This is a Justification for Other than Full and Open Competition (JOFOC) dated February 26, 2025, for DLA Document Services to issue a 2-month extension contract (April 1, 2025 - May 30, 2025) with 2 option months (June 1, 2025 - July 30, 2025) for continued services under contracts SP7000-20-F-0097 and SP7000-20-F-0101.
The requirement covers leased multi-functional devices (MFDs) with full service maintenance and consumable supplies (excluding paper) for OCONUS operations. Specifically, SP7000-20-F-0097 procured 22 devices and SP7000-20-F-0101 procured 4 devices. The sole source justification cites FAR 13.106-1(b) as Fuji Film is the only vendor capable of continuing the lease of the existing equipment, as they retain title/ownership of the devices. The extension is needed to maintain uninterrupted support until replacement devices are delivered under Japan IDIQ. No public notice is required per FAR 5.101(a)(1), and market research indicates an adequate competition pool exists for future requirements of this type.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEFENSE LOGISTICS AGENCY
, A
Date
Justification for Other than Full and Open Competition IAW FAR .
1. Nature and/or description of the action being approved:
2. A description of the supplies or services required to meet the agency’s needs (including the estimated value):
3. An identification of the statutory authority permitting other than full and open competition:
4. A demonstration that the proposed contractor’s unique qualifications or the nature of the acquisition requires use of the authority cited:
5. A description of efforts made to ensure that offers are solicited from as many potential sources as is practicable, including whether a notice was or will be publicized as required by Subpart 5.2 and, if not, which exception under 5.202 applies:
6. A description of the market research conducted (see Part 10) and the results or a statement of the reason market research was not conducted:
7. Any other facts supporting the use of other than full and open competition, such as:
Explanation of why technical data packages, specifications, engineering descriptions, statements of work, or purchase descriptions suitable for full and open competition have not been developed or are not available.
When 6.302-1 is cited for follow-on acquisitions as described in 6.302-1(a)(2)(ii), an estimate of the cost to the Government that would be duplicated and how the estimate was derived.
• Include a copy of the previous justification.
• The approval authority shall determine whether the planned actions were completed. If the actions were not completed, the justification for the follow-on acquisition shall be approved by the approval authority one-level above the approval authority for the previous justification (see FAR 6.304). If the previous justification was approved by the Senior Procurement Executive (SPE), the approval remains at the SPE level. DFARS PGI
206.304 (a)(s-70)(ii)
When 6.302-2 is cited, data, estimated cost, or other rationale as to the extent and nature of the harm to the Government.
8. A listing of the sources, if any, that expressed, in writing, an interest in the acquisition (Include the results of the request for information or the sources sought notification in accordance with DFARS PGI 206.302-1 or include the waiver from the HCA or designee):
9. A statement of the actions, if any, the agency may take to remove or overcome any barriers to competition before any subsequent acquisition for the supplies or services required:
I certify that any supporting data that is the responsibility of technical or requirements personnel and which form a basis for the justification are complete and accurate.
Technical Personnel
Approval:
The justification, as presented above, is accurate and complete to the best of my knowledge and belief. Additionally, I have determined that the anticipated cost to the Government will be fair and reasonable.
Contracting Officer
Competition Advocate (Above $ K )
Head of the Procuring Activity (Above $1 .5 million but not exceeding $ million)
Senior Procurement Executive (Above $ million and as required by DFARS PGI 20 0 ( ))