the key functions? What is the page limit for this document? What information is to be provided, etc.?
Please refer to “Instructions for Preparations of Quotes” listed in FAR clause 52.212-2, Evaluations
Commercial Item.
3. Does the requirement still exist for offerors to submit copies of proposed employees certifications, as well as the FAA Master Rigger licenses? If the answer is no, may offerors submit those is they desire to do so, in an effort to prove Evaluation Factor 1, that we will have qualified and certified personnel ready to commence work on day one of the contract?
Please refer to Technical Capability Sub factor C. “Submit a document outlining "key functions" that the personnel will be performing collectively that demonstrate experience and qualifications to perform the duties of this contract as stated in the PWS. All certifications and clearance information must be provided prior to the period of performance.”
4. May offerors submit signed resumes if they still desire to do so?
Signed resumes are not required.
(End of Summary of Changes)