Legion Hall Road Paving_BID SCHEDULE.pdf

PDF 81 KB Posted

Attached to
Legion Hall Road Drainage Paving Project
Solicitation number
QQ-128255
Issued by
Brunswick County, Virginia

About this file

This is a Bid Schedule for the Legion Hall Road Drainage Paving Project, a Commonwealth of Virginia project located at 1077 Legion Hall Road, Grundy, Buchanan County, Virginia. The project involves the reclamation of an abandoned mine portal, clogged stream, and associated land. The bid schedule contains nine line items encompassing mobilization, site preparation and access route work, and various paving and drainage-related activities. Specific quantities include 360 linear feet of stone (VDOT No. 1), 180 tons of stone (VDOT No. 21B), 20 tons of silt fence, 100 linear feet of asphalt repair for ditch work, 60 linear feet of asphalt repair for SM9.5A, 20 tons of asphalt sealer, 170 gallons of revegetation materials, and 0.01 acres of site preparation. Mobilization is limited to a maximum of 10 percent of the total base bid amount.

Bidders are required to submit unit prices for all line items, with payment calculated on actual units used and verified in the field. Any bid totaling $100,000 or more requires submission of a bid bond. The total bid price encompasses line items 2 through 9, with line item 1 (mobilization) calculated separately as a percentage of the base bid. The bid schedule specifies that the total bid price will be used to establish contract award value and determine performance and payment bond amounts. Bidders who enter $0 as a unit price or leave unit prices blank will be considered nonresponsive. In cases of pricing errors, unit prices will govern over extended price calculations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Line

Item No.

Technical Specifications

Section Approx.

Quantity Units Unit Price Total Price

1 1 1 Each

2 2 360 L.F.

3 4 180 Ton

4 4 20 Ton

5 5 100 L.F.

6 6 60 L.F.

7 6 20 Ton

8 7 170 Gal

9 8 0.01 Acre

Gal - Gallon

(Signature) (Title)

"The Total Bid Price will be utilized for determining the amount of bid, to establish a contract award value, and to determine the performance and payment bond amounts for the successful Bidder. Each Bidder must submit a bid bond for all bids of

$100,000 or more. Payment will be made on actual units used and verified in the field. Correct pricing is extremely important and price should be double checked before submitting a bid. In the case of errors in the extension of prices, the unit price shall govern." Any bidder who enters $0 as a unit price or leaves the unit price blank shall be considered a nonresponsive bidder.

Total Bid Price (Line Items 1 - 9)

(Firm) (Date)

Measurement Unit Definitions Total Base Bid (Line Item 2 - 9)

L.F. - Linear Feet

Revegetation

VDOT No. 21B Stone

VDOT No. 1 Stone

Silt Fence

Asphalt Repair - Ditch Repair

Asphalt Repair - SM9.5A

Asphalt Sealer

BID SCHEDULE

LEGION HALL ROAD DRAINAGE PAVING PROJECT

Item Name

Mobilization Maximum Limit of No greater than 10% of Total Base Bid amount.

Site Preperation - Access Route

BID SCHEDULE

File details come from the government source that posted it. Updated .