M26-127 Nitrogen Generator Booster - SOW.pdf

PDF 200 KB Posted

Attached to
Nitrogen Generator Booster Federal contract opportunity
Solicitation number
FA812626Q0020
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

This is a Statement of Work (SOW) for the purchase and upgrade of a Nitrogen Generator Booster system at Tinker Air Force Base. The contract M26-127 is classified under PSC 4320 and NAICS 333999, prepared by OBCA on December 10, 2025.

The primary requirement is the delivery, disconnection, transportation, and upgrade of one Nitrogen Generator Booster unit (Serial Number 5407 H23494001) located in Building 2210, Room E7 at Tinker AFB in Oklahoma. The Contractor must accomplish delivery and upgrade work within five business days of initial delivery and provide notification to the Government Point of Contact five business days prior to installation beginning. The Contractor is responsible for all unit pickup and transportation, booster assembly replacement with a new fully compatible assembly meeting or exceeding original manufacturer specifications, piping work and fittings installation, and comprehensive performance testing including nitrogen purity, flow rate, pressure, leak, and operational run-time testing. All work must be performed by certified Generon technicians with expertise in nitrogen generation systems and high-pressure booster compressors. Work hours are Monday through Friday, 7:30 a.m. to 2:30 p.m., excluding federal holidays and base closures.

The Contractor must deliver updated engineering specification documents in electronic format, performance testing reports, warranty documentation for the new booster assembly, and shipping documentation upon completion. The SOW includes extensive requirements for environmental compliance, including RCRA training certification, proper wastewater discharge to permitted facilities with documentation provided within ten calendar days of contract award, spill reporting procedures, housekeeping standards, and hazardous waste management compliance. Additional requirements include FOD/DOP training certification for all personnel within ten business days of award, visitor pass coordination seven business days before arrival, compliance with safety and occupational health regulations, emergency procedures participation, and trafficking in persons awareness.

View the file

Other files for this federal contract opportunity

Other files attached to Nitrogen Generator Booster, newest first.
File Type Posted
FA812626Q0020 Nitrogen Generator Booster - CSS.pdf PDF
M26-127 Nitrogen Generator Booster - Item Description_Redacted.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

STATEMENT OF WORK

FOR

M26-127 Nitrogen Generator Booster

PSC: 4320

NAICS: 333999

Prepared by

OBCA

10 December 2025

PREAMBLE

Commander’s Safety Intent

The safety of everyone on Tinker AFB is our top priority. All Individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment. Everyone working on Tinker AFB is challenged to find, fix (if able) and report all hazards and near-misses. It is our shared duty to take every reasonable step and precaution to prevent accidents and preserve the health/safety of each Contractor and Government employee.

1 SCOPE. This Statement of Work (SOW) defines the effort required for the purchase of one

(1) each Nitrogen Generator Booster to include Delivery and Upgrade, in Building 2210, Room E7 at Tinker Air Force Base, OK.

1.1 The Contractor shall be responsible for ensuring all services, parts and Original Equipment Manufacturer (OEM) components provided under this contract are in accordance with (IAW) the terms and conditions outlined herein, conform to the manufacturer’s equipment specifications and the SOW.

2 REQUIREMENTS

2.1 General. Delivery and Upgrade shall be accomplished within five (5) business days of delivery. The Contractor shall provide to the Government Point of Contact (GPOC) the date that the Delivery and Upgrade will begin five (5) business days prior to installation beginning.

2.2 Item Description. 76 MXSG is requesting utilization of funds for the purchase Nitrogen Generator Booster upgrade. The requirement must have the following specifications:

• Contractor shall provide one (1) Nitrogen Generator Booster upgrade.

• Contractor shall provide Machine Disconnection and Removal for outbound service.

• Contractor shall provide transportation for both pickup and return.

• Contractor must meet all requirements outlined In Accordance with (IAW) this SOW.

2.3 Contractor Requirements:

• Unit Pickup and Transportation: Generon IGS will arrange and execute freight transportation for the Nitrogen Generator Unit from its current location to their designated facility. This includes proper packaging and securing of the unit for safe transport.

• Booster Assembly Replacement: Complete removal of the failed booster assembly and installation of a new, fully compatible, and performance-optimized booster assembly. The new assembly must meet or exceed the original manufacturer's specifications. Documentation (e.g., product data sheets and drawings) must be provided for the new assembly.

• Piping Work and Fittings: All necessary piping work, including fabrication, installation, and testing, to ensure proper integration of the new booster assembly within the existing Nitrogen Generator Unit framework. This includes utilizing compatible, high-quality fittings appropriate for the operating pressures and temperatures of the system.

• Engineering Specification Updates: Generon IGS will update all relevant engineering specification documents, including schematics, diagrams, and operating procedures, to reflect the changes made during the retrofit. These documents will be delivered in electronic format suitable for integration into existing maintenance documentation.

• Performance Testing and Validation: Upon completion of the retrofit, Generon IGS will conduct comprehensive performance testing to ensure the upgraded Nitrogen Generator Unit meets all required operational specifications. This testing will include, but not be limited to:

• Nitrogen purity testing

• Flow rate testing

• Pressure testing

• Leak testing

• Operational run-time testing Detailed test results and reports will be provided to Tinker personnel.

The nitrogen generator unit will be considered accepted upon successful completion of the following criteria:

• Fully upgraded and tested Nitrogen Generator Unit (Serial Number: 5407 H23494001)

• Updated engineering specification documents (electronic format)

• Performance testing report

• Warranty documentation for the new booster assembly (if applicable)

• Shipping Documentation

2.4 Contractor Qualifications:

• The Contractor shall provide certified Generon technician with nitrogen generation systems and high-pressure booster compressors upgrade. The Contractor shall be capability to perform precision piping, fittings, and system integration work in compliance with engineering requirements.

2.5 Hours of Operation: The Contractor shall perform the work required under this contract during the following days and hours: Monday through Friday, 7:30 – 2:30. If work hours are required outside the hours stated, the Contractor shall contact the Government POC for approval from the CO. Upon approval from the CO, the SME or GPOC escort Contractor personnel at all times.

2.5.1 These dates and hours exclude Federal Holidays, base closures due to inclement weather, and furlough days, as applicable.

3.0 Off-Site Discharges: For discharges outside of Tinker AFB, the Contractor shall ensure wastewater discharges, that may contain pollutants resulting from any contracted service, go to a state or federally permitted treatment facility such as a municipal Publicly Owned Treatment Works (POTW). The Contractor shall provide official correspondence ten (10) calendar days after contract award date to the COR from the POTW that states the POTW is permitted for all pollutants that the Contractor may discharge during the contracted service.

3.3.1 Spills: Upon occurrence of any spill that could enter the storm system or cause any harmful environmental effects, the Contractor shall immediately call 911 to report the incident. When possible, the Contractor shall use a base telephone to receive help from Tinker AFB 911. If using a cell phone, the Contractor shall request Tinker AFB 911. The Contractor shall immediately report all environmental violations to the COR and UEC. The Contractor shall provide five (5) copies of a typed or written report about the incident within four (4) clock hours as follows:

One (1) copy to CO, two (2) copies to the COR, a copy for UEC and one (1) copy for record. The format of the report shall be left up to the Contractor, but the report shall contain the following information:

1.) Name and contact number of person reporting the spill 2.) Date and time of incident 3.) Location and source of spill 4.) Substance or pollutant spilled 5.) Amount spilled and rate of discharge 6.) Any damages or injuries involved 7.) Extent of area impacted 8.) Potential hazards 9.) Actions taken 10.) Organizations contacted

11.) Remarks Section - that addresses the cause of the spill (e.g. human error, equipment, etc.)

and whether 911 was called and which agencies responded.

3.3.2 Environmental Training: Upon COR receipt of the “No Hazardous Waste Generation” certification, the requirements of this section no longer apply.

Contractor personnel performing duties in the service of this PWS shall have training that acquaints the person with the details of Resource Conservation Recovery Act (RCRA) regulations in 40 CFR 260 through 279; applicable State Laws and regulations; DoD, Air Force and local requirements. This training can be obtained through creditable training institutions or companies. All training shall be approved by 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). RCRA training is available at http://www.natlenvtrainers.com/RCRA-hazardous-waste.htm; http://www.skillsoft.com/catalog/detail.asp?CourseCode=esh_sah_a34_sh_enus000000 and http://www.lion.com/Storing-Hazardous-Waste-for-LQGs at the Contractor’s expense. Prior to obtaining training, the Contractor shall provide the name of the training institution or company and course description to the COR for approval within ten (10) calendar days after contract award date. Once written approval is received from the COR, the Contractor shall provide the environmental training certificates for employees performing duties in the service of this PWS to the COR, within thirty (30) calendar days after contract award date. In addition to the required environmental training, Contractors shall be compliant with Tinker AFB procedures per TAFB HWMP, “Hazardous Waste Management”.

3.2 Reserved

3.3 Housekeeping: The Contractor shall keep the work areas clean and neat IAW industry standards, OSHA, fire and safety standards, and this SOW.

3.4 Foreign Object Damage (FOD) and Dropped Object Prevention: Contractor personnel who work in or travel though areas near operational and production aircraft, engines, munitions, missiles, drones, space systems, support equipment, Aerospace Ground Equipment (AGE), trainers, and the Contactor personnel operating vehicles and equipment on flight lines, runways, taxiways, parking ramps, and in aircraft hangers and maintenance areas are required to receive the FOD/DOP training and to comply with AFI 36-2650, AFMC Supplement 1, paragraph 9.2., and A4.4.4. (Initial)/A4.4.5. (Refresher). The Contractor and Contractor personnel shall acknowledge the FOD/DOP training either by viewing the Digital Versatile Disc (DVD) provided by the GPOC or the You Tube site, http://www.youtube.com/watch?v=tYcbodjFPnM.

http://www.natlenvtrainers.com/RCRA-hazardous-waste.htm http://www.natlenvtrainers.com/RCRA-hazardous-waste.htm http://www.skillsoft.com/catalog/detail.asp?CourseCode=esh_sah_a34_sh_enus000000 http://www.lion.com/Storing-Hazardous-Waste-for-LQGs

3.4.1 The Contract Manager shall provide written certification to the GPOC for each employee within ten (10) business days after the contract award date. The certification shall have the title of the training, the name of the person who received the training, and the date of the training. The Contractor shall also ensure all new employees view the FOD/DOP training and provide written certification of training to the GPOC prior to the employees starting work in the OC-ALC shops. Every 36 Months, the Contractor and Contractor personnel shall be required to review the FOD/DOP training and to provide written certification to the GPOC.

3.5 Tool Control and Accountability: N/A (if applicable)

3.6 Privately Owned Motor Vehicles (POV): Contractor personnel shall comply with the directives pertaining to operation of POVs on Tinker AFB per AFMAN 31-116, in its entirety, “Motor Vehicle Traffic Supervision”. The Contractor shall comply with Tinker AFBI 24-302, in its entirety for the operation of POVs within Tinker AFB.

3.7 Visitors Pass: The Contractor shall contact the Government POC seven (7) business days before arriving on Tinker AFB in order to make arrangements for Visitors Passes. The Government POC will assign a sponsor for the Contractor from within the organization. The Contractor and the sponsor shall arrange to meet at Pass and Registration, Building 6611 at the Tinker Gate, which is South of I-40 off Air Depot Blvd. The Contractor shall provide two (2) forms of identification, one of which shall be a picture ID, to the 72 SFS. The 72 SFS will provide an AF Form 75, Visitors Pass, which will be valid for up to thirty (30) calendar days.

3.8 Foreign Nationals: The Contractor shall notify the Government POC before sending a Foreign National representative to perform services. Special rules apply for foreign nationals visiting a US Government facility.

3.9 Safety and Health on Government Installations: While performing work under this contract on a Government installation, the Contractor shall comply with federal, state and local regulations, and AFI 91-203, “Air Force Consolidated Occupational Safety Instruction”, as established by this contract and Appendix C. The Contractor shall notify the CO, Government POC, and Government Contract Administrator (CA) within one (1) business day of any injuries that occur to Contractor personnel while they are on the installation. The Contractor shall notify the CO, Government POC, and Government CA within one (1) business day of damage to Government property or equipment during the execution of the contract.

3.10 Combating Trafficking in Persons: IAW DFARS PGI 222.17, the COR shall pursue, as appropriate, the following methods of monitoring the Contractor’s performance regarding trafficking in persons such that non-compliances with FAR clause 52.222-50 are brought to the immediate attention of the Contracting Officer:

a. Keep the lines of communication open with the Contractor. At the post-award conference, remind the Contractor of his contractual responsibilities to notify the government if the Contractor receives notification of any alleged violations to this policy or if actions have been taken against the Contractor employees, subcontractor’s or subcontractor employees pursuant to the clause.

b. When appropriate, encourage Contractor to complete Human Trafficking Awareness Training.

c. Encourage the Contractor to take steps to investigate and eliminate slavery and human trafficking in their supply chains and to publish information for consumer awareness.

d. Periodically access the Department of State’s Trafficking in Person (TIP) website for updates and to view the latest reports. http://www.state.gov/g/tip

3.11 Commanders Safety Intent: The safety of everyone on Tinker AFB is our top priority. All Individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment. Everyone working on Tinker AFB is challenged to find, fix (if able) and report all hazards and near-misses. It is our shared duty to take every reasonable step and precautions to prevent accidents and preserve the health/safety of each Contractor and government employee.

3.12 Speak up for safety: Safety surety is an integral part of our overall goal of establishing a world class safety and health program. Our “Speak Out for Safety” initiative ensures a partnership with Contractors and government employees to further enhance safety to ensure we are looking out for all our partners and empowers all employees to actively participate in each other’s safety.

A safe workplace is everyone's business. As part of the contract team, military, civilian and Contractor personnel are empowered to Speak Out for Safety (S.O.S.) when they observe an unsafe act. Events that present imminent danger to personnel or catastrophic damage to property we empower our employees to intercede to ensure continued safe operations.

3.13 Communicating Hazards Of Workplace (CHOW): Contractor’s onsite representative communicates all hazards being introduced to the worksite by the Contractor. This is accomplished prior to commencement of work and refreshed daily during performance, IAW Contractor’s Site Safety Plan.

3.14 Emergency Procedures: The Contractor personnel shall follow the direction of the Government personnel regarding emergency procedures, such as fire, tornado, active shooter, bomb threats, or other emergency. It is the responsibility of the Contractor to provide guidance and to establish procedures for its employees to respond to an emergency. It is the Contractor’s responsibility to account for their employees following an emergency evacuation. The Contractor personnel shall participate with the Government personnel in all fire and tornado drills at no additional cost to the Government.

http://www.state.gov/g/tip

2 REQUIREMENTS
3.4 Foreign Object Damage (FOD) and Dropped Object Prevention: Contractor personnel who work in or travel though areas near operational and production aircraft, engines, munitions, missiles, drones, space systems, support equipment, Aerospace Ground E...
3.4.1 The Contract Manager shall provide written certification to the GPOC for each employee within ten (10) business days after the contract award date. The certification shall have the title of the training, the name of the person who received the ...