About this file

This is a project manual and Invitation for Bids (IFB) issued by the City of Peachtree City, Georgia for the Kedron Pool Boiler Replacement project at the Kedron Aquatic Center. The project involves replacing the boiler used to heat water for both pools, replacing pumps and related piping to circulate heating fluid through heat exchangers, and testing and balancing the entire system once installed. A mandatory pre-bid meeting will be held on February 13, 2025 at 10:00 AM local time at the Kedron Fieldhouse and Aquatic Center. Sealed bids are due February 27, 2025 at 3:00 PM local time. The project must reach substantial completion within 120 calendar days from Notice to Proceed, with final completion 30 days thereafter.

The project is locally funded and requires a 5% bid security. Performance and payment bonds will be required at 100% and 110% of the contract value respectively. Liquidated damages of $250 per day will be assessed for late completion beyond both substantial and final completion deadlines. The contractor must have a current Georgia General Contractor's License and at least 5 years of experience installing commercial grade mechanical equipment. No substitutions will be allowed for the specified boiler equipment. The contract will be awarded to the lowest responsive and responsible bidder.

View the file

Other files

File Type Posted
Addendum 1 _Kedron Pool Boiler Replacement.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual For

KEDRON POOL

BOILER

REPLACEMENT

INTENTIONALLY

LEFT BLANK

Kedron Pool Boiler Replacement 00 01 10-1

25-111BES TABLE OF CONTENTS

SECTION 00 01 10

TABLE OF CONTENTS

00 11 13 Invitation for Bids 00 21 13 Instructions to Bidders 00 22 13 Supplementary Instructions to Bidders 00 31 00 Available Project Information 00 41 00 Bid Form 00 43 13 Bid Security Form 00 45 13 Bidder’s Qualifications 00 45 19 Non-Collusion Affidavit 00 45 20 Security and Immigration Compliance 00 51 00 Notice of Award 00 52 00 Agreement 00 55 00 Notice to Proceed 00 61 13 Performance Bond 00 61 15 Payment Bond 00 65 16 Certificate of Substantial Completion 00 65 19 Affidavit of Payment and Debts and Claims 00 65 20 Affidavit of Release of Liens 00 65 21 Consent of Surety to Final Payment 00 72 00 General Conditions 00 73 00 Supplementary Conditions 00 73 19 Drug Free Workplace Certification 00 94 39 Field Order 00 94 49 Work Change Directive 00 94 63 Change Order 01 10 00 Summary 01 20 00 Price and Payment Procedures 01 30 00 Administrative Requirements 01 33 00 Submittal Procedures

Kedron Pool Boiler Replacement 00 01 10-2

25-111BES TABLE OF CONTENTS

01 40 00 Quality Requirements 01 45 29 Testing Laboratory Services 01 50 00 Temporary Facilities and Controls 01 60 00 Product Requirements 01 70 00 Execution and Closeout Requirements 01 75 16 Start-up Procedures Appendix A Plans Appendix B Technical Specifications

END OF SECTION

Kedron Pool Boiler Replacement 00 11 13-1

25-111BES INVITATION FOR BIDS

SECTION 00 11 13

INVITATION FOR BIDS

Project Name: Kedron Pool Boiler Replacement Date of Issue: January 28, 2025

City of Peachtree Contract No.:

25-111BES Bid Date: February 27, 2025/3:00 pm local time

Owner Engineer City of Peachtree City 151 Willowbend Road Peachtree City, GA 30269 (email) aegan@peachtree-city.org

Bryan Kler N/A N/A

The City of Peachtree City will be receiving separate sealed Bids for all material, labor and equipment for the “Kedron Pool Boiler Replacement”. This includes the following, with all related accessories as shown on the Construction Drawings and called for in the Contract Documents and Technical Specifications:

Project includes furnishing equipment and labor to replace the boiler used to heat the water for both pools at the Kedron Aquatic Center, replace the pumps and related piping to circulate heating fluid through heat exchangers, and test and balance entire system once installed.

This contract is locally funded.

Contract Documents may be downloaded at the following location:

• www.peachtree-city.org, then click on “Business”, then doing business with the City.

It is mandatory that all prospective bidders download the Project Manual and Construction Drawings from the website above. Each Bidder is responsible for checking the website above for any future Addendums and emailing the Purchasing Agent with any questions.

Each Bidder must deposit with his bid, security in the amount of 5%, and shall be subject to the conditions provided in Section 00 21 13 “Instruction to Bidders.”

Each Bidder is required to submit a “Construction Contractors Qualification Statement”, “Bid Security”, “Bid Form”, Non-Collusion Affidavit”, and “Security and Immigration Compliance Affidavit” as outlined in Section 00 22 13 “Supplementary Instructions to Bidders.”

The City of Peachtree City will receive sealed bids until February 27, 2025/3:00 pm local time at 151 Willowbend Road, Peachtree City, GA 30269. Bids received after this time will not be accepted. Bids will be opened and publicly read aloud. The contract will be awarded to the low, responsive, and responsible bidder with reservation of right to reject all bids. Bids may not be withdrawn by Bidders for 60 days following opening of the bids.

http://www.peachtree-city.org/

Kedron Pool Boiler Replacement 00 11 13-2

25-111BES INVITATION FOR BIDS

The project shall be Substantially Complete within 120 calendar days from the date of Notice to Proceed of the contract. Liquidated Damages shall be assessed in the amount of $250.00 per day for each calendar day required to achieve Substantial Completion.

The project shall be Final Complete within 30 calendar days beyond Substantial Completion.

Liquidated Damages shall be assessed in the amount of $250.00 per day for each calendar day required to achieve Final Completion.

There will be a “Pre-Bid” meeting on February 13, 2025/10:00 am local time located at Kedron Fieldhouse and Aquatic Center – 202 Fieldhouse Dr., Peachtree City, GA 30269. If there is a pre-bid meeting, all contractors submitting a Bid are required to attend or send a designee to attend. A sign-in sheet will be available to record attendance.

The City of Peachtree City provides assurances to Bidder that all anticipated Federal, State, and Local Permits along with anticipated Rights of Way and Easements have been obtained or will be obtained by N/A.

The City of Peachtree City will not accept pre-bid project questions within a period of 120 hours prior to the advertised time for opening bids, excluding Saturdays, Sundays, and Peachtree City Legal Holidays.

The City of Peachtree City will not issue or cause to be issued any addenda modifying the Project Manual or Construction Drawings within a period of 72 hours prior to the advertised time for opening bids, excluding Saturdays, Sundays, and Peachtree City Legal Holidays.

Agreement will require a Payment Bond in the amount of 110%, and a Performance Bond in the amount of 100% of the project cost.

The City of Peachtree City reserves the right to bid a project in phases and award the contract on the phases it deems to be in the City’s best interest.

Kedron Pool Boiler Replacement 00 21 13-1

25-111BES INSTRUCTIONS TO BIDDERS

SECTION 00 21 13

INSTRUCTIONS TO BIDDERS

TABLE OF CONTENTS

Page

Article 1 – Defined Terms

Article 2 – Copies of Bidding Documents

Article 3 – Qualifications of Bidders

Article 4 – Examination of Bidding Documents, Other Related Data, and Site

Article 5 – Pre-Bid Conference

Article 6 – Site and Other Areas

Article 7 – Interpretations and Addenda

Article 8 – Bid Security

Article 9 – Contract Times

Article 10 – Liquidated Damages

Article 11 – Substitute and “Or Equal” Items

Article 12 – Subcontractors, Suppliers and Others

Article 13 – Preparation of Bid

Article 14 – Basis of Bid; Comparison of Bids

Article 15 – Submittal of Bid

Article 16 – Modification and Withdrawal of Bid

Article 17 – Opening of Bids

Article 18 – Bids to Remain Subject to Acceptance

Article 19 – Evaluation of Bids and Award of Contract

Article 20 – Contract Security and Insurance

Article 21 – Signing of Agreement

Kedron Pool Boiler Replacement 00 21 13-2

ARTICLE 1 – DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General

Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. The City of Peachtree City or www.peachtree-city.org – The office from which the

Bidding Documents are to be issued and where the bidding procedures are to be administered, otherwise known as issuing office.

B. Business Day(s) – 24 hours measured from midnight to next midnight excluding weekend and Peachtree City observed holidays.

C. Calendar Day(s) – 24 hours measured from midnight to next midnight including weekend and Peachtree City observed holidays.

ARTICLE 2 – COPIES OF BIDDING DOCUMENTS

2.01 Complete sets of the Bidding Documents in the number and for the deposit sum, if any, stated in the advertisement or invitation to bid may be obtained electronically from the Issuing Office.

2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.

ARTICLE 3 – QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, within three (3) business days of Owner’s request, Bidder shall submit written evidence of any data requested by Owner over and above what is to be provided in Section 00 45 13 “Bidder’s Qualifications.”

3.02 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.

ARTICLE 4 – EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED

DATA, AND SITE

4.01 Subsurface and Physical Conditions, if applicable in Section 00 31 00

A. The Supplementary Conditions identify:

1. Those reports known to Owner of explorations and tests of subsurface conditions at or contiguous to the Site.

2. Those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).

Kedron Pool Boiler Replacement 00 21 13-3

B. Copies of reports and drawings referenced in Paragraph 4.01.A will be made available by Owner to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in Paragraph 4.02 of the General Conditions has been identified and established in Paragraph 4.02 of the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

4.02 Underground Facilities

A. Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the Site is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.

4.03 Hazardous Environmental Condition, if applicable in Section 00 31 00 A. The Supplementary Conditions identify any reports and drawings known to Owner relating to a Hazardous Environmental Condition identified at the Site.

B. Copies of reports and drawings referenced in Paragraph 4.03.A will be made available by Owner to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in Paragraph 4.06 of the General Conditions has been identified and established in Paragraph 4.06 of the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

4.04 Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 4.02, 4.03, and

4.04 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 4.06 of the General Conditions.

4.05 On request and subsequent approval of Owner and Property Owner, Owner will provide Bidder access to the Site to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies. Bidder shall comply with all applicable Laws and Regulations relative to excavation and utility locates. Bidder to provide a description of tests, etc. prior to approval.

4.06 A. On request, Owner will provide to each Bidder for examination, access to, or copies

Kedron Pool Boiler Replacement 00 21 13-4 of contract documents for such other work. If a reference is made to Article 7 of the Supplementary Conditions for the identification of the general nature of other work that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) that relates to the Work contemplated by these Bidding Documents.

B. Paragraph 6.13.C of the General Conditions indicates that if an Owner safety program exists, it will be noted in the Supplementary Conditions.

4.07 It is the responsibility of each Bidder before submitting a Bid to:

A. examine and carefully study the Bidding Documents, and the other related data identified in the Bidding Documents;

B. visit the Site and become familiar with and satisfy Bidder as to the general, local, and

Site conditions that may affect cost, progress, and performance of the Work;

C. become familiar with and satisfy Bidder as to all federal, state, and local Laws and

Regulations that may affect cost, progress, and performance of the Work;

D. if provided in Section 00 31 00, Available Project Information carefully study all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities) that have been identified in Paragraph 4.02 of the Supplementary Conditions as containing reliable "technical data," and (2) reports and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in the Paragraph 4.06 of the Supplementary Conditions as containing reliable "technical data";

E. consider the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs;

F. agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;

G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;

H. promptly give Peachtree City written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Peachtree City is acceptable to Bidder; and

I. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.

Kedron Pool Boiler Replacement 00 21 13-5

4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given Peachtree City written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in the Bidding Documents and the written resolutions thereof by Peachtree City are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.

ARTICLE 5 – PRE-BID CONFERENCE

5.01 There will be a “Pre-Bid” meeting on February 13, 2025/10:00 am local time located at

Kedron Fieldhouse and Aquatic Center – 202 Fieldhouse Dr., Peachtree City, GA 30269.

If there is a pre-bid meeting, all contractors submitting a Bid are required to attend or send a designee to attend. Representatives of Peachtree City and Engineer will be present to discuss the Project. Peachtree City will post to the website for all prospective Bidders of record such Addenda as Peachtree City considers necessary in response to questions arising at the conference or thereafter. Oral statements may not be relied upon and will not be binding or legally effective. It is the responsibility of the Bidder to check the Peachtree City website for such Addenda.

ARTICLE 6 – SITE AND OTHER AREAS

6.01 The Site is identified in the Bidding Documents. Easements for permanent structures or permanent changes in existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.

ARTICLE 7 – INTERPRETATIONS AND ADDENDA

7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted in writing via Email Communication to the Purchasing Manager at aegan@peachtree-city.org. Interpretations or clarifications considered necessary by Peachtree City in response to such questions will be issued by Addenda posted to the website. Questions received less than five business days prior to the date for opening of Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by Peachtree City. No Addenda shall be issued later than 72 hours prior to the date and time fixed for opening the Bids. Failure of any Bidder to receive any such Addendum shall not relieve the Bidder from any obligation under his Bid submitted. All Addenda so issued shall become a part of the Contract.

ARTICLE 8 – BID SECURITY

Kedron Pool Boiler Replacement 00 21 13-6

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 5 of Bidder’s maximum Bid price and in the form of a certified check, bank money order, or a Bid bond (on the form attached) issued by a surety meeting the requirements of Paragraphs 5.01 and 5.02 of the General Conditions.

8.02 The bidder to whom the award is made shall execute a written contract to do the work and maintain the same in good repair until final acceptance by the proper authorities and shall furnish good and sufficient bonds as hereinafter specified, within ten (10) calendar days after receiving such contract for execution. If the bidder to whom the first award is made fails to enter into a contract as herein provided, the award may be annulled and the contract let to the next higher bidder who is reliable, and responsible in the opinion of the City Council. Such bidder shall fulfill every stipulation embraced herein as if he were the original party to whom award was made.

8.03 Bid security of other Bidders whom Owner believes do not have a reasonable chance of receiving the award will be returned within seven calendar days after the Bid award.

ARTICLE 9 – CONTRACT TIMES

9.01 The number of calendar days within which, or the dates by which the Work is to be substantially completed and ready for final payment are set forth in the Agreement.

ARTICLE 10 – LIQUIDATED DAMAGES

10.01 Provisions for liquidated damages, if any, are set forth in the Agreement.

ARTICLE 11 – SUBSTITUTE AND “OR EQUAL” ITEMS

11.01 The Contract, if awarded, will be on the basis of new (not used) materials and equipment specified or described in the Bidding Documents, or those substitute or “or-equal” materials and equipment approved by Peachtree City and identified by Addendum. The materials and equipment described in the Bidding Documents establish a standard of required type, function, and quality to be met by any proposed substitute or “or-equal” item. No item of material or equipment will be considered by Peachtree City as a substitute or “or-equal” unless written request for approval has been submitted by Bidder and has been received by Peachtree City at least thirteen (13) calendar days prior to the date for receipt of Bids. Each such request shall conform to the requirements of Paragraph 6.05 of the General Conditions. The burden of proof of the merit of the proposed item is upon Bidder. Peachtree City’s decision of approval or disapproval of a proposed item will be final. If Peachtree City approves any proposed item, such approval will be set forth in an Addendum issued to all prospective Bidders. Bidders shall not rely upon approvals made in any other manner.

11.02 For this project there will be no allowed substituions for the boiler. The only acceptable product for this component is the one listed in the attached plans.

ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS AND OTHERS

12.01 If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, individuals, or entities to be submitted to Owner in advance of a specified date prior to the Effective Date of the Agreement, the apparent Successful Bidder, and any other

Kedron Pool Boiler Replacement 00 21 13-7

Bidder so requested, shall within five business days after Bid opening, submit to Owner a list of all such Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work for which such identification is required. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, individual, or entity if requested by Owner. If Owner, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit a substitute, in which case apparent Successful Bidder shall submit an acceptable substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award. Owner shall be notified if at any time after award, Contractor substitutes a Subcontractor, Supplier, or other entity doing work on the project so Owner will have same opportunity to object.

12.02 Contractor shall not be required to employ any Subcontractor, Supplier, individual, or entity against whom Contractor has reasonable objection.

ARTICLE 13 – PREPARATION OF BID

13.01 The Bid Form is included with the Bidding Documents.

13.02 All blanks on the Bid Form shall be completed in ink and the Bid Form signed in ink.

Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each [section, Bid item, alternative, adjustment unit price item, and unit price item] listed therein. In the case of optional alternatives, the words “No Bid,” “No Change,” or “Not Applicable” may be entered.

13.03 A Bid by a corporation shall be executed in the corporate name by the president or a vice-president or other corporate officer accompanied by evidence of authority to sign. The corporate seal shall be affixed and attested by the Administrative Assistant. The corporate address and state of incorporation shall be shown.

13.04 A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership shall be shown.

13.05 A Bid by a limited liability company shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign. The state of formation of the firm and the official street address of the firm shall be shown.

13.06 A Bid by an individual shall show the Bidder’s name and official address.

13.07 A Bid by a joint venture shall be executed by each joint venturer in the manner indicated on the Bid Form. The official address of the joint venture shall be shown.

13.08 All names shall be printed in ink below the signatures.

13.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.

13.10 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.

Kedron Pool Boiler Replacement 00 21 13-8

13.11 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.

ARTICLE 14 – BASIS OF BID; COMPARISON OF BIDS

14.01 Lump Sum

A. Bidders shall submit a Bid on a lump sum basis for the base Bid and include a separate price for each alternate described in the Bidding Documents as provided for in the Bid Form. The price for each alternate will be the amount added to or deleted from the base Bid if Owner selects the alternate. In the comparison of Bids, alternates will be applied in the same order as listed in the Bid form.

14.02 Optional Alternatives

A. Bidders shall submit a Bid for each optional alternative item listed on Bid Form.

B. Optional alternative item prices shall cover cost above and beyond base price for extra materials and work necessary to furnish and install alternative work.

C. Decision to include or exclude optional alternative work shall be at the sole discretion of Peachtree City.

14.03 Unit Price

A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the Bid schedule.

B. The total of all estimated prices will be the sum of the products of the estimated quantity of each item and the corresponding unit price. The final quantities and Contract Price will be determined in accordance with Paragraph 11.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

D. Unit Prices for Lump Sum contracts or bids are only relevant if the quantities reflected in the schedule of values are exceeded or are less than such quantities projected in the bid due to change in the scope of work via a duly executed change order.

14.04 Allowances

A. For cash allowances the Bid price shall include such amounts as the Owner deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 11.02.B of the General Conditions.

ARTICLE 15 – SUBMITTAL OF BID

15.01 With each copy of the Bidding Documents, a Bidder is furnished one separate unbound

Kedron Pool Boiler Replacement 00 21 13-9 copy of the Bid Form, and, if required, the Bid Bond Form. Or, if Bidding Documents are all electronic, it will be the Contractor’s responsibility to print from online resource. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the following documents:

A. See Section 00 22 13 for a list of documents typically required to be submitted with the

Bid.

15.02 A Bid shall be submitted no later than the date and time prescribed and at the place indicated in the advertisement or invitation to bid and shall be enclosed in a plainly marked package with the Project title and number (and, if applicable, the designated portion of the Project for which the Bid is submitted), the name and address of Bidder, and shall be accompanied by the Bid security and other required documents. For bids sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid shall be addressed to City of Peachtree City, Attention:

Purchasing Agent, 151 Willowbend Road, Peachtree City, GA 30269.

ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID

16.01 A Bid may be modified or withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids.

16.02 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.

ARTICLE 17 – OPENING OF BIDS

17.01 Bids will be opened at the time and place indicated in the Advertisement or Invitation to

Bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders within five business days after the opening of Bids.

ARTICLE 18 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE

18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT

19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner further reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to not be responsible or having outstanding debt to the City or other government entity. Owner may also reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder. Owner

Kedron Pool Boiler Replacement 00 21 13-10 also reserves the right to waive any and all irregularities and to negotiate contract terms with the Successful Bidder.

19.02 More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.

19.03 In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.

19.04 In evaluating Bidders, Owner will consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities must be submitted as provided in the Supplementary Conditions.

19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, proposed Sub-Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work in accordance with the Contract Documents.

ARTICLE 20 – CONTRACT SECURITY AND INSURANCE

20.01 Article 5 of the General Conditions, as may be modified by the Supplementary

Conditions, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it shall be accompanied by such bonds.

20.02 Agreement will require a Payment Bond in the amount of 110%, and a Performance Bond in the amount of 100% of the project cost. The City of Peachtree City reserves the right to bid a project in phases and award the contract on the phases it deems to be in the City’s best interest.

ARTICLE 21 – SIGNING OF AGREEMENT

21.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement along with the other Contract Documents which are identified in the Agreement as attached thereto. Within 15 business days thereafter, Successful Bidder shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner. Within ten business days thereafter, Owner shall deliver one fully signed counterpart to Successful Bidder with a complete set of the Drawings with appropriate identification.

Kedron Pool Boiler Replacement 00 22 13-1

25-111BES SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

SECTION 00 22 13

SUPPLEMENTARY INSTRUCTIONS TO BIDDERS

The City will make available a copy of the Project Manual on the website (www.peachtree-city.org). It is the responsibility of the Bidder to complete and submit one (1) separate unbound copy of the Bidding Documents, which includes the following documents:

1. Bid Form – Section 00 41 00

2. Bid Security – Section 00 43 13

3. Bidder’s Qualifications – Section 00 45 13

4. Non-Collusion Affidavit – Section 00 45 19

5. Security and Immigration Compliance – Section 00 45 20

6. Drug-Free Workplace Certification – Section 00 73 19

Place all of the above in a sealed envelope clearly marked as follows:

BID FOR

Kedron Pool Boiler Replacement

25-111BES

NOTE: The envelope should bear on the outside the NAME and ADDRESS of the

QUALIFIED BIDDER.

If mailed, this envelope should be placed inside the mailing envelope.

Bids will be opened at February 27, 2025/3:00 pm local time at 151 Willowbend Road, Peachtree City, GA 30269.

Kedron Pool Boiler Replacement 00 31 00-1

25-111BES AVAILABLE PROJECT INFORMATION

SECTION 00 31 00

AVAILABLE PROJECT INFORMATION

1.01 SUMMARY

A. Document Includes:

1. No reports generated for this project.

B. Available Project information has been furnished by Owner for use in designing this Project.

1. Each Bidder shall be fully familiar with available Project information, which has been prepared for Owner by separate consultants.

2. Available Project information is offered solely for reference and shall not be considered part of Contract Documents. Data contained in Documents prepared by Owner's separate consultants is believed to be reliable;

however, Owner and Architect/Engineer do not guarantee their accuracy or completeness.

3. In preparing their Bids, Bidders shall consider and evaluate data contained in available Project information as well as Contract Documents prepared by Architect/Engineer.

1.02 SUBSURFACE AND PHYSICAL CONDITIONS REPORT

A. None.

1.03 UNDERGROUND FACILITIES REPORT

A. None.

1.04 HAZARDOUS ENVIRONMENTAL CONDITION REPORT

A. None.

Kedron Pool Boiler Replacement 00 41 00-1

25-111BES BID FORM

SECTION 00 41 00

BID FORM

TABLE OF CONTENTS

Page

Article 1 – Bid Recipient

Article 2 – Bidder’s Acknowledgements

Article 3 – Bidder’s Representations

Article 4 – Bidder’s Certification

Article 5 – Basis of Bid

Article 6 – Time of Completion

Article 7 – Attachments to This Bid

Article 8 – Defined Terms

Article 9 – Bid Submittal

Kedron Pool Boiler Replacement 00 41 00-2

ARTICLE 1 – BID RECIPIENT

1.01 This Bid is submitted to: City of Peachtree City

151 Willowbend Road Peachtree City, GA 30269

This Bid is submitted from:

(Name and Address of Individual, Partnership, or Corporation)

P.O. Box Not Acceptable

Georgia Contractor No. (if applicable)

This Bid is for: Kedron Pool Boiler Replacement

February 27, 2025/3:00 pm local time

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an

Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2 – BIDDER’S ACKNOWLEDGEMENTS

2.01 Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 60 calendar days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

ARTICLE 3 – BIDDER’S REPRESENTATIONS

3.01 In submitting this Bid, Bidder represents that:

A. Bidder has examined and carefully studied the Bidding Documents, other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged:

Kedron Pool Boiler Replacement 00 41 00-3

B.

Addendum No. Addendum Date

C. Bidder has visited the Site and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

D. Bidder is familiar with and is satisfied as to all Laws and Regulations that may affect cost, progress, and performance of the Work.

E. Bidder has carefully studied all (if applicable): (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities) that have been identified in SC-4.02 as containing reliable "technical data," and (2) reports and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in SC-4.06 as containing reliable "technical data."

F. Bidder has considered the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports (if applicable) and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs.

G. Based on the information and observations referred to in Paragraph 3.01.E above, Bidder does not consider that further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents.

H. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

I. Bidder has given Purchasing Agent written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Purchasing Agent is acceptable to Bidder.

Kedron Pool Boiler Replacement 00 41 00-4

1. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.

ARTICLE 4 – BIDDER’S CERTIFICATION

4.01 Bidder certifies that:

A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;

B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;

C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and

D. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 4.01.D:

1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process;

2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;

3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and

4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

ARTICLE 5 – BASIS OF BID

5.01 Bidder will complete the Work in accordance with the Contract Documents for the following price(s):

A. LUMP SUM BASE BID:

Lump Sum Base Bid Price $

All specified cash allowances are included in the price(s) set forth above, and have been computed in accordance with Paragraph 11.02 of the General Conditions.

Kedron Pool Boiler Replacement 00 41 00-5

CHANGE ORDER UNIT PRICES

Item No. Description Unit Bid Unit Price 1 4” HWS Piping LF $ 2 3” HWS Piping LF $ 3 1-1/4” Gas Piping LF $ 4 2” Gas Piping LF $

The bid items outlined above have been provided for bid comparison. The bid unit prices will also be utilized for establishing contract price modifications in the event of a duly authorized change order to results in the modification of the contract amount due to the contractor. Examples of such modification shall include but not be limited to increases in the scope of work resulting in additional work or modifications of the scope of work wherein the amount of work is reduced.

B. LUMP SUM BID WITH DEDUCT/ALTERNATE:

Contractor to provide price below for alternate work as a change to the Base Bid Price for the alternate boiler equipment purchase and installation including any variations to the work necessary to accommodate this alternate equipment.

Lump Sum Base Bid Price $ Deduction for Alternate Boiler - $ TOTAL LUMP SUM PRICE w/ ALTERNATE BOILER $

ARTICLE 6 – TIME OF COMPLETION

6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 14.07 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

6.02 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 7 – ATTACHMENTS TO THIS BID

7.01 The following documents are submitted with and made a condition of this Bid:

A. All documents as outlined in Section 00 22 13 “Supplementary Instructions to Bidders.”

Kedron Pool Boiler Replacement 00 41 00-6

ARTICLE 8 – DEFINED TERMS

8.01 The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 9 – BID SUBMITTAL

9.01 This Bid is submitted by:

If Bidder is:

An Individual

Name (typed or printed):

By:

(Individual’s signature)

Doing business as:

A Partnership

Partnership Name:

By:

(Signature of general partner -- attach evidence of authority to sign)

Name (typed or printed):

A Corporation

Corporation Name: (SEAL)

State of Incorporation:

Type (General Business, Professional, Service, Limited Liability):_______

By:

(Signature -- attach evidence of authority to sign)

Name (typed or printed):

Title:

(CORPORATE SEAL)

Attest

Date of Qualification to do business in Georgia is ____/____/____.

Kedron Pool Boiler Replacement 00 41 00-7

A Joint Venture

Name of Joint Venture:

First Joint Venturer Name: (SEAL)

By:

(Signature of first joint venture partner -- attach evidence of authority to sign)

Name (typed or printed):

Title:

Second Joint Venturer Name: (SEAL)

By:

(Signature of second joint venture partner -- attach evidence of authority to sign)

Name (typed or printed):

Title:

(Each joint venturer must sign. The manner of signing for each individual, partnership, and corporation that is a party to the joint venture should be in the manner indicated above.)

Bidder's Business Address

Phone No. _____________________________________ Fax No.

E-mail _____________________________________

SUBMITTED on , 20____.

State Contractor License No. . [If applicable]

Kedron Pool Boiler Replacement 00 43 13-1

25-111BES BID SECURITY FORM

SECTION 00 43 13

BID SECURITY FORM

BIDDER (Name and Address):

SURETY (Name and Address of Principal Place of Business):

OWNER (Name and Address):

Peachtree City, GA 30269

BID

Bid Due Date: February 27, 2025/3:00 pm local time

Description:

Project includes furnishing equipment and labor to replace the boiler used to heat the water for both pools at the Kedron Aquatic Center, replace the pumps and related piping to circulate heating fluid through heat exchangers, and test and balance entire system once installed.

BOND

Bond Number:

Date (Not earlier than Bid due date):

Penal sum $ (Words) (Figures)

Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth below, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

BIDDER SURETY

(Seal) (Seal) Bidder’s Name and Corporate Seal Surety’s Name and Corporate Seal

By: By:

Signature Signature (Attach Power of Attorney)

Print Name Print Name

Title Title

Attest: Attest:

Signature Signature

Kedron Pool Boiler Replacement 00 43 13-2

Note: Surety companies executing bonds must appear on the Treasury Department’s most current list (Circular 570 as amended) and be authorized to transact business in the state where the project is located.

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond. Payment of the penal sum is the extent of Bidder’s and Surety’s liability. Recovery of such penal sum under the terms of this Bond shall be Owner’s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder shall occur upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation shall be null and void if:

3.1 Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding

Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or

3.2 All Bids are rejected by Owner, or

3.3 Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding

Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).

4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.

5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions shall not in the aggregate exceed 120 days from Bid due date without Surety’s written consent.

6. No suit or action shall be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety and in no case later than one year after Bid due date.

7. Any suit or action under this Bond shall be commenced only in a court of competent jurisdiction located in the state in which the Project is located.

8. Notices required hereunder shall be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United States Registered or Certified Mail, return receipt requested, postage pre-paid, and shall be deemed to be effective upon receipt by the party concerned.

9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby.

10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond shall be deemed to be included herein as if set forth at length. If any provision of this Bond conflicts with any applicable statute, then the provision of said statute shall govern and the remainder of this Bond that is not in

Kedron Pool Boiler Replacement 00 43 13-3 conflict therewith shall continue in full force and effect.

11. The term “Bid” as used herein includes a Bid, offer, or proposal…