Lima Armory Plaster SOW.pdf
PDF 664 KB Posted
- Solicitation number
- SRC0000027898
- Issued by
- Allen County, Ohio
About this file
This Statement of Work from the Ohio National Guard outlines requirements for repairing and painting deteriorating plaster areas of the drill floor walls and ceiling at the Lima Armory located at 855 S. Collet St. in Lima, Ohio. The scope requires the contractor to furnish all labor, materials, supplies, tools, equipment, utilities, and other necessary means to complete the work, including scaffolding or lifts for high areas. The work involves sand scraping and cleaning loose plaster and paint areas, patching plaster to blend with surrounding areas, and repainting with one coat of primer and two coats of Sherwin Williams Pro Mar 200 or equal product (sprayed or rolled application, not brushed).
The accompanying photos show the current condition of the facility's interior, featuring brick walls with deteriorating plaster areas above, arched windows, and a curved ceiling. The contractor must provide a dumpster for debris removal and is responsible for daily cleanup and final restoration of the area to safe, normal operating conditions. The project requires coordination with Project Officer Kerry Hawke, and invoices must be submitted on company letterhead to a specified email address, with the State of Ohio's tax exempt status noted. Pricing terms and specific funding amounts are not detailed in the document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
REPAIRING AND PAINTING OF DRILL FLOOR WALLS AND
CEILING AREAS
SW-1 SCOPE
Contractor will furnish all labor, materials, supplies, tools, equipment, utilities, and other means necessary or proper for performing and completing the repairing and painting of the deteriorating plaster areas of the drill floor walls, and a potion of the ceiling area. (including any scaffolding or lift needed for high work.)
SW-2 SITE OF WORK
Ohio National Guard (Lima Armory)
855 S. Collet St.
Lima, Ohio 45804 (Allen County)
SW-3 WORK TO BE ACCOMPLISHED
The work to be accomplished includes, but is not limited to the following items listed below:
3.1 3.1.1
3.1.2 After patching plaster, repaint all areas to blend in with one coat (1) of primer and two (2) coats of Sherwin Wiliams, Pro Mar 200 or equal. (sprayed or rolled- not brushed on)
3.1.3 Patch any plaster as needed, so it blends in with surrounding areas.
3.1.4 Contractor to provide the a dumpster for the proper debris generated.
SW-4 POINT OF CONTACT
4.1 Kerry Hawke Office-614-336-6979 Cell-614-307-1825
Sand scrape and clean any loose plaster and paint areas on walls and ceilings.
kerry.g.hawke.nfg@army.mil
SW-5-INVOICING
Invoices: All invoices should be submitted on vendors company letterhead or standard invoice document to include vendors. name, address, remit to address if different from main office, invoice date, invoice number, itemized description of goods delivered, or services performed to include pricing less any tax. (The State of Ohio is Tax exempt)
Submitting Invoices: All invoices should be submitted using one of the methods listed below.
Preferred method: Email Invoices to ng.oh.oharng.mbx.invoices-dimr@mail.mil
SW-6 PERFORMANCES
6.1 Submittal of a Bid by a Contractor shall be accepted as prime fade evidence that he has examined the Specifications and the Job Site and has satisfied •himself as to the nature and location of the work and all matters which can in any way affect the work or cost thereof, under the contract. Any failure of the Contactor to acquaint himself with all available information, including physical survey of the proposed work, will not relieve him from successfully performing all work to be done for a complete and acceptable job
6.2 The above brief outline of principle features of work in no way limits the responsibility of the Contractor to perform all work and furnish all labor and materials required by the
Specifications referred herein. Any omission from the Specifications, or misdescriptions thereof, shall not relieve the Contractor from performing all work required, and furnishing the materials required to completely fulfill the intent of the Contract
6.3 The Contractor shall confine operations at the site of areas permitted by the Project
Officer. He shall not unreasonably encumber the site with materials or equipment and shall assume full responsibility for the protection and safekeeping of products that interfere with the operation of the facility and, if necessary, obtain and pay for additional storage areas.
6.4 At the completion of each working day, the Contractor shall clean and clear away any excess supplies and debris from site.
Upon completion and before the final acceptance of the work, the Contractor is responsible for the removal of all material rubbish. All property shall be restored to safe, normal operating conditions. The area shall be in a neat, clean, presentable condition satisfactory to the Project Officer.