LB-WV 2022 Part 12 Inspection Pre-Proposal Meeting.pdf
PDF 2 MB Posted
- Solicitation number
- S-P00140-00001695
- Issued by
- Lane County, Oregon
About this file
This document is a pre-proposal meeting presentation for a state and local contract opportunity from the Eugene Water & Electric Board (EWEB) to provide Leaburg-Walterville Part 12D Safety Inspection Services in Lane County, Oregon. The objectives of the project are to perform a five-year safety inspection and evaluation of the Leaburg-Walterville Hydroelectric Project, a FERC-regulated project owned and operated by EWEB, in accordance with new FERC guidelines. The scope of work includes document review, physical inspections, potential failure mode analysis, and preparation of a final Part 12D Safety Inspection Report. The procurement schedule includes a proposal due date of February 10, 2022, evaluation and selection by March 2, 2022, and a contract award on April 7, 2022. The final deliverables are due by December 9, 2022.
The contract will be a professional services agreement with a not-to-exceed cost structure. Pricing information should be submitted separately from the technical proposal. The procurement process involves an initial written evaluation, potential interviews, and a subsequent request for pricing from the most qualified proposers. Incumbent and funding information is not provided, but the project is FERC-regulated and will require continued technical and professional assistance through most of 2023.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2022200038_G1_Notice of Intent to Award.pdf | ||
| Addendum 2 21-269-Q.pdf | ||
| 21-269-Q LB-WV Insp Report.pdf | ||
| Addendum 1 21-269-Q.pdf | ||
| NDA Form 21-269-Q~1.docx | DOCX document | |
| NDA Form 21-269-Q~1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Monday, January 24, 2022
2:30 – 4:00 PM PST
PRE-PROPOSAL MEETING
FOR
LEABURG-WALTERVILLE
PART 12D SAFETY INSPECTION SERVICES
▪ EWEB Team o Daniel Huang - Dam Safety Supervisor o Mark Zinniker - Generation Engineering Supervisor
▪ Notes o Make sure you have filled in sign-up sheet and returned o Please enter your NAME, COMPANY NAME and EMAIL in the chat as one entry o Please mute your microphone o Save questions for the end of each section and Q/A time o Use either of the two methods to ask questions
• Use hand raise feature in MS Teams and we will call your name, ask your question and lower your hand
• Drop your question in the chat and we will read it
INTRODUCTION
o Sandra Hahn - Purchasing Analyst o Dan Olmstead, Senior Engineer o Jeremy Somogye, Planner IV
▪ Objectives
▪ About Leaburg-Walterville Hydro Project
▪ Project Tasks
▪ Schedule Overview
▪ Solicitation Review
▪ Questions
OUTLINE
▪ Today’s Meeting Objectives o Orientation of Project Developments o Review of Project Needs and SOW o Review Main RFP Items o Opportunities for Questions and Clarifications
OBJECTIVES
▪ Project Objectives o Perform five-year IC Safety Inspection & Evaluation on the
Leaburg-Walterville Project (FERC Project P-2496) o Safety inspections & evaluations to follow Chapter 14 guidelines prior to the newly enacted rules in November 2021
▪ Owned and operated by EWEB, Regulated by
FERC
▪ 20 miles east of Eugene, OR on the McKenzie
River
▪ Two developments o Leaburg completed in late 1920’s o Walterville completed in 1911, modified in 1948
LEABURG-WALTERVILLE BACKGROUND
Leaburg Dam and Canal Intake Looking Upstream-1929
Walterville Forebay Construction/Modification
▪ ~4 miles long canal with earth embankment
▪ Canal capacity ~2700 cfs
▪ Critical components include:
o Intake, Fish screen, Decommissioned Storage
Pond, Forebay, Penstock, Spillway
▪ Old project with limited information available
WALTERVILLE DEVELOPMENT
▪ Two sections with high hazard rating
▪ Short videos of the facility
Walterville Canal Intake Structure Walterville Canal Fish Screen
Walterville Canal Decommissioned Storage Pond Walterville Canal Forebay, Powerhouse and Spillway
Forebay
Concrete Wall
Penstock
Forebay
Embankment
Spillway
▪ A low head dam
▪ ~5 miles long canal with earth embankment
▪ Canal capacity ~2500 cfs
▪ Several components o Intake, Fish Screen, Spillways, Forebay, Penstock
LEABURG DEVELOPMENT
Leaburg Dam and Canal Intake Structure Wasteway Gate
Luffman Spillway Forebay, Siphon Spillway, Penstock
▪ Project Management:
o Consultant to provide and maintain a project schedule that includes tasks descriptions and completion milestones o Consultant to provide bi-monthly status reports
▪ Project Meetings o Consultant to facilitate a virtual Owners Kick Off Meeting o Consultant to participate in a virtual Regulatory Pre-Inspection Meeting the minimum of 90 days prior to the project inspection (Task 3) and PFMA Workshop
(Task 4)
PROJECT TASK 1
Leaburg Dam
▪ Document Review o Previous Part 12 Safety Inspection Reports o Supporting technical information documents o Available project design and construction documentation o PFMA reports & the Leaburg Semi-Qualitative Risk Assessment report o Dam Safety Surveillance and Monitoring Reports o Reports and correspondence on all work items and status or results of previous
Part 12D recommendations or FERC requirements after the previous Part 12D inspection o Other documents identified by the consultant
PROJECT TASK 2
▪ Project Inspections o A physical field inspection of each development in its entirety excluding transmission, transformer facilities and generation equipment o Inspection of the Walterville Project Canal under full operation and during outage conditions if necessary o Inspection of the Leaburg Project Canal in the current state of operations o Observations and documentation of project features and changes (as listed in the FERC letter) with sufficient photos taken o Observations with respect to each identified PFM o Adequacy/operation of public alert systems o Interview and discussions with project staff with regard to operation and maintenance
(O&M) programs, including adequacy of O&M procedures, communications, human factors, and O&M procedures related to PFMs o Briefing of observations and concerns with EWEB engineers and operators
PROJECT TASK 3
▪ Potential Failure Mode Analysis (PFMA) o Specific PFMA instructions detailed in the March 29,2021 letter from FERC.
o Virtual meeting with FERC at least 90 days prior to discuss expectations for PFMA review
▪ PFMA Workshop o Consultant to facilitate an interactive PFMA workshop with EWEB engineering & operations staff and FERC dam safety staff o A draft PFMA report shall be provided following the general format in Chapter 14
Appendix D of the FERC Engineering Guidelines and finalized after addressing all review comments.
o Consultant shall document/track review comments on the draft report and provide clear responses.
o A review meeting may be necessary to address the comments.
o Final PFMA Report in both searchable PDF and Word formats o List of recommended follow-up actions on Category III PFMs.
PROJECT TASK 4
▪ Part 12D Safety Inspection Report o Prepare a report in accordance with FERC requirements and is acceptable by FERC reviewers.
o Utilize the report outline enclosed in the March 9,2021 Letter from the FERC Regional
Engineer o The final Part 12D report for the Project will have two parts, Division 1 – Part 12D Safety
Inspection Report for Leaburg Development and Division 2 – Part 12D Safety Inspection
Report for Walterville Development.
o Consultant to facilitate a meeting to discuss the draft report comments o Final report is due December 9, 2022
PROJECT TASK 5
▪ Continued Technical & Professional Assistance o Support is expected to continue throughout most of 2023.
PROJECT TASK 6
▪ Contract Type o Professional Services Contract – A&E o Not to exceed cost structure
▪ Proposal Evaluation o Step 1- Written proposal evaluation/potential interview
• Up to 3 of the most qualified proposers may be added to the short list.
• Pricing information should be submitted in a sealed envelope o Step 2-Cost Request
▪ Non-disclosure agreement needed for STID and additional project information
▪ Schedule
SOLICITATION REVIEW
Request for Proposal Released January 10, 2022
Mandatory Pre-Proposal Conference January 24, 2022
Last day for EWEB to receive questions from Proposers February 3, 2022
Last day EWEB will post Addenda February 7, 2022
Closing Date (last day to submit proposals to EWEB) February 10, 2022
Responses Evaluated February 17, 2022
Interviews / Presentations Held Week of Feb 21-25
Pricing Evaluation and Completion of Evaluation March 1, 2022
Intent to Award Announcement March 2, 2022
Board Approval April 5, 2022
Contract Award April 7, 2022
Draft Report submitted to EWEB October 14, 2022
Final Deliverables submitted to EWEB December 09, 2022
SCHEDULE OVERVIEW
QUESTIONS