Lemon Crest Elementary School Kitchen Expansion.pdf
PDF 1 MB Posted
- Attached to
- Claremont Boulevard Complete Street Improvement Project Between Ninth Street and Foothill Boulevard
- Solicitation number
- 2026-02
- Issued by
- San Bernardino County, California
About this file
This is a Construction Contract Document package for the Lakeside Union School District (LUSD) for Bid No. 2026-02, the Lemon Crest Elementary School Kitchen Expansion project. The District is soliciting sealed bids from qualified California Class B licensed contractors for the construction of a kitchen expansion at Lemon Crest Elementary School located at 12463 Lemon Crest Drive, Lakeside, California 92040. A mandatory pre-bid job walk and conference is scheduled for May 26, 2026 at 9:00 AM, with attendance required for bid responsiveness. Bids must be submitted to the District Office, Attention: Kristine Rosado, Director of Maintenance, Operations and Transportation, at 12335 Woodside Avenue, Lakeside, CA 92040, no later than 2:00 PM on June 2, 2026. The work shall be completed within eighty-nine (89) calendar days from the Notice to Proceed, and the District reserves the right to reject any or all bids and award the contract to the lowest responsible bidder whose bid complies with all prescribed requirements.
Bid security of not less than 10% of the total bid amount is required, submitted as cash, certified check, cashier's check, or bid bond from a California-admitted surety. The successful bidder must provide a Performance Bond and Payment Bond, each equal to 100% of the total contract price, within ten (10) consecutive calendar days of the Notice of Intent to Award. This is a public works project subject to prevailing wage requirements under California Labor Code Sections 1720-1861, and all contractors and subcontractors must be registered with the California Department of Industrial Relations (DIR). Liquidated damages are set at $1,500.00 per calendar day for delays beyond the completion deadline. The project requires compliance with multiple certifications and documentation including workers' compensation, non-collusion affidavits, asbestos-free materials certification, drug-free workplace certification, tobacco-free school certification, fingerprinting requirements for employees with student contact, and Disabled Veteran Business Enterprise (DVBE) participation goal of 3% of state funds allocated to the District. The project is subject to the Leroy F. Greene School Facilities Act of 1998, requiring prequalification for projects exceeding one million dollars; prequalification status is valid for one calendar year.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid No. 2026-02
LAKESIDE UNION SCHOOL DISTRICT
CONSTRUCTION
CONTRACT DOCUMENTS
For
BID NO. 2026-02
LUSD Lemon Crest Elementary School
KITCHEN EXPANSION
MANDATORY
PRE-BID JOB WALK:
May 26, 2026 9:00 A.M.
BID DUE: June 2, 2026 @ 2:00 P.M.
ALL BONDS AND INSURANCE DOCUMENTS MUST BE RETURNED TO THE FISCAL
SERVICES DEPARTMENT WITHIN 10 DAYS OF THE BOARD AWARD DATE
DOCUMENT 00010
CONTENTS
DOCUMENT DESCRIPTION PAGE
00010 Table of Contents
00020 Notice to Contractors Calling for Bids
00100 Information for Bidders
00200 Contractor’s Certification Regarding Workers Compensation
00300 *Bid Form
00410 *Bid Bond
00430 *Designation of Subcontractors
00450 *Designation of DVBE Subcontractors
00460 Information Required of Bidders
00470 Asbestos-Free Materials Certification
00480 *Non-Collusion Affidavit
00490 *Certification of Contractor & Subcontractor DIR Registration…
00500 Contract
00600 Performance Bond
00610 Payment Bond for Public Works
00620 Recycled Content Certification
00630 Contractors & Subcontractors Fingerprinting Requirements
00640 Drug-Free Workplace Certification
00650 Tobacco-free School Certification…
00655 Tuberculosis Clearance…
00660 Equal Employment Opportunity Statement
00670 Certificate of Non-Debarment
00700 General Conditions
00800 Special Conditions
00810 Request for Substitution…
General Requirements/Specifications
* Denotes pages that must be completed and returned with the bid prior to 2:00 PM on June 2, 2026.
Please contact Kristine Rosado at 619-390-2680 if additional information is needed.
DOCUMENT 00020
NOTICE TO CONTRACTORS CALLING FOR BIDS
NOTICE IS HEREBY GIVEN that the Lakeside Union School District (“District”) is seeking sealed bids from qualified construction contractors for construction of the following public-works project (“Project”):
LUSD LEMON CREST ELEMENTARY SCHOOL KITCHEN EXPANSION
PLACE FOR SUBMITTING BIDS: Bids must be submitted to the District at the following location (“Place for Submitting Bids”):
Lakeside Union School District Office Attn: Kristine Rosado, Director of Maintenance, Operations and Transportation 12335 Woodside Avenue Lakeside, CA 92040
BID DEADLINE: Bids must be received at the Place for Submitting Bids not later than 2:00 PM on June 2, 2026 (“Bid Deadline”).
BID DOCUMENTS: A contractor may obtain/download the documents necessary to submit a bid (“Bid Documents”) from: www.lsusd.net/purchasing.
REQUIRED BID SECURITY: Each bid must be submitted with bid security as described in the Information For Bidders.
CONTRACTOR LICENSE: The class or classes of California contractor licenses required to bid on and perform the Work are: B.
PRE-BID CONFERENCE: The District will conduct a mandatory pre-bid conference and site visit at Lemon Crest Elementary School, 12463 Lemon Crest Dr., Lakeside, CA 92040 at 9:00 AM on May 26, 2026. Attendance at the pre-bid conference and site visit is MANDATORY, and any bidder that does not attend shall be deemed non-responsive.
SURETY BONDS: As described in the General Provisions, the successful bidder must provide a Performance Bond and a separate Payment Bond, each in an amount equal to 100% of the total Contract Price, and each issued by a California-admitted surety as defined in Code of Civil Procedure Section 995.120.
LABOR LAW: The Project is a “public work” project that is subject to, among other laws, Labor Code Sections 1720 through 1861, inclusive. As described in the Instructions For Bidders, each contractor (including subcontractors) must be registered with the California Department of Industrial Relations (“DIR”) in accordance with Labor Code Section 1725.5, and bidders must provide evidence of registration for themselves and their subcontractors. Each worker on the Project must be paid not less than the applicable prevailing rates of per-diem wages in the locality in which the Work is to be performed for each craft or type of worker needed to execute the Contract (“Prevailing Wages”). The Project is subject to compliance monitoring and enforcement by the DIR. The successful bidder will be required to post all job-site notices required by DIR regulations and other applicable law. If so, specified in the Special Provisions, the District will conduct a mandatory conference for the purpose of describing labor-law requirements.
PUBLICATION DATES: May 8, 2026; May 15, 2026.
[END OF DOCUMENT]
DOCUMENT 00020
NOTICE TO CONTRACTORS CALLING FOR BIDS
DOCUMENT 00100
INFORMATION FOR BIDDERS
1. Preparation of Bid Form.
The District invites bids on the attached form to be submitted at such time and place as is stated in the Notice to Contractors Calling for Bids. All blanks in the bid form must be appropriately filled in. All bids must be submitted in sealed envelopes bearing on the outside the name of the bidder, his address, and the name of the Project for which the bid is submitted. All prices must be stated in both words and figures where so indicated, and where there is a conflict in the words and figures, the words shall govern. Prices, wording and notations must be in ink or typewritten. Erasures or other changes shall be noted over by signature of the bidder. It is the sole responsibility of the bidder to see that his bid is received in proper time. All bids received after the scheduled closing time for receipt of bids will be returned to the bidder unopened.
2. Unit Prices.
If the unit prices and the extended amount expressed by a Bidder for any item are not in agreement, the unit price alone will be considered as representing the Bidder’s intention.
If the amount set forth as a unit price is ambiguous, unintelligible or uncertain for any cause, or is omitted, or in the case of unit basis items, is the same amount as the entry in the “Total” column, then the amount set forth in the “Total” column for the item shall prevail in accordance with the following:
(a) As to lump sum items, the amount set forth in the “Total” column shall be the unit price.
(b) As to unit basis items, the amount set forth in the “Total” column shall be divided by the estimated quantity for the item and the price thus obtained shall be the item price.
3. Bid Security.
Each bid shall be accompanied by: (a) cash; (b) a certified check made payable to the District; (c) a cashier’s check made payable to the District; or (d) a satisfactory bid bond payable to the District executed by the bidder as principal and an admitted surety approved to conduct business in the State of California as surety, in an amount not less than 10% of the maximum amount of the bid. Personal sureties and unregistered surety companies are unacceptable. The California admitted surety insurer, as defined in California Code of Civil Procedure Section 995.120, shall be a satisfactory corporate surety. The cash, check or bid bond shall be given as a guarantee that the bidder shall execute the Contract if it be awarded to the bidder in conformity with the Contract Documents and shall provide the surety bond or bonds as specified therein within ten (10) consecutive calendar days after Notice of Intent to Award Contract to the bidder
In the event the bidder to whom the Notice of Intent to Award Contract is given fails or refuses to post the required bonds, as provided in Section 10 below, and return executed copies of the Contract within ten (10) consecutive calendar days, the District may declare the bidder’s bid deposit or bond forfeited as damages caused by the failure of the bidder to post the required bonds and execute such copies of the Contract, and may award the Contract to the next lowest responsible bidder, or may call for new bids.
4. Faxed or US Mail/FedEx or Overnight Service Carrier Bids.
Normally, all bids must be under sealed cover. However in this case, the District will not accept any bids or bid modifications submitted by facsimile or US mail/FedEx or any overnight carrier service transmission.
5. Signature.
The bid must be signed in the name of the bidder and must bear the signature in longhand of the person or persons duly authorized to sign the bid on behalf of the bidder. All signatures are to be in ink. In the event that the bidder is a joint venture or partnership, there shall be submitted with the bid certifications signed by authorized officers of each of the parties to the joint venture or partnership, naming the individual who shall be the agent of the joint venture or partnership, who shall sign all necessary documents for the joint venture or partnership and who, should the joint venture or partnership be the successful bidder, shall act in all matters relative to the Contract for the joint venture or partnership.
6. Modifications.
Changes in or additions to the bid form, recapitulations of the work bid upon, alternative proposals, or any other modification of the bid form that is not specifically called for in the Contract Documents may result in the District’s rejection of the bid as not being responsive to the Invitation to Bid. No oral or telephonic modification of any bid submitted will be considered and a modification may be considered only if the postmark evidences that a confirmation, duly signed by the bidder, was placed in the mail prior to the opening of bids.
Bids may be rejected if they show any alteration in form, are incomplete, or contain irregularities of any kind.
7. Erasures/Mutilation of Bid Documents.
The bid submitted must not contain any erasures, interlineations, or other corrections unless each such correction is suitably authenticated by affixing in the margin immediately opposite the correction the surname or surnames of the person or persons signing the bid.
Bidders should not deface or mutilate the bid documents to the extent that they may not be usable for construction purposes.
8. Examination of Site and Contract Documents.
At its own expense and prior to submitting its bid, each bidder shall visit the site of the proposed work and fully acquaint himself with the conditions relating to the construction and labor so that the bidder may fully understand the facilities, which include but are not limited to difficulties, and restrictions attending the execution of the work under the Contract. Bidders shall be responsible for scheduling their site visit with the District Representative at a time convenient to the District Representative. Bidders shall thoroughly examine and be familiar with the drawings and specifications. Each bidder shall also determine the local conditions which may, in any way affect the performance of the work, including the prevailing wages and other relevant cost factors; familiarize itself with all federal, state and local laws, ordinances, rules, regulations and codes affecting the performance of the work, including the cost of permits and licenses required for the work;
make such surveys and investigations, including investigations of subsurface or latent physical conditions at the site or where work is to be performed. The failure or omission of any bidder to receive or examine any Contract Documents, form, instrument, addendum, or other document or to visit the site and acquaint himself with conditions there existing shall in no way relieve any bidder from any obligation with respect to their bid or to the Contract. The submission of a bid shall be taken as incontrovertible evidence of compliance with this section.
9. Withdrawal of Bids.
Any bidder may withdraw his bid either personally or by confirmed written request at any time prior to the scheduled closing time for receipt of bids. Any request to withdraw a bid shall be so worded so as not to reveal the amount of the original bid. Withdrawn bids may be resubmitted until the scheduled time for receipt of bids, so long as the resubmitted bids are in full conformance with the Contract Documents. After the scheduled closing time for receipt of bids, a bidder may not withdraw its bid until the expiration of ten (10) calendar days, after which time a bid may be withdrawn only in writing and in advance of actual award of the Contract.
10. Contracts and Bonds.
The Contract form which the successful bidder, as Contractor, will be required to execute, and the form of the Performance Bond equal to 100% of the successful bid, and Payment Bond equal to 100% of the successful bid which the bidder will be required to furnish at the time of execution of the Contract, are included in the Contract Documents and should be carefully examined by the bidder. The required number of executed copies of the Contract, the Performance Bond, and the Payment Bond for Public Works is as specified in the Special Conditions. The Performance and Payment Bonds must be executed by an admitted Surety approved to conduct business in the State of California, pursuant to California Code of Civil Procedure Section 995.120. In addition, to the extent required by law, the Payment and Performance Bonds must be accompanied by a certified copy of the Certificate of Authority of the insurer issued by the Insurance Commissioner of the State of California, a certificate from the Clerk of the County of San Diego that the Certificate of Authority of the insurer has not been surrendered, revoked, cancelled, annulled, or suspended, or if it has that it has been renewed, and four copies of the insurer’s most recent annual statement and quarterly statement filed with the Department of Insurance of the State of California.
11. Interpretation of Plans and Documents.
If any person contemplating submitting a bid for the proposed Contract is in doubt as to the true meaning of any part of the drawings, specifications, or other Contract Documents, or finds discrepancies in, or omissions from the drawings and specifications, that person may submit to Kristine Rosado a written request for an interpretation or correction thereof.
Such submittal may be submitted to the by emailing to (krosado@lsusd.net). The person submitting the request will be responsible for its prompt delivery. Any interpretation or correction of the Contract Documents will be made only by addendum duly issued. Any addenda or bulletins issued by the District Representative and/or the Architect during the time of bidding or forming a part of the documents furnished to bidders for bid preparation shall be covered in the bid and made part of the Contract Documents. In the event that an addendum or bulletin, setting forth material changes, additions or deletions is issued when there is seventy-two (72) hours or less to the bid deadline, the District will extend the bidding deadline by at least seventy-two (72) hours. No person is authorized to make any oral interpretation of any provision in the Contract Documents to any bidder, and no bidder is authorized to rely on any such unauthorized oral interpretation.
12. Bidders Interested in More Than One Bid.
No person, firm, or corporation shall be allowed to make, or file, or be interested in more than one bid for the same work unless alternate bids are specifically called for. A person, firm, or corporation that has submitted a sub-proposal to a bidder, or that has quoted prices of materials to a bidder, is not thereby disqualified from submitting a sub-proposal or quoting prices to other bidders or making a prime proposal.
13. Non-Collusion Affidavit.
Bidders on all public works contracts are required to submit an Affidavit of Non-Collusion with their bid. This form is included with the bid package and must be signed under the penalty of perjury and dated.
14. Reservation.
The District reserves the right to reject any or all bids, or to waive any irregularities or informalities in any bids or in the bidding.
15. Award of Contract.
The award of the Contract, if made by the District, will be to the lowest responsible bidder therefore whose bid complies with all of the prescribed requirements. If alternate bids are called for, the Contract may be awarded at the election of the governing board to the lowest responsible bidder on the base bid, plus any alternate or combination of alternates, as specifically established in the Notice to Contractors Calling for Bids. The time required for completion of the alternate Bid items has been factored into the Contract duration and no additional Contract Time will be awarded for any of the alternate Bid items. The District may elect to include one or more of the alternate Bid items, or to otherwise remove certain work from the Project scope of work, accordingly each Bidder must ensure that each Bid item contains a proportionate share of profit, overhead and other costs or expenses which will be incurred by the Bidder.
16. Evidence of Responsibility.
If bidders were not required to pre-qualify prior to being allowed to bid on the Project, the following information will be required to accompany bids submitted to the District:
Each bid shall be supported by a statement of the bidder’s experience as of recent date on the form entitled “Information Required of Bidder,” bound herein. District may also consider the qualifications and experience of subcontractors and other persons and organizations (including those who are to furnish the principal items of material and equipment) proposed for those portions of the work. Operating costs, maintenance considerations, performance data and guarantees of materials and equipment may also be considered by the District. In this regard, the District may conduct such investigations as the District deems necessary to assist in the evaluation of any bid and to establish the responsibility, qualifications and financial ability of the bidder, proposed subcontractors, and other persons and organizations to do the work in accordance with the Contract Documents to the District’s satisfaction within the prescribed time; the District reserves the right to reject the bid of any bidder who does not pass any such evaluation to the satisfaction of the District.
17. Listing Subcontractors.
Each bidder shall set forth on the form provided herein, and submit with its sealed bid at the time bids are due the name and address of the place of business of each subcontractor who will perform work, labor, furnish materials, or render service to the bidder on said Contract in excess of one-half (1/2) of one percent (1%) of the total bid. Bidders are required to submit the address, phone number, DIR registration numbers, license number and license expiration date of each subcontractor listed in its bid within twenty-four (24) hours of bid opening. No time extension will be allowed for submission of additional information required by this Section.
18. Workers’ Compensation.
In accordance with the provisions of Section 3700 of the Labor Code, Contractor shall secure the payment of compensation to his employees. Contractor shall sign and file with the District the following certificate prior to performing the work under this Contract:
I am aware of the provisions of Section 3700 of the Labor Code, which requires every employer to be insured against liability for Workers’ Compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this Contract.
The form of such certificate, Contractors Certificate Regarding Workers Compensation, is included as part of the Contract Documents.
19. Substitution of Security.
The Contract Documents call for monthly progress payments based upon the percentage of the work completed. The District will retain five percent (5%) of each progress payment as security for completion of the work. At the request and expense of the successful bidder, the District will substitute securities for the amount so retained in accordance with Public Contract Code Section 22300 and the Contract Documents.
20. Prevailing Wages.
This is a public works project, and the bidder to which the District awards a contract for the Project, and each of that bidder’s subcontractors of any tier, shall be required to pay not less than the general prevailing rates of per-diem wages in the locality in which the work is to be performed for each craft or type of worker needed to execute the contract (“Prevailing Wages”). A copy of the per-diem rates of Prevailing Wages shall be posted at the site of the Project. Rates are available at http://www.dir.ca.gov/dlsr/pwd/index.htm.
21. Labor Compliance.
Except as provided in Labor Code section 1771.1(a), no Contractor or Subcontractor may be listed on a bid proposal for a public works project submitted or perform work on a public works contract awarded unless registered with the Department of Industrial Relations pursuant to California Labor Code section 1725.5. This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
Contractor and any Subcontractors engaging in work on the Project are required to review and comply with the provisions of the California Labor Code sections 1720 et seq., and http://www.dir.ca.gov/dlsr/pwd/index.htm the regulations of the Department of Industrial Relations implementing those provisions.
These statutory and regulatory provisions contain specific requirements concerning, for example, the determination and payment of prevailing wages, retention, inspection and auditing of payroll records, use of apprentices, payment of overtime compensation, and various penalties or fines which may be imposed for violations of the requirements of the chapter. Submission of a bid proposal constitutes the Bidder's representation that it has thoroughly reviewed these statutory and regulatory requirements and agrees to bind every Subcontractor performing work on the Project to these requirements to the extent such requirements are applicable to the Subcontractor’s work.
22. Contractor's License.
To perform the work required for this Project, bidders must possess the appropriate Contractor's License for the portion of the work bid upon, and bidders must maintain the license throughout the duration of the Contract. If, at the time the bids are opened, bidder is not licensed to perform the Project in accordance with Division 3, Chapter 9 of the Business and Professions Code of the State of California and the Notice to Contractors Calling for Bids, the bid will not be considered. The first payment for work or material under any contract shall not be made unless and until the Registrar of Contractors verifies to the District that the records of the Contractor’s State License Board indicate that the Contractor was properly licensed at the time the contract was awarded. Any bidder or contractor not so licensed shall be subject to all legal penalties imposed by law, including, but not limited to, any appropriate disciplinary action by the Contractor’s State License Board. Failure of the bidder to obtain proper and adequate licensing for an award of a contract shall constitute a failure to execute the contract and may result in the forfeiture of the security by the bidder.
23. Storm Water Permit for Construction Activity.
a. It shall be the responsibility of the successful Bidder to file a Notice of Intent and procure a State Water Resources Control Board (State Water Board) Water Quality Order No. 99-08-DWQ, National Pollutant Discharge Elimination System General Permit for Storm Water Discharges Associated with Construction Activity (Permit) for all projects that involve construction on or disturbance of one acre or more of land.
b. The successful Bidder shall be solely responsible for preparing and implementing a Storm Water Pollution Prevention Plan (SWPPP) prior to initiating work. The successful Bidder shall be responsible for procuring, implementing and complying with the provisions of the Permit and the SWPPP, including the standard provisions, and monitoring and reporting requirements as required by the Permit.
The Permit requires the SWPPP to be a “living document” that changes as necessary to meet the conditions and requirements of the job site as it progresses through different phases of construction and is subject to different weather conditions.
c. It shall be the responsibility of all Bidders to evaluate and include in the bid the cost of procuring the Permit and preparing the SWPPP, as well as complying with the SWPPP and any necessary revisions to the SWPPP. The successful Bidder shall also include in his or her bid the cost of monitoring as required by the Permit.
d. Bidder shall also comply with the lawful requirements of any applicable municipality, the District, drainage district, and other local agencies regarding discharges of storm water to separate storm drain system(s) or other water courses under their jurisdiction, including applicable requirements in municipal storm water management programs. This requirement applies to all projects, including those projects that impact less than one acre or disturb less than one acre.
e. Storm, surface, nuisance or other waters may be encountered at various times during the course of construction. By submitting its bid, Bidder hereby acknowledges that it has investigated the risk arising from such waters, has prepared its bid accordingly, and assumes any and all liabilities arising there from.
f. Failure to comply with the Permit or any applicable municipal permit is a violation of law and may be subject to penalties, fines, or additional regulatory requirements.
In addition to the other indemnities included herein, Bidder hereby agrees to indemnify and hold harmless District, its officers, directors, agents and employees from and against any and all fines, penalties, claims or other regulatory requirements imposed as a result of noncompliance with the Permit or the applicable municipal permit, unless such noncompliance is the result of District’s sole established negligence, willful misconduct or active negligence.
g. District may seek damages from Bidder for project delays in accordance with the contract documents caused by Bidder’s failure to comply with the Permit or applicable municipal permit.
24. Bid Deposit Return.
The District will return the security accompanying the bids of all unsuccessful bidders no later than sixty (60) calendar days after award of the Contract.
25. Insurance.
Prior to commencement of the work, the successful bidder shall purchase and maintain insurance as set forth in the General Conditions, in the amounts specified in the Special Conditions to these Contract Documents, and in a form acceptable to the District, from a company or companies lawfully authorized to do business in California as admitted carriers having an “A” policy holders rating and a financial size rating of at least Class VII in accordance with the most current Best’s Key Rating Guide, Property-Casualty. Such insurance shall be adequate to protect themselves from claims under Workers’ Compensation Acts, and from claims from damages for personal injury, including death, and damage to property, which may arise from operations under the Contract and from the ownership, maintenance or uses of motor vehicles, or claims involving blanket contractual liability applicable to the successful bidder’s obligations under the Contract Documents, and completed operations, independent contractors, and Broad Form Property damage, without exclusion for collapse, explosion, demolition, underground coverage, and excavating. The successful bidder shall be required to file with the District certificates of such insurance, and shall name, by way of endorsement on any policy of insurance, the District as additional insured. Failure to furnish such evidence of insurance may be considered default by the successful bidder.
26. Request For Substitutions.
a. For purposes of this provision the term "substitution" shall mean the substitution of any material, process or article that is substantially equal or better in every respect to that so indicated or specified in the specifications.
b. Whenever in specifications any material, process, or article is indicated or specified by grade, patent, or proprietary name or by name of manufacturer, such specifications shall be deemed to be used for the purpose of facilitating the description of the material, process or article desired and shall be deemed to be followed by words "or equal." Bidders may, unless otherwise stated, offer for substitution any material, process or article which shall be substantially equal or better in every respect to that so indicated or specified. However, the District has adopted certain uniform standards for certain materials, processes and articles. If any material, process or article offered for substitution by bidders is not, in the opinion of the Architect and the District, substantially equal or better in every respect to that specified, bidders shall furnish the material, process or article specified. The burden of proof as to the equality of any material, process or article shall rest with the bidders.
c. Bidders shall submit requests together with substantiating data for substitution of any
"or equal" material, process or article no later than ten (10) calendar days prior to the bid opening. Provisions authorizing submission of "or equal" substitution justification data shall not in any way authorize an extension of time for performance of this Contract. Furthermore, if a proposed "or equal" substitution request is rejected, a bidder shall be responsible for including the specified material, process or article in its bid. The District shall not be responsible for any costs of bidders associated with "or equal" substitution requests. The District has the complete and sole discretion to determine if a material, process or article is an "or equal" material, process or article that may be substituted.
d. For purposes of subdivision (c) above, data required to substantiate requests for substitutions of an "or equal" material, process or article data shall include a signed affidavit from the bidder stating that the substituted "or equal" material, process or article is equivalent to that specified in the specification in every way except as listed on the affidavit. Substantiating data shall also include any and all illustrations, specifications, and other relevant data including catalogue information which describes the requested substitution "or equal" material, process or article and substantiates that it is an “or equal” to the material process or article specified. In addition, the submittal documentation must also include a statement of the cost implications of the substitution being requested stating whether and why the substitution of the "or equal" material, process or article will reduce or increase the Contract price. The substantiating data must also include information regarding the durability and lifecycle cost of the requested substituted "or equal" material, process or article. Failure to submit all the needed substantiating data, including the signed affidavit, to the District Representative in a timely fashion so that the substitution can be adequately reviewed may result in the rejection of the proposed substitution. The District Representative and Architect are not obligated to review multiple substitution submittals for the same product or item due to the bidder’s failure to submit a complete package initially.
e. Time limitations in this Article must be complied with strictly and in no case will an extension of time for completion be granted because of bidder’s failure to request the substitution of an alternative item at the times and manner set forth herein in subdivision (c). Further, the bidder shall bear the costs of all engineering work associated with the review of submittals for substitution of equals.
f. In event Contractor furnishes material, process, or article more expensive than that specified, the difference in cost of such material, process, or article so furnished shall be borne by Contractor.
27. Anti-Discrimination.
It is the policy of the District that in connection with all work performed under contracts, there be no discrimination against any prospective or active employees engaged in the work because of race, color, ancestry, national origin, religious creed, sex, age or marital status. The successful bidder agrees to comply with applicable Federal and California laws including, but not limited to, the California Fair Employment and Housing Act, beginning with Government Code 12900, and Labor Code 1735. In addition, the successful bidder agrees to require like compliance by any subcontractors employed on the work.
28. Disabled Veteran Business Enterprises.
Compliance with Disabled Veteran Business Enterprise (DVBE) contracting goals is required for this project. In accordance with Education Code Section 17076.11 the District has a DVBE participation goal of 3% per year of the overall dollar amount of state funds allocated to the District pursuant to the Leroy F. Greene School Facilities Act of 1998, and expended each year by the District. The District is seeking DVBE participation in this project.
Bidders must indicate on the bid form whether they are a certified DVBE and provide a copy of the DVBE Certification Letter. Prior to, and as a condition precedent for final payment under the Contract, the successful bidder may be required to provide the District with written documentation identifying the amount paid to certified DVBE subcontractors and suppliers in performance of the Contract and provide a copy of the DVBE Certification Letter for each DVBE. This documentation will be used by the District to evaluate its success in meeting its DVBE participation goal.
29. Pre-Bid Meeting.
There will be a mandatory pre-bid job walk at 9:00 A.M. on the 26th of May, 2026 at Lemon Crest Elementary School, 12463 Lemon Crest Dr., Lakeside, CA 92040.
Bids will not be accepted from any bidder who does not attend the mandatory pre-bid job walk. Only bidders that attend the pre- bid meeting will receive any addendums that are issued.
30. No Telephone Availability.
Bidders are advised that on bid date telephones WILL NOT be available at the District Administrative Offices for use by bidders or their representatives.
31. Fingerprinting Requirements.
By law it is the District’s responsibility to determine whether a contractor must provide fingerprint certification. Pursuant to Education Code Section 45125.2, the District considers the totality of the circumstances in order to determine if fingerprinting of employees of a contractor working on a school site is required. Factors to be considered include the length of time the contractor’s employees are on school grounds, whether students are in proximity with the location where the contractor’s employees are working, and whether the contractor’s employees are working alone or with others.
A determination regarding whether fingerprint certification is required is contained in the Special Conditions. This form is included with the bid package and must be signed under penalty of perjury and dated.
32. Ethics in Bidding.
The District expects the bidders to maintain high ethical standards in engaging in the competitive bidding process. The bid amount of one bidder should not be divulged to another before the award of the subcontract or order, nor should it be used by bidders to secure a lower proposal from another bidder on that project (bid shopping). Subcontractors or suppliers should not request information for the bidder regarding any sub-bid in order to submit a lower proposal on that project (bid peddling). The District may consider any bidder found to be engaging in such practices to be a non-responsive or non- responsible bidder and may reject its bid on that ground.
33. Contract Procedures.
The Contract Documents contemplate the following procedures upon receipt of bid and the District obtaining an appropriation from the State Allocation Board (SAB) (when required):
a. The District will give the successful bidder a Notice of Intent to Award Contract. The
District will be bound to enter into the Contract if the SAB apportions funds for the Project, provided that the Project is not placed on the SAB "unfunded list," and the successful bidder does all acts described in subparagraph b below.
b. Following the giving of the Notice of Intent to Award of Contract, the successful bidder shall post the Performance and Payment Bonds, provide certificates of insurance, and other certificates, and return executed copies of bonds and Contracts.
34. Filing of Bid Protests.
Bidders may file a “protest” of a Bid with Kristine Rosado at krosado@lsusd.net. In order for a Bidder’s protest to be considered valid, the protest must:
a. Be filed in writing within three (3) calendar days after the bid opening;
b. Clearly identify the specific irregularity or accusation;
c. Clearly identify the specific District staff determination or recommendation being protested;
d. Specify, in detail, the grounds of the protest and the facts supporting the protest: and
e. Include all relevant, supporting documentation with the protest at time of filing.
If the protest does not comply with each of these requirements, it will be rejected as invalid.
If the protest is valid, the Controller, or other designated District staff member, shall review the basis of the protest and all relevant information. The District will provide a written decision to the protestor, which decision shall be final.
35. Prequalification
Bidders and subcontractors are required to be prequalified for projects in excess of one million dollars ($1,000,000) in estimated value using any funds received or reimbursed pursuant to the Leroy F. Greene School Facilities Act of 1998 or any state school bond.
For qualifying projects, subcontractors in the trades of mechanical, electrical and plumbing are required to be prequalified. Prequalification status is valid for one (1) calendar year.
This Project is/is not_ X subject to prequalification.
DOCUMENT 00100
INFORMATION FOR BIDDERS
DOCUMENT 00200
CONTRACTOR’S CERTIFICATE REGARDING WORKERS’ COMPENSATION
Labor Code Section 3700 in relevant part provides:
Every employer except the State shall secure the payment of compensation in one or more of the following ways:
(a) By being insured against liability to pay compensation in one or more insurers duly authorized to write compensation insurance in this State.
(b) By securing from the Director of Industrial Relations a certificate of consent to self-insure, which may be given upon furnishing proof satisfactory to the Director of Industrial Relations of ability to self-insure and to pay any compensation that may become due to his employees
I am aware of the provisions of Section 3700 of the Labor Code, which require every employer to be insured against liability for Workers’ Compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this Contract.
Contractor
By Signature
Title
(In accordance with Article 5 (commencing at Section 1860), Chapter 1, Part 7, Division 2 of the Labor Code, the above certificate must be signed and filed with the awarding body prior to performing any work under this Contract.)
DOCUMENT 00300
BID FORM
Company
TO: LAKESIDE UNION SCHOOL DISTRICT, acting by and through its Board of Education, herein called the “District”:
1. Pursuant to and in compliance with your Notice to Contractors Calling for Bids and the other documents relating thereto, the undersigned bidder, having thoroughly examined and familiarized himself with the terms of the Contract, the local conditions affecting the performance of the Contract and the cost of the work at the place where the work is to be done, and with the drawings and specifications and other Contract Documents, hereby proposes and agrees to perform, within the time stipulated, the Contract, including all of its component parts, and everything required to be performed, including its acceptance by the District and to provide and furnish any and all of the labor, materials, tools, expendable equipment, and all utility and transportation services necessary to perform the Contract and complete in a workmanlike manner all of the work required in connection with the Project described below:
BID NO. 2026-02
PROJECT TITLE: LUSD LEMON CREST ELEMENTARY SCHOOL KITCHEN
EXPANSION
all in strict conformity with the drawings and specifications and other Contract Documents, including addenda nos. , , ,and , on file at the office of the said District, for the total sum of:
Bid Amount
$ 80,000.00
Allowance
Total Bid in Numbers
Total Bid Price in Written Form
TOTAL BID PRICE INCLUDES ALLOWANCES FROM THE SPECIAL CONDITIONS
Base 10% Bid Bond on total bid price.
Bid will be awarded to one vendor.
Bids shall be valid for 30 calendar days after the Bid opening date.
In case of discrepancy between the written price and the numerical price, the written price shall prevail. Said sums include all applicable taxes and costs.
It is understood that the District reserves the right to reject this bid and that this bid shall remain open and not be withdrawn for the period specified in the Notice to Contractors Calling for Bids.
2. Attached is the required bid security in the amount of not less than 10% of the Bid:
$ . Bid Bond, Certified check, cashier’s check or cash
(Circle one)
3. Non-Collusion Affidavit is attached hereto.
4. The required list of proposed subcontractors is attached hereto.
5. It is understood and agreed that if written notice of intent to accept this bid is mailed, emailed, or delivered to the undersigned after the opening of the bid, and within the time this bid is required to remain open, or at any time thereafter before this bid is withdrawn, the undersigned will execute and deliver to the District a contract in the form attached hereto. The undersigned will submit the executed Contract, Performance Bond and Payment Bond, and Insurance Certificates as specified, all within ten (10) consecutive calendar days after Notice of Intent to Award Contract. The work under the Contract shall be commenced by the undersigned bidder, if awarded the Contract, on the date to be stated in the District’s Notice to the Contractor to Proceed and shall be completed by the Contractor in the time specified in the Contract Documents. The Contractor shall not start work on the Project until all paperwork required herein is timely and correctly submitted to the District. No time extensions shall be granted to Contractor for Contractor's failure to comply with these provisions.
6. Notice of Acceptance or requests for additional information should be addressed to the undersigned at the address stated below:
7. The names of all persons interested in the foregoing proposal as principals are as follows:
(IMPORTANT NOTICE: If bidder or other interested person is a corporation, state legal name of corporation, also names of the president, secretary, treasurer, and manager thereof; if a co partnership, state true name of firm, also names of all individual copartners comprising the firm; if bidder or other interested person is an individual, state first and last names in full.)
8. Bidder certifies that he is licensed in accordance with the law providing for the registration of Contractors, License No. , Expiration Date , Class of License . If the bidder is a joint venture, each member of the joint venture must include the above information.
9. Bidder certifies that his is/is not (circle one) DVBE certified. If bidder is DVBE certified, please attach a copy of the DVBE certification letter.
10. Pursuant to Section 7103.5 of the Public Contract Code submitting a bid to the District, the bidder offers and agrees that if the bid is accepted, it will assign to District all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Section 15) or under the Cartwright Act (Chapter 2 (commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, materials, or services by the bidder for sale to the purchasing body pursuant to the bid. Such assignment shall be made and become effective at the time the purchasing body tenders final payment to the bidder.
Proper Name of Bidder
Address
Signature of Bidder Date
Note: If bidder is a corporation or partners authorized to sign contracts on behalf of the partnership; and if bidder is an individual, the bidder’s signature shall be placed above. If bidder is a corporation, affix corporation seal.
I, , the of the bidder, hereby certify under penalty of perjury under the laws of the State of California, that all of the information submitted by the bidder in connection with this bid and all of the representations made herein are true and correct. Executed on this day of , at County, California.
Proper Name of Bidder
Signature of Bidder
NOTE: If bidder is a corporation, the legal name of the corporation shall be set forth above together with the signatures of authorized officers or agents and the document shall bear the corporate seal; if bidder is a partnership, the true name of the firm shall be set forth above together with the signature of the partner or partners authorized to sign contracts on behalf of the partnership; and if bidder is an individual, his or her signature shall be placed above.
Business Address:
Place of Residence:
Telephone: ( ) Fax: ( )
Bidder must submit the following documents with this Bid Form in order to be considered responsive:
Bid Bond Designation of Subcontractors Designation of DVBE Subcontractors Non-Collusion Affidavit Certification of Contractor and Subcontractor DIR Registration
Other documents to be submitted with this bid or within 24 hours after bid opening:
Contractor's Certification Regarding Workers' Compensation Information Required of Bidders Asbestos-Free Materials Certification
Recycled Content Certification Subcontractors’ Address, Phone Numbers, License Numbers & Expiration Dates Tobacco-free Certification Equal Opportunity Statement Certificate of Non-Debarment
DOCUMENT 00300
BID FORM
DOCUMENT 00410
BID BOND
We, , as Principal, and , as Surety, are held and firmly bound unto the LAKESIDE UNION SCHOOL DISTRICT, hereinafter called the District, in the penal sum of PERCENT ( %) OF THE TOTAL AMOUNT OF THE BID of the Principal submitted to the said DISTRICT for the work described below for the payment of which sum in lawful money of the United States, well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that whereas the Principal has submitted the accompanying bid dated 2026 for .
NOW, THEREFORE. If the Principal shall not withdraw said bid within the period specified therein after the opening of the same, or, if no period be specified, within sixty (60) days after said opening; and, if the Principal be awarded the contract, and shall within the period specified therefore, or if no period be specified, within ten (10) consecutive calendar days after the Award of Contract (which date shall be the day following the Board of Education approval of the award) complete the prescribed forms are presented to him for signature enter into a written contract with the District in accordance with the bid as accepted and give bond with good and sufficient surety or sureties, as may be required, for the faithful performance and proper fulfillment of such contract and for the payment for labor and materials used for the performance of the contract, or in the event of the withdrawal of said bid within the period specified or the failure to enter into such contract and give such bonds within the time specified. If the Principal shall pay the District the difference between the amount specified in said bid and the amount for which the District may procure the required work and/or supplies, if the latter amount be in excess of the former, together with all costs incurred by the District in again calling for bids, then the above obligation shall be void and of no effect, otherwise to remain in full force.
Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract on the call for bids, or to the work to be performed hereunder, or the specifications accompanying the same, shall affect its obligation under this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of said contract or the call for bids, or to the work, or to the specifications.
In the event a lawsuit is brought upon this bond by the District and judgment is recovered, the surety shall pay all litigation expenses incurred by the District in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and investigation expenses.
IN WITNESS WHEREOF, the above-bound parties have executed this instrument under their several seals this day of 2026, the name and corporate seal of each corporate party being hereto affixed and these presents duly assigned by its undersigned representative, pursuant to authority of its governing body.
(Corporate Seal)
Principal
(Corporate Seal) Surety
By Attorney-in-Fact (Attach Attorney-in-Fact Certificate) Title
DOCUMENT 00410
BID BOND
DOCUMENT 00430
DESIGNATION OF SUBCONTRACTORS
In compliance with the Subletting and Subcontracting Fair Practices Act (Chapter 4 (commencing at Section 4100), Part 1, Division 2 of the Public Contract Code of the State of California) and any amendments thereof, each bidder shall set forth the information requested below for each subcontractor who will perform work or labor or render service to the prime contractor in or about the construction of the work or improvement to be performed under this Contract in an amount in excess of one-half (1/2) of one percent (1%) of the prime contractor’s total bid. The prime contractor shall list only one subcontractor for each such portion as is defined by the prime contractor in this bid.