Kellogg_Park_Nature_Center_-_EOPCC_1.6.2025.xlsx

XLSX spreadsheet 614 KB Posted

Attached to
Kellogg Park Nature Center State and local contract opportunity
Solicitation number
25-07
Issued by
Bay County, Florida

About this file

The document is an Engineers Opinion of Probable Construction Cost (EOPCC) for the Kellogg Park Nature Center project in Walton County, Florida. The project involves a comprehensive site development including erosion control, paving, earthwork, water and sewer infrastructure, site miscellaneous work, landscaping, and building construction. The total estimated project cost is $1,271,547.20, with a breakdown of major categories such as erosion control ($75,600), paving ($178,310), earthwork ($39,000), water and sewer infrastructure ($39,560), site miscellaneous work ($157,875), landscaping and irrigation ($73,482), and building construction ($592,125). The cost estimate includes a 10% owner's contingency and covers elements like sidewalks, water service, sewer connections, site lighting, fencing, and extensive landscaping including various native plant species like Shumard Oak, Saw Palmetto, and Bahiagrass.

The pricing breakdown indicates a detailed approach to project costing, with unit prices for specific components ranging from $5 per linear foot for silt fence to $185 per ton for asphalt paving. The project appears to be a comprehensive nature center development with significant infrastructure and environmental considerations. While the document does not specify funding sources directly, it provides a granular view of expected construction costs. The estimate includes provisions for mobilization, dewatering, as-built surveys, irrigation, and site preparation, suggesting a thorough and professional approach to project planning and budgeting.

View the file

Other files for this state and local contract opportunity

Other files attached to Kellogg Park Nature Center, newest first.
File Type Posted
Kellogg_Park_Nature_Center_(Addendum_#4_Revision).pdf PDF
Kellogg_Park_Nature_Center_(Addendum_#4_Revision).pdf PDF
Kellogg_Park_Nature_Center_-_Bid_Schedule.xlsx XLSX spreadsheet
Kellogg_Park_Nature_Center_-_Bid_Schedule.xlsx XLSX spreadsheet
Kellogg_Park_Nature_Center_-_EOPCC_1.6.2025.xlsx XLSX spreadsheet
Kellogg_Park_Nature_Center_-_Photometric_Plans.pdf PDF
Kellogg_Park_Nature_Center_-_Photometric_Plans.pdf PDF
Kellogg_Park_ITB_25-07_Electrical_DS6-LED.pdf PDF
Kellogg_Park_ITB_25-07_Electrical_RTAP25_-_6_-_9_-_F_-_2_-_BC_-_VDP.pdf PDF
Kellogg_Park_ITB_25-07_Electrical_RTAP25_-_6_-_9_-_F_-_2_-_BC_-_VDP.pdf PDF
Kellogg_Park_ITB_25-07_Electrical_BDAR5-LED_(1).pdf PDF
Kellogg_Park_ITB_25-07_Electrical_DS6-LED.pdf PDF
Kellogg_Park_ITB_25-07_Electrical_BDAR5-LED_(1).pdf PDF
Kellogg_Park_Nature_Center_-_Geotech_Report.pdf PDF
Kellogg_Park_Nature_Center_-_Geotech_Report.pdf PDF
Contract_No._25-07.pdf PDF
Contract_No._25-07.pdf PDF
FDEP_Permit_No._0452113-001-DWC_CG.pdf PDF
Northwest_Florida_Water_Management_District_Permit_No._IND-131-7626-2.pdf PDF
FDEP_Permit_No._0452113-001-DWC_CG.pdf PDF
Minor_Development_Order_No._MIN24-000024.pdf PDF
Northwest_Florida_Water_Management_District_Permit_No._IND-131-7626-2.pdf PDF
Minor_Development_Order_No._MIN24-000024.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Architectural_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Electrical_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Electrical_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_Energy_Form_-_DS.pdf PDF
Completed_Kellogg_Nature_Center_Intake_Form_1_6_2025_AM.doc DOC document
Kellogg_Park_Nature_Center_-_100%_Plumbing_Submittal.pdf PDF
Completed_Kellogg_Nature_Center_Intake_Form_1_6_2025_AM.doc DOC document
Kellogg_Park_Nature_Center_-_100%_Architectural_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Civil_Plans.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Landscape_&_Irrigation_Plans.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Structural_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Civil_Plans.pdf PDF
Kellogg_Park_Nature_Center_-_100%_HVAC_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Landscape_&_Irrigation_Plans.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Structural_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_Energy_Form_-_DS.pdf PDF
Kellogg_Park_Nature_Center_-_100%_HVAC_Submittal.pdf PDF
Kellogg_Park_Nature_Center_-_100%_Plumbing_Submittal.pdf PDF
Public_Construction_Bond_(25).doc DOC document
Public_Construction_Bond_(25).doc DOC document
25-07_Required_Submittals.pdf PDF
25-07_Cost_Proposal.pdf PDF
25-07_ADA_Public_Beach_Access_#16_Final.pdf PDF
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Preliminary Bid Items

Engineers Opinion of Probable Construction Cost
Kellogg Park Nature Center
Walton County, FL
January 2025
DESCRIPTIONUNITQTYUNIT PRICETOTAL
EROSION CONTROL
Erosion Control - Silt FenceLF1,000$ 5.00$ 5,000.00
Erosion Control - Inlet ProtectionEA2$ 300.00$ 600.00
Eroision Control Construction EntranceLS1$ 10,000.00$ 10,000.00
Clearing and Grubbing/DemolitionAC0.80$ 75,000.00$ 60,000.00
Subtotal$ 75,600.00
PAVING
SP-12.5 (1.5")TN190$ 185.00$ 35,150.00
SP-9.5 (1")TN130$ 185.00$ 24,050.00
6" Limerock BaseSY2,300$ 35.00$ 80,500.00
12" SubgradeSY2,400$ 13.00$ 31,200.00
Concrete Sidewalk (4" Thick)SY95$ 78.00$ 7,410.00
Subtotal$ 178,310.00
EARTHWORK
Excavation and EmbankmentCY1,300$ 30.00$ 39,000.00
Subtotal$ 39,000.00
WATER
1" HDPE Water ServiceLF60$ 65.00$ 3,900.00
Subtotal$ 3,900.00
SEWER
2" Tapping Sleeve and ValveEA1$ 7,500.00$ 7,500.00
4" PVC SewerLF45$ 78.00$ 3,510.00
Grinder PumpLS1$ 10,000.00$ 10,000.00
2" PVC Force MainLF130$ 105.00$ 13,650.00
4" CleanoutEA1$ 1,000.00$ 1,000.00
Subtotal$ 35,660.00
SITE MISC.
MobilizationLS1$ 43,000.00$ 43,000.00
SignageEA4$ 500.00$ 2,000.00
StripingLS1$ 4,000.00$ 4,000.00
DewateringLS1$ 10,000.00$ 10,000.00
As-Built SurveyLS1$ 10,000.00$ 10,000.00
3' Wooden FenceLF85$ 75.00$ 6,375.00
Site LightingLS1$ 82,500.00$ 82,500.00
Subtotal$ 157,875.00
LANDSCAPE/IRRIGATION
IrrigationSF2,600$ 2.00$ 5,200.00
Irrigation WellLS1$ 5,000.00$ 5,000.00
Tree ProtectionLS1$ 2,500.00$ 2,500.00
Shumard OakEA5$ 1,200.00$ 6,000.00
Saw PalmettoEA59$ 70.00$ 4,130.00
Dwarf Walter's ViburnumEA75$ 50.00$ 3,750.00
Florida CooniteEA135$ 60.00$ 8,100.00
Sad CordgrassEA67$ 25.00$ 1,675.00
African LilySF493$ 20.00$ 9,860.00
Dune SunflowerSF116$ 20.00$ 2,320.00
BahiagrassSF10,772$ 1.00$ 10,772.00
Top SoilCY405$ 35.00$ 14,175.00
Subtotal$ 73,482.00
Building ConstructionLS1$592,125.00$592,125.00
Subtotal$592,125.00
Combined Subtotals$ 1,155,952.00
Owner's Contingecy - 10%$ 115,595.20
Grand Total$ 1,271,547.20
NOTE

The Consultant has no control over the cost of labor, materials, equipment, or over the Contractor's methods of determining prices or over competitive bidding or market conditions. Opinions of probable costs provided herein are based on the information known to Consultant at this time and represent only the Consultant's judgment as a design professional familiar with the construction industry. The Consultant cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from its opinions of probable costs.