This is a Project Manual and specifications document prepared for the Regional Transportation District (RTD) for the Civic Center Station Parking Garage Lighting Upgrade project located at 1560 Broadway, Denver, Colorado 80202. The project scope encompasses LED lighting upgrades including LED lamp replacements and installation of LED retrofit kits for existing fluorescent light fixtures along with new linear LED fixtures at the Civic Center Parking Garage. The project manual is dated 04/30/2026 and includes divisions covering procurement and contracting requirements, general requirements, electrical work, and lighting systems. The document organizes specifications across multiple divisions including Division 00 (Procurement and Contracting Requirements), Division 01 (General Requirements), and Division 26 (Electrical), with specific sections addressing summary, project management and coordination, submittal procedures, product requirements, construction waste management, closeout procedures, and operation and maintenance data.

The design professionals of record are Chris Sigit-Sidharta, AIA, from Short Elliott Hendrickson, Inc. (Architect), and Charlene Bocek from CMO Consulting Engineers LLC (Electrical Engineer). The electrical engineer certification section indicates that the technical submission was prepared under the direct supervision of a registered Professional Engineer in Colorado, with the discipline designated as Electrical. The contractor is required to furnish all necessary labor, materials, equipment, supervision, permits, and insurance to complete the modifications as shown in the construction drawings and specification package. No pricing terms, set-asides, incumbent information, or specific funding details are identified within this specifications document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

CIVIC CENTER STATION PARKING

GARAGE - LIGHTING UPGRADE

1560 BROADWAY, DENVER 80202

OWNER:

REGIONAL TRANSPORTATION DISTRICT

1660 BLAKE STREET

DENVER, CO 80202

THIS PAGE INTENTIONALLY LEFT BLANK

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

000100 PROJECT DIRECTORY

000105 CERTIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

011000 SUMMARY

013100 PROJECT MANAGEMENT AND COORDINATION

013300 SUBMITTAL PROCEDURES

016000 PRODUCT REQUIREMENTS

017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 CLOSEOUT PROCEDURES

017823 OPERATION AND MAINTENANCE DATA

017839 PROJECT RECORD DOCUMENTS

DIVISION 26 - ELECTRICAL

260500 COMMON WORK RESULTS FOR ELECTRICAL

260533 RACEWAY FOR ELECTRICAL SYSTEMS

260534 CABINETS, BOXES AND FITTINGS

260583 WIRING CONECTIONS

265000 LIGHTING

CIVIC CENTER STATION PARKING GARAGE -

LIGHTING UPGRADE

04/30/2026

PROJECT DIRECTORY

000100 - 1

DOCUMENT 000100 – PROJECT DIRECTORY

1.1 DESIGN PROFESSIONALS OF RECORD

ARCHITECT Chris Sigit-Sidharta, AIA Short Elliott Hendrickson, Inc.

2000 S Colorado Blvd, Suite 1200 Denver, CO 80222 720.540.6843 csigit-sidharta@sehinc.com

ELECTRICAL

ENGINEER

Charlene Bocek CMO Consulting Engineers LLC 11646 Sun Bear Trail Golden, Colorado 80403 cbocek@cmoengineering.com

END OF DOCUMENT 000100

04/30/2026

PROJECT DIRECTORY

000100 - 2

THIS PAGE IS INTENTIALLY LEFT BLANK

WO #13 - CIVIC CENTER STATION PARKING

04/30/2026

CERTIFICATIONS

000105 - 1

DOCUMENT 000105 CERTIFICATIONS

I hereby certify that this technical submission was prepared by me or under my direct supervision and responsible charge in accordance with the rules and regulations governing Engineers practicing in the State of Colorado. I am a duly registered Professional Engineer in the State of Colorado.

Discipline: Electrical

Name: Charlene Bocek

Registration No.:

Expiration:

Signature

'11.\\\ \\II I l 11111 ///////.

���oO REG1J1

10/, # o"<"'� ····r·:v��-� �Ne• 'V • � �

�o.- ·-��

� :o 36245 -"• =

� 1� :!J:-� a II�;::, � a• •,";'-f,:::;

� ·�·. .. � �:',,/, ''.8�········�(3 � �,,,,, 'IONAL € ,,,,,�

11111111111 Ill\\\\\\\\\;

36245

10/31/2027

04/30/2026

CERTIFICATIONS

000105 - 2

THIS PAGE IS INTENTIONALLY LEFT BLANK

04/30/2026

SUMMARY

011000 - 1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes:

1. Project information.

2. Work covered by Contract Documents.

3. Access to site.

4. Coordination with occupants.

5. Work restrictions.

6. Applicable Standards

7. Specification and drawing conventions.

1.2 PROJECT INFORMATION

A. Project Identification: Civic Center Station Parking Garage - Lighting Upgrade

1. Project Location: 1560 Broadway, Denver 80202

B. Owner: RTD

1. Owner's Representative/Project Manager: Abhishek Phanse

2. When documents refer to Owner, RTD’s Owner’s Representative/Project Manager, as noted above, will be assumed.

C. Architect: SEH; 2000 South Colorado Blvd, Suite 1200 Colorado Center Tower Two, Denver CO 80222.

D. Other Owner Consultants: The Owner has retained the following design professionals who have prepared designated portions of the Contract Documents:

1. CMO Consulting Engineers LLC (Electrical Engineer)

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of the Project is defined by the Contract Documents and consists of the following:

B. This project includes the replacement of the existing Civic Center Station parking garage lighting system with new lighting.

C. Type of Contract

04/30/2026

SUMMARY

011000 - 2

1. Project will be constructed under a single prime contract.

1.4 ACCESS TO SITE

A. General: Contractor shall have limited use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.

B. Use of Site: Limit use of Project site to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Driveways, Walkways and Entrances: Keep entry driveways and personnel entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period.

Repair damage caused by construction operations.

1.5 COORDINATION WITH OCCUPANTS

A. Full Owner Occupancy: Owner will occupy site and existing building(s) during entire construction period, but not Asset Management Office space. Cooperate with RTD Project Manager during construction operations to minimize conflicts and facilitate RTD usage. Perform the Work so as not to interfere with RTD’s day-to-day operations.

Maintain existing exits and drives unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from RTD Project Manager and approval of authorities having jurisdiction.

2. Notify RTD Project Manager not less than 72 hours in advance of activities that will affect RTD’s operations.

1.6 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 6:00 p.m., Monday through Friday, except as otherwise indicated.

04/30/2026

SUMMARY

011000 - 3

1. Early Morning Hours/Weekend Hours: Confirm with authorities having jurisdiction if and when early morning or weekend work hours are permitted and receive associated approval prior to beginning any work.

2. Hours for Utility Shutdowns: Notify RTD Project Manager prior to Utility shutdowns.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by RTD or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify RTD Project Manager not less than 72 hours in advance of proposed utility interruptions.

D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with RTD Project Manager.

1. Notify RTD Project Manager not less than 72 hours in advance of proposed disruptive operations.

E. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

F. APPLICABLE STANDARDS

1. The Contractor shall conduct work according to all federal, state, and local regulations (EPA, OSHA, NEMA, IEE, UL, NEC and City of Denver).

2. All workers shall be properly licensed or certified according to all applicable codes and regulations. If a license or certification is not required by law for all workers, all workers still must demonstrate, to the satisfaction of the RTD Project Manager, sufficient expertise to perform the required work safely and in a good workman like manner. All work must be done under the supervision of personnel licensed or certified in the area, which the work is performed. RTD has the right, in the RTD Project Manager’s sole discretion, to prohibit workers from the site who have been working in an unsafe manner or who do not demonstrate sufficient expertise to professionally do the work, including warranty work.

3. The Contractor shall comply with RTD safety and environmental policies; the RTD Project Manager or ECO (Environmental Compliance Officer) will have the authority to stop Contractor work (at the Contractor’s expense) if the work is deemed to be in violation of regulatory requirements, RTD’s policies, or presents a safety hazard.

4. The terms and conditions of this Contract.

04/30/2026

SUMMARY

011000 - 4

1.7 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on the Drawings are described in detail in the Specifications. One or more of the following are used on the Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

1.8 MISCELLANEOUS PROVISIONS

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

04/30/2026

PROJECT MANAGEMENT AND

COORDINATION

013100 - 1

SECTION 013100 – PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions.

2. Informational submittals.

3. Coordination procedures.

4. Coordination drawings.

5. Project meetings.

6. Requests for Interpretation (RFIs).

7. Digital project management procedures.

8. Environmental coordination.

9. Permits.

1.2 DEFINITIONS

A. Request for Interpretation (RFI): Request from Contractor seeking interpretation or clarification of the Contract Documents.

1.3 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

1.4 COORDINATION PROCEDURES

A. Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.

04/30/2026

PROJECT MANAGEMENT AND

COORDINATION

013100 - 2

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

9. Commissioning activities.

1.5 COORDINATION DRAWINGS

A. Coordination Drawings: Prepare Coordination Drawings according to requirements in individual Sections and where installation is not completely indicated on the Shop drawings, where limited space availability necessitates coordination, or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, and civil systems.

b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Owner for resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.

04/30/2026

PROJECT MANAGEMENT AND

COORDINATION

013100 - 3

1.6 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Record significant discussions and agreements. Distribute the meeting minutes to everyone concerned, including Owner, within three days of the meeting.

B. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to the Owner, but no later than 15 days after execution of the Agreement. Hold the conference at Project site or other convenient location.

Conduct the meeting to review responsibilities and personnel assignments, review required work, project drawings, specifications, construction schedules, payroll, payments, and administrative provisions of the Contract. Be prepared to summarize and explain procedures planned for the project and present specified preconstruction submittals.

Attendees: Authorized representatives of Owner, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

1. Agenda: Discuss items of significance that could affect progress, including the following:

a. Tentative construction schedule.

b. Critical work sequencing and long-lead items.

c. Designation of key personnel and their duties.

d. Procedures for processing field decisions and Modifications.

e. Procedures for RFIs.

f. Procedures for testing and inspecting.

g. Procedures for processing Applications for Payment.

h. Distribution of the Contract Documents.

i. Submittal procedures.

j. Preparation of Record Documents.

k. Use of the premises.

l. Work restrictions.

m. Owner occupancy requirements.

n. Responsibility for temporary facilities and controls.

o. Construction waste management and recycling.

p. Parking availability, office, work, and storage areas.

q. Equipment deliveries and priorities.

r. First aid.

s. Security.

04/30/2026

PROJECT MANAGEMENT AND

COORDINATION

013100 - 4

t. Progress cleaning.

u. Working hours.

2. Minutes: Record and distribute meeting minutes.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Owner of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs and Related Modifications.

d. Purchases, Deliveries, Submittals.

e. Review of mockups.

f. Possible conflicts and/or Compatibility problems.

g. Time schedules and Weather limitations.

h. Manufacturer's written recommendations.

i. Warranty requirements.

j. Acceptability of substrates.

k. Space and access limitations.

l. Regulations of authorities having jurisdiction.

m. Testing and inspecting requirements.

n. Installation procedures.

o. Coordination with other work.

p. Required performance results.

q. Protection of adjacent work.

r. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to parties who should have been present.

5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Progress Meetings: Conduct progress meetings at weekly intervals. Hold the meetings at the project site. Coordinate dates of meetings with preparation of payment requests.

Additional progress meetings may be requested by either the Owner or Contractor.

1. Attendees: In addition to representatives of Owner, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be

04/30/2026

PROJECT MANAGEMENT AND

COORDINATION

013100 - 5 represented. All participants shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting.

Review items of significance that could affect progress. Include as appropriate:

a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead or behind schedule. Determine how construction behind schedule will be expedited;

secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

1) Interface requirements.

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Off-site fabrication.

6) Access.

7) Site utilization.

8) Temporary facilities and controls.

9) Work hours.

10) Hazards and risks.

11) Progress cleaning.

12) Quality and work standards.

13) Status of correction of deficient items.

14) Field observations.

15) RFIs.

16) Status of proposal requests.

17) Pending changes.

18) Status of Modifications.

19) Pending claims and disputes.

20) Documentation of information for payment requests.

c. Reporting: Record the meeting minutes. Distribute minutes of the meeting to each party present and to parties who should have been present.

d. Schedule Updating: Revise Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

04/30/2026

PROJECT MANAGEMENT AND

COORDINATION

013100 - 6

1.7 REQUESTS FOR INTERPRETATION (RFIs)

A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, and if not possible to request interpretation at Project meeting, prepare and submit an RFI in the form specified.

1. RFIs shall originate with Contractor. RFIs submitted by entities other than Contractor will be returned with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing interpretation and the following:

1. Project name.

2. Date.

3. Name of Contractor.

4. Name of Owner

5. RFI number, numbered sequentially.

6. Specification Section number and title and related paragraphs, as appropriate.

7. Drawing number and detail references, as appropriate.

8. Field dimensions and conditions, as appropriate.

9. Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract

Time or the Contract Sum, Contractor shall state impact in the RFI.

10. Contractor's signature.

11. Requested date for response.

12. Attachments: Include drawings, descriptions, measurements, photos, Product

Data, Shop Drawings, and other information necessary to fully describe items needing interpretation. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFIs:

1. Identify each page of attachments with the RFI number and sequential page number.

D. Architect/Engineer's Action: Architect/Engineer will review each RFI, determine action required, and return it. Allow five calendar days for Architect/Engineer's response for each RFI. RFIs received after 1:00 p.m. will be considered as received the following working day.

1. The following RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor’s means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

04/30/2026

PROJECT MANAGEMENT AND

COORDINATION

013100 - 7

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect/Engineer's actions on submittals.

g. Incomplete RFIs or RFIs with numerous errors.

2. Architect/Engineer's action may include a request for additional information, in which case the Architect/Engineer's time for response will start again.

E. On receipt of Architect/Engineer's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Owner & Architect/Engineer within seven days if Contractor disagrees with response.

F. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly. Include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Owner/Contracting Officer.

4. RFI number including RFIs that were dropped and not submitted.

5. RFI description.

6. Date the RFI was submitted.

7. Date Owner's response was received.

8. Identification of related bilateral or unilateral modifications, extensions, and changes in scope, as appropriate.

1.8 DIGITAL PROJECT MANAGEMENT PROCEDURES

A. Use of Architect's Digital Data Files: Digital data files of Architect's BIM model and CAD drawings will be provided by Architect for Contractor's use during construction.

1. Digital data files may be used by Contractor in preparing coordination drawings, Shop Drawings, and Project Record Drawings.

2. Architect makes no representations as to the accuracy or completeness of digital data files as they relate to Contract Drawings.

3. Digital Drawing Software Program: Drawings are available in Autodesk Revit or AutoCAD 2018.

4. At completion of Project, provide digital archive in format that is readable by common desktop software applications in format acceptable to Owner. Provide data in locked format to prevent further changes.

B. PDF Document Preparation: PDFs required to be submitted shall be prepared as follows:

1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.

2. Name file with submittal number or other unique identifier, including revision identifier.

04/30/2026

PROJECT MANAGEMENT AND

COORDINATION

013100 - 8

3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.

1.9 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Ensure compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implement the Waste Management Plan (WMP).

c. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.

d. Provide training for Contractor personnel in accordance with their position requirements.

e. Monitor and document environmental procedures.

B. Perform project quality control in accordance with specified requirements including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Construction Waste Management.

4. Compliance with environmental regulations: As specified in Regulatory

Requirements. Submit Contractor 40 CFR employee training records upon request of Owner.

1.10 PERMITS

A. General:

1. Permits and Responsibilities: The Contractor shall, without additional expense to the Owner, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.

04/30/2026

PROJECT MANAGEMENT AND

COORDINATION

013100 - 9

2. For the purpose of this contract the Contractor will not be considered an agent of the Owner. Therefore the Contractor will comply with the appropriate Federal, State and local laws.

B. Coordination with Agencies with Jurisdiction for Utility Connections: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying the work: Coordinate meetings, reporting requirements, inspections, or any other requirements.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 013100

04/30/2026

PROJECT MANAGEMENT AND

COORDINATION

013100 - 10

04/30/2026

SUBMITTAL PROCEDURES

013300 - 1

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

1.3 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require RTD Project Manager's responsive action. Action submittals are those submittals indicated in individual Specification Sections as action submittals.

B. Informational Submittals: Written and graphic information and physical samples that do not require RTD Project Manager's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as informational submittals.

C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.

D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.

1.4 ACTION SUBMITTALS

A. SUBMITTAL SCHEDULE

1. Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or modifications to submittals noted by the RTD Project Manager and additional time for handling and reviewing submittals required by those corrections.

04/30/2026

SUBMITTAL PROCEDURES

013300 - 2

a. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule.

b. Initial Submittal: Submit concurrently with start-up construction schedule.

Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.

c. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.

1) Submit revised submittal schedule to reflect changes in current status and timing for submittals.

2. Format: Arrange the following information in a tabular format:

a. Scheduled date for first submittal.

b. Specification Section number and title.

c. Submittal category: Action, informational.

d. Name of subcontractor.

e. Description of the Work covered.

f. Scheduled date for Architect's final release or approval.

g. Scheduled date of fabrication.

h. Scheduled dates for purchasing.

i. Scheduled dates for installation.

j. Activity or event number.

B. THREE-WEEK LOOK AHEAD SCHEDULE

1. If submittal schedule is not available, Contractor shall include upcoming submittals in the Three-Week Look Ahead Schedule. This schedule shall be submitted weekly to the RTD Project Manager, immediately following weekly construction progress meetings, whether or not the RTD Project Manager was in attendance. The Three-Week Look Ahead Schedule shall be submitted to the RTD Project Manager each week for the duration of all construction activities on site.

1.5 SUBMITTAL ADMINISTRATIVE REQUIREMENTS

A. Architect's Digital Data Files: When requested, Electronic copies of CAD Drawings of the Contract Drawings will be provided by Architect for Contractor's use in preparing submittals.

1. Architect will furnish Contractor one set of digital data drawing files of the Contract Drawings for use in preparing Shop Drawings and Project record drawings.

a. Architect makes no representations as to the accuracy or completeness of digital data drawing files as they relate to the Contract Drawings.

b. Digital Drawing Software Program: The Contract Drawings are available in Revit 2014 or AutoaCAD.

c. Contractor shall execute a data licensing agreement in the form of AIA Document C106, Digital Data Licensing Agreement

04/30/2026

SUBMITTAL PROCEDURES

013300 - 3

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all items required for each Specification Section in one single submittal.

Architect will reject and not review submittals that are not complete, including all requirements of the Section into one single submittal.

3. Informational submittals shall be clearly identified as such.

4. Coordinate transmittal of different types of submittals for related parts of the

Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. RTD Project Manager reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on RTD Project Manager’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. RTD Project Manager will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 15 days for review of each resubmittal.

4. Sequential Review: Where sequential review of submittals by Architect's consultants, Owner, or other parties is required, allow 21 days for initial review of each submittal.

5. Concurrent Consultant Review: Where the Contract Documents indicate that submittals may be transmitted simultaneously to Architect and to Architect's consultants, allow 15 days for review of each submittal. Submittal will be returned to RTD Project Manager before being returned to Contractor.

D. Identification and Information: Place a permanent label or title block on each paper copy submittal item for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by Architect.

3. Include the following information for processing and recording action taken:

a. Project name.

b. Date.

c. Name of RTD Project Manager.

d. Name of Construction Manager.

04/30/2026

SUBMITTAL PROCEDURES

013300 - 4

e. Name of Contractor.

f. Name of subcontractor.

g. Name of supplier.

h. Name of manufacturer.

i. Submittal number or other unique identifier, including revision identifier.

1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 061000.01).

Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 061000.01.A).

j. Number and title of appropriate Specification Section.

k. Drawing number and detail references, as appropriate.

l. Location(s) where product is to be installed, as appropriate.

m. Other necessary identification.

E. Identification and Information: Identify and incorporate information in each electronic submittal file as follows:

1. Assemble complete submittal package into a single indexed file with links enabling navigation to each item.

2. Name file with submittal number or other unique identifier, including revision identifier.

a. File name shall use project identifier and Specification Section number followed by a decimal point and then a sequential number (e.g., LNHS- 061000.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., LNHS-061000.01.A).

3. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by Architect.

4. Include the following information on an inserted cover sheet:

a. Project name.

b. Date.

c. Name of RTD Project Manager.

d. Name and address of Architect.

e. Name of Contractor.

f. Name of firm or entity that prepared submittal.

g. Name of subcontractor.

h. Name of supplier.

i. Name of manufacturer.

j. Number and title of appropriate Specification Section.

k. Drawing number and detail references, as appropriate.

l. Location(s) where product is to be installed, as appropriate.

m. Related physical samples submitted directly.

n. Other necessary identification.

5. Include the following information as keywords in the electronic file metadata:

a. Project name.

04/30/2026

SUBMITTAL PROCEDURES

013300 - 5

b. Number and title of appropriate Specification Section.

c. Manufacturer name.

d. Product name.

F. Options: Identify options requiring selection by the RTD Project Manager.

G. Deviations: Identify deviations from the Contract Documents on submittals.

H. Transmittal: Assemble each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. RTD Project Manager will discard submittals received from sources other than Contractor.

1. Transmittal Form: Use AIA Document G810

2. Transmittal Form: Provide locations on form for the following information:

a. Project name.

b. Date.

c. Destination (To:).

d. Source (From:).

e. Names of subcontractor, manufacturer, and supplier.

f. Category and type of submittal.

g. Submittal purpose and description.

h. Specification Section number and title.

i. Indication of full or partial submittal.

j. Drawing number and detail references, as appropriate.

k. Transmittal number, numbered consecutively.

l. Submittal and transmittal distribution record.

m. Remarks.

n. Signature of transmitter.

3. On an attached separate sheet, prepared on Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by Architect on previous submittals, and deviations from requirements in the Contract Documents, including minor variations and limitations. Include same identification information as related submittal.

I. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are marked with approval notation from Architect's action stamp.

J. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

K. Use for Construction: Use only final submittals that are marked with approval notation from RTD Project Manager’s action stamp.

04/30/2026

SUBMITTAL PROCEDURES

013300 - 6

PART 2 - PRODUCTS

2.1 SUBMITTAL PROCEDURES

A. General Submittal Procedure Requirements: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Submit electronic submittals via email as a single PDF electronic file per submittal.

a. RTD Project Manager will return annotated file or provide a separate comment response form. Annotate and retain one copy of file as an electronic Project record document file.

2. Submit all items required for each Specification Section in one single submittal.

RTD Project Manager will reject and not review submittals that are not complete, including all requirements of the Section into one single submittal. When submittals are submitted at different times for products, certifications, warranties, accessories, etc. listed in the same Section, the Contractor shall compensate the Owner who shall then compensate the RTD Project Manager for additional time required to review these submittals, unless approved in writing by the RTD Project Manager prior to submitting any portion of the submittal for a given Section.

3. Action Submittals: Submit three paper copies of each submittal, unless otherwise indicated. RTD Project Manager will return two copies.

4. Informational Submittals: Submit two paper copies of each submittal, unless otherwise indicated. RTD Project Manager will not return copies.

5. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified in Division 01 Section "Closeout Procedures."

6. Certificates and Certifications Submittals: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

a. Provide a digital signature with digital certificate on electronically-submitted certificates and certifications where indicated.

b. Provide a notarized statement on original paper copy certificates and certifications where indicated.

7. Test and Inspection Reports Submittals: Comply with requirements specified in Division 01 Section "Quality Requirements."

B. Product Data: Collect all information from the same Section into a single submittal.

1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

04/30/2026

SUBMITTAL PROCEDURES

013300 - 7

3. Include the following information, as applicable, and additional information where required:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams showing factory-installed wiring.

b. Printed performance curves.

c. Operational range diagrams.

d. Clearances required to other construction, if not indicated on accompanying Shop Drawings.

5. Submit Product Data before or concurrent with Samples.

6. Submit Product Data in the following format:

a. PDF electronic file.

b. Six paper copies of Product Data, unless otherwise indicated. RTD Project

Manager will return two copies.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional engineer if specified.

2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches.

3. Submit Shop Drawings in the following format:

a. PDF electronic file.

b. Three opaque copies of each submittal. RTD Project Manager will retain two copies; remainder will be returned.

04/30/2026

SUBMITTAL PROCEDURES

013300 - 8

D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

a. When different Sections include samples of materials installed adjacent to each other or within the same room or space, the Contractor shall submit complete submittals for each Section on the same day, when any of the submittals include a substitute product from what is exactly specified. If submittals include products, materials, and colors as specified, such coordination (same day submittal) is not required, but is recommended.

1.) RTD Project Manager reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

2. Identification: Attach label on unexposed side of Samples that includes the following:

a. Generic description of Sample.

b. Product name and name of manufacturer.

c. Sample source.

d. Number and title of applicable Specification Section.

3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity.

Sample sets may be used to determine final acceptance of construction associated with each set.

a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use.

b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.

4. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

a. Number of Samples: Submit one full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. RTD Project Manager/Architect will return submittal with options selected.

5. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or

04/30/2026

SUBMITTAL PROCEDURES

013300 - 9 fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

a. Number of Samples: Submit three sets of Samples. RTD Project Manager will retain two Sample sets; remainder will be returned.

1) Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated.

2) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations.

E. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location.

Include the following information in tabular form:

1. Type of product. Include unique identifier for each product, matching that identified in the contract documents when noted.

2. Manufacturer and product name, and model number if applicable.

3. Number and name of room or space.

4. Location within room or space.

5. Submit product schedule in the following format:

a. PDF electronic file.

b. Three paper copies of product schedule or list, unless otherwise indicated.

RTD Project Manager will return two copies.

F. Contractor's Construction Schedule: Comply with requirements specified below.

1. Time Frame: Extend schedule from date established for commencement of the

Work to date of final completion.

a. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

2. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with and include the following.

a. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

b. Include Startup and Testing Time

c. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for RTD Project Manager's administrative procedures necessary for certification of Substantial Completion.

d. Punch List and Final Completion: Include not more than 14 days for punch list and final completion.

04/30/2026

SUBMITTAL PROCEDURES

013300 - 10

3. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.

a. Phasing: Arrange list of activities on schedule by phase.

b. Work under More Than One Contract: Include a separate activity for each contract.

c. Work by Owner: Include a separate activity for each portion of the Work performed by Owner.

d. Work Restrictions: Show the effect of the following items on the schedule:

1) Revise list below to suit Project.

2) Coordination with existing construction.

3) Limitations of continued occupancies.

4) Uninterruptible services.

5) Partial occupancy before Substantial Completion.

6) Use of premises restrictions.

7) Provisions for future construction.

8) Seasonal variations.

9) Environmental control.

e. Work Stages: Indicate important stages of construction for each major portion of the Work.

4. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and final completion.

5. Upcoming Work Summary: Prepare summary report indicating activities scheduled to occur or commence prior to submittal of next schedule update.

Summarize the following issues:

a. Unresolved issues.

b. Unanswered RFIs.

c. Rejected or unreturned submittals.

d. Notations on returned submittals.

G. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified.

H. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on American Welding Society (AWS) forms. Include names of firms and personnel certified.

I. Installer Certificates: Submit written…