KEYS_Bid_01-25_Addendum_1.pdf
PDF 141 KB Posted
- Attached to
- Specifications for Substation Battery Purchase
- Solicitation number
- 01-25
- Issued by
- Florida
About this file
This document is Addendum 1 for KEYS BID 01-25, a bid specification for substation battery replacement issued by the Keys Energy Services (KEYS) in Florida. The addendum provides clarification on bid requirements, specifically addressing whether a bid bond is required for this procurement. According to the document, no bid bond is necessary for this bid; however, the awarded vendor must provide a supply bond.
The addendum is part of a procurement process for substation batteries, focusing on critical infrastructure equipment replacement. While the document is limited in scope, it indicates an important procedural detail that potential vendors should note when preparing their bid submissions. The supply bond requirement suggests the government entity is seeking to mitigate financial risks associated with the battery replacement project by ensuring the selected vendor can fulfill the contract obligations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| KEYS_Bid_01-25_Addendum_2.pdf | ||
| 01-25_Specifications_for_Substation_Battery_Replacement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KEYS BID 01-25 SPECIFICATIONS FOR SUBSTATION BATTERY REPLACEMENT
Addendum 1
Questions and Answers:
1. Is a bid bond required?
a. No, a bid bond is not required. However, a supply bond must be provided by the awarded vendor.