Lighting_Upgrades_at_Denver_Union_Station_and_Civic_Center_Parking_Garage.pdf
PDF 276 KB Posted
- Solicitation number
- IFB-326DM017
- Issued by
- Denver County, Denver City, Colorado
About this file
This Invitation for Bid (IFB-326DM017) is issued by the Regional Transportation District (RTD) in Denver, Colorado, for lighting upgrades at two facilities: Denver Union Station Light Rail Plaza and Civic Center Parking Garage. The project involves LED lamp replacements at Denver Union Station and installation of LED retrofit kits for existing fluorescent fixtures along with new linear LED fixtures at Civic Center Parking Garage. The contractor must provide all necessary labor, materials, equipment, supervision, permits, and insurance to complete the work as specified in the construction drawings and technical specifications. The pre-bid briefing is scheduled for November 18, 2026, at 10:00 a.m. at Civic Center Plaza (non-mandatory). The inquiry period closes November 26, 2026, at 2:00 p.m., with RTD providing responses to questions by November 30, 2026, at 2:00 p.m. Bids are due electronically through RTD's online procurement portal by 2:00 p.m. on December 7, 2026. RTD anticipates making the final selection by December 14, 2026. The contract period of performance is three months from the effective date or notice to proceed, with potential option periods available. The pricing form specifies line items for both locations, including LED lamps, replacement fixtures, cable extensions, and EMT conduit with conductors, with quantities ranging from 5 to 114 units depending on the line item.
Bids must be submitted on a fixed-price basis and will be evaluated based on price and other factors outlined in the IFB, with the bidder's proposed schedule serving as the primary mechanism to evaluate project understanding. Bid security of five percent of the bid amount is required in the form of a bid bond, cashier's check, certified check, or cash. RTD has not established a Small Business Enterprise (SBE) participation goal; however, the agency encourages bidders to document efforts to include SBEs through subcontracting, mentoring, joint ventures, and teaming arrangements. The apparent low bidder must submit a Schedule of Values within 72 hours of bid opening detailing unit determinations, material and labor costs, overhead, profit, and mobilization charges. All bids must remain valid for a minimum of 90 days from the bid due date. The contractor must perform at least 51 percent of the total work with its own staff. RTD reserves the right to reject all bids and re-solicit or cancel the IFB if deemed in its best interest. Responses must be submitted electronically through OpenGov's online procurement portal at https://procurement.opengov.com/portal/rtd-denver, and contact information for inquiries is provided by Marla Bainbridge, Procurement Specialist, at marla.bainbridge@rtd-denver.com or (303) 299-2411.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Regional Transportation District
Contracting and Procurement
1660 Blake St.
Denver, CO 80202
Invitation for Bid
IFB-326DM017
LIGHTING UPGRADES AT DENVER UNION STATION AND CIVIC CENTER PARKING
GARAGE
November 9, 2026
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://procurement.opengov.com/portal/rtd-denver https://procurement.opengov.com/portal/rtd-denver
Regional Transportation District
INVITATION FOR BID
Lighting Upgrades at Denver Union Station and Civic Center Parking Garage
Sections
1. INTRODUCTION
2. INSTRUCTIONS TO BIDDERS
3. GENERAL INSTRUCTIONS
4. BIDS
5. AWARD PROCESS
6. LEGAL NOTICE TO BIDDERS
7. BID CONTENTS CHECKLIST (FORMS TO BE SUBMITTED)
8. PRICING FORM
9. SCOPE OF WORK SERVICES/TECHNICAL SPECIFICATIONS
Attachments:
A - SOW-1
B - 326DM017 Drawings - Denver Union Station
C - 326DM017 Specs - Denver Union Station
D - 326DM017 - Form of Contract
E - 326DM017 Drawings - Civic Center
F - 326DM017 Specs - Civic Center
IFB-326DM017 - Lighting Upgrades at Denver Union Station and Civic Center Parking Garage
1. INTRODUCTION
RTD is seeking responses from qualified respondents to provide: Lighting Upgrades at
Denver Union Station and Civic Center Parking Garage
1.1. Summary
RTD is seeking Lighting Upgrades involving LED lamp replacements at Denver Union
Station Light Rail Plaza. Project scope also involves installation of LED retrofit kits for existing fluorescent light fixtures along with new linear LED fixtures at the Civic Center
Parking Garage. The Contractor shall furnish all necessary labor, materials, equipment, supervision, permits and insurance necessary to make the modifications as shown in the construction drawings and specification package.
1.2. Contact Information
Marla Bainbridge
Procurement Specialist
Email: marla.bainbridge@rtd-denver.com
Phone: (303) 299-2411
Department:
Capital Programs-Engineering
1.3. Timeline
IFB advertised and made available to prospective bidders.
November 9, 2026
Pre-bid briefing (Non-
Mandatory)
November 18, 2026, 10:00am
Civic Center - 1560 Broadway, Denver, CO
80202
(meeting place will be at the main lobby area of Civic Center Plaza)
Inquiry Period: Written questions from prospective bidders are to be received in the online procurement portal.
November 26, 2026, 2:00pm mailto:marla.bainbridge@rtd-denver.com tel:(303)299-2411
RTD sends responses to written questions, if any, to all prospective bidders through
RTD’s online procurement portal.
November 30, 2026, 2:00pm
Bids due: Bids must be received through RTD’s online procurement portal.
December 7, 2026, 2:00pm
RTD anticipates making final selection.
December 14, 2026
2. INSTRUCTIONS TO BIDDERS
2.1. Work
RTD will accept bids from qualified companies until 2:00 pm on Monday, December 7, 2026 via RTD's online procurement portal, OpenGov. This Invitation for Bid (“IFB”) is for Lighting Upgrades at Denver Union Station and Civic Center Parking Garage, per the enclosed specifications and requirements.
2.2. Cost Type
Payments are anticipated to be made on a Fixed Price basis.
2.3. Award of Contract
The Contract shall be awarded to the responsible bidder whose bid is responsive to the
IFB and is most advantageous to RTD, considering price and the factors as may be set out in the IFB.
2.4. Period of Performance
Subject to the Termination provision of the Contract, performance shall commence as of the Effective Date (or in the event that RTD provides a Notice to Proceed to the
Contractor, the Period of Performance shall commence on the date of the Notice to
Proceed) and shall continue for 3 months (subject to the exercise of any option periods).
2.5. Small Business Requirement for Contracts with No SBE Goal
RTD has not specified an SBE participation goal for the Work to be performed under the
Contract. However, RTD encourages and expects bidders to pursue subcontracting, mentoring, joint venturing, teaming and partnering opportunities with SBE firms in the ordinary course of its business/teaming strategies. Bidders are encouraged and expected to create a level playing field to the maximum practicable extent consistent with the objectives and requirements of the RTD SBE program based on federal regulations codified at 49 CFR Part 26 and RTD’s SBE Program Policy. Therefore, bidders are requested to document their efforts to include SBEs in this contracting opportunity, if any. Bidders are also requested to explain in their executive summary how they intend to utilize and/or will encourage subcontracting, mentoring, joint venturing and/or partnering opportunities with SBEs for this project. Furthermore, bidders are to submit a general workforce breakdown for their company (including affiliates) and the project. RTD is interested in your strategies and approach to seeking diversity in the bidder team to include SBEs in all phases of subcontracting, supplier and workforce opportunities associated with the Contract. RTD is an equal opportunity employer and also operates a successful Small Business Opportunity Office. Therefore, RTD expects bidders to demonstrate the same meaningful level of commitment to diversity from businesses that participate in RTD’s procurement process.
2.6. Bid Validity Period
Bids shall be valid for a duration of no less than ninety (90) days from bid due date.
Bids that are late will not be accepted!
3. GENERAL INSTRUCTIONS
3.1. General
Each Bidder is solely responsible for submitting any necessary forms and certifications that may be required by the IFB. Enclosed is a copy of the Contract contemplated for award substantially in the form to be executed.
A list of all holders (“followers”) of the IFB is available for view and/or print on the online procurement portal. The list is obtainable from the IFB advertisement date through the IFB close date.
3.2. Option(s)
If RTD has included the potential for options on this Contract, bids should be adjusted to cover such option(s). The option quantities or periods contained in the bid shall be evaluated in order to determine Contract award. When options have not been evaluated as part of the award, the exercise of such options will be considered “sole source” procurements. RTD will evaluate bids for award purposes by adding the total bid price for all options to the total bid price for the initial term of the Contract. Award of a
Contract containing options shall not obligate RTD to exercise such option(s).
3.3. Addenda to IFB
In the event that it becomes necessary to revise any part of this IFB, or if additional information is necessary to enable potential Bidders to make an adequate interpretation of the provisions of this IFB, an addendum to the IFB will be provided to each recipient of this IFB through RTD's online procurement portal.
3.4. Inquiries
Questions about RTD and this IFB, including requests for approved equals, shall be directed to Marla Bainbridge, Procurement Specialist, through RTD’s online procurement portal.
From the issuance date of this IFB until RTD selects a bid for award, Marla Bainbridge, Procurement Specialist, is the sole point of contact for RTD and RTD’s project team members concerning this IFB. (In this IFB and the Contract Documents, this point of contact may be referred to as the Contract Administrator, Contracting Officer, Purchasing Agent, Buyer, or the like.) Any violation of this condition may be cause for
RTD to reject the offending Bidder’s bid. If RTD later discovers that the Bidder has engaged in any violations of this condition, RTD may reject the offending Bidder’s bid or rescind its Contract award. Bidders must agree not to distribute any part of their bid beyond RTD. A Bidder who shares information contained in its bid with other RTD personnel, RTD project team members, RTD board members, and/or competing
Bidders’ personnel may be disqualified.
Bidders’ questions must be submitted through RTD’s online procurement portal. All questions or requests for clarifications regarding this solicitation, including the form of the Contract, must be made during the Inquiry Period. RTD has no obligation to respond to questions or requests for clarifications that are not submitted through RTD’s online procurement portal, nor to those submitted outside of the Inquiry Period. Except as provided below, RTD’s responses to all inquiries properly submitted will be answered in the form of an addendum that will be provided to all recipients of this IFB through
RTD’s online procurement portal. To the extent that Bidders request changes to the form of the Contract, including additional terms, conditions, and agreements (such as license agreements, master services agreements, and user agreements), such requested changes must be submitted with proposals. See “Legal Notice to Bidders - Rights Reserved to RTD.”
If the IFB Schedule provides for a pre-bid briefing (“Briefing”), RTD will not respond to any questions regarding the IFB until the Briefing is complete and the Inquiry Period if closed. Firms that have received this IFB, whether present for the Briefing or not, will receive: (1) a copy of the minutes; (2) answers to all questions presented; (3) a listing of all recipients of the IFB (current to date of Briefing); and (4) a copy of the sign-in sheet from the Briefing.
If a Respondent needs assistance using the online procurement portal, Respondents may access the Help Center for vendor training guides provided by OpenGov ("Software
Administrator"). Respondents may also contact the Software Administrator using the real-time chat function on the online procurement portal (located in lower right-hand corner of the screen), or via email at procurement-support@opengov.com for support.
3.5. Submission & Withdrawal
Respondents shall register on RTD’s online procurement portal. Once registered, Respondents may view and click "Follow" to be a Prospective Respondent for this IFB and will appear on the Follower’s list. Respondents that fail to Follow this project will not receive automated Addenda notifications, nor will they be able to submit a
Response in the online procurement portal, and therefore will be unable to participate, nor be considered for this IFB. Respondents must click “Draft Response” to properly begin and submit a Response via the online procurement portal.
RTD will accept responses to this IFB electronically via the online procurement portal until 2:00 pm on Monday, December 7, 2026. Responses received after the scheduled https://help.procurement.opengov.com/en/articles/5815468-video-guides-opengov-procurement-vendor-training mailto:procurement-support@opengov.com due date and time for submission will not be accepted. Responses submitted in any other format other than via the online procurement portal, including but not limited to, hard copy (mailed or hand delivered), facsimile, or emailed submittals, will not be accepted.
RTD and the Software Administrator are not responsible for untimely submissions due to personal or company internet or hardware limitations, settings or restrictions, internet speed, power outage, network connection, or use of a malfunctioning electronic device, or the like. Respondents are solely responsible for the capability of their computer system while responding to this IFB and for the stability of their internet service. Failure of the Respondent to successfully submit an electronic Response before the deadline indicated herein shall be at the Respondent’s sole risk, and RTD will not accept late and/or improperly submitted Responses. Once file(s) have been uploaded and the Submission Status shows as “Submitted,” a submission is complete. At that point, the Respondent will also receive an email confirmation from the online procurement portal. Respondents may withdraw their submittal electronically via the online procurement portal at any time prior to the scheduled due date and time for submission.
Bids that are late will not be accepted.
4. BIDS
4.1. Submission Requirements
Any alteration, insertion, or erasure by the Bidder in the form of the IFB documents as originally prepared by RTD shall render the Bidder non-responsive and may constitute cause for rejection. Conditional bids or those that take exception to the IFB documents or Scope of Work may be treated as non-responsive.
4.2. Bid Submission
RTD’s Procurement Specialist must receive one copy of your bid through RTD’s online procurement portal in a format that complies with Level AA of the Web Content
Accessibility Guidelines 2.1 of the World Wide Web Consortium (W3C) Web Accessibility
Initiative, and one “Open Records” copy of your bid per the Colorado Open Records Act, C.R.S. § 24-72-200.1 et seq. (as amended), including the redaction of any confidential or proprietary information. To do this you will have to export the Pricing Form or Cost
Submittal Form, redact sensitive data, and then submit it as the Open Records Copy of
Bid in the Bid Contents Checklist (FORMS TO BE SUBMITTED).
Your bid must be received no later than the time and date set forth in the IFB Schedule.
4.3. Signatures
Bids must be electronically submitted by a duly authorized official of the firm. Bids submitted by consortiums, joint ventures, or teams, although permitted and encouraged, will not be considered responsive unless it is established that all contractual responsibility rests solely with one contractor or one legal entity which shall not be a subsidiary or affiliate with limited resources. Each submittal should indicate the entity responsible for execution on behalf of the consortium, joint venture, or team.
4.4. Bid Format
Bids MUST be completed using the enclosed bid form submitted through RTD’s online procurement portal.
4.5. Bid Security
The Bidder must enclose its bid security with the bid in the amount of five percent (5%) of the bid amount. Acceptable bid security shall be limited to: (a) a one-time bid bond underwritten by a company licensed to issue bid bonds in the State of Colorado; (b) a bank cashier's check made payable to RTD; or (c) a bank certified check made payable to RTD. The bid security serves as a guarantee that Bidder will enter into a Contract with RTD if the bid is accepted.
4.6. Information from RTD
In the course of the planning of the Work and primarily for its own internal purposes, RTD may obtain data regarding engineering work, geological work, studies, rock or survey reports, soil boring reports, and any other matter whatsoever of an informational nature. Such information may be made available to the Bidder for informational purposes only, and the Bidder cannot rely on the information in formulating its bid.
4.7. Omissions from IFB
Should RTD omit any item from this IFB which is necessary to a clear understanding of the Work, or should it appear that various provisions are inconsistent or in conflict, then the Bidder shall request written instructions from RTD prior to the end of the Inquiry
Period.
4.8. Unbalanced Bids
Bids which, in the opinion of the Contracting Officer, are unbalanced so that each item does not reasonably carry its own proportion of cost, or which contain inadequate or unreasonable prices for any item, may be rejected.
4.9. Withdrawal of Bids
A Bidder may withdraw its bid at any time prior to the bid opening through RTD’s online supplier Portal not later than the exact time set for opening of bids.
4.10. Only One Bid Accepted
RTD will accept only one bid for the Work from any one Bidder. This includes bids that may be submitted under different names by one firm or corporation.
4.11. Conflicting Information from Bidder
The information and/or pricing provided by the Bidder in the required bid form and attachments will control in the event of a conflict with any information and/or pricing the Bidder types into RTD’s online supplier portal when submitting the bid.
4.12. Content Requirements
All bids must include the electronically acknowledged Addenda. Failure to electronically acknowledge any and all addenda in the online procurement portal may cause the bid to be rejected as non-responsive.
In addition to any information required elsewhere in this IFB and by the Scope of Work and specifications, if any, all bids shall contain the information required in the BID
CONTENTS CHECKLIST (FORMS TO BE SUBMITTED) section.
4.13. Prices Quoted and Discrepancies
All prices must be quoted at a firm price, FOB, Regional Transportation District 1660
Blake St Denver, CO 80202, delivered to and accepted by RTD through RTD's online procurement portal. Where both the written word and numerical dollar amounts are reflected on the bid form, the written word amount is the amount that controls and that shall be publicly read. In cases of discrepancy between the unit price and the computed total price, the unit price alone will be considered as representing the Bidder’s intention.
5. AWARD PROCESS
5.1. Evaluation Criteria
The Contract shall be awarded to the responsible Bidder whose bid is responsive to the
IFB and is most advantageous to RTD, considering price and the factors as may be set out in the IFB. The Bidder’s proposed schedule shall be the primary mechanism used to evaluate its understanding of the project’s scope and workflow (to include timing). It shall be completed according to the Technical Specifications and submitted with the bid;
it is a Contract requirement for the Contractor to have read and understood all of the
Technical Specifications prior to bidding the Work. The Contract duration shown in the
Bidder’s proposed schedule shall be the same as the Contract Schedule.
5.2. Notification to Successful Bidder
Award decisions of RTD shall be reduced to writing by the Director of Contracting and
Procurement, or delegate, and shall be final. RTD will notify the successful Bidder, if any, by sending a notice of intent to award, which is subject to any required RTD approval. Following RTD approval, the Contracting Officer will initiate the Contract signature process and then issue the notice to proceed with the executed Contract.
Upon award of the Contract, the Contractor will be given complete sets of plans and specifications.
5.3. Notifications to Unsuccessful Bidders
Post-Award Notices of Exclusion. The Procurement Specialist shall notify unsuccessful
Bidders of exclusion from award through RTD’s online procurement portal.
Protests. Bidders must submit protests related to this IFB in writing to Marla Bainbridge, Procurement Specialist, pursuant to the procedures set forth in RTD’s procurement standards manual. Copies of RTD’s protest procedures are available upon request to the
Purchasing Agent. Bidders must exhaust all administrative remedies prescribed by
RTD’s protest procedures before proceeding to court.
5.4. Construction Contracts
Within 72 hours of the opening of the bids, the apparent low Bidder must provide a
Schedule of Values (SOV) used in compiling the bid including calculations, data, etc., sufficient for RTD to determine how the bid was computed. Specifically the SOV must show the following:
A. The Bidder’s determination of the number of units for each line item provided by
RTD in the bid packet (i.e., the number of units, linear feet, square feet, cubic feet, etc.,).
B. The cost in material, equipment, labor and/or subcontractor expenses for each line item.
C. The Bidder’s profit and total anticipated overhead expenses for the entire term of the Contract as that time period is established by RTD in the Contract
Documents. The Bidder must specifically break down its charges for mobilizations at each segment of the Work requiring mobilization, field overhead for each segment of the Work (including field personnel not calculated in the labor expenses under (b) above), office overhead, cleanup costs at pertinent time periods, insurances, bonds and profit.
D. The amount that the Bidder is charging RTD for each line item (costs plus overhead and profit if appropriate).
The documents should be compiled in such a way that the sum of the items above equal the Contract Cost. The bid price should not rely upon anticipation that RTD will accept an expedited schedule as the Contract Schedule.
Within 72 hours of the opening of the bids, the apparent low Bidder must also submit the form or forms in these bid documents that list, in line-item form, a description of items and Work that is to be provided or performed under the Contract.
The bid documents should reflect the fact that the Bidder will have labor expenses, management expenses, field overhead, office overhead, insurance, bonds, and other costs throughout the entire term of the Contract as that time period is specified by RTD in the Contract. The bid price should not rely upon anticipation that RTD will accept an expedited schedule as the Contract Schedule.
6. LEGAL NOTICE TO BIDDERS
6.1. Organizational Conflict of Interest
A. The bidder shall review the attached Organizational Conflicts of Interest
Disclosure Requirements and submit its Organizational Conflicts of Interest
Certification with the bid.
B. If the bidder prepared or assisted RTD in the preparation of a statement of work, work program, or system specifications to be used in a competitive procurement by RTD, the bidder will be ineligible to supply the same in connection with this
Contract. The bidder may otherwise compete for RTD business on an equal basis with other parties.
C. Except as provided above, if RTD determines that a potential conflict exists, the bidder shall be excluded from award unless the conflict can be avoided or otherwise resolved through the inclusion of a special Contract provision or other appropriate means.
6.2. Insurance and Bond Requirements
Bidders’ attention is directed to the section entitled Insurance and Bond Requirements herein. It is highly recommended that bidders confer with their insurance carriers or brokers in advance of bid submission to determine the availability of bonds, insurance certificates and any endorsements. The cost of such insurance and bonds shall be included in the bid.
6.3. Performance of Work by Contractor
The Contractor shall perform on site and with its own staff Work equivalent to at least
51 percent of the total amount of Work to be performed under the Contract. This percentage may be reduced by a change order to the Contract if, while performing the
Work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of RTD.
6.4. Investigations
Bidders must satisfy themselves, by personal investigation and by such other means as they deem necessary or desirable, as to the location of and conditions affecting the proposed Work and as to the cost of the Work. Bidders shall review RTD’s proposed
Work schedule and become familiar with all conditions, including the site, which may affect the Work and costs under this Contract. No information derived from the maps, plans, specifications, or drawings will relieve the subsequently awarded Contractor from any risk or from fulfilling all of the terms of the Contract. The Contractor shall not at any time make claim to any additional payments or considerations on account of any misunderstanding regarding the nature or amount of Work to be done.
6.5. News Releases
RTD’s written approval is required prior to any communication with the press or any public disclosure relating to this IFB or any subsequent awards.
6.6. Pre-award Audit
RTD reserves the right to conduct a pre-award audit to verify labor rates, overhead rates, etc. should RTD determine that such an audit is required prior to negotiation or award of a Contract.
6.7. Cost of Bid Preparation
RTD shall not reimburse bidders for costs incurred for preparation of bids or required documentation.
6.8. Materials Submitted
All materials submitted shall become the property of RTD and will not be returned to the bidder.
6.9. Confidentiality
RTD is a public entity subject to the provisions of the Colorado Open Records Act, C.R.S. § 24-72-200.1 et seq. (“CORA”), and all materials submitted with this IFB, with the exception of trade secrets, privileged information, and confidential commercial, financial, geological, or geophysical data pursuant to C.R.S. § 24-72-204(3)(a)(IV), may become public records subject to inspection by the public at any time after the Contract is executed. Therefore, any confidential or proprietary information that the bidder discloses to RTD with respect to this IFB must be clearly designated as confidential or proprietary at the time of disclosure by the bidder to RTD. RTD shall not disclose properly designated information unless such information is required to be disclosed by law or court order. In the event of a legal challenge to the confidentiality of records so designated by the bidder, RTD shall make reasonable efforts to notify the bidder prior to disclosing any such information, and in some cases may tender to the bidder the defense of any action filed. By submitting a bid under this IFB, the bidder agrees to accept such tender of defense and in all cases assumes exclusive responsibility for defending its position as to the confidentiality of the requested information. RTD is not obligated to assist in such defense, and cannot and does not guarantee that the confidentiality of records so designated will be upheld by a reviewing court. If the bidder fails to submit a copy of its redacted bid that may be released under
CORA, the bidder acknowledges that RTD has the authority to disclose, and may disclose in its discretion, any information contained in the bid in response to a CORA request.
6.10. Rights Reserved to RTD
A. All bidders are notified that the award of a Contract pursuant to this IFB is dependent upon execution of a Contract with the successful bidder(s) and appropriation by RTD’s Board of Directors of the necessary funds. Successful bidders must be prepared to execute the Contract that is provided with this IFB. RTD has no obligation to accept requested changes to the form of the Contract. At RTD’s sole discretion, RTD may deny any requested changes submitted after the deadline for bid submission. Requested changes must be specific (including, as applicable, section reference, reason for requested change and proposed revised language) and clearly identified in the bid. If a bidder does not submit any requested Contract changes, the bidder will be deemed to have accepted the terms, conditions, and requirements of this solicitation, including the form of Contract.
RTD will not accept blanket exceptions to any or all terms, conditions, or requirements of this solicitation to be negotiated at a later date. At
RTD’s sole discretion, RTD may deny requested changes that are embedded by hyperlink or cited by reference in a bid and related documents. FAILURE TO ACCEPT THE TERMS AND CONDITIONS IN
THIS SOLICITATION MAY RESULT IN A BIDDER BEING DEEMED NON-
RESPONSIVE.
B. It is the intent of RTD to make an award within 30 days from the bid due date;
however, all bids shall be valid for no less than ninety (90) days.
C. RTD reserves the right to postpone the bid opening for its own convenience.
D. Issuance of this IFB does not commit RTD to award the Contract. RTD reserves the right to reject all bids and re-solicit or cancel this IFB if deemed by RTD to be in its best interest.
6.11. Prohibited Interests
A. No employee of RTD or any member of its governing body shall have any personal or financial interest, direct or indirect, in this Contract or any contract executed subsequently in connection with this Contract during his or her tenure or for one year thereafter. No director, officer, employee, or agent of RTD shall be interested in any contract or transaction with RTD except in his or her official representative capacity.
B. No member of or delegate to Congress, or resident commissioner, shall be admitted to any share or part of any Contract awarded, or to any benefit arising from it.
6.12. Competition in Subcontracting
Bidders shall select subcontractors (including suppliers) on a competitive basis to the maximum practicable extent consistent with the objectives and requirements of any
Contract awarded.
6.13. Personnel Availability
By submitting its bid, the bidder certifies that it and each of its subcontractors possess an adequate supply of workers qualified to perform the work specified within the
Contract schedule; that there is no existing or impending dispute between it and any labor organization; and that it is prepared to comply fully with prevailing wage requirements, minimum wages, maximum hours of work, and equal opportunity provisions contained in the Contract Terms and Conditions.
7. BID CONTENTS CHECKLIST (FORMS TO BE SUBMITTED)
Note to Respondents: In order to download the submittal forms in the
"Forms to be Completed and Submittal Requirements section," Respondents must download them directly from the online procurement portal.
Please only include cost in designated "cost" sections, or cost table if provided. Any cost information submitted or duplicated in other sections may result in response disqualification.
7.1. In addition to any information required elsewhere in this Solicitation and in the Scope of Work, all responses shall contain and will be evaluated based on the following sections:
7.1.1. Name and Title of Individual(s) Authorized to Sign the Contract* Please enter the full name(s) and title(s) and email address(es) of the individual(s) authorized to sign the contract if awarded to your company. Only list multiple names if multiple individuals are required to sign.
*Response required
7.1.2. Name and Title of Respondent’s Authorized Official*
The following questions are prepared in electronic format, and the Respondent is required to respond in this format. All required certifications, documentation, and response information below shall be answered and provided by an authorized official with binding authority. Electronic selections and confirmations shall be as binding as a signature from the authorized official submitting this response on behalf of the
Respondent.
Please type the full name and title of the authorized official electronically submitting this response.
*Response required
7.1.3. I certify that I have read, understood, and agree to be bound to the terms in the General Instructions, Solicitation Instructions, Award Process, and Legal Notice in this solicitation, and that I am authorized to submit this response on behalf of my organization.*
☐ Please confirm
*Response required
7.1.4. I certify that I have read, understood and agree, on behalf of the firm submitting this response, to the terms and conditions including, but not limited to, the insurance requirements set forth herein with the exception of any modification requests approved by RTD during the Q&A period.*
☐ Please confirm
*Response required
7.1.5. In Section IV.7.4.1.c.iv, "Profit" (Page 72) of the Form of Contract, please propose a profit multiplier (%) to be applied to Change Orders. The profit multiplier will serve as the basis for determining profit on Change Orders;
however, the final profit percentage shall be subject to negotiation and may be adjusted downward, as appropriate, based on the nature and scope of the Change Order*
Maximum response length: 10 characters
*Response required
7.1.6. Open Records Copy of Bid
Submit your Open Records Copy of Bid per the instructions in the solicitation.
THIS SECTION IS FOR COST ONLY. PLEASE DO NOT INCLUDE ANY
ADDITIONAL INFORMATION HERE.
7.1.7. Form of Bid Security Being Submitted?*
☐ Bid Bond
☐ Cashier's Check
☐ Cash
☐ Certified Check
*Response required
7.1.8. Bid Security *
A. If Contractor selected "Cashier's Check or Certified Check" above, Contractor shall Upload a copy of the signed check (front and back). Actual Bond document(s) must be received by RTD Procurement Agent within 5 business days.
B. If Contractor selected "Bid Bond" above, Contractor shall upload a fully executed bid bond obtained from an authorized Surety Company. Actual Bond document(s) must be received by RTD Procurement Agent within 5 business days.
C. If Contractor selected "Cash" above, Contractor shall deliver the cash to Marla
Bainbridge at 1660 Blake St, Denver, CO, 80202 in a sealed envelope clearly labeled as Bid Security with the Project No (IFB-326DM017) and Title (Lighting
Upgrades at Denver Union Station and Civic Center Parking Garage) before the deadline to submit responses to this solicitation. The Contractor shall also upload a letter here stating that the Contractor is delivering their bid security in the form of cash. Contractor shall understand that Bid Security in the form of "Cash" not physically received in original and complete form by RTD before the deadline will be cause for disqualification.
*Response required
7.1.9. ORGANIZATIONAL CONFLICT OF INTEREST DISCLOSURE REQUIREMENTS*
A. Organizational conflict of interest means that, because of other activities or relationships with other persons, a person is unable or potentially unable to render impartial assistance or advice to RTD, or the person's objectivity in performing the Work is or might be otherwise impaired, or a person has an unfair competitive advantage.
B. Each firm responding to the Solicitation shall provide the statement described in paragraph (c). This requirement will apply individually to any of the firm’s consultants or lower-tier subcontractors that also furnish Work in performance of the Contract to be awarded.
C. The statement must contain the following:
1. Name of the firm and the number of the Solicitation in question.
2. The name, address, telephone number, and federal taxpayer identification number, if applicable, of the firm.
3. A description of the nature of the Work rendered by or to be rendered on the
Contract or related to the Contract.
4. A statement of any past (within the past 12 months), present, or currently planned financial, contractual, organizational, or other interests relating to the performance of the Contract. For contractual interests, such statement must include the name, address, and telephone number of the client or client(s), a description of the services rendered to the previous client(s), and the name of a responsible officer or employee of the firm who is knowledgeable about the services rendered to each client, if, in the 12 months preceding the date of the statement, services were rendered to RTD or any other client respecting the same subject matter of the Solicitation or directly relating to such subject matter. The client and contract number under which the services were rendered must also be included, if applicable. For financial interests, the statement must include the nature and extent of the interest and any entity or entities involved in the financial relationship. For these and any other interests, enough information must be provided to allow a meaningful evaluation of the potential effect of the interest on the performance of the
Contract.
5. A statement that no actual or potential conflict of interest or unfair competitive advantage exists with respect to the Work to be provided in connection with the Contract or that any actual or potential conflict of interest or unfair competitive advantage that does or may exist with respect to the
Contract or related to the Contract has been communicated as part of the statement required by section (c).
D. Failure of a firm to provide the required statement may result in the firm being determined ineligible for award. Misrepresentation or failure to report any fact may result in the assessment of penalties associated with false statements or such other provisions provided for by law or regulation.
ORGANIZATIONAL CONFLICT OF INTEREST CERTIFICATION
If the Respondent is aware of information bearing on whether a potential conflict may exist, the Respondent shall provide a disclosure statement describing this information as described in the Disclosure Requirements above.
☐ The Respondent IS aware of any information bearing on the existence of any potential organizational conflict of interest as described in the Disclosure Requirements.
☐ The Respondent IS NOT aware of any information bearing on the existence of any potential organizational conflict of interest as described in the Disclosure Requirements.
*Response required
7.1.10. Current W9 *
Please download the below documents, complete, and upload.
• 02.12_W9_updated_1822.pdf
*Response required
7.1.11. KEY PERSONNEL*
Please download the below documents, complete, and upload.
• Key_Personnel.docx
*Response required
7.1.12. The Respondent understands that any condition stated above, clarification of the above, or information submitted on or with this form other than requested will render the quotation non-responsive.*
☐ Please confirm https://procure-now.s3.us-west-2.amazonaws.com/shared-sections/production/36/2715a66a-0788-44f4-923d-4592ac83cb02_02.12_W9_updated_1822.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4CCJTRGYE%2F20261109%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20261109T222142Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEGYaCXVzLXdlc3QtMiJIMEYCIQDXCkaKwk6pW2U3A7dG5gIRFOn%2FOcUf4C05914n6C2aHAIhALJBBEKiUf84UBQfRxUOmYqx0CDrRoyfcJYhSkyY9Lc5KowFCC8QAhoMODkyMzY0Njg3NjcyIgwU2Lp%2FiiwMQjWvZXoq6QRON2HgukApESAk3wY%2FANpzgpCbiDAPiu194es%2F%2FzxSeQkt%2Bbp5X1%2BTlYqZAYpNzPg6v9AvBIPtUKyoVR3axEDsYhKFDYeKesMc81n63mrOgQ0rXpjzgEUVJIXl5Qe9Mb9iKX4JRm3b%2Fn9xSUc6Mg3jTEcZyVkGIeHkHtfkDIOAqEcmXDdQwIX8K76cfhvk%2FBw364e0waQ2phFGIXxc6A1C2oDNaR%2BBEy7RKw3HjfyqAsA5XLHu0PS16GI%2Fo%2F4XkdbyAkgfHoBRxbv%2FveU7sm%2B%2Fo9jwuw5VJpmqObBQ4%2Fn1FNhkSqTDY%2Fd2s%2FNv1Kcm2Afl3KfTA81fUR6NBW7tQuWrnT4b3W%2Fk3kuCA7G32bBvH51U3gS3Hf%2BtMDGnUEWT3Bn57aHtie5S0rzGr6frhb5%2FPxVzbhu6UEpKtJlFYNU%2F5tIeaLasxueRuzAH68cNfO3PtjZzWwrEtG99BG3gtEUQJgP8VHCWYUyaTkQ7tIq9cCVM2uz1MTHJbtqXAwVxlU4T8YZ6uPi0zbWiGZlzxYejuYNE5SvDr9SDal28RcpVHkUNxVZt2xAENSxaVUVzzUZsjwPHC%2FO2frUF1VIp2qBnzvIEgvdlieAjgVJPGx5K0ZFfLvN4qjEWkAH6hRaD70TN6r%2FeY4uvqVdQbdQL3gYKbQzGGxaGqXYlZw7K9RXnt0vbShtHhV2yazV4X6WZcIOroACvEMr3QGworWMJJUY4mQDFEbuwpZ04YslEHiYIhvJLWJN%2BzRJwDvFiI1G9np7yvg%2FYhMJt46T9bqYg4kDeg1TafyGetG2%2FVtVGN0%2BC5ZcnWsPGsFYFuzDahcnXBjqYAfCF%2Bgw88uKUwzc8VCZgQs9q6S7j5x8Zo6D%2FSRjWkf4QweOv1LhnBZuMx%2By8HlJSKiwDsR2%2BOhUxidHC%2FMwe8SNyhULJo786cqoJZ0dlroWDYrpfpGPh1zjrSwqSaIC%2BcbyQ8UohkilUDhC7TJ7bQxLPluLG9IsMV7JYe74VPrjnlTb%2B7xsOMKxmt6QBVAhoIpgJ%2Be%2F2IONW&X-Amz-Signature=dbdc9ddef64cacbac210f4d22841fc12473f9d7a8843fad20c0c8c2da33dd140&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%2202.12_W9_updated_1822.pdf%22&x-id=GetObject https://procure-now.s3.us-west-2.amazonaws.com/shared-sections/production/36/387664a0-f1d1-4e62-b529-fc5284b50777_Key_Personnel.docx?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4CCJTRGYE%2F20261109%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20261109T222142Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEGYaCXVzLXdlc3QtMiJIMEYCIQDXCkaKwk6pW2U3A7dG5gIRFOn%2FOcUf4C05914n6C2aHAIhALJBBEKiUf84UBQfRxUOmYqx0CDrRoyfcJYhSkyY9Lc5KowFCC8QAhoMODkyMzY0Njg3NjcyIgwU2Lp%2FiiwMQjWvZXoq6QRON2HgukApESAk3wY%2FANpzgpCbiDAPiu194es%2F%2FzxSeQkt%2Bbp5X1%2BTlYqZAYpNzPg6v9AvBIPtUKyoVR3axEDsYhKFDYeKesMc81n63mrOgQ0rXpjzgEUVJIXl5Qe9Mb9iKX4JRm3b%2Fn9xSUc6Mg3jTEcZyVkGIeHkHtfkDIOAqEcmXDdQwIX8K76cfhvk%2FBw364e0waQ2phFGIXxc6A1C2oDNaR%2BBEy7RKw3HjfyqAsA5XLHu0PS16GI%2Fo%2F4XkdbyAkgfHoBRxbv%2FveU7sm%2B%2Fo9jwuw5VJpmqObBQ4%2Fn1FNhkSqTDY%2Fd2s%2FNv1Kcm2Afl3KfTA81fUR6NBW7tQuWrnT4b3W%2Fk3kuCA7G32bBvH51U3gS3Hf%2BtMDGnUEWT3Bn57aHtie5S0rzGr6frhb5%2FPxVzbhu6UEpKtJlFYNU%2F5tIeaLasxueRuzAH68cNfO3PtjZzWwrEtG99BG3gtEUQJgP8VHCWYUyaTkQ7tIq9cCVM2uz1MTHJbtqXAwVxlU4T8YZ6uPi0zbWiGZlzxYejuYNE5SvDr9SDal28RcpVHkUNxVZt2xAENSxaVUVzzUZsjwPHC%2FO2frUF1VIp2qBnzvIEgvdlieAjgVJPGx5K0ZFfLvN4qjEWkAH6hRaD70TN6r%2FeY4uvqVdQbdQL3gYKbQzGGxaGqXYlZw7K9RXnt0vbShtHhV2yazV4X6WZcIOroACvEMr3QGworWMJJUY4mQDFEbuwpZ04YslEHiYIhvJLWJN%2BzRJwDvFiI1G9np7yvg%2FYhMJt46T9bqYg4kDeg1TafyGetG2%2FVtVGN0%2BC5ZcnWsPGsFYFuzDahcnXBjqYAfCF%2Bgw88uKUwzc8VCZgQs9q6S7j5x8Zo6D%2FSRjWkf4QweOv1LhnBZuMx%2By8HlJSKiwDsR2%2BOhUxidHC%2FMwe8SNyhULJo786cqoJZ0dlroWDYrpfpGPh1zjrSwqSaIC%2BcbyQ8UohkilUDhC7TJ7bQxLPluLG9IsMV7JYe74VPrjnlTb%2B7xsOMKxmt6QBVAhoIpgJ%2Be%2F2IONW&X-Amz-Signature=5986dd940ba0dc25a72cab6df5e8c2faeb7841a8b349cdd5d58b68371dfb3c4b&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22Key_Personnel.docx%22&x-id=GetObject
*Response required
8. PRICING FORM
LIGHTING UPGRADE - DENVER UNION STATION LRT PLAZA
Line Item Description Quantity Unit of
Measure Unit Cost Total
1 LED Lamp 21 EA
2 LED Lamp (Spare) 5 EA
3 Miscellaneous Materials, Labor, Equipment, and Incidental Work
Required to Complete the Project in Accordance with the Contract
Documents
1 EA
LIGHTING UPGRADE - CIVIC CENTER STATION PARKING GARAGE
1 T8 to LED Replacement 114 EA
2 New Vapor-Tight Fixture 35 EA
4 6' MC Cable Extension 35 EA
5 1/2" EMT with Conductors 35 EA
6 Miscellaneous Materials, Labor, Equipment, and Incidental Work
Required to Complete the Project in Accordance with the Contract
Documents
1 EA
TOTAL
9. SCOPE OF WORK SERVICES/TECHNICAL SPECIFICATIONS
See Attachments for the Scope of Work/Technical Specifications.
9.1. Scope of Work
See Attachment A
| 1. INTRODUCTION |
| 1.1. Summary |
| 1.2. Contact Information |
| 1.3. Timeline |
| 2. INSTRUCTIONS TO BIDDERS |
| 2.1. Work |
| 2.2. Cost Type |
| 2.3. Award of Contract |
| 2.4. Period of Performance |
| 2.5. Small Business Requirement for Contracts with No SBE Goal |
| 2.6. Bid Validity Period |
| 3. GENERAL INSTRUCTIONS |
| 3.1. General |
| 3.2. Option(s) |
| 3.3. Addenda to IFB |
| 3.4. Inquiries |
| 3.5. Submission & Withdrawal |
| 4. BIDS |
| 4.1. Submission Requirements |
| 4.2. Bid Submission |
| 4.3. Signatures |
| 4.4. Bid Format |
| 4.5. Bid Security |
| 4.6. Information from RTD |
| 4.7. Omissions from IFB |
| 4.8. Unbalanced Bids |
| 4.9. Withdrawal of Bids |
| 4.10. Only One Bid Accepted |
| 4.11. Conflicting Information from Bidder |
| 4.12. Content Requirements |
| 4.13. Prices Quoted and Discrepancies |
| 5. AWARD PROCESS |
| 5.1. Evaluation Criteria |
| 5.2. Notification to Successful Bidder |
| 5.3. Notifications to Unsuccessful Bidders |
| 5.4. Construction Contracts |
| 6. LEGAL NOTICE TO BIDDERS |
| 6.1. Organizational Conflict of Interest |
| 6.2. Insurance and Bond Requirements |
| 6.3. Performance of Work by Contractor |
| 6.4. Investigations |
| 6.5. News Releases |
| 6.6. Pre-award Audit |
| 6.7. Cost of Bid Preparation |
| 6.8. Materials Submitted |
| 6.9. Confidentiality |
| 6.10. Rights Reserved to RTD |
| 6.11. Prohibited Interests |
| 6.12. Competition in Subcontracting |
| 6.13. Personnel Availability |
| 7. BID CONTENTS CHECKLIST (FORMS TO BE SUBMITTED) |
| 7.1. In addition to any information required elsewhere in this Solicitation and in the Scope of Work, all responses shall contain and will be evaluated based on the following sections: |
| 7.1.1. Name and Title of Individual(s) Authorized to Sign the Contract* |
| 7.1.2. Name and Title of Respondent’s Authorized Official* |
| 7.1.3. I certify that I have read, understood, and agree to be bound to the terms in the General Instructions, Solicitation Instructions, Award Process, and Legal Notice in this solicitation, and that I am authorized to submit this response on behalf ... |
| 7.1.4. I certify that I have read, understood and agree, on behalf of the firm submitting this response, to the terms and conditions including, but not limited to, the insurance requirements set forth herein with the exception of any modification requ... |
| 7.1.5. In Section IV.7.4.1.c.iv, "Profit" (Page 72) of the Form of Contract, please propose a profit multiplier (%) to be applied to Change Orders. The profit multiplier will serve as the basis for determining profit on Change Orders; however, the fin... |
| 7.1.6. Open Records Copy of Bid |
| 7.1.7. Form of Bid Security Being Submitted?* |
| 7.1.8. Bid Security * |
| 7.1.9. ORGANIZATIONAL CONFLICT OF INTEREST DISCLOSURE REQUIREMENTS* |
| 7.1.10. Current W9 * |
| 7.1.11. KEY PERSONNEL* |
| 7.1.12. The Respondent understands that any condition stated above, clarification of the above, or information submitted on or with this form other than requested will render the quotation non-responsive.* |
| 8. PRICING FORM |
| 9. SCOPE OF WORK SERVICES/TECHNICAL SPECIFICATIONS |
| 9.1. Scope of Work |