This is a Request for Quotation document issued by the West Virginia Department of Health and Human Resources for construction services. The project involves the replacement of the existing roofing system at The Logan Mingo Mental Health Facility located at Route 10 Three Mile Curve, Logan, West Virginia 25601. The scope of work includes removal of existing ballasted roof and asbestos-containing materials, installation of approximately 19,700 square feet of fully adhered EPDM roofing system with tapered polyisocyanurate insulation, installation of approximately 50 protective EPDM pads around rooftop HVAC equipment, installation of Kynar finish coping and edge metals, flashing of all curbs and penetrations, and replacement of approximately 1,000 ceiling tiles. The contract will be awarded to the lowest qualified responsible bidder. Vendors must possess a valid West Virginia Contractors License and demonstrate successful completion of at least five similar projects through references or documented experience. Standard work hours are Monday through Friday from 7:00 a.m. to 4:00 p.m., excluding state-recognized holidays.
The contractor shall furnish all labor, materials, equipment, and incidental work necessary to complete the construction services, including procurement of all required permits and licenses in compliance with applicable federal, state, and local regulations. The contractor is responsible for verifying actual roof measurements prior to installation and for identifying and properly documenting the disposal of asbestos-containing materials in accordance with applicable laws. Upon completion, the contractor must provide a 20-year manufacturer's warranty for all labor and materials and participate in final inspection with the Agency's project manager. The contract specifications take precedence over project plans, and any substitution requests must be submitted during the official question and answer period with supporting product documentation.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUOTATION
[Construction Services being sought]
GENERAL CONSTRUCTION SPECIFICATIONS ARFQ BHS17*8
1. PURPOSE AND SCOPE: The West Virginia Department of Health and Human Resources is soliciting bids to establish a contract for the following: One-time purchase to provide all labor, materials, equipment, and anything incidental to replace the existing roofing system with a fully adhered membrane roofing system located at The Logan Mingo Mental Health Facility located at Route 10 Three Mile Curve, Logan WV 25601.
The Vendor shall furnish all materials, labor, and equipment necessary to complete all Construction Services. The Vendor shall furnish any incidental work, materials, labor, and equipment that are necessary to complete the Construction Services, even if such incidental work is not explicitly included in the Project Plans.
2. DEFINITIONS: The terms listed below shall have the meanings assigned to them below. Additional definitions can be found in section 2 of the General Terms and Conditions and in the Project Plans as defined below.
2.1 “Construction Services” means replacement of existing ballasted roof with a fully adhered EPDM roofing system as more fully described in the Project Plans.
2.2 “Pricing Page” means the pages contained in wvOASIS, attached hereto as Exhibit A, or included in the Project Plans upon which Vendor should list its proposed price for the Construction Services.
2.3 “Solicitation” means the official notice of an opportunity to supply the State with Construction Services.
2.4 “Project Plans” means documents developed by an architect, an engineer, the Agency, or another design professional, which are attached hereto as Exhibit B, that provide detailed instructions on how the Construction Services are to be performed. In the event that Project Plans contain drawings or other documents too large to attach in Exhibit B, Vendors can obtain copies in accordance with Section 9 of these Specifications.
3. ORDER OF PRECEDENCE: This General Construction Specifications document will have priority over, and supersede, anything contained in the Project Plans.
4. QUALIFICATIONS: Vendor, or Vendor’s staff if requirements are inherently limited to individuals rather than corporate entities, shall have the following minimum qualifications:
4.1. Experience: Vendor, or Vendor’s supervisory staff assigned to this project, must have successfully completed at least five (5) projects that involved work similar to that described in these specifications or the Project Plans. Compliance with this experience requirement will be determined prior to contract award by the State through references provided by the Vendor upon request, through knowledge or documentation of the Vendor’s past projects, through confirmation of experience requirements from the architect assisting the State in this project, or some other method that the State determines to be acceptable. Vendor must provide any documentation requested by the State to assist in confirmation of compliance with this provision. References, documentation, or other information to confirm compliance with this experience requirement may be requested after bid opening and prior to contract award.
4.2. Valid West Virginia Contractors License
5. CONTRACT AWARD: The Contract is intended to provide Agency with a purchase price for the Construction Services. The Contract will be awarded to the lowest qualified responsible bidder meeting the required specifications. If the Pricing Pages contain alternates/add-ons, the Contract will be awarded based on the grand total of the base bid and any alternates/add-ons selected.
6. SELECTION OF ALTERNATES: If the Pricing Pages contain alternates/add-ons, the alternates/add-ons will be selected as follows. The alternate/add-on will be selected in the order of priority listed on the Pricing Pages. The first alternate/add-on must be selected before the second alternate/add-on can be selected and so on.
7. PERFORMANCE: Vendor shall perform the Construction Services in accordance with this document and the Project Plans.
8. SUBSTITUTIONS: Any substitution requests must be submitted in accordance with the official question and answer period described in the INSTRUCTIONS TO VENDORS SUBMITTING BIDS, Paragraph 4. Vendor Question Deadline. Vendors submitting substitution requests should submit product brochures and product specifications during the official question and answer period.
9. PROJECT PLANS: The checked box will apply to Project Plans for this solicitation.
No Additional Project Plan Documents: There are no additional Project Plans other than those attached hereto as Exhibit B or any subsequent addenda modifying Exhibit B.
□ Additional Project Plan Documents: There are additional Project Plan documents other than those attached as Exhibit B. Copies of the additional Project Plan documents not attached as Exhibit B can be obtained by contacting the entity identified below.
10. CONDITIONS OF THE WORK
10.1. Permits: The Vendor shall procure all necessary permits and licenses to comply with all applicable Federal, State, or Local laws, regulations and ordinances of any regulating body.
10.2. Existing Conditions: If discrepancies are discovered between the existing conditions and those noted in the specifications, Vendor must immediately notify the Agency's representative. Vendor must also immediately notify the Agency if suspected hazardous materials are encountered.
10.3. Standard Work Hours: The standard hours of work for this Contract will be Monday through Friday 7:00am – 4:00pm excluding holidays recognized by the State of West Virginia. Any work outside of the standard hours of work must be approved in advance at the Agency’s sole discretion. Authorization of work outside of the standard hours of work will not entitle Vendor to additional compensation.
10.4. Project Closeout: Project Closeout shall include the following:
10.4.1. Final Cleanup: Vendor shall perform the final cleanup activities listed below, along with any other final cleanup activities normally associated with the work performed under this Contract, prior to final inspection:
10.4.1.1. Vendor shall remove all debris associated with the replacement process as well as repair any damage to the surrounding grounds/grass/pavement due to the replacement of the roof
10.4.2. Final Inspection: Vendor shall participate in a final inspection with the Agency’s project manager. The purpose of the final inspection will be to identify deficiencies that need to be remedied prior to Agency’s final acceptance of the work. Vendor shall at all times be obligated to perform in accordance with the Contract and must take all actions necessary to ensure that work complies with requirements of Contract prior to final acceptance. Final acceptance does not waive or release Vendor from its obligation to ensure that work complies with the Contract requirements. Vendor shall submit any warranty documents to the Agency project manager at final inspection.
11.2 11.3 11.4
11. FACILITIES ACCESS: Performance of Contract Services may require access cards and/or keys to gain entrance to Agency’s facilities. In the event that access cards and/or keys are required:
8.
9.
10.
11.
12.
11.1. Vendor must identify principal service personnel which will be issued access cards and/or keys to perform service.
11.2. Vendor will be responsible for controlling cards and keys and will pay replacement fee, if the cards or keys become lost or stolen.
11.3. Vendor shall notify Agency immediately of any lost, stolen, or missing card or key.
11.4. Anyone performing under this Contract will be subject to Agency’s security protocol and procedures.
11.5. Vendor shall inform all staff of Agency’s security protocol and procedures.
12. MISCELLANEOUS:
12.1. Contract Manager: During its performance of this Contract, Vendor must designate and maintain a primary contract manager responsible for overseeing Vendor’s responsibilities under this Contract. The Contract manager must be available during normal business hours to address any customer service or other issues related to this Contract. Vendor should list its Contract manager and his or her contact information below.
Contract Manager: _________________________________________________
Telephone Number: ________________________________________________
Fax Number: ______________________________________________________
Email Address: ____________________________________________________
EXHIBIT A – Pricing Page
EXHIBIT B – PROJECT PLANS
1. Contactor shall remove any existing ballast rock and dispose of off-site adhering to any local, state and federal law.
2. Contractor shall remove existing roofing system down to metal decking on approximately 19,700 square feet of roofing. All measurements on roof size and additional components are estimates only. Vendor will be responsible for verifying measurements prior to installation and actual needs will be provided, whether it is greater or less than stated.
3. Contractor shall be responsible for the removal and proper disposal of all asbestos containing material per attached survey. Contractor shall provide written documentation to the owner regarding the proper disposal and shall ensure that all local, state and federal laws regarding asbestos abatement are followed.
4. Contractor shall mechanically fasten a minimum of 2.5” Polyisocyanurate, or equal insulation. 1/4” slope per foot, fully tapered insulation to the entire roof area. Average R-Value of tapered insulation shall be R-25 at a minimum. Add wood blocking as necessary at perimeters to maintain constant perimeter edge height equal to or above the maximum height of tapered insulation. Insulation shall have a Long Term Thermal Resistance (LTTR) Value 12.1 or better.
5. Contractor shall install a Carlisle, or equal .060 fully adhered Ethylene Propylene Diene Monomer (EPDM) rubber roof system over new insulation.
6. Contractor shall install approximately fifty (50) 30” x 30” EPDM Pads around existing rooftop HVAC equipment to protect roof from foot traffic due to maintenance of equipment. Location of equipment pads shall be determined by Maintenance Director.
7. Contractor shall furnish and install 0.040” Kynar, or equal finish coping and edge metals across roof edges.
8. Contractor shall flash all curbs and penetrations as well as counterflashing at all existing curbs
9. Contractor shall, upon completion, furnish a written 20 year manufacturer’s warranty for all labor and material.
10. Contractor shall replace approximately one thousand ceiling tiles that have been identified by the owner. Ceiling tiles shall be recessed in style and 2’x2’ in size USG 707 2x2 Reveal Edge White 32 SF CTN, or equal.
Revised 10/13/2016