LCS GC Bid Package - 26-03-30.pdf
PDF 13 MB Posted
- Solicitation number
- 35886
- Issued by
- New London County, Connecticut
About this file
This is an Invitation to Bid (ITB) document issued by the Town of Lisbon, Connecticut, through the Lisbon Central School Building Committee for general contractor services to renovate approximately 1,200 square feet of science laboratory space at Lisbon Central School located at 15 Newent Road, Lisbon, CT 06351. The project scope encompasses selective demolition, interior finishes (acoustical ceiling, resilient flooring, painting), casework installation, plumbing modifications, HVAC work, and electrical upgrades including LED lighting fixtures and control systems. A non-mandatory site walk-through was held on April 6, 2026, at 4:00 PM. Questions and requests for information were due by April 7, 2026, end of day. Sealed bids were due on April 23, 2026, at 1:00 PM at the First Selectman's office, with bid opening and reading held immediately following submission. The anticipated construction schedule includes a Notice to Proceed on April 29, 2026, construction start on June 22, 2026 (or upon vacancy of the science wing), casework delivery on July 13, 2026, and project completion by August 19, 2026, with science room occupancy on August 20, 2026.
The project is a prevailing wage municipal project requiring certified payroll documentation and standard AIA billing procedures. Bid surety in the form of a certified check or bid bond in the amount of five percent (5%) of the bid is required. The successful bidder shall furnish a 100% Performance Bond and Payment Bond along with proof of liability insurance naming the Town of Lisbon and Lisbon Board of Education as additional insureds. Minimum liability insurance limits include $1,000,000 each occurrence for bodily injury and property damage, $2,000,000 general aggregate, and $5,000,000 excess umbrella liability. The sample contract references anticipated liquidated damages of $1,000 per day for schedule delays. Contractors must submit three owner references for similar work, acknowledgment of all addenda, and a non-collusive bid statement. All materials except paint are assumed to be either specified or equivalent, with substitutions requiring separate documentation and submittals. Work shall be performed between 7:00 AM and 7:00 PM, with CORI checks required for all workers, daily sign-in logs mandatory, and strict safety and behavioral standards enforced on the school property.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| LCS GC Bid Package - 26-03-30.pdf.crdownload | CRDOWNLOAD file | |
| 35886_Apr_6_26_solicitation_doc.pdf | ||
| LCS GC Bid Package - Addendum 1 4-15-26.pdf | ||
| 35886_Apr_1_26_solicitation_doc.pdf | ||
| 35886_Apr_27_26_solicitation_doc.pdf | ||
| 35886_Apr_20_26_solicitation_doc.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 1 of 11
Invitation to Bid 2026-01
General Contractor Services
Renovation of Science Lab at Lisbon Central School, Lisbon, CT
March 30, 2026
Site Walk Through: April 6, 2026
Questions Due: April 7, 2026
Sealed Bids Due: April 23, 2026 @ 1pm
All questions to be emailed to:
dave.w@river-electric.net
Copy the following:
athibeault@downesco.com raymond.joly860@gmail.com baah84@comcast.net mikezelasky@gmail.com
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 2 of 11
Table of Contents
Division 0 – Procurement & Contract Requirements
1. Invitation to Bid
2. Schedule
3. Contract Documents
4. Wages & Invoices
5. Intent to Bid/Bid Forms
6. Equivalent Notice
Division 1 – Existing Conditions
1. Related Documents
2. Project Description
3. Contractor Use of Property
4. Special Requirements
Division 9 – Finishes 095113 Acoustical Panel Ceilings 096500 Resilient Flooring 096513 Resilient Base 099000 Interior Painting
Division 12 – Furnishing 123200 Casework
Division 22 – Plumbing
Division 23 – HVAC
Division 26 - Electrical
Appendix A1/A2/A3 – Sample Contracts, Insurance Requirements, Payment Schedule B – Intent to Bid C – Bid Form D – Existing Condition Photos / Casework documentation / Electrical Plan & Submittals
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 3 of 11
Division 0 – Procurement & Contract Requirements
1. Invitation to Bid
Invitation to Bid 2026-01
March 30, 2026
The Town of Lisbon is accepting bids for a general contractor to support the renovations of an approximate 1,200 sf science room within the Lisbon Central School located at 15 Newent Rd, Lisbon, CT 06351.
Bid documents may be obtained at no charge by downloading from the Town of Lisbon’s website via the following link: https://www.lisbonct.gov/bids.aspx
Sealed bids will be accepted until April 23, 2026, at 1:00 pm at the First Selectman's office at Lisbon Town Hall, 1 Newent Road, Lisbon, CT 06351. A bid opening and reading will be held immediately following submission in the Town Hall meeting room. Bids received after the opening date and time will not be considered for award.
A non-mandatory bidder’s conference will be held on April 6, 2026 at 4:00pm at the project site located at 15 Newent Road, Lisbon, CT to review the scope of work. Existing conditions or drawings are not available; attendance is strongly encouraged for field measurements. Visitors must sign in at the main entrance and wait in the lobby. Any questions or RFI’s are to be submitted by April 7, 2026 end of day, with addenda issued as soon as possible.
Bid surety in the form of a certified check from any bank or bid bond in the amount of five percent 5% of this bid is required. If a certified check is provided, it should be written out to the Town of Lisbon.
Additionally, the successful bidder shall also furnish a 100% Performance Bond and Payment Bond as well as proof of liability insurance.
The Town reserves the right to waive any informalities in the bid, to reject any or all bids, and to accept the bid that in its judgment is in its best interest. Bids must be firm and may not be withdrawn for a period of 90 days following the bid opening.
The Contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment without regard to their race, color, religion, gender, or national origin.
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 4 of 11
2. Schedule The project will take place during the summer of 2026, when school is technically closed. However, faculty and students may be in the building as needed for possible events. Additionally, there may be work in other areas of the school, and the fields and playground may be in use. Below is the anticipated construction schedule:
Award / Notice to Proceed: April 29, 2026 Construction Start: June 22, 2026 or upon vacancy of the science wing Casework Delivery: July 13, 2026 Construction Complete: August 19, 2026 Science Room Occupancy: August 20, 2026
3. Contract Documents
A sample contract, which may be modified, is attached as Appendix A for review. Please note that at this time, we anticipate liquidated damages to be $1,000 per day. Also, the anticipated insurance requirements and payment schedule are outlined at the conclusion of the sample contract.
4. Wages and Invoicing The project is a municipal project and shall be prevailing wage. Certified payroll is required, and standard AIA billing is acceptable.
5. Intent to Bid and Bid Form
The intent to bid is attached as Appendix B. Please complete this form immediately and electronically submit it to dave.w@river-electric.net and athibeault@downesco.com to ensure all notifications of addenda are received. The bid form is also attached as Appendix C for completion. By submitting a proposal, the contractor accepts all terms and conditions, scope of work, and schedule requirements.
6. Equivalent Notice
Assume all materials (except paint) can be either specified or equivalent. If the items specified are not used within your bid and are equivalent, list substitution on a separate piece of paper and attach it to the bid form. Also, include submittals for each item.
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 5 of 11
Division 1 – General Requirements
1. Related Documents
a. Existing conditions documents are not available. The documents available for review are the casework layout and specifications, the various scopes of work below, existing condition photos, and a sample contract.
2. Project Description
a. The project scope includes a classroom refresh of approximately 1,200 sf of academic space during the summer of 2026. The science room will require temporary protection, selective demolition, furnishing, interior finishes, electrical, plumbing, and minor HVAC installations.
3. Contractor Use of Property
a. Work hours will be between 7am to 7pm. The duration will be based on need to meet the schedule.
b. Limit use of the premises to the construction activity areas indicated. Do not disturb portions of the site beyond areas in which the work is indicated.
c. Keep driveways and entrances serving the premises clear and available to the Owner at all times. Do not use these areas for parking or storage of materials.
d. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.
e. Dumpsters will be provided by the owner in close proximity to the area of work. The area around the dumpster must be kept clean and tidy. All debris must be within the confines of the dumpster. The dumpster will not be loaded to the point of overflow.
f. All areas of the site must be cleaned daily to avoid safety hazards and remain in compliance with OSHA standards.
g. Temporary protection and dust mitigation controls must be used to keep the remainder of the school free from debris and additional cleaning.
h. Security is essential. Contractor will maintain a daily log of all individuals entering the site. The log must include the date, full name, contractor, sign-in time, and sign-out time.
Contact with students, parents, or faculty not related to the project is prohibited.
Additionally, poor behavior, obscene actions, or language onsite will result in permanent removal from the project.
4. Special Requirements
a. The Contractor shall ensure that all work performed is done so in a safe manner and that all workers adhere to all applicable safety procedures and practices at all times. There may be children and staff in the vicinity of the work area during working hours.
b. The Contractor shall be aware at all times that additional safety considerations should be taken. Particular care shall be taken by the Contractor, Subcontractors and all those in their employ, that all tools, equipment, ladders, etc. are never left unsupervised.
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 6 of 11
c. Use of tobacco products, alcoholic beverages, and other controlled substances inside the building or on the grounds is not permitted. Strict adherence to the regulations will be enforced for the entire duration of the construction.
d. CORI checks are required for all workers onsite as well as daily sign-in logs.
e. Daily cleaning and storage of equipment and materials is required.
f. Contractor will gently clean casework grids and clean radiators of all existing dust and construction debris.
g. Contractor responsible for temporary protection from the access point to the science room.
i. Use tack mats as appropriate
ii. Floor protection
iii. Corridor separation for dust control
h. A punch list will be required, and work must be completed prior to turnover.
i. General Contractor to provide any line drawings or documentation necessary to satisfy the needs of the Building Official, permitting, and Town policy.
j. General Contractor to acquire acceptance from all local, state, and federal codes as well as authorities having jurisdiction.
k. As-builts, in PDF format, are required at the completion of the project.
l. A final construction clean is required before turnover.
Division 2 – Existing Conditions 024113 Selective Demolition
1. Remove and store all casework top grills for reuse.
a. Storage will be on-site, location TBD.
2. Remove and dispose of all countertops.
3. Remove and dispose of all wall and base cabinets.
a. MEP make safe and additional detail under division 22 and division 23.
4. Remove and dispose of the veneer and bottom cabinet doors only on the fume hood.
5. Remove and salvage all HVAC ceiling registers/grills.
a. Storage will be on-site, location TBD.
6. Remove and dispose of all ceiling lighting and associated hanging wires.
a. Electrical and hanging wires in the storage room must remain.
b. Disconnect and make safe all electrical devices in the ceiling.
7. Remove and dispose of acoustical ceiling tiles and grid.
a. All ductwork is to remain for reuse. See division 23.
b. Ceiling grid in the storage room to remain. Tile disposal only.
8. Remove and dispose of all base resilient base molding.
9. Remove and dispose of all existing flooring and mastic.
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 7 of 11
10. Remove and dispose of the single door leading into the small office area.
a. Door hardware to be salvaged and storage for future reuse
b. Door frame remains
11. Remove and dispose of all window treatments.
12. Remove and dispose of the eyewash station.
13. Remove and dispose of the abandoned and empty fuel line.
14. Exclusions:
a. All work in the large storage room adjacent to the small office with the exception of the acoustical ceiling tile and fixtures, flooring, and cove base.
b. Disposing of the existing chalkboard/whiteboard
c. Disposing of HVAC ceiling or base cabinet grills
d. Disposing of door hardware
e. Removal or disposal of all ductwork
f. Removal or disposal of any HVAC equipment, condensate lines, insulation, etc.
Division 9 – Finishes 095113 Acoustical Panel Ceilings
1. Supply and install new 24”x24” grid pattern
a. Armstrong PRELUDE Concealed in White
b. Item numbers ARM7300, ARM 7800, and ARMXL7328
2. Supply and install new 24"x24"x3/4" acoustical ceiling tiles
a. Armstrong Fine Fissured
b. Item number ARM 1713
3. Supply and install hanging wires for lighting fixtures.
a. Lights will be 2’-0” x 2’-0” LED fixtures.
b. Assume 14 fixtures. 12 in the classroom and 2 in the office.
c. Space in a uniform pattern
4. Replace all storage room acoustical tile only.
a. Replace in-kind.
5. Exclusions:
a. Storage room acoustical ceiling grid
096500 Resilient Flooring
1. Prep Floor for LVT plank
a. Prep per manufacturer's recommendations
2. Supply new 36” x 6” LVT plank flooring
a. Tarkett Commercial - Palladian PCPD PALAZZO 4662 SKU: 251105236
b. Color samples required before install
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 8 of 11
3. Install new LVT Flooring
a. Use of Tarkett adhesive only. See the installation manual for adhesive options.
b. Install per manufacturer's recommendations
4. All flooring to be installed prior to casework installation.
a. General Contractor to provide and ensure that floor protection (e.g. rosin paper) is used.
096513 Resilient Base
1. Supply standard 4” cove base. Color to be gray or black.
2. Install cove base around:
a. All perimeter walls
b. All base fixed cabinets
c. Adhesive based on the manufacturer's recommendations
099000 Interior Painting
1. Paint all CMU block
a. Two coats. Sherwin-Williams SW7066 Gray Matter.
b. Protect and paint around chalk/whiteboard.
2. Paint steel door frames
a. Office frame
b. Interior classroom frame
c. Storage room frame
d. Two coats. Benjamin Moore & Co. HP25
3. Paint window frames
a. Two coats. Benjamin Moore & Co. HP25
4. Touch up paint prior to turnover
5. Exclusions:
a. Brickwork
b. Doors
c. Storage room
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 9 of 11
Division 12 – Furnishing 123200 Casework
1. Casework to be provided under a separate proposal.
a. Drawings and specs attached for reference in Appendix D
2. General Contractor to receive and check-in material upon delivery
a. Casework will be stored at the old firehouse on 8 Newent Road until needed. There are no costs associated with storage at the firehouse. Billing for stored materials is not acceptable. The firehouse does not have climate controls.
3. General Contractor to coordinate installation date with the casework provider, school, and building committee.
4. General Contractor to ensure protection of casework through the project. Any protection materials to be removed and disposed of prior to final clean.
Division 22 – Plumbing
1. Make safe all plumbing. Cut and cap in the basement.
2. Eyewash station. Cut and cap.
3. Phase -1:
a. Perform demolition of existing natural gas piping to six student lab stations and existing instructor stations. Piping shall be removed from old mill work and appropriate cap/plug shall be installed in terminated basement gas header, and header shall be tested and verified tight witnessed by town Building Official.
b. Perform demo of all plumbing/waste drain (WD) tied to the existing Instructor lab station.
c. All plumbing/WD shall be removed and capped in basement area below lab. WD fitting should match Like and Kind to existing ENFIELD piping, and all plumbing connections shall be capped in accordance with (IAW) IPC standards and inspected by town Building Official.
d. Perform demo of all hot water piping to 6 student lab stations. All hot water piping shall be removed and capped in basement below IAW IPC standards and inspected by town Building Official.
e. Perform disconnect of all sinks to trap connections and cold-water connections of 6 student lab stations in current mill work to support removal of old mill work.
4. Phase-2
a. Perform installation of Like and Kind ENFIELD WD piping to support installation of 2 new instructor Lab Stations in new Mill Work attached to East facing external wall. All piping shall be tested IAW IPC standards and inspected by town Building Official.
b. Perform Installation of one cold water supply to left instructor Lab station and one cold/Hot water supply to Right hand instructor Lab Station IAW IPC.
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 10 of 11
c. Perform installation of Hot Water supply and appropriately sized mixing valve connecting to existing Cold-Water supply to chemical deluge shower to convert system to a warm water deluge system IAW current IPC requirement.
d. Perform required finish work to all newly installed Mill Work lab stations and perform operational test of all sinks verifying proper flow and no leaks witnessed by town Building Official.
Division 23 – HVAC
1. Pin the ductwork to the roof deck. Keep proximity similar to the existing.
2. Supply and install all 2’x2’ ceiling registers.
a. Confirm fit in the ceiling grid
b. Provide all returns in the classroom.
c. Provide all registers in the classroom.
d. Reconnect ductwork.
3. Install one new flex duct to office.
a. Create small opening in CMU
b. Supply and install one register. Match existing.
4. Insulate the condensate line after repair work is complete.
5. Reinstall and connect the salvaged register in the storage room.
6. Reinstall the used ledge top grilles and wall cleating as appropriate.
7. Coordinate activities as needed and provide access.
8. Exclusions:
a. DDC controls are under a separate contract.
b. Repairs to the existing system are under a separate contract.
Division 26 – Electrical
1. Make safe above ceiling.
a. Lighting in storage room will remain in the same location.
2. Rewire power to rooftop unit.
3. Lighting controls
a. Install Keilton ceiling-mounted motion/daylight harvesting sensors with 12/2 luminary control cable with 16/2 0-10 dimming and modules specifying Keilton products
b. Install one module for the office, and two zones with two modules for the classroom.
c. Install an emergency lighting controller to bypass low-voltage controls during power failure.
d. Provide both QR codes after completion
4. Office:
a. Install one 2x2 RAB EZP2X2/LCBS
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 11 of 11
b. Install one 2x2 RAB EZP2X2/LCBS/E
c. Install one ceiling-mounted motion sensor and one module
5. Classroom:
a. Install ten 2x2 RAB EZP2X2/LCBS
b. Install two 2x2 RAB EZP2X2/LCBS/E
c. Replace 16' of 120v track for lighting in the southwest corner parallel to cabinets in elevation 3B and C
d. Replace all station and countertop receptacles with Leviton T5633-W USB receptacles.
e. Replace all other receptacles in the classroom with Leviton TBR20-W.
f. Replace all circuit breakers with GFCI breakers that are compatible with the existing load center.
g. Install Uline H5643 power reel above the teacher's station.
6. Storage Room:
a. Install two RAB EZP2X4 lights.
7. Submittals and a power plan are included within Appendix D.
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 1 of 3
APPENDIX A-1
Sample Contract 2026-01
AIA A101-2017
Standard Form of Agreement Between Owner and Contractor
Document A101 – 2017 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
Init.
AIA Document A101 – 2017. © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects.
To report copyright violations, e-mail copyright@aia.org. 1
This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.
The parties should complete A101 –2017, Exhibit A, Insurance and Bonds, contemporaneously with this Agreement.
AIA Document A201 –2017, General Conditions of the Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified.
AGREEMENT made as of the ________ day of ________ in the year ________ (In words, indicate day, month and year.)
BETWEEN the Owner:
(Name, legal status, address and other information) and the Contractor:
(Name, legal status, address and other information) for the following Project:
(Name, location and detailed description)
The Architect:
(Name, legal status, address and other information)
The Owner and Contractor agree as follows.
Init.
TABLE OF ARTICLES
1 THE CONTRACT DOCUMENTS
2 THE WORK OF THIS CONTRACT
3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
4 CONTRACT SUM
5 PAYMENTS
6 DISPUTE RESOLUTION
7 TERMINATION OR SUSPENSION
8 MISCELLANEOUS PROVISIONS
9 ENUMERATION OF CONTRACT DOCUMENTS
EXHIBIT A INSURANCE AND BONDS
ARTICLE 1 THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary, and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9.
ARTICLE 2 THE WORK OF THIS CONTRACT
The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others.
ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
§ 3.1 The date of commencement of the Work shall be:
(Check one of the following boxes.)
The date of this Agreement.
A date set forth in a notice to proceed issued by the Owner.
Established as follows:
(Insert a date or a means to determine the date of commencement of the Work.)
If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this Agreement.
§ 3.2 The Contract Time shall be measured from the date of commencement of the Work.
§ 3.3 Substantial Completion § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
(Check one of the following boxes and complete the necessary information.)
Not later than ( ) calendar days from the date of commencement of the Work.
AIA Document A101 – 2017. © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects.
To report copyright violations, e-mail copyright@aia.org.
By the following date:
§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates:
Portion of Work Substantial Completion Date
§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.
ARTICLE 4 CONTRACT SUM
§ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract. The Contract Sum shall be ( $ ), subject to additions and deductions as provided in the Contract Documents.
§ 4.2 Alternates § 4.2.1 Alternates, if any, included in the Contract Sum:
Item Price
§ 4.2.2 Subject to the conditions noted below, the following alternates may be accepted by the Owner following execution of this Agreement. Upon acceptance, the Owner shall issue a Modification to this Agreement.
(Insert below each alternate and the conditions that must be met for the Owner to accept the alternate.)
Item Price Conditions for Acceptance
§ 4.3 Allowances, if any, included in the Contract Sum:
(Identify each allowance.)
Item Price
§ 4.4 Unit prices, if any:
(Identify the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable.)
Item Units and Limitations Price per Unit ($0.00)
§ 4.5 Liquidated damages, if any:
(Insert terms and conditions for liquidated damages, if any.)
§ 4.6 Other:
(Insert provisions for bonus or other incentives, if any, that might result in a change to the Contract Sum.)
AIA Document A101 – 2017. © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by
ARTICLE 5 PAYMENTS
§ 5.1 Progress Payments § 5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.
§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as follows:
§ 5.1.3 Provided that an Application for Payment is received by the Architect not later than the day of a month, the Owner shall make payment of the amount certified to the Contractor not later than the day of the month. If an Application for Payment is received by the Architect after the application date fixed above, payment of the amount certified shall be made by the Owner not later than ( ) days after the Architect receives the Application for Payment.
(Federal, state or local laws may require payment within a certain period of time.)
§ 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. The schedule of values shall be prepared in such form, and supported by such data to substantiate its accuracy, as the Architect may require. This schedule of values shall be used as a basis for reviewing the Contractor’s Applications for Payment.
§ 5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment.
§ 5.1.6 In accordance with AIA Document A201™–2017, General Conditions of the Contract for Construction, and subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
§ 5.1.6.1 The amount of each progress payment shall first include:
.1 That portion of the Contract Sum properly allocable to completed Work;
.2 That portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction, or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing; and
.3 That portion of Construction Change Directives that the Architect determines, in the Architect’s professional judgment, to be reasonably justified.
§ 5.1.6.2 The amount of each progress payment shall then be reduced by:
.1 The aggregate of any amounts previously paid by the Owner;
.2 The amount, if any, for Work that remains uncorrected and for which the Architect has previously withheld a Certificate for Payment as provided in Article 9 of AIA Document A201–2017;
.3 Any amount for which the Contractor does not intend to pay a Subcontractor or material supplier, unless the Work has been performed by others the Contractor intends to pay;
.4 For Work performed or defects discovered since the last payment application, any amount for which the
Architect may withhold payment, or nullify a Certificate of Payment in whole or in part, as provided in Article 9 of AIA Document A201–2017; and
.5 Retainage withheld pursuant to Section 5.1.7.
§ 5.1.7 Retainage § 5.1.7.1 For each progress payment made prior to Substantial Completion of the Work, the Owner may withhold the following amount, as retainage, from the payment otherwise due:
(Insert a percentage or amount to be withheld as retainage from each Application for Payment. The amount of retainage may be limited by governing law.)
AIA Document A101 – 2017. © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by
§ 5.1.7.1.1 The following items are not subject to retainage:
(Insert any items not subject to the withholding of retainage, such as general conditions, insurance, etc.)
§ 5.1.7.2 Reduction or limitation of retainage, if any, shall be as follows:
(If the retainage established in Section 5.1.7.1 is to be modified prior to Substantial Completion of the entire Work, including modifications for Substantial Completion of portions of the Work as provided in Section 3.3.2, insert provisions for such modifications.)
§ 5.1.7.3 Except as set forth in this Section 5.1.7.3, upon Substantial Completion of the Work, the Contractor may submit an Application for Payment that includes the retainage withheld from prior Applications for Payment pursuant to this Section 5.1.7. The Application for Payment submitted at Substantial Completion shall not include retainage as follows:
(Insert any other conditions for release of retainage upon Substantial Completion.)
§ 5.1.8 If final completion of the Work is materially delayed through no fault of the Contractor, the Owner shall pay the Contractor any additional amounts in accordance with Article 9 of AIA Document A201–2017.
§ 5.1.9 Except with the Owner’s prior approval, the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site.
§ 5.2 Final Payment § 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Contractor when
.1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct Work as provided in Article 12 of AIA Document A201–2017, and to satisfy other requirements, if any, which extend beyond final payment; and
.2 a final Certificate for Payment has been issued by the Architect.
§ 5.2.2 The Owner’s final payment to the Contractor shall be made no later than 30 days after the issuance of the Architect’s final Certificate for Payment, or as follows:
§ 5.3 Interest Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated below, or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located.
(Insert rate of interest agreed upon, if any.)
ARTICLE 6 DISPUTE RESOLUTION
§ 6.1 Initial Decision Maker The Architect will serve as the Initial Decision Maker pursuant to Article 15 of AIA Document A201–2017, unless the parties appoint below another individual, not a party to this Agreement, to serve as the Initial Decision Maker.
(If the parties mutually agree, insert the name, address and other contact information of the Initial Decision Maker, if other than the Architect.)
AIA Document A101 – 2017. © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by
§ 6.2 Binding Dispute Resolution For any Claim subject to, but not resolved by, mediation pursuant to Article 15 of AIA Document A201–2017, the method of binding dispute resolution shall be as follows:
(Check the appropriate box.)
Arbitration pursuant to Section 15.4 of AIA Document A201–2017
Litigation in a court of competent jurisdiction
Other (Specify)
If the Owner and Contractor do not select a method of binding dispute resolution, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims will be resolved by litigation in a court of competent jurisdiction.
ARTICLE 7 TERMINATION OR SUSPENSION
§ 7.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A201–2017.
§ 7.1.1 If the Contract is terminated for the Owner’s convenience in accordance with Article 14 of AIA Document A201–2017, then the Owner shall pay the Contractor a termination fee as follows:
(Insert the amount of, or method for determining, the fee, if any, payable to the Contractor following a termination for the Owner’s convenience.)
§ 7.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201–2017.
ARTICLE 8 MISCELLANEOUS PROVISIONS
§ 8.1 Where reference is made in this Agreement to a provision of AIA Document A201–2017 or another Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract Documents.
§ 8.2 The Owner’s representative:
(Name, address, email address, and other information)
§ 8.3 The Contractor’s representative:
(Name, address, email address, and other information)
§ 8.4 Neither the Owner’s nor the Contractor’s representative shall be changed without ten days’ prior notice to the other party.
AIA Document A101 – 2017. © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by
§ 8.5 Insurance and Bonds § 8.5.1 The Owner and the Contractor shall purchase and maintain insurance as set forth in AIA Document A101™– 2017, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum, Exhibit A, Insurance and Bonds, and elsewhere in the Contract Documents.
§ 8.5.2 The Contractor shall provide bonds as set forth in AIA Document A101™–2017 Exhibit A, and elsewhere in the Contract Documents.
§ 8.6 Notice in electronic format, pursuant to Article 1 of AIA Document A201–2017, may be given in accordance with AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, if completed, or as otherwise set forth below:
(If other than in accordance with AIA Document E203–2013, insert requirements for delivering notice in electronic format such as name, title, and email address of the recipient and whether and how the system will be required to generate a read receipt for the transmission.)
§ 8.7 Other provisions:
ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS
§ 9.1 This Agreement is comprised of the following documents:
.1 AIA Document A101™–2017, Standard Form of Agreement Between Owner and Contractor
.2 AIA Document A101™–2017, Exhibit A, Insurance and Bonds
.3 AIA Document A201™–2017, General Conditions of the Contract for Construction
.4 AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, dated as indicated below:
(Insert the date of the E203-2013 incorporated into this Agreement.)
.5 Drawings
Number Title Date
.6 Specifications
Section Title Date Pages
.7 Addenda, if any:
Number Date Pages
Portions of Addenda relating to bidding requirements are not part of the Contract Documents unless the bidding requirements are also enumerated in this Article 9.
.8 Other Exhibits:
(Check all boxes that apply and include appropriate information identifying the exhibit where required.)
AIA Document E204™–2017, Sustainable Projects Exhibit, dated as indicated below:
(Insert the date of the E204-2017 incorporated into this Agreement.)
AIA Document A101 – 2017. © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by
The Sustainability Plan:
Title Date Pages
Supplementary and other Conditions of the Contract:
Document Title Date Pages
.9 Other documents, if any, listed below:
(List here any additional documents that are intended to form part of the Contract Documents. AIA Document A201™–2017 provides that advertisement or invitation to bid, Instructions to Bidders, sample forms the Contractor’s bid are not part of the Contract Documents unless enumerated in this Agreement.
should be listed here only if intended to be part of the Contract Documents.)
This Agreement entered into as of the day and year first written above.
OWNER (Signature) CONTRACTOR (Signature)
(Printed name and title) (Printed name and title)
AIA Document A101 – 2017. © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by
Town of Lisbon, CT – Lisbon Central School Science Room Renovations Page 2 of 3
APPENDIX A-2
Sample Contract 2026-01
AIA A201 – 2017
General Conditions of the Contract for Construction
Document A201™ – 2017 General Conditions of the Contract for Construction
Init.
AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. To report copyright violations of AIA Contract Documents, e-mail The American Institute of Architects’ legal counsel, copyright@aia.org.
This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.
For guidance in modifying this document to include supplementary conditions, see AIA Document A503™, Guide for Supplementary Conditions.
for the following PROJECT:
(Name and location or address)
THE OWNER:
(Name, legal status and address)
THE ARCHITECT:
(Name, legal status and address)
TABLE OF ARTICLES
1 GENERAL PROVISIONS
2 OWNER
3 CONTRACTOR
4 ARCHITECT
5 SUBCONTRACTORS
6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS
7 CHANGES IN THE WORK
8 TIME
9 PAYMENTS AND COMPLETION
10 PROTECTION OF PERSONS AND PROPERTY
11 INSURANCE AND BONDS
12 UNCOVERING AND CORRECTION OF WORK
13 MISCELLANEOUS PROVISIONS
14 TERMINATION OR SUSPENSION OF THE CONTRACT
15 CLAIMS AND DISPUTES
AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. To report copyright violations of AIA Contract Documents, e-mail The American Institute of Architects’ legal counsel, copyright@aia.org.
INDEX
(Topics and numbers in bold are Section headings.)
Acceptance of Nonconforming Work 9.6.6, 9.9.3, 12.3 Acceptance of Work 9.6.6, 9.8.2, 9.9.3, 9.10.1, 9.10.3, 12.3 Access to Work 3.16, 6.2.1, 12.1 Accident Prevention Acts and Omissions 3.2, 3.3.2, 3.12.8, 3.18, 4.2.3, 8.3.1, 9.5.1, 10.2.5, 10.2.8, 13.3.2, 14.1, 15.1.2, 15.2 Addenda 1.1.1 Additional Costs, Claims for 3.7.4, 3.7.5, 10.3.2, 15.1.5 Additional Inspections and Testing 9.4.2, 9.8.3, 12.2.1, 13.4 Additional Time, Claims for 3.2.4, 3.7.4, 3.7.5, 3.10.2, 8.3.2, 15.1.6 Administration of the Contract 3.1.3, 4.2, 9.4, 9.5 Advertisement or Invitation to Bid 1.1.1 Aesthetic Effect 4.2.13 Allowances 3.8 Applications for Payment 4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5.1, 9.5.4, 9.6.3, 9.7, 9.10 Approvals 2.1.1, 2.3.1, 2.5, 3.1.3, 3.10.2, 3.12.8, 3.12.9, 3.12.10.1, 4.2.7, 9.3.2, 13.4.1 Arbitration 8.3.1, 15.3.2, 15.4
ARCHITECT
Architect, Definition of 4.1.1 Architect, Extent of Authority 2.5, 3.12.7, 4.1.2, 4.2, 5.2, 6.3, 7.1.2, 7.3.4, 7.4, 9.2, 9.3.1, 9.4, 9.5, 9.6.3, 9.8, 9.10.1, 9.10.3, 12.1, 12.2.1, 13.4.1, 13.4.2, 14.2.2, 14.2.4, 15.1.4, 15.2.1 Architect, Limitations of Authority and Responsibility 2.1.1, 3.12.4, 3.12.8, 3.12.10, 4.1.2, 4.2.1, 4.2.2, 4.2.3, 4.2.6, 4.2.7, 4.2.10, 4.2.12, 4.2.13, 5.2.1, 7.4, 9.4.2, 9.5.4, 9.6.4, 15.1.4, 15.2 Architect’s Additional Services and Expenses 2.5, 12.2.1, 13.4.2, 13.4.3, 14.2.4 Architect’s Administration of the Contract 3.1.3, 3.7.4, 15.2, 9.4.1, 9.5 Architect’s Approvals 2.5, 3.1.3, 3.5, 3.10.2, 4.2.7 Architect’s Authority to Reject Work 3.5, 4.2.6, 12.1.2, 12.2.1
Architect’s Copyright 1.1.7, 1.5 Architect’s Decisions 3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 4.2.14, 6.3, 7.3.4, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4.1, 9.5, 9.8.4, 9.9.1, 13.4.2, 15.2 Architect’s Inspections 3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 13.4 Architect’s Instructions 3.2.4, 3.3.1, 4.2.6, 4.2.7, 13.4.2 Architect’s Interpretations 4.2.11, 4.2.12 Architect’s Project Representative 4.2.10 Architect’s Relationship with Contractor 1.1.2, 1.5, 2.3.3, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5, 3.7.4, 3.7.5, 3.9.2, 3.9.3, 3.10, 3.11, 3.12, 3.16, 3.18, 4.1.2, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3, 12, 13.3.2, 13.4, 15.2 Architect’s Relationship with Subcontractors 1.1.2, 4.2.3, 4.2.4, 4.2.6, 9.6.3, 9.6.4, 11.3 Architect’s Representations 9.4.2, 9.5.1, 9.10.1 Architect’s Site Visits 3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.4 Asbestos 10.3.1 Attorneys’ Fees 3.18.1, 9.6.8, 9.10.2, 10.3.3 Award of Separate Contracts 6.1.1, 6.1.2 Award of Subcontracts and Other Contracts for Portions of the Work 5.2 Basic Definitions 1.1 Bidding Requirements 1.1.1 Binding Dispute Resolution 8.3.1, 9.7, 11.5, 13.1, 15.1.2, 15.1.3, 15.2.1, 15.2.5, 15.2.6.1, 15.3.1, 15.3.2, 15.3.3, 15.4.1 Bonds, Lien 7.3.4.4, 9.6.8, 9.10.2, 9.10.3 Bonds, Performance, and Payment 7.3.4.4, 9.6.7, 9.10.3, 11.1.2, 11.1.3, 11.5 Building Information Models Use and Reliance 1.8 Building Permit 3.7.1 Capitalization 1.3 Certificate of Substantial Completion 9.8.3, 9.8.4, 9.8.5 Certificates for Payment 4.2.1, 4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9.10.1, 9.10.3, 14.1.1.3, 14.2.4, 15.1.4 Certificates of Inspection, Testing or Approval 13.4.4
AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. To report copyright violations of AIA Contract Documents, e-mail The American Institute of Architects’ legal counsel, copyright@aia.org.
Certificates of Insurance 9.10.2 Change Orders 1.1.1, 3.4.2, 3.7.4, 3.8.2.3, 3.11, 3.12.8, 4.2.8, 5.2.3, 7.1.2, 7.1.3, 7.2, 7.3.2, 7.3.7, 7.3.9, 7.3.10, 8.3.1, 9.3.1.1, 9.10.3, 10.3.2, 11.2, 11.5, 12.1.2 Change Orders, Definition of 7.2.1
CHANGES IN THE WORK
2.2.2, 3.11, 4.2.8, 7, 7.2.1, 7.3.1, 7.4, 8.3.1, 9.3.1.1, 11.5 Claims, Definition of 15.1.1 Claims, Notice of 1.6.2, 15.1.3
CLAIMS AND DISPUTES
3.2.4, 6.1.1, 6.3, 7.3.9, 9.3.3, 9.10.4, 10.3.3, 15, 15.4 Claims and Timely Assertion of Claims 15.4.1 Claims for Additional Cost 3.2.4, 3.3.1, 3.7.4, 7.3.9, 9.5.2, 10.2.5, 10.3.2, 15.1.5 Claims for Additional Time 3.2.4, 3.3.1, 3.7.4, 6.1.1, 8.3.2, 9.5.2, 10.3.2, 15.1.6 Concealed or Unknown Conditions, Claims for 3.7.4 Claims for Damages 3.2.4, 3.18, 8.3.3, 9.5.1, 9.6.7, 10.2.5, 10.3.3, 11.3, 11.3.2, 14.2.4, 15.1.7 Claims Subject to Arbitration 15.4.1 Cleaning Up 3.15, 6.3 Commencement of the Work, Conditions Relating to 2.2.1, 3.2.2, 3.4.1, 3.7.1, 3.10.1, 3.12.6, 5.2.1, 5.2.3, 6.2.2, 8.1.2, 8.2.2, 8.3.1, 11.1, 11.2, 15.1.5 Commencement of the Work, Definition of 8.1.2 Communications 3.9.1, 4.2.4 Completion, Conditions Relating to 3.4.1, 3.11, 3.15, 4.2.2, 4.2.9, 8.2, 9.4.2, 9.8, 9.9.1, 9.10, 12.2, 14.1.2, 15.1.2
COMPLETION, PAYMENTS AND
Completion, Substantial 3.10.1, 4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 12.2, 15.1.2 Compliance with Laws 2.3.2, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 9.6.4, 10.2.2, 13.1, 13.3, 13.4.1, 13.4.2, 13.5, 14.1.1, 14.2.1.3, 15.2.8, 15.4.2, 15.4.3 Concealed or Unknown Conditions 3.7.4, 4.2.8, 8.3.1, 10.3 Conditions of the Contract 1.1.1, 6.1.1, 6.1.4 Consent, Written 3.4.2, 3.14.2, 4.1.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3, 13.2, 15.4.4.2
Consolidation or Joinder 15.4.4
CONSTRUCTION BY OWNER OR BY
SEPARATE CONTRACTORS
1.1.4, 6 Construction Change Directive, Definition of 7.3.1 Construction Change Directives 1.1.1, 3.4.2, 3.11, 3.12.8, 4.2.8, 7.1.1, 7.1.2, 7.1.3, 7.3, 9.3.1.1 Construction Schedules, Contractor’s 3.10, 3.11, 3.12.1, 3.12.2, 6.1.3, 15.1.6.2 Contingent Assignment of Subcontracts 5.4, 14.2.2.2 Continuing Contract Performance 15.1.4 Contract, Definition of 1.1.2
CONTRACT, TERMINATION OR SUSPENSION
OF THE
5.4.1.1, 5.4.2, 11.5, 14 Contract Administration 3.1.3, 4, 9.4, 9.5 Contract Award and Execution, Conditions Relating to 3.7.1, 3.10, 5.2, 6.1 Contract Documents, Copies Furnished and Use of 1.5.2, 2.3.6, 5.3 Contract Documents, Definition of 1.1.1 Contract Sum 2.2.2, 2.2.4, 3.7.4, 3.7.5, 3.8, 3.10.2, 5.2.3, 7.3, 7.4, 9.1, 9.2, 9.4.2, 9.5.1.4, 9.6.7, 9.7, 10.3.2, 11.5, 12.1.2, 12.3, 14.2.4, 14.3.2, 15.1.4.2, 15.1.5, 15.2.5 Contract Sum, Definition of 9.1 Contract Time 1.1.4, 2.2.1, 2.2.2, 3.7.4, 3.7.5, 3.10.2, 5.2.3, 6.1.5, 7.2.1.3, 7.3.1, 7.3.5, 7.3.6, 7, 7, 7.3.10, 7.4, 8.1.1, 8.2.1, 8.2.3, 8.3.1, 9.5.1, 9.7, 10.3.2, 12.1.1, 12.1.2, 14.3.2, 15.1.4.2, 15.1.6.1, 15.2.5 Contract Time, Definition of 8.1.1
CONTRACTOR
Contractor, Definition of 3.1, 6.1.2 Contractor’s Construction and Submittal Schedules 3.10, 3.12.1, 3.12.2, 4.2.3, 6.1.3, 15.1.6.2 Contractor’s Employees 2.2.4, 3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3, 11.3, 14.1, 14.2.1.1 Contractor’s Liability Insurance 11.1 Contractor’s Relationship with Separate Contractors and Owner’s Forces 3.12.5, 3.14.2, 4.2.4, 6, 11.3, 12.2.4
AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. To report copyright violations of AIA Contract Documents, e-mail The American Institute of Architects’ legal counsel, copyright@aia.org.
Contractor’s Relationship with Subcontractors 1.2.2, 2.2.4, 3.3.2, 3.18.1, 3.18.2, 4.2.4, 5, 9.6.2, 9.6.7, 9.10.2, 11.2, 11.3, 11.4 Contractor’s Relationship with the Architect 1.1.2, 1.5, 2.3.3, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5.1, 3.7.4, 3.10, 3.11, 3.12, 3.16, 3.18, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3, 12, 13.4, 15.1.3, 15.2.1 Contractor’s Representations 3.2.1, 3.2.2, 3.5, 3.12.6, 6.2.2, 8.2.1, 9.3.3, 9.8.2 Contractor’s Responsibility for Those Performing the Work 3.3.2, 3.18, 5.3, 6.1.3, 6.2, 9.5.1, 10.2.8 Contractor’s Review of Contract Documents 3.2 Contractor’s Right to Stop the Work 2.2.2, 9.7 Contractor’s Right to Terminate the Contract 14.1 Contractor’s Submittals 3.10, 3.11, 3.12, 4.2.7, 5.2.1, 5.2.3, 9.2, 9.3, 9.8.2, 9.8.3, 9.9.1, 9.10.2, 9.10.3 Contractor’s Superintendent 3.9, 10.2.6 Contractor’s Supervision and Construction Procedures 1.2.2, 3.3, 3.4, 3.12.10, 4.2.2, 4.2.7, 6.1.3, 6.2.4, 7.1.3, 7.3.4, 7.3.6, 8.2, 10, 12, 14, 15.1.4 Coordination and Correlation 1.2, 3.2.1, 3.3.1, 3.10, 3.12.6, 6.1.3, 6.2.1 Copies Furnished of Drawings and Specifications 1.5, 2.3.6, 3.11 Copyrights 1.5, 3.17 Correction of Work 2.5, 3.7.3, 9.4.2, 9.8.2, 9.8.3, 9.9.1, 12.1.2, 12.2, 12.3, 15.1.3.1, 15.1.3.2, 15.2.1 Correlation and Intent of the Contract Documents 1.2 Cost, Definition of 7.3.4 Costs 2.5, 3.2.4, 3.7.3, 3.8.2, 3.15.2, 5.4.2, 6.1.1, 6.2.3, 7.3.3.3, 7.3.4, 7.3.8, 7.3.9, 9.10.2, 10.3.2, 10.3.6, 11.2, 12.1.2, 12.2.1, 12.2.4, 13.4, 14 Cutting and Patching 3.14, 6.2.5 Damage to Construction of Owner or Separate Contractors 3.14.2, 6.2.4, 10.2.1.2, 10.2.5, 10.4, 12.2.4 Damage to the Work 3.14.2, 9.9.1, 10.2.1.2, 10.2.5, 10.4, 12.2.4 Damages, Claims for 3.2.4, 3.18, 6.1.1, 8.3.3, 9.5.1, 9.6.7, 10.3.3, 11.3.2, 11.3, 14.2.4, 15.1.7 Damages for Delay 6.2.3, 8.3.3, 9.5.1.6, 9.7, 10.3.2, 14.3.2 Date of Commencement of the Work, Definition of 8.1.2
Date of Substantial Completion, Definition of 8.1.3 Day, Definition of 8.1.4 Decisions of the Architect 3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 6.3, 7.3.4, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4, 9.5.1, 9.8.4, 9.9.1, 13.4.2, 14.2.2, 14.2.4, 15.1, 15.2 Decisions to Withhold Certification 9.4.1, 9.5, 9.7, 14.1.1.3 Defective or Nonconforming Work, Acceptance, Rejection and Correction of 2.5, 3.5, 4.2.6, 6.2.3, 9.5.1, 9.5.3, 9.6.6, 9.8.2, 9.9.3, 9.10.4, 12.2.1 Definitions 1.1, 2.1.1, 3.1.1, 3.5, 3.12.1, 3.12.2, 3.12.3, 4.1.1, 5.1, 6.1.2, 7.2.1, 7.3.1, 8.1, 9.1, 9.8.1, 15.1.1 Delays and Extensions of Time 3.2, 3.7.4, 5.2.3, 7.2.1, 7.3.1, 7.4, 8.3, 9.5.1, 9.7, 10.3.2, 10.4, 14.3.2, 15.1.6, 15.2.5 Digital Data Use and Transmission 1.7 Disputes 6.3, 7.3.9, 15.1, 15.2 Documents and Samples at the Site 3.11 Drawings, Definition of 1.1.5 Drawings and Specifications, Use and Ownership of 3.11 Effective Date of Insurance 8.2.2 Emergencies 10.4, 14.1.1.2, 15.1.5 Employees, Contractor’s 3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3.3, 11.3, 14.1, 14.2.1.1 Equipment, Labor, or Materials 1.1.3, 1.1.6, 3.4, 3.5, 3.8.2, 3.8.3, 3.12, 3.13, 3.15.1, 4.2.6, 4.2.7, 5.2.1, 6.2.1, 7.3.4, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1, 10.2.4, 14.2.1.1, 14.2.1.2 Execution and Progress of the Work 1.1.3, 1.2.1, 1.2.2, 2.3.4, 2.3.6, 3.1, 3.3.1, 3.4.1, 3.7.1, 3.10.1, 3.12, 3.14, 4.2, 6.2.2, 7.1.3, 7.3.6, 8.2, 9.5.1, 9.9.1, 10.2, 10.3, 12.1, 12.2, 14.2, 14.3.1, 15.1.4 Extensions of Time 3.2.4, 3.7.4, 5.2.3, 7.2.1, 7.3, 7.4, 9.5.1, 9.7, 10.3.2, 10.4, 14.3, 15.1.6, 15.2.5 Failure of Payment 9.5.1.3, 9.7, 9.10.2, 13.5, 14.1.1.3, 14.2.1.2 Faulty Work (See Defective or Nonconforming Work) Final Completion and Final Payment 4.2.1, 4.2.9, 9.8.2, 9.10, 12.3, 14.2.4, 14.4.3 Financial Arrangements, Owner’s 2.2.1, 13.2.2, 14.1.1.4
GENERAL PROVISIONS
AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. To report copyright violations of AIA Contract Documents, e-mail The American Institute of Architects’ legal counsel, copyright@aia.org.
Governing Law 13.1 Guarantees (See Warranty) Hazardous Materials and Substances 10.2.4, 10.3 Identification of Subcontractors and Suppliers 5.2.1 Indemnification 3.17, 3.18, 9.6.8, 9.10.2, 10.3.3, 11.3 Information and Services Required of the Owner 2.1.2, 2.2, 2.3, 3.2.2, 3.12.10.1, 6.1.3, 6.1.4, 6.2.5, 9.6.1, 9.9.2, 9.10.3, 10.3.3, 11.2, 13.4.1, 13.4.2, 14.1.1.4, 14.1.4, 15.1.4 Initial Decision 15.2 Initial Decision Maker, Definition of 1.1.8 Initial Decision Maker, Decisions 14.2.4, 15.1.4.2, 15.2.1, 15.2.2, 15.2.3, 15.2.4, 15.2.5…