KEYS BID 18-26 SPECIFICATIONS FOR POLE INSPECTIONS
This is a Request for Proposals (RFP) issued by Keys Energy Services (KEYS), a municipal electric utility operated by the Utility Board of the City of Key West, Florida. KEYS seeks qualified contractors to perform visual inspection, sounding, and boring of wood poles in approximately 50% of its service area, which extends from Key West eastwardly to the west end of the Seven-Mile Bridge in Monroe County, Florida. The scope includes photographing poles, documenting third-party attachments, and providing detailed inspection data in electronic format. Contractors must conduct pole loading assessments on distribution poles with significant third-party attachments and identify NESC violations and attachment inventory issues. Sealed electronic proposals are due by 10:00 a.m. on Friday, August 21, 2026, via VendorLink or DemandStar, with paper submittals accepted only if hand-delivered to 6900 Front Street Extended, Key West, Florida 33040. The contract is anticipated to be awarded in September 2026, with work commencing October 1, 2026, and completion required by September 30, 2027. Questions must be submitted in writing to purchasing@keysenergy.com by noon on Friday, August 7, 2026. The contract term extends from execution through December 31, 2027, with potential extension at the same unit price if KEYS desires, and liquidated damages of $500 per day apply for work not substantially completed by the deadline.
Proposals must include a Bid Bond or Certified Check equal to five percent of the total bid amount, evidence of insurance, three professional references, a detailed schedule, and documentation of personnel qualifications demonstrating at least three years of pole inspection experience. All contractor personnel must be U.S. citizens or legally authorized to work in the United States, wear properly identified company apparel, and carry pictured identification cards. KEYS reserves the right to reject any or all proposals and reserves the right to cancel the contract without cause with thirty days' written notice. Evaluation criteria include experience with similar projects (25%), pricing (40%), references (15%), schedule (10%), and qualified personnel (10%). Contractor shall maintain Commercial General Liability insurance with a $2,000,000 general aggregate limit, Business Automobile Policy coverage of $1,000,000 per occurrence, and Workers' Compensation insurance with $1,000,000 per accident limits. The contractor must develop and implement a safety program compliant with the American Public Power Association (APPA) Safety Manual and obtain the latest edition at its own expense. All inspection data, reports, photographs, and work products become the sole property of KEYS, and the contractor provides a one-year warranty on inspection services following acceptance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| KEYS_Bid_1826_Bid_Opening_Meeting.pdf | ||
| KEYS_Bid_1826_Addendum_1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KEYS BID 18-26 SPECIFICATIONS FOR POLE INSPECTIONS
CALL FOR BIDS
THE UTILITY BOARD OF THE CITY OF KEY WEST, FLORIDA, operator of Keys Energy Services (KEYS), hereby gives notice to prospective bidders that sealed proposals will be received by KEYS electronically until 10:00 a.m. on Friday, August 21, 2026, for:
KEYS BID 18-26
SPECIFICATIONS FOR POLE INSPECTIONS
KEYS has instituted VendorLink and DemandStar systems to provide current information to potential bidders. These systems will allow you to receive bid information quickly and at your convenience 24 hours a day, 7 days a week. Specifications may be obtained from their websites at www.myvendorlink.com or www.DemandStar.com. Registered vendors will be notified automatically of all Requests for Proposals. You may also visit www.KeysEnergy.com for links and download information for all KEYS bid specifications.
It shall be the sole responsibility of each bidder to have their bid electronically delivered on or before the time for opening proposals last announced to bidders. Emailed proposals will not be accepted. Should a vendor not be able to submit via VendorLink or DemandStar, paper submittals will be accepted. Paper submittals must be received prior to the opening date and time in order to be considered. Paper submittals, if applicable, are to be delivered via FedEx, UPS, or in-person to:
Keys Energy Services Bid Opening Committee – KEYS Bid 18-26 6900 Front Street Extended Key West, FL 33040 Note: This address does not receive US Postal Service.
Any proposal received after the time last announced for opening proposals may be retained by KEYS or returned to the bidder, but such proposal may be rejected as not responsive.
Vendors with questions pertaining to this bid specification must submit them in writing via email to purchasing@keysenergy.com no later than Friday, August 7, 2026 at noon. Any questions received after noon on Friday, August 7, 2026 will not be addressed.
Each proposal should be accompanied by a Certified Check or Bid Bond payable to the UTILITY BOARD OF THE CITY OF KEY WEST in an amount not less than five (5%) percent of the amount of the proposal as security.
Each proposal should constitute an offer to KEYS, as outlined therein, and should be irrevocable after the time announced for the opening thereof.
At a meeting of the BID OPENING COMMITTEE to be held virtually on Friday, August 21, 2026 at 10:00 a.m. Proposals will be opened and vendor names will be publicly read aloud.
KEYS reserves the right to reject any or all proposals, to waive irregularities and informalities in any or all proposals, and to separately accept or reject any item, items, bid schedule or bid schedules of the proposal which KEYS deems to be in the best interest of the Utility Board.
Tyler Randolph, Purchasing Supervisor http://www.myvendorlink.com/ http://www.demandstar.com/taf/agencycp.taf?_function=list&A=335 http://www.keysenergy.com/ mailto:purchasing@keysenergy.com
GENERAL
Keys Energy Services (KEYS) is a municipal electric utility supplying power to residents of the lower Florida Keys. KEYS is located in the extreme southern tip of peninsular Florida, situated in Monroe County, Florida, primarily what is considered the “Lower Keys”, which extends eastwardly from Key West to the west end of the Seven-Mile Bridge. Corporate Offices are located at 1001 James Street, Key West, Florida and the Transmission and Distribution (T&D) Facility is located on Stock Island at 6900 Front Street Extended, Key West, Florida 33040.
KEYS and its representatives have exercised due care in preparing this Request for Proposals (RFP). All information contained herein is believed to be substantially correct. However, bidders should verify information independently if desired. KEYS and its representatives do not warrant the accuracy of information contained herein.
SPECIFICATIONS
1.0 General Pole Testing Specifications
1.1 Scope
This specification is the basis for the visual inspection of KEYS poles and supplemental sounding and boring of wood poles in approximately 50% of KEYS service area. The inspection shall consist of taking a photograph of the pole, noting third party attachments, and whether there is an adjacent topped pole with or without attachments. Any wood poles will be visually inspected, sounded and bored. Results of inspections will be provided to KEYS in an electronic format.
KEYS anticipates this contract being awarded in September of 2026. Contractor start date shall be October 1st, 2026, and completed prior to September 30th, 2027.
2.0 Contractor Requirements
The Contractor shall furnish all supervision, labor, tools, equipment, and material necessary, or required for the evaluation, inspection, and reporting of KEYS’ poles as identified. KEYS will furnish copies of this specification and necessary maps and/or data showing locations of poles, which are the subject for this inspection. Contractor shall designate a Project Manager who will serve as the single point of contact throughout the project. Each Contractor work crew shall have an iOS device on which KEYS shall install their Partner program. The iOS device shall have remote internet access and GPS capability. Partner shall be used to identify and verify the KEYS pole number.
2.1 Contractor Personnel Qualifications
2.1.1 All pole inspectors shall be professional pole inspectors with at least three (3) years experience in pole inspecting, and if requested, be able to pass a demonstration test to the satisfaction of KEYS.
2.1.2 KEYS reserves the right to ask for evidence of previous experience and training in the form of letters of reference and test results. Personnel are subject to approval by KEYS before awarding the contract or at any time thereafter.
2.1.3 All Contractor employees shall wear as a minimum a T-shirt with the Contractor’s company name and logo, long pants and work boots. The work shirts shall not be tank tops nor have the sleeves cut out of them. Any Contractor employee not complying with this requirement shall be prohibited from further work until they comply. Repeated offenses shall prohibit the employee from working in KEYS service area. All Contractor vehicles shall properly be identified by Company’s name and Logo. Each employee shall have a pictured identification card displayed on his/her person while working in KEYS service area. The identification card shall include Contractor’s logo, phone number, employee’s name, and photograph.
2.2 Workmanship and Damages
All work shall be in accordance with good workmanship standards and shall be in accordance with this specification and all applicable Federal and State regulations. The Contractor shall exercise care at all times to prevent injury to any persons and to prevent damage to any property during performance of the work.
KEYS considers work not in accordance with this specification of work, not in accordance with State or Federal regulations, unskilled or carless work, to be sufficient reason to order the Contractor to stop work. Work will not be allowed to resume until deficiencies are corrected.
2.3 Quality Control
2.3.1 Quality Control Inspection
A quality control inspection shall be performed per a week’s work but not to exceed two (2) weeks previous work. The Contractor’s Supervisor and KEYS’ Representative will conduct the quality control when both are available. The quality control inspection shall consist of the partial to complete re-inspection of those poles selected by KEYS’ representative to compare the results against the inspection report. The re-inspection shall include, but not limited to, re-excavation and ground restoration. At least 3 poles will be selected for each quality control inspection. KEYS shall receive a copy of the quality control field report.
KEYS reserves the right to independently inspect any completed work. Contract shall correct deficient inspections at no additional cost.
2.3.2 Discrepancies and Corrective Action
Serious errors will be brought to the attention of the Contractor. Corrective action, reasonably satisfactory to KEYS, must be taken by the Contractor to remedy the situation before the next quality control check. The corrective action may include, but not limited to re-working each pole back to the previous satisfactory quality control inspection report.
2.4 Definitions for Inspection Categories
2.4.1 Visual Inspection
The visual inspection shall consist of taking a photograph of the pole, noting third party attachments, and whether there is an adjacent topped pole. Location of third party attachments shall be noted (i.e. Note which pole the third party is attached to).
2.4.2 Reported Pole (Visual Inspection)
Reported Pole is any pole that is judged unserviceable prior to excavation (per Section 3.3) or any pole which is determined by Contractor’s reasonable opinion to be inaccessible.
2.4.3 Sounding and Boring
Poles must be sounded from below ground line to a minimum of six feet above the ground line. Sounding shall be done on all four sides of the pole to locate exterior decay or interior pockets of decay.
Inspector shall bore pole to detect interior decay. If there is evidence of possible interior voids or rot, at least one boring shall be made where a void is indicated.
If rot or voids are detected, several boring shall be made per rot or void location and a shell gauge shall be used to determine the extent of all voids or rot. In any event, at least two borings shall be made at the ground line to check for rot.
Poles set in concrete or pavement shall be bored at least twice at opposite sides at the ground line down at a 45 degree angle into the pole and the boring sample checked for rot or voids. Afterwards, all holes shall be plugged with treated dowels.
2.4.4 Rejected Pole
The Contractor is responsible for determining when a pole shall be deemed a reject. Contractor shall document the reason for rejection using the criteria established herein and provide supporting photographs. A reject pole is any pole designated by the contactor upon inspection, which is found deteriorated below the required minimum as indicated on Circumference Tables 1 and 2 provided in the attachment section herein. Poles shall also be classified as sound and bore rejects or visual rejects in accordance with Section 3.3.
2.4.5 Priority Reject Pole
A pole that is in need of immediate attention (replacement) usually has average shell rot of one inch or more, or less than one third of its original circumference.
The location of priority poles will be reported to KEYS’ representative daily.
3.0 Pole Inspection Procedure
3.1 General
3.1.1 Preparation
When work is to be done in close proximity to a home, the property owner should be notified as to what is being accomplished. Light brush will be removed from around the pole to allow for proper excavation, inspection unless property owner denies permission for removal. Denial will be indicated in the remarks on the pole report. If permission for excavation is denied, the pole will be sounded and bored, providing the pole is serviceable. Contractor will not inspect or perform work on a pole inaccessible by acts of God or by any causes beyond the control of the Contractor. Reason for the lack of inspection will be noted in the pole report.
3.1.2 Work Schedule
Contractor must supply a schedule outlining the number of crews proposed to complete work along with start dates and completion dates. The work hours shall be 8 a.m to 7 p.m Monday – Saturday.
3.2 Visual Inspection and Testing
3.2.1 A visual inspection shall be performed on all poles inside the limits of the City of Key West, Florida, and between Keys West and Shark Key, including Shark Key.
3.2.2 A photograph of the shall be taken of the pole. Images should be a minimum of
12 MP and clearly show the full length of the pole. Shadowy images will not be accepted and will need to be retaken.
3.2.3 The quantity and owner of third party attachments shall be noted.
3.2.4 If there is an adjacent topped pole, and if so the quantity and owner of any third party attachments, if any.
3.2.5 Wood poles shall include both visual inspection of and testing.
3.3 Above Ground Inspection (Wood Poles)
A visual inspection of all poles shall be made from the ground line to the top of the pole before any other inspection. The visual inspection shall include: type of wood, original treatment, circumference, height, and any obvious visible defects will be noted:
woodpecker holes, split tops, decayed tops, broken insulators, rotten/broken cross arms, and slack/broken guywires, broken insulators, leaking transformers, abandoned poles etc.
If the pole is obviously not suited for continued service due to serious defects, it shall either. 1) Not be tested further, reported and marked as a reject on the inspection report or 2) the pole may be sound and bored to determine whether or not it is a priority pole and be reported on the inspection report as a sound and bored reject.
3.4 Excavation (Wood Poles)
Earth shall be removed from the entire circumference of the pole to a minimum depth of
18 inches below ground line. Width of the hole shall be 4 inches clearance from the pole surface at the bottom and 10 inches at the ground line.
If there are riser shields or a number of cable risers on a pole, it shall be excavated in such a manner as to permit inspection of the pole as much as possible without damage to cables.
In case that it should not be possible to excavate at least 75% of the way around the pole, the area excavated and the pole shall be sounded, bored.
For excavation in lawns, sod grass areas or flower gardens, care will be taken to keep surrounding area as clean as possible. The sod around pole shall be carefully cut and neatly stacked. Tarpaulins or ground cloths shall be used whenever possible to minimize the possibility of any property damage and to aide in the tracking of excavated holes.
4.1 Determining Remaining Strength and Reject Criteria
Contractor is to define the data that is collected and explain how the data is processed to evaluate remaining pole strength. Contractor will further explain criteria used to determine whether a pole is serviceable or a reject.
This procedure should include measuring all decay, insect, and mechanical damage in the ground-line zone. The remaining sound circumference (after removing shell rot) measured and then entered into the data collection software of the mobile computer. Exposed Pockets, Enclosed Pockets and Mechanical Damage include more precision in reference the orientation from the line of lead. The handheld computing software determines the remaining bending strength by calculating the remaining section modulus and displaying the remaining strength as a percent of the original strength.
It is expected to have the remaining pole strength quantified as a percent of the original pole capacity so that more effective prioritization can be accomplished.
Note that some wood poles have previously been treated with a preservative paste and wrapped with a moisture barrier. The moisture barrier is stapled to the pole at the top and side seams. The preservative paste ingredients are:
44.4% Sodium Fluoride 44.4 % Sodium Fluoride 17.68% Copper Naphthenate - 20.0 % Copper Naphthenate - (2% Copper as metal) (or) (2% Copper as metal) 35.6% Inert Ingredients 35.6 % Inert Ingredients
Contractors should be aware of handling requirements of existing pole wrap. Wrap should be removed for inspection. If possible, wrap shall be reinstalled. Otherwise, the wrap shall be disposed of appropriately.
4.2 Pole Loading Estimates
Contractor shall provide pole loading assessments on all distribution poles with third party attachments exceeding one-half inch diameter, but no secondary-only or service poles identified by KEYS to determine whether a pole has sufficient strength remaining to adequately support the attached facilities while maintaining applicable code requirements. Pole loading assessment shall also indicate whether the pole failed the strength requirements before or after the third party, attachment was included in the wind loading calculations. Contractor shall define the data collected and explain the assessment process. The loading calculations will be based on the latest edition of NESC for Light Loading District, and NESC Construction Grade “C”. The load calculations shall be submitted in an electronic format.
4.3 Pole Attachment Inventory Contractor shall provide pole attachment inventory on all distribution and/or transmission poles with third party attachments as specified below.
1. Survey the list of poles provided
a. Provide a count of all poles with Telco attachments.
b. Provide a count of all poles with CATV attachments.
c. Provide a list and count of any unknown foreign attachments to poles.
2. Identify locations where obvious NESC violations exist, including ownership of attachments in violation and type of violation. Visual inspection is sufficient.
3. Denote locations where transfers are needed, including name of all parties and the order in which transfers need to be made.
4. Denote locations where poles are ready for removal.
5 Restoration of Work Site
5.1 Backfilling
After excavation all poles will be solidly back filled. The first of excavation will be backed filled and tamped completely around the pole by walking on the replaced excavation, the second half back filled and tamped completely around the pole. The excess earth should be banked up to a maximum of 3 inches above normal ground level to allow for settlement.
In grass areas, the sod shall be carefully placed around the pole. Rocks or stones should not be laid expect where they serve to key the pole or where no other fill is available.
5.2 Clean up
All debris, loose soil, etc., shall be removed from the work area and disposed of by the Contractor. Private property turf, including that between curb and sidewalk, bushes, and plants, and shrubbery are to be replaced with care.
6 Pole Marking
6.1 Tagging
All poles inspected shall be marked with a weatherproof tag identifying the work performed, the Contractor name and date in a fashion similar to the designations shown in the following example drawings. The tagging scheme used by the Contractor must be shown to KEYS representative and approved before it is used.
Tags shall be supplied by the Contractor and placed approximately 5 to 6 feet above ground line on the roadside of the pole. If inspecting or a pole that was previously inspected or treated, attach the tag directly below the existing tag(s).
The following are illustrations examples of various types of tags used along with an explanation as to when they are used.
Examples Inspection Tags
REJECT TAGS
Yellow Silver White
One yellow reject tag One white or silver tag is used to is used to denote the denote that a pole is a non-restorable Pole is a restorable reject. reject.
This tag is an example of a contractor’s tag. This round tag represents an inspection via a full 18” dig. The tag should incorporate the contractors name and the year they performed the work.
This tag is an example of a contractor’s tag. This oval tag is to be used whenever any inspection aside from a full excavate takes place. This will include “Sound and Bore”, “Sound Only”, Sound and Select Bore” etc inspections. The tag should incorporate the contractors name and the year they performed the work.
Yellow
Two yellow tags are used to denote a Danger or Priority pole that is restorable.
This may vary by Contractor.
OR
Silver White
Two white or silver tags are used to denote a Danger or Priority pole that is not restorable. This may vary by Contractor.
7 Pole Inspection Data Collection and Delivery Report Records KEYS will be responsible for furnishing the Contractor with maps and data in an electronic format, for all poles which are to be inspected and treated under this contract. The electronic information will be provided in Arc Map or ESRI geo-database. All information, reports, and invoices are to be delivered to the designated contract administrator.
7.1 Data Collection
Field data shall be supplied to KEYS at least weekly. The data will be delivered in a geospatial software application that provides information and support for decision making to coordinate lower cost repair, replacement or maintenance activities. The deliverable should include a map view of pole locations along with the ability to query the data and generate reports. The geospatial software application shall also be capable of exporting an Access database for use by KEYS. The Contractor shall supply the data to KEYS in a mutually agreed upon format.
7.2 Data Requirements
The Contractor will digitally capture and deliver pole attribute and condition information as part of this project. The Contractor also will place pole locations relative to the specified land base while in the field. The inspection data will be delivered with the land base in a geospatial display for viewing, as well as querying the results of the inspections.
The following information shall be provided by the Contractor. This information shall be recorded daily and submitted to KEYS weekly. Reports shall be submitted by each crew.
Computerized pole reports shall provide individual pole information for all poles inspected during the week by an individual inspector. It shall be provided no more than one week after the work is performed. Each summary report shall report the previous week data and all previous inspections data within the same year.
All information listed below shall be contained in the report:
Heading - Each report sheet shall have the information listed below in the heading
Utility Name Quadrant Contractor’s Name Line/Map number Inspector Name Page Number Supervisor Name Date of Work
Report Content - Include pole categories listed below
1. Total Poles Inspected
2. Excavated
a. No Decay Found
b. Decay Found
c. Reject
3. Not Excavated
a. Sound & Bore no Decay
b. Sound & Bore with Decay
c. Sound & Bore Reject
d. Visual Report
e. Visual Reject
4. Total Rejected Poles
a. Total Priority Rejected Poles
b. Non-Restorable
5. Ground wire repair
6. Poles with Decayed Top
7. Poles with broken or defective ground wire
8. Poles with woodpecker holes
9. Poles with broken or defective KEYS guy wire
10. Poles with split tops
11. Poles with mechanical damage above ground line
12. Pole and class size
13. Down guy guard replaced
14. Poles with broken or defective AT&T and Comcast down guy attachment
Ductile Iron Pole Inspection In the inspection report, Contractor shall take note of the base of each ductile iron distribution pole. Specifically making note if there is any degradation to the Induron (black) coating or any surface rust identified.
Cross Arm Identification In the inspection report, Contractor shall take note of any cross arms attached to the inspected pole. Contractor shall provide the number of cross arms and material (wood or fiberglass).
7.3 Electronic Data Management Software
The Contractor shall provide and maintain support for a software application capable of using ESRI geo-database information input and managing all inspection criteria and all pole category inspection data.
The Contractor will be required to demonstrate a successful history in completing similar field projects in electronic format. The Contractor will include, in the quoted price, all required hardware, software, setup services, field services, data processing, project management, data deliverables and customer support necessary to fulfill the outlined project requirements.
The Contractor will capture a digital photograph and deliver pole attribute and condition information (including the specification of non-reinforceable rejects) as part of this project including GPS coordinates. The Contractor also will place pole locations relative to the specified land base while in the field. The inspection data will be delivered with the land base in a geospatial display for viewing, with the ability to query the results of the inspection data and to export the data to an Access database or Excel spreadsheet.
Data will be delivered in a geospatial software application that provides the following capabilities:
• Integrated display of pole position on the lad base and inspection results
• Queries of the inspection and maintenance data
• View and manipulate digital images
• Report generation
• User-friendly integration with email
• Export of data in an Access database format
• Copy map views to other documents
• Plotting of map display
• Data loaders to streamline the installation process of incremental data deliveries
• Compatibility with industry standard Windows operating systems
7.4 Software Capabilities
Software Capabilities must be extendable and scalable by allowing for the following extra cost upgrades:
• Multiple users
• Network/Server configurations for multiple users
• Editing of data for record maintenance
• Data migration to specified target systems
• Additional data collection applications
The software shall be capable of sorting all pole categories and producing reports, which can be viewed and printed within the software.
7.5 Software Support
The Contractor shall offer support to KEYS on all software.
7.6 Weekly Inspection Report
This report shall summarize an inspector’s work for a specific week. It shall provide all category information listed in section 7.2: the total quantity, percentage, and total cost by category as well as the average unit price. It shall be attached to each POLE INSPECTION DETAIL REPORT each week.
Computerized Records – Computerized records are required through field data entry on hand-held computer. Requirements are as follows:
1. One electronic copy provided by delivery via share drive, to include inspection area, per area per week.
2. One electronic copy provided by delivery via share drive, to include rejected poles for replacement, per area per week.
3. One electronic copy provided by delivery using a share drive, to include rejected poles for reinforcement, per area per week.
4. One electronic copy provided by delivery using a share drive, to update database in Microsoft Excel format each month, to include all reports.
Field data shall be supplied to KEYS on a timely basis. The data will be delivered in a geospatial software application that provides information and support for decision making to coordinate lower cost repair, replacement or maintenance activities. The deliverable should include a map view of pole locations along with the ability to query the data and generate reports. The geospatial software application shall also be capable of printing all summary reports by specified date range and pole category prompts, exporting to an Excel or Access database for use. The data shall be supplied by Contractor to KEYS electronically or another format as agreed upon.
All topics represented in the specifications for inspection and treatment and any conditions of interest noticed during the visual inspection shall be provided in the electronically collected data.
7.7 Ownership
KEYS shall retain ownership of all data. All reports, GIS data, databases, photographs, software-generated files, calculations, and work products produced under this Contract shall become the sole property of KEYS.
7.8 Warranty
Contractor warrants inspection services for one (1) year following acceptance. Contractor shall correct any inspection errors identified during the warranty period at no additional cost.
PROPOSAL CONTENTS & EVALUATION
The proposal should include a description of the firm’s capabilities and experience with providing the requested services, including a description of any special qualifications which are indicative of working familiarity with similar projects.
Proposals will be evaluated by an Evaluation Committee using the criteria identified herein. The evaluation criteria will include a variety of considerations, including, but not limited to:
a. Experience with similar projects
b. Range and suitability of services provided
c. Project management approach
d. Pricing
e. References
f. Overall Schedule
KEYS reserves the right to request clarifications, conduct interviews, negotiate with the highest-ranked proposer(s), and award the contract in the best interest of KEYS.
The proposals will be rated by the following Evaluation Matrix, which is based on the above Evaluation Criteria.
ATTACHMENTS
Table 1 Average Ground Line Circumference
For New Poles by Height/Class
Class 1 2 3 4 5 6
30' 37 34 32 30 28 25 H 35' 39 37 34 32 29 27 E 40' 41 39 36 34 31 29 I 45' 43 40 37 35 32 30 G 50' 45 42 39 36 34 -- H 55' 46 43 40 38 -- -- T 60' 47 44 41 38 -- --
Table 2 Minimum Ground Line Circumference in Inches For a Safety Factor of 2.65
Class 1 2 3 4 5 6 30' 33 31 29 27 25 23
H 35' 35 33 31 29 26 25 E 40' 37 35 33 30 28 26 I 45' 39 37 34 32 29 27 G 50' 41 38 35 33 31 -- H 55' 42 39 36 34 -- -- T 60' 43 40 38 35 -- --
Bid Evaluation
Matrix
Criteria Rating
Scale of 1-5
Weighted Value of Rating
Total Weighted
Score Comments
References 3 References provided 15% Price Lowest Cost 40%
Experience Qualified Personnel to perform the inspection and review
10%
Schedule Schedule submitted, estimated time to test 10%
Similar Projects
List of inspection job and amount of poles tested
25%
Total 100%
BID SUBMITTAL
Proposals shall be submitted electronically via VendorLink or DemandStar prior to the opening date and time. Emailed proposals will not be accepted. Should a vendor not be able to submit via VendorLink or DemandStar, paper submittals will be accepted. Paper submittals must be received before the opening date and time to be considered.
Paper submittals can be sent via FedEx, UPS, or In-Person to:
Keys Energy Services Bid Opening Committee – Bid 18-26 6900 Front Street Extended Key West, Florida 33040 Note: This address does not receive US Postal Service.
Bidders must submit the following to be found responsive:
1. Bid Bond or Cashier’s Check for 5% of Total
2. Proposal Page
3. Insurance Agent’s Statement
4. Bidder’s Statement
5. Safety Compliance Affidavit
6. Drug-Free Workplace Statement
7. Public Entity Crimes Sworn Statement
8. 3 References
9. Schedule
KEYS ENERGY SERVICES
GENERAL TERMS & CONDITIONS
ADDITIONS/DELETIONS
KEYS reserves the right to add or delete any item from this bid or resulting contract when deemed to be in the best interest of KEYS.
ALTERATIONS IN PROPOSAL
Except as otherwise provided herein, Proposals which are conditional in any way, or which contain erasures or interlineations not authenticated as provided herein, or which contain items not called for, items not in conformity with applicable laws, changes, additions, recapitulations, alternative Proposals, or any other modifications of the Proposal forms which are not specifically called for in the Contract Documents, will be rejected as not responsive unless specifically agreed to in writing by KEYS. Erasures, interlineations or other corrections shall be authenticated by affixing in the margin immediately opposite the correction, the handwritten initials of each person executing the Proposal.
APPLICABLE LAW
This Contract shall be interpreted in accordance with the law of the State of Florida.
ASSIGNMENT
No contract awarded under these terms, conditions, and specifications, may be sold, transferred or assigned in full or part without the written permission of KEYS. Such written permission shall not relieve contractor from its obligations and liabilities.
ATTORNEY FEES
The prevailing party in any litigation or mediation relating to the contract shall be entitled to recover it reasonable attorney fees and costs from the other party for all matters, including, but not limited to, appeals.
BASIS OF AWARD
A. The award will be made by KEYS on the basis of the Proposal from the lowest responsive* responsible**, Bidder which, in KEYS’ sole and absolute judgment, will best serve the interest of KEYS.
B. KEYS reserves the right to accept or reject any or all Proposals, and to waive any informalities and irregularities in said Proposal.
*Responsive Bidder: Any person, firm, or corporation submitting a bid for the work contemplated whose bid form is complete and regular, free of excisions or special conditions and has no alternative bids for any item unless requested in the technical specifications.
**Responsible Bidder: Any person, firm, or corporation submitting a bid for the work contemplated who maintains a permanent place of business, has adequate manpower and equipment to do the work properly and within the time limit that is established, has adequate financial status to meet his obligations contingent to the work and has a history of performance of like contracts (acceptable to KEYS).
C. Evaluation: The lowest evaluated price shall be determined from an analysis which assesses the impact of the contract price, operational and maintenance costs.
BID BOND/CERTIFIED CHECK
Each proposal should be accompanied by a Bid Bond or Certified Check payable to the UTILITY BOARD OF THE CITY OF KEY WEST, FLORIDA in an amount not less than five (5%) percent of the amount of the proposal as security.
BID PROPOSAL PRICING
All bid proposals must remain firm for 120 days minimum.
BIDDER QUALIFICATIONS
Please provide this information in your bid response.
CITY/COUNTY LICENSING
For the term of the contract, Contractor shall maintain City of Key West and Monroe County licenses and/or other requirements to work within the City or County limits. Contractor should provide KEYS with a copy of all licenses.
COMPLETENESS OF PROPOSAL
A. Each Bidder shall respond to all items on Proposal Page. When quoting on all items including optional items, bidders shall insert the words
“No Bid” in the space provided for any item for which no offer is made. Failure to do so may result in the Proposal being rejected as not responsive.
B. KEYS will consider alternative, additive, or deductive options with no initial pricing.
C. Each Proposal shall include specific acknowledgment of receipt of all Addenda issued during the bidding period. Failure to do so may result in the Proposal being rejected as not responsive.
D. Each Bidder shall furnish information relating to its experience, facilities, material, equipment and business as is required by the Proposal form. Failure to do so may result in the Proposal being rejected as not responsive.
E. Additional technical data furnished by a Bidder, but not required by the Request for Proposal (RFP), may at KEYS’ option be considered part of the Proposal to the extent that it is supplementary to, is consistent with and not contrary to the RFP.
CONTACT REFERENCES
KEYS contact for bidding requirements and technical specifications: Tyler Randolph, Supervisor of Purchasing, Tyler.Randolph@keysenergy.com or purchasing@keysenergy.com.
CONTRACT DURATION
The duration of the base contract shall be from the date of execution by the Utility Board through December 31, 2027. If this contract is for a unit price and estimated quantities and if KEYS desires, KEYS and Contractor can extend the contract at the same unit price. KEYS reserve the right to cancel this contract without cause with 30 days written notice and with cause within 10 days.
CONTRACT CHANGES
No changes, over the contract period, shall be permitted unless prior written approval is given by the Utility Board of the City of Key West, Florida. No Contractor shall assign the contract or any rights or obligations there under without the written consent of KEYS. In the event of such approved subcontracting, contractor agrees to provide KEYS with written documentation relative to the Subcontractor(s) employed in this contract.
CONTRACT COMPLIANCE
All contracts are subject to the terms and conditions of the Fair and Accurate Credit Transactions Act of 2003. The said provisions and compliance therewith are expressly made part of the contract and are binding covenants on the party contracting with KEYS.
CONTRACTOR LIABILITY
In the event of default by Contractor, KEYS reserves the right to utilize the next lowest Bidder as the new Contractor. In the event of this occurrence, the next lowest Bidder, if it wishes the award, shall be required to provide the bid items at the prices as contained on its proposal or bid for this specification.
CONTRACTOR’S RESPONSIBILITIES
A. Contractor shall be responsible for all loss, damage, vandalism, theft, etc. for all equipment, tools, materials, etc. left on the job site.
B. Contractor shall be responsible for maintaining the site in a clean condition during installation. Contractor and KEYS at which time the site should be cleaned up will make a final walk down of the sites.
C. Prior to completion of demobilization, Contractor shall remove all construction materials, waste, demolition debris, excess materials, temporary installation, etc. that have not been specifically turned over and accepted by KEYS.
D. Contractor shall be responsible for any and all costs for cleanup of oil or gasoline spills which result from his equipment or from any work performed as part of this contract.
E. Permit violations or environmental damage caused by contractor shall be mitigated or repaired by contractor, at contractor’s expense, to the satisfaction of the governing authority citing such damage.
F. Items discussed in this section are not intended to be all-inclusive of Federal, State, and Local Laws and Regulations. Information is provided as anticipated minimum requirements. Contractor shall be familiar and comply with all requirements of applicable laws and regulations.
G. Contractor will assume total responsibility for materials, delivery to/from job site, installation, and testing of system.
DELIVERY
A. Delivery, inspection and acceptance - delivery, inspections and acceptance will be at destination, F.O.B. Key West as specified in the RFP, KEYS Warehouse, unless otherwise provided. Until delivery and acceptance and after any rejections, risk of loss will be on the Vendor, unless loss results from negligence of KEYS.
B. Notwithstanding the requirements for any KEYS inspection and test contained in the specifications applicable to this proposal, except where specialized inspections or tests are specified for performance solely by KEYS, contractor shall perform or have performed the inspections and tests required to substantiate that the supplies and services provided under this proposal conform to the drawings, specifications and proposal requirements listed herein, including if applicable, the technical requirements for the manufacturer’s part numbers specified herein.
C. Delivery of Excess Quantities – Contractor is responsible for the delivery of each item quantity within allowable variations, if any.
If contractor delivers and KEYS receives quantities of any item in excess of the quantity called for (after considering any allowable variations of quantity) such excess quantities will be treated as being delivered for the convenience of contractor. KEYS may retain such excess quantities without compensating the interests herein. Quantities in excess, will at the option of KEYS, either be returned at contractor’s expense, or retained and paid for by KEYS at the contract unit price.
D. Deliveries – In the event of failure to deliver material of the quality or within the time specified, KEYS may cancel the order and buy elsewhere. Contractor will be responsible for any cost differences encountered in the procurement of materials. Failure of KEYS to exercise this option with respect to any installment shall not be deemed a waiver with respect of future installments, if any.
E. Delivery tickets – All shipments under this agreement shall be accompanied with delivery tickets, or packing slips, in triplicate, which shall contain the following minimum information: name of supplier, purchase order number, date of order, date of delivery or shipment, itemized list of supplies or services furnished, quantity, unit price, and extension of each line item. Upon delivery, the Warehouse will retain a copy of the related delivery ticket.
F. Inspection, Acceptance and Title – Inspection and acceptance will be at destination, unless otherwise provided. Title and risk of loss or damage to all items shall be the responsibility of the contract supplier until accepted by KEYS in writing.
ENTIRE AGREEMENT
The terms, specifications and/or drawings included in a duly executed contract will constitute the entire agreement between the parties. No modification or waiver of terms of this agreement shall be binding, unless in writing, signed by a duly authorized representative of KEYS.
mailto:Tyler.Randolph@keysenergy.com mailto:purchasing@keysenergy.com
ERROR IN BID CALCULATION
In the event there is a mathematical error in the bid, KEYS will recalculate using the line items and correct the total.
EXECUTION OF PROPOSAL
If a Proposal is made by a partnership, it shall contain the name and address of each partner and shall be executed in the partnership name, followed by the handwritten signature of a partner authorized to execute the Proposal for the partnership. If a Proposal is made by a corporation, it shall be executed in the name of the corporation, followed by the handwritten signature of an officer authorized to execute the Proposal for the corporation, and the printed or typewritten designation of the office he holds in corporation. Another partner of the partnership or official of the corporation shall attest to the authority of the person executing the Proposal. KEYS may require any Bidder to furnish certified copies of extracts of the minutes of meetings of the governing body of the Bidder authorizing execution of the Proposal and Contract Documents.
FORCE MAJEURE
KEYS shall not be liable in any way to contractor as a result of an event, circumstance or act of a third party that is beyond a party’s reasonable control (e.g. an act of God, and act of the public enemy, an act of a government entity, strikes or other labor disturbances, hurricanes, earthquakes, fires, floods, epidemics, embargoes, war and riots).
LITIGATION SEARCH
KEYS reserve the right to conduct a litigation search on contractor’s history of past litigation.
LIQUIDATED DAMAGES
In the event the Scope of Work is not substantially complete on or before September 30, 2027, liquidated damages shall be payable by Contractor to KEYS in the amount of $500.00 per day for each day the Scope of Work is not substantially complete.
The parties recognize that the damages to be incurred by KEYS as a result of delay in completion of the Scope of Work are difficult to estimate at this time and would be difficult for KEYS to prove. The parties intend that the payment of Liquidated Damages set forth above would serve to compensate KEYS for its damages resulting from such delay in completion, and constitutes a reasonable, good faith approximation of such damages. The liquidated damages set forth herein are not intended to, nor shall be construed to, function as a penalty, and shall not preclude other remedies available to KEYS at law or in equity.
MATERIAL
No goods or materials provided pursuant to the proposal shall consist of or contain any equipment which has been manufactured or supplied by persons or entities owned by, controlled by, or subject to the jurisdiction or direction of the government of the People’s Republic of China.
MODIFICATION OF PROPOSAL
A modification of a proposal already received will be considered only if the modification is received prior to the time last announced for opening Proposals. All modifications shall be made in writing, executed and submitted in the same form and manner as the original proposal, fax or E-mail.
Phone modifications will not be considered.
NOTICE TO PROCEED
KEYS will issue the successful bidder a Notice to Proceed after the following activities have been completed: 1) the Performance Bond and Insurance Certificates have been received and approved by KEYS, 2) a meeting has been held and issues regarding environmental, lien releases, payment procedures, safety, security, and use of sub-contractor notification were discussed. The successful bidder will be asked to complete the signature to acknowledge receipt of this notice.
OPENING PROPOSALS
At the time and place last announced for opening Proposals, each Proposal which has been received prior to the time last announced for opening Proposals, except those which have been properly withdrawn, will be publicly opened, irrespective of any irregularities or informalities in such Proposals.
KEYS INSPECTIONS/MEETINGS
KEYS will make inspections and/or meetings as deemed necessary to ensure that all work is being performed in compliance with these specifications and guarantees.
PAYMENT
Payment will be made after acceptance of services and materials and within 30 days after receipt of invoice. KEYS will hold 5% retention until 30 days after project completion and final acceptance. Contractor will complete and submit the provided Contractor’s Request for Payment form, prior to any payment of draw request. Contractor’s request for payment shall be accompanied by a breakdown of material and labor associated with that particular request. KEYS does not pay service charges on late payments.
PENALTIES
KEYS reserves the right to increase or decrease quantities shown without penalties.
PERSONNEL
A. The project supervisor must be capable of communicating fluently in English at all times.
B. On a project, the foreman must be capable of communicating fluently in English.
C. All employees of company must be United States Citizens or legally authorized to reside and work in the United States.
D. KEYS may request at any time throughout the contract the following within eight (8) hours:
- Proof of citizenship for all employees
- Proof of employee’s salary is at or above state and federal minimum requirements
- Proof of eligibility to legally work in the United States
POSTPONEMENT OF OPENING
KEYS reserves the right to postpone the date and time last announced for opening Proposals and such postponement may be made at any time prior to the time last announced for opening Proposals. KEYS will give written notice in the form of an Addendum by email to each party to whom Contract Documents have been issued in addition to posting the Addendum on DemandStar, Vendorlink, and Keysenergy.com websites, stating the change in date and time of any such postponement.
PRICES
A. All prices bid shall be firm unless the conditions of the RFP permit price escalation. If an escalation method or indices are specified, the
Bidder shall indicate in its bid the specific items subject to escalation, and shall give the method and indices to be used in computing the amount thereof.
B. The vendor shall provide the proposal price in U.S. dollars only.
PROPOSAL GUARANTEE
A. The Proposal Guarantee shall be the cashier’s check or Bid Bond required in the Notice to Bidders. A bid bond or cashier’s check in lieu of a surety bond in the amount of (five) 5% of the proposal shall be submitted with all proposals. This bid bond requirement is to be used as security and will be returned to bidder after KEYS enters into a Contract with the successful bidder. This (five) 5% shall be based on the total bid price. The bid bond or cashier’s check shall be valid for a period of no less than 120 days after bid opening date.
B. KEYS may reject all Proposals, and in such event, all cashier’s checks and Bid Bonds will thereupon be returned to the Bidders.
C. When a Proposal is accepted, all checks and Bid Bonds will thereupon be returned to the bidders, except for the approved proposal. The cashier’s check or Bid Bond of the approved Bidder will be returned after completion of the requirements in the following paragraph.
D. Within (ten) 10 days after delivery of Notice of Utility Board Approval, or such additional time as is allowed by KEYS, the Bidder shall furnish satisfactory Performance and Payment Bond, Insurance Certificate and Insurance Policies.
PROTESTS
Any bidder who believes he has been aggrieved in connection with the staff recommendation or award of a contract may protest in writing to the KEYS Purchasing Department. The deadline for filing a protest is prior to the commencement of the Utility Board meeting wherein the award is to be considered. It is the responsibility of the bidder to ascertain the bid award information from DemandStar or VendorLink.
Protests shall specifically describe the subject matter and facts giving rise to the protest.
PUBLIC RECORDS ACT
Pursuant to F.S. 119.0701 of the Public Records Act, any request to inspect or copy public records relating to a public agency’s contract for services must be made directly to the public agency. Contractors is required to comply with public records laws and upon request by the public records custodian, shall provide a copy of the requested records or allow the records to be inspected or copied within a reasonable time at a cost not to exceed the cost provided in Ch. 119, F.S. or as otherwise provided by law. A contractor who fails to provide the records to the agency within a reasonable time may be subject to penalties as provided in F.S. 119.10
IF CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION OF
CHAPTER 119, FLORIDA STATUTES, TO CONTRACTOR’S DUTY TO
PROVIDE PUBLIC RECORDS RELATING TO THIS CONTRACT, CONTACT
THE CUSTODIAN OF PUBLIC RECORDS AT:
KEYS ENERGY SERVICES
P.O. BOX 6100
Key West, FL 33041-6100
(305) 295-1067
Gricel Owen Email: gricel.owen@keysenergy.com
PUBLIC ENTITY CRIME CLAUSE
Any person submitting a bid or proposal in response to this invitation must execute the enclosed form FOR 094, SWORN STATEMENT UNDER SECTION 287.133 (3) (a), FLORIDA STATUTES ON PUBLIC ENTITY CRIMES, including proper check(s), in the space(s) provided, and enclose it with his bid proposal. If you are submitting as bid or proposal on behalf of dealers or suppliers who will ship commodities and receive payment from the resulting contract, it is your responsibility to see that copies of the form are executed by them and are included with your bid or proposal. Corrections to the form will not be allowed after the bid or proposal opening time and date.
Failure to complete this form may result in immediate disqualification of your bid or proposal.
QUALITY ASSURANCE PROVISIONS