Am_0006.pdf
PDF 44 KB Posted
- Solicitation number
- LPV52A-09-H-0037
About this file
Am_0006 to LPV52A-09-H-0037
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Am_0005.pdf | ||
| Am_0004.pdf | ||
| Am_0003.pdf | ||
| Am_0002.pdf | ||
| Am_0001.pdf | ||
| LPV52A-09-H-0037.pdf | ||
| Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION ( Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
1 3
0006 Dec 3, 2009 LPV 05.2a
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
LPV52A-09-H-0037
Nov 9, 2009
The above numbered solicitation for LPV 05.2a, Lake Pontchartrain And Vicinity, Louisiana Project, North Of Airline Hwy., St. Charles Parish, Levee – Reach 2A Shell Pipeline To Goodhope And Shell Pipeline Floodwall Replacement – Phase 2, is hereby amended as follows:
Delete pages 00010-3 thru 00010-4 and replace with attached pages 00010-3 thru 00010-4.
PROPOSAL DUE DATE
Proposal due date of 9 December 2009, 2:00 PM CST remains unchanged.
00010-3 ED 09-037
SECTION 00010 – TASK ORDER BIDDING SCHEDULE
Lake Pontchartrain And Vicinity, Louisiana Project, North Of Airline Highway, St. Charles Parish, Levee – Reach 2A Shell Pipeline To Goodhope And Shell Pipeline Floodwall Replacement – Phase 2, LPV – 05.2A
Item
DESCRIPTION
Estimated Quantity
Unit
Unit Price
Estimated Amount
Mobilization and Demobilization 1 LS
0002 Utilities 1 LS
Traffic Control and Coordination 1 LS
0004 Truck Wash-Down Rack 1 LS
0005 Demolition 1 LS
Reinforced Bridge Approach Slab (9”)
1 LS
0007 Separator Geotextile 10,100 SY
0008 Reinforcement Geotextile 26,500 SY
0009 Clearing and Grubbing 1 LS
0010 Degrading Existing Levees 66,000 CY
Embankment, Compacted Fill
190,000 CY
0012 Uncompacted Fill 5,380 CY
0013 Sand Fill 14,800 CY
Piling, Concrete Precast, Prestressed (16" x16")
1,978 LF
0015** Road Surfacing 2,200 CY
Chain Link Fences and Gates 1 LS
0017 Precast Concrete Bridge 1 LS
0018 Seeding and Mulching 38 AC
Lime Soil Amendment (Optional)
38 TON
Sulfur Soil Amendment (Optional)
19 TON
0021 Fertilizer
00010-4 ED 09-037
0021AA First 2,300 LBS 2,300 LBS
0021AB All Over 2,300 LBS 1,700 LBS
0022 Guard Rail 352 LF
0023 Temporary Access Ramps 1 LS
**Denotes Change from previous bidding schedule
TOTAL: $
Award will be made as a whole to one bidder.
NOTE 1: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED TOTAL OR ESTIMATED AMOUNT FOR ANY ITEM, ITS BID SHALL
BE DECLARED NON-RESPONSIVE AND THEREFORE INELIGIBLE FOR AWARD.
NOTE 2: Any bid may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only total price of bid, but the price for individual line items as well. Any bid may be rejected if the prices for any line items or sub line items are materially unbalanced (See
FAR 14.404-2).
NOTE 3: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within seven (7) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Program, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.
NOTE 4: OPTIONAL ITEMS. The Government may require the delivery of the numbered line item(s), identified in the schedule as optional items, in the quantities and prices stated in the schedule. The Contracting Officer may exercise the options by written notice to the Contractor. Bidders shall bid on all items including optional items (see “Evaluation of Options” FAR 52.217-5). Failure to bid on all items will result in a non-responsive bid.
NOTE 5: EVALUATION OF OPTIONS (FAR 52.217-5 JUL 1990). The Government will evaluate offers for award purposes by adding the total price for all options to the total price for this basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
NOTE 6: RAPID VENDOR PAYMENT: Web based instructions for the submission of invoices;