This is an Engineers Opinion of Probable Construction Cost (EOPCC) document for the Kellogg Park Nature Center project in Walton County, Florida, dated January 2025. The project encompasses comprehensive site development including erosion control, paving, earthwork, water and sewer infrastructure, site improvements, landscape and irrigation work, and building construction. The EOPCC provides itemized cost estimates across multiple work categories with specific quantities and unit prices, including 1,000 linear feet of silt fence, 190 tons of SP-12.5 asphalt paving, 2,400 square yards of subgrade work, 1,300 cubic yards of excavation and embankment, water service installation, sewer infrastructure including grinder pump and force main, site mobilization and lighting, and extensive landscape work featuring native plantings such as Shumard oak, saw palmetto, and bahiagrass totaling over 10,000 square feet.

The total estimated construction cost is $1,155,952.00 for all bid items, with an owner's contingency of 10% ($115,595.20) bringing the grand total to $1,271,547.20. The cost estimates are based on unit prices and quantities as outlined in each category, with notable expenses including site lighting at $82,500, building construction at $592,125, mobilization at $43,000, and paving work totaling $178,310. The consultant notes that these opinions of probable costs are based on information known at the time of preparation and represent professional judgment; actual bids and construction costs may vary due to factors beyond the consultant's control, including labor costs, material prices, equipment availability, contractor pricing methods, and market conditions.

View the file

Other files for this state and local contract opportunity

Other files attached to Kellogg Park Nature Center, newest first.
File Type Posted
Kellogg_Park_Nature_Center_(Addendum_#4_Revision).pdf PDF
Kellogg_Park_Nature_Center_(Addendum_#4_Revision).pdf PDF
Kellogg_Park_Nature_Center_-_Bid_Schedule.xlsx XLSX spreadsheet
Kellogg_Park_Nature_Center_-_Bid_Schedule.xlsx XLSX spreadsheet
Kellogg_Park_Nature_Center_-_EOPCC_1.6.2025.xlsx XLSX spreadsheet
Kellogg_Park_Nature_Center_-_Photometric_Plans.pdf PDF
Kellogg_Park_Nature_Center_-_Photometric_Plans.pdf PDF
Kellogg_Park_ITB_25-07_Electrical_RTAP25_-_6_-_9_-_F_-_2_-_BC_-_VDP.pdf PDF
Kellogg_Park_ITB_25-07_Electrical_BDAR5-LED_(1).pdf PDF
Kellogg_Park_ITB_25-07_Electrical_DS6-LED.pdf PDF
Kellogg_Park_ITB_25-07_Electrical_BDAR5-LED_(1).pdf PDF
Kellogg_Park_ITB_25-07_Electrical_DS6-LED.pdf PDF
Kellogg_Park_ITB_25-07_Electrical_RTAP25_-_6_-_9_-_F_-_2_-_BC_-_VDP.pdf PDF
Kellogg_Park_Nature_Center_-_Geotech_Report.pdf PDF
Kellogg_Park_Nature_Center_-_Geotech_Report.pdf PDF
Contract_No._25-07.pdf PDF
Contract_No._25-07.pdf PDF
FDEP_Permit_No._0452113-001-DWC_CG.pdf PDF
Minor_Development_Order_No._MIN24-000024.pdf PDF
Northwest_Florida_Water_Management_District_Permit_No._IND-131-7626-2.pdf PDF
Minor_Development_Order_No._MIN24-000024.pdf PDF
FDEP_Permit_No._0452113-001-DWC_CG.pdf PDF
Northwest_Florida_Water_Management_District_Permit_No._IND-131-7626-2.pdf PDF
Completed_Kellogg_Nature_Center_Intake_Form_1_6_2025_AM.doc DOC document
Kellogg_Park_Nature_Center_-_100%_Plumbing_Submittal.pdf PDF
Completed_Kellogg_Nature_Center_Intake_Form_1_6_2025_AM.doc DOC document
Kellogg_Park_Nature_Center_-_100%_Architectural_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Civil_Plans.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Landscape_&_Irrigation_Plans.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Structural_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Civil_Plans.pdf PDF
Kellogg_Park_Nature_Center_-_100%_HVAC_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Landscape_&_Irrigation_Plans.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Structural_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_Energy_Form_-_DS.pdf PDF
Kellogg_Park_Nature_Center_-_100%_HVAC_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Plumbing_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Architectural_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Electrical_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Electrical_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_Energy_Form_-_DS.pdf PDF
Public_Construction_Bond_(25).doc DOC document
Public_Construction_Bond_(25).doc DOC document
25-07_Required_Submittals.pdf PDF
25-07_Cost_Proposal.pdf PDF
25-07_ADA_Public_Beach_Access_#16_Final.pdf PDF
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Preliminary Bid Items

Engineers Opinion of Probable Construction Cost
Kellogg Park Nature Center
Walton County, FL
January 2025
DESCRIPTIONUNITQTYUNIT PRICETOTAL
EROSION CONTROL
Erosion Control - Silt FenceLF1,000$ 5.00$ 5,000.00
Erosion Control - Inlet ProtectionEA2$ 300.00$ 600.00
Eroision Control Construction EntranceLS1$ 10,000.00$ 10,000.00
Clearing and Grubbing/DemolitionAC0.80$ 75,000.00$ 60,000.00
Subtotal$ 75,600.00
PAVING
SP-12.5 (1.5")TN190$ 185.00$ 35,150.00
SP-9.5 (1")TN130$ 185.00$ 24,050.00
6" Limerock BaseSY2,300$ 35.00$ 80,500.00
12" SubgradeSY2,400$ 13.00$ 31,200.00
Concrete Sidewalk (4" Thick)SY95$ 78.00$ 7,410.00
Subtotal$ 178,310.00
EARTHWORK
Excavation and EmbankmentCY1,300$ 30.00$ 39,000.00
Subtotal$ 39,000.00
WATER
1" HDPE Water ServiceLF60$ 65.00$ 3,900.00
Subtotal$ 3,900.00
SEWER
2" Tapping Sleeve and ValveEA1$ 7,500.00$ 7,500.00
4" PVC SewerLF45$ 78.00$ 3,510.00
Grinder PumpLS1$ 10,000.00$ 10,000.00
2" PVC Force MainLF130$ 105.00$ 13,650.00
4" CleanoutEA1$ 1,000.00$ 1,000.00
Subtotal$ 35,660.00
SITE MISC.
MobilizationLS1$ 43,000.00$ 43,000.00
SignageEA4$ 500.00$ 2,000.00
StripingLS1$ 4,000.00$ 4,000.00
DewateringLS1$ 10,000.00$ 10,000.00
As-Built SurveyLS1$ 10,000.00$ 10,000.00
3' Wooden FenceLF85$ 75.00$ 6,375.00
Site LightingLS1$ 82,500.00$ 82,500.00
Subtotal$ 157,875.00
LANDSCAPE/IRRIGATION
IrrigationSF2,600$ 2.00$ 5,200.00
Irrigation WellLS1$ 5,000.00$ 5,000.00
Tree ProtectionLS1$ 2,500.00$ 2,500.00
Shumard OakEA5$ 1,200.00$ 6,000.00
Saw PalmettoEA59$ 70.00$ 4,130.00
Dwarf Walter's ViburnumEA75$ 50.00$ 3,750.00
Florida CooniteEA135$ 60.00$ 8,100.00
Sad CordgrassEA67$ 25.00$ 1,675.00
African LilySF493$ 20.00$ 9,860.00
Dune SunflowerSF116$ 20.00$ 2,320.00
BahiagrassSF10,772$ 1.00$ 10,772.00
Top SoilCY405$ 35.00$ 14,175.00
Subtotal$ 73,482.00
Building ConstructionLS1$592,125.00$592,125.00
Subtotal$592,125.00
Combined Subtotals$ 1,155,952.00
Owner's Contingecy - 10%$ 115,595.20
Grand Total$ 1,271,547.20
NOTE

The Consultant has no control over the cost of labor, materials, equipment, or over the Contractor's methods of determining prices or over competitive bidding or market conditions. Opinions of probable costs provided herein are based on the information known to Consultant at this time and represent only the Consultant's judgment as a design professional familiar with the construction industry. The Consultant cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from its opinions of probable costs.