K21636 JCB-79-82_ Bid Tabs 06-10-2025.xlsx
XLSX spreadsheet 125 KB Posted
- Attached to
- Logo wear apparel and promotional items
- Solicitation number
- S-R09145-00013853
- Issued by
- Deschutes County, Oregon
About this file
This is a Bid Tabs document for a state and local infrastructure construction project on SE Johnson Creek Boulevard between 79th Place and 82nd Avenue, with bid opening held on June 10, 2025. The project encompasses comprehensive street reconstruction and utility work including traffic signal installation, storm and sanitary sewer infrastructure, pavement removal and replacement, concrete work, erosion control, and landscaping improvements. The scope includes 93 line items ranging from mobilization and traffic management to final seeding and site restoration. Six contractors submitted bids: Westech Construction ($1,714,494.04), Corpac Construction Co. ($1,833,291.00), Moore Excavation ($1,847,677.50), Dirt & Aggregate Interchange ($1,959,099.95), and Kodiak Pacific Construction ($2,128,912.44), with the engineers' estimate at $1,645,052.75. The lowest responsive bid was Westech Construction at 4.22% above the engineers' estimate.
Notable bid discrepancies include quantity changes and missing items identified during the bidding process. Westech Construction emerged as the apparent low bidder, approximately $69,442 above the engineers' estimate, with significant variations noted on individual line items such as item 22 (asbestos material removal), where bids ranged from $3,290 to $41,250, and item 78 (traffic signal installation), the project's largest single cost component ranging from $432,200 to $502,302. The bid analysis reveals substantial price variations across all contractors, with some items showing bids exceeding the estimate by over 200 percent while others came in significantly below. No specific contract term, renewal options, or funding source information is provided in this bid tabulation document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP Addendum 1- Q and A.pdf | ||
| RFP- BPRD Logo wear.pdf | ||
| Attachment E - SAMPLE General Services Contract.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID TABS
| SE JOHNSON CREEK BLVD: 79TH PL-82ND AVE | ||||||||||||||||||
| Bid Opening June 10, 2025 | ||||||||||||||||||
| Engineers Estimate | Westech Construction | Corpac Construction Co | Moore Excavation | Dirt & Agg interchange | Kodiak Pacific Construction | |||||||||||||
| Item # | Spec | Item Description | Unit | Quantity | Unit | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | LOW | HIGH |
| 1 | 0210-0100000A | MOBILIZATION | LS | 1 | 135,000.00 | 135,000.00 | 171,000.00 | 171,000.00 | 183,330.00 | 183,330.00 | 175,000.00 | 175,000.00 | 174,655.00 | 174,655.00 | 241,000.00 | 241,000.00 | 171,000.00 | 241,000.00 |
| 2 | 0221-0100000A | TEMPORARY PROTECTION AND DIRECTION OF TRAFFIC | LS | 1 | 41,000.00 | 41,000.00 | 22,000.00 | 22,000.00 | 75,000.00 | 75,000.00 | 75,000.00 | 75,000.00 | 78,200.00 | 78,200.00 | 72,800.00 | 72,800.00 | 22,000.00 | 78,200.00 |
| 3 | 0222-0102000J | TEMPORARY SIGNS | SQFT | 200 | 24.00 | 4,800.00 | 33.30 | 6,660.00 | 25.00 | 5,000.00 | 33.00 | 6,600.00 | 29.50 | 5,900.00 | 31.00 | 6,200.00 | 5,000.00 | 6,660.00 |
| 4 | 0222-0162000E | SEQUENTIAL ARROW SIGNS | EACH | 1 | 5,000.00 | 5,000.00 | 1,345.00 | 1,345.00 | 750.00 | 750.00 | 2,000.00 | 2,000.00 | 1,600.00 | 1,600.00 | 1,025.00 | 1,025.00 | 750.00 | 2,000.00 |
| 5 | 0223-0168000T | FLAGGERS | HOUR | 800 | 50.00 | 40,000.00 | 80.00 | 64,000.00 | 78.00 | 62,400.00 | 82.00 | 65,600.00 | 90.56 | 72,448.00 | 67.00 | 53,600.00 | 53,600.00 | 72,448.00 |
| 6 | 0224-0104000E | TEMPORARY BARRICADES, TYPE II | EACH | 4 | 80.00 | 320.00 | 36.00 | 144.00 | 50.00 | 200.00 | 65.00 | 260.00 | 30.00 | 120.00 | 62.00 | 248.00 | 120.00 | 260.00 |
| 7 | 0224-0105000E | TEMPORARY BARRICADES, TYPE III | EACH | 2 | 150.00 | 300.00 | 99.00 | 198.00 | 100.00 | 200.00 | 225.00 | 450.00 | 120.00 | 240.00 | 180.00 | 360.00 | 198.00 | 450.00 |
| 8 | 0224-0145000E | TEMPORARY PLASTIC DRUMS | EACH | 26 | 50.00 | 1,300.00 | 22.00 | 572.00 | 50.00 | 1,300.00 | 70.00 | 1,820.00 | 24.00 | 624.00 | 88.00 | 2,288.00 | 572.00 | 2,288.00 |
| 9 | 0225-0153000F | TEMPORARY STRIPING | FOOT | 2700 | 1.00 | 2,700.00 | 1.60 | 4,320.00 | 0.20 | 540.00 | 2.75 | 7,425.00 | 1.81 | 4,887.00 | 1.54 | 4,158.00 | 540.00 | 7,425.00 |
| 10 | 0225-0154000F | STRIPE REMOVAL | FOOT | 3250 | 0.50 | 1,625.00 | 1.60 | 5,200.00 | 3.75 | 12,187.50 | 1.50 | 4,875.00 | 1.81 | 5,882.50 | 1.54 | 5,005.00 | 4,875.00 | 12,187.50 |
| 11 | 0228-0141600F | PEDESTRIAN CHANNELIZING DEVICES | FOOT | 300 | 10.00 | 3,000.00 | 5.50 | 1,650.00 | 25.00 | 7,500.00 | 30.00 | 9,000.00 | 24.15 | 7,245.00 | 45.00 | 13,500.00 | 1,650.00 | 13,500.00 |
| 12 | 0280-0100000A | EROSION CONTROL | LS | 1 | 3,000.00 | 3,000.00 | 10,000.00 | 10,000.00 | 15,500.00 | 15,500.00 | 5,000.00 | 5,000.00 | 5,390.00 | 5,390.00 | 7,835.65 | 7,835.65 | 5,000.00 | 15,500.00 |
| 13 | 0280-0113000F | SEDIMENT FENCE | FOOT | 485 | 4.00 | 1,940.00 | 8.00 | 3,880.00 | 3.50 | 1,697.50 | 4.00 | 1,940.00 | 3.60 | 1,746.00 | 4.71 | 2,284.35 | 1,697.50 | 3,880.00 |
| 14 | 0280-0114040E | INLET PROTECTION, TYPE 4 | EACH | 14 | 125.00 | 1,750.00 | 46.00 | 644.00 | 75.00 | 1,050.00 | 125.00 | 1,750.00 | 81.00 | 1,134.00 | 155.00 | 2,170.00 | 644.00 | 2,170.00 |
| 15 | 0280-0110010E | CONSTRUCTION ENTRANCE, TYPE 1 | EACH | 1 | 750.00 | 750.00 | 2,700.00 | 2,700.00 | 1,875.00 | 1,875.00 | 5,000.00 | 5,000.00 | 4,600.00 | 4,600.00 | 6,500.00 | 6,500.00 | 1,875.00 | 6,500.00 |
| 16 | 0280-0111010E | TIRE WASH FACILITY, TYPE 1 | EACH | 1 | 750.00 | 750.00 | 6,500.00 | 6,500.00 | 3,500.00 | 3,500.00 | 2,500.00 | 2,500.00 | 3,900.00 | 3,900.00 | 24,550.00 | 24,550.00 | 2,500.00 | 24,550.00 |
| 17 | 0290-0100000A | POLLUTION CONTROL PLAN | LS | 1 | 1,000.00 | 1,000.00 | 1,100.00 | 1,100.00 | 1,500.00 | 1,500.00 | 1,000.00 | 1,000.00 | 600.00 | 600.00 | 400.00 | 400.00 | 400.00 | 1,500.00 |
| 18 | 0294-0100000A | HEALTH AND SAFETY PLAN | LS | 1 | 2,500.00 | 2,500.00 | 2,200.00 | 2,200.00 | 1,500.00 | 1,500.00 | 2,000.00 | 2,000.00 | 600.00 | 600.00 | 400.00 | 400.00 | 400.00 | 2,200.00 |
| 19 | 0294-0200010M | CONTAMINATED SOIL DISPOSAL | TON | 138 | 100.00 | 13,800.00 | 112.00 | 15,456.00 | 100.00 | 13,800.00 | 125.00 | 17,250.00 | 104.00 | 14,352.00 | 123.00 | 16,974.00 | 13,800.00 | 17,250.00 |
| 20 | 0294-0500000A | LEAD COMPLIANCE PLAN | LS | 1 | 2,500.00 | 2,500.00 | 5,500.00 | 5,500.00 | 1,500.00 | 1,500.00 | 2,000.00 | 2,000.00 | 1,800.00 | 1,800.00 | 400.00 | 400.00 | 400.00 | 5,500.00 |
| 21 | 0295-0100000F | REMOVE ASBESTOS MATERIAL, FRIABLE | FOOT | 5 | 300.00 | 1,500.00 | 61.00 | 305.00 | 85.00 | 425.00 | 55.00 | 275.00 | 1,875.00 | 9,375.00 | 1,025.00 | 5,125.00 | 275.00 | 9,375.00 |
| 22 | 0295-0200000F | REMOVE ASBESTOS MATERIAL, NON-FRIABLE | SQFT | 2750 | 5.00 | 13,750.00 | 3.50 | 9,625.00 | 15.00 | 41,250.00 | 7.00 | 19,250.00 | 7.85 | 21,587.50 | 9.00 | 24,750.00 | 9,625.00 | 41,250.00 |
| 23 | 0305-0100000A | CONSTRUCTION SURVEY WORK | LS | 1 | 40,000.00 | 40,000.00 | 20,000.00 | 20,000.00 | 19,000.00 | 19,000.00 | 25,000.00 | 25,000.00 | 18,100.00 | 18,100.00 | 19,000.00 | 19,000.00 | 18,100.00 | 25,000.00 |
| 24 | 0310-0100000F | REMOVAL OF PIPES | FOOT | 248 | 30.00 | 7,440.00 | 10.25 | 2,542.00 | 35.00 | 8,680.00 | 30.00 | 7,440.00 | 23.50 | 5,828.00 | 150.00 | 37,200.00 | 2,542.00 | 37,200.00 |
| 25 | 0310-0104000E | REMOVAL OF INLETS | EACH | 3 | 500.00 | 1,500.00 | 1,555.00 | 4,665.00 | 650.00 | 1,950.00 | 700.00 | 2,100.00 | 500.00 | 1,500.00 | 2,400.00 | 7,200.00 | 1,500.00 | 7,200.00 |
| 26 | 0310-0106000A | REMOVAL OF STRUCTURES AND OBSTRUCTIONS | LS | 1 | 27,000.00 | 27,000.00 | 9,000.00 | 9,000.00 | 34,500.00 | 34,500.00 | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 80,000.00 | 80,000.00 | 9,000.00 | 80,000.00 |
| 27 | 0310-0109000A | REMOVAL OF BUILDINGS | LS | 1 | 40,000.00 | 40,000.00 | 24,000.00 | 24,000.00 | 54,500.00 | 54,500.00 | 15,000.00 | 15,000.00 | 49,000.00 | 49,000.00 | 23,000.00 | 23,000.00 | 15,000.00 | 54,500.00 |
| 28 | 0310-0119000F | ASPHALT PAVEMENT SAW CUTTING | FOOT | 1030 | 5.00 | 5,150.00 | 3.25 | 3,347.50 | 5.75 | 5,922.50 | 6.00 | 6,180.00 | 2.70 | 2,781.00 | 2.00 | 2,060.00 | 2,060.00 | 6,180.00 |
| 29 | 0320-0100000A | CLEARING AND GRUBBING | LS | 1 | 12,000.00 | 12,000.00 | 4,000.00 | 4,000.00 | 7,500.00 | 7,500.00 | 11,500.00 | 11,500.00 | 15,350.00 | 15,350.00 | 20,000.00 | 20,000.00 | 4,000.00 | 20,000.00 |
| 30 | 0330-0105000K | GENERAL EXCAVATION | CUYD | 793 | 60.00 | 47,580.00 | 70.00 | 55,510.00 | 45.00 | 35,685.00 | 80.00 | 63,440.00 | 105.00 | 83,265.00 | 112.00 | 88,816.00 | 35,685.00 | 88,816.00 |
| 31 | 0331-0109000J | 18 INCH SUBGRADE STABILIZATION | SQYD | 114 | 65.00 | 7,410.00 | 19.00 | 2,166.00 | 35.00 | 3,990.00 | 65.00 | 7,410.00 | 10.00 | 1,140.00 | 235.00 | 26,790.00 | 1,140.00 | 26,790.00 |
| 32 | 0350-0105000J | SUBGRADE GEOTEXTILE | SQYD | 946 | 2.00 | 1,892.00 | 1.69 | 1,598.74 | 2.25 | 2,128.50 | 1.50 | 1,419.00 | 3.00 | 2,838.00 | 4.30 | 4,067.80 | 1,419.00 | 4,067.80 |
| 33 | 0390-0119000K | GROUTED RIPRAP | CUYD | 190 | 20.00 | 3,800.00 | 65.00 | 12,350.00 | 95.00 | 18,050.00 | 50.00 | 9,500.00 | 72.50 | 13,775.00 | 112.00 | 21,280.00 | 9,500.00 | 21,280.00 |
| 34 | 0415-0100000F | MAINLINE VIDEO INSPECTION | FOOT | 331 | 5.00 | 1,655.00 | 9.00 | 2,979.00 | 22.00 | 7,282.00 | 13.00 | 4,303.00 | 6.00 | 1,986.00 | 10.50 | 3,475.50 | 1,986.00 | 7,282.00 |
| 35 | 0415-0400000E | SERVICE LINE LATERAL VIDEO INSPECTION | EACH | 1 | 750.00 | 750.00 | 275.00 | 275.00 | 1,500.00 | 1,500.00 | 300.00 | 300.00 | 600.00 | 600.00 | 820.00 | 820.00 | 275.00 | 1,500.00 |
| 36 | 0445-030006BF | 6 INCH SANITARY SEWER PIPE, 10 FT DEPTH | FOOT | 52 | 150.00 | 7,800.00 | 340.00 | 17,680.00 | 250.00 | 13,000.00 | 300.00 | 15,600.00 | 325.00 | 16,900.00 | 258.00 | 13,416.00 | 13,000.00 | 17,680.00 |
| 37 | 0445-035012AF | 12 INCH STORM SEWER PIPE, 5 FT DEPTH | FOOT | 331 | 130.00 | 43,030.00 | 175.00 | 57,925.00 | 145.00 | 47,995.00 | 280.00 | 92,680.00 | 222.00 | 73,482.00 | 150.00 | 49,650.00 | 47,995.00 | 92,680.00 |
| 38 | 0445 | 6 INCH STORM SEWER CLEANOUT | EACH | 1 | 500.00 | 500.00 | 1,275.00 | 1,275.00 | 1,800.00 | 1,800.00 | 1,000.00 | 1,000.00 | 1,850.00 | 1,850.00 | 8,600.00 | 8,600.00 | 1,000.00 | 8,600.00 |
| 39 | 0470-0101000E | CONCRETE STORM SEWER MANHOLES | EACH | 1 | 7,000.00 | 7,000.00 | 6,800.00 | 6,800.00 | 9,750.00 | 9,750.00 | 8,500.00 | 8,500.00 | 9,865.00 | 9,865.00 | 15,800.00 | 15,800.00 | 6,800.00 | 15,800.00 |
| 40 | 0470-0315000E | CONCRETE INLETS, TYPE GB-2 | EACH | 5 | 2,900.00 | 14,500.00 | 2,250.00 | 11,250.00 | 4,000.00 | 20,000.00 | 4,200.00 | 21,000.00 | 3,600.00 | 18,000.00 | 6,990.00 | 34,950.00 | 11,250.00 | 34,950.00 |
| 41 | 0490-0100000E | ADJUSTING BOXES | EACH | 2 | 500.00 | 1,000.00 | 320.00 | 640.00 | 850.00 | 1,700.00 | 200.00 | 400.00 | 600.00 | 1,200.00 | 2,700.00 | 5,400.00 | 400.00 | 5,400.00 |
| 42 | 0490-0102000E | ADJUSTING CATCH BASINS | EACH | 1 | 1,000.00 | 1,000.00 | 1,200.00 | 1,200.00 | 800.00 | 800.00 | 2,000.00 | 2,000.00 | 1,000.00 | 1,000.00 | 2,000.00 | 2,000.00 | 800.00 | 2,000.00 |
| 43 | 0490-0104000E | CONNECTION TO EXISTING STRUCTURES | EACH | 2 | 2,000.00 | 4,000.00 | 2,300.00 | 4,600.00 | 4,500.00 | 9,000.00 | 5,000.00 | 10,000.00 | 2,800.00 | 5,600.00 | 4,000.00 | 8,000.00 | 4,600.00 | 10,000.00 |
| 44 | 0490-0120000E | MINOR ADJUSTMENT OF MANHOLES | EACH | 4 | 1,500.00 | 6,000.00 | 2,400.00 | 9,600.00 | 2,000.00 | 8,000.00 | 1,400.00 | 5,600.00 | 2,500.00 | 10,000.00 | 2,600.00 | 10,400.00 | 5,600.00 | 10,400.00 |
| 45 | 0620-0123000J | COLD PLANE PAVEMENT REMOVAL, 4 INCHES DEEP | SQYD | 3363 | 7.00 | 23,541.00 | 6.50 | 21,859.50 | 8.00 | 26,904.00 | 13.00 | 43,719.00 | 7.25 | 24,381.75 | 10.00 | 33,630.00 | 21,859.50 | 43,719.00 |
| 46 | 0640-0100000M | AGGREGATE BASE | TON | 740 | 45.00 | 33,300.00 | 75.00 | 55,500.00 | 45.00 | 33,300.00 | 65.00 | 48,100.00 | 67.50 | 49,950.00 | 106.00 | 78,440.00 | 33,300.00 | 78,440.00 |
| 47 | 0295-0200000F | REMOVE ASBESTOS MATERIAL, FRIABLE | SQFT | 470 | 25.00 | 11,750.00 | 19.00 | 8,930.00 | 15.00 | 7,050.00 | 7.00 | 3,290.00 | 7.85 | 3,689.50 | 1.00 | 470.00 | 470.00 | 8,930.00 |
| 48 | 0744-0302000M | LEVEL 3, 1/2 INCH ACP MIXTURE | TON | 1052 | 125.00 | 131,500.00 | 130.00 | 136,760.00 | 135.00 | 142,020.00 | 130.00 | 136,760.00 | 140.00 | 147,280.00 | 127.00 | 133,604.00 | 133,604.00 | 147,280.00 |
| 49 | 0748-0103000J | 6 INCH ASPHALT CONCRETE PAVEMENT REPAIR | SQYD | 500 | 50.00 | 25,000.00 | 118.00 | 59,000.00 | 72.00 | 36,000.00 | 100.00 | 50,000.00 | 72.50 | 36,250.00 | 30.00 | 15,000.00 | 15,000.00 | 59,000.00 |
| 50 | 0749-0100000E | EXTRA FOR ASPHALT APPROACHES | EACH | 5 | 2,000.00 | 10,000.00 | 685.00 | 3,425.00 | 2,200.00 | 11,000.00 | 1,000.00 | 5,000.00 | 1,350.00 | 6,750.00 | 1,540.00 | 7,700.00 | 3,425.00 | 11,000.00 |
| 51 | 0759-0103000F | CONCRETE CURBS, CURB AND GUTTER | FOOT | 634 | 40.00 | 25,360.00 | 42.95 | 27,230.30 | 55.00 | 34,870.00 | 40.00 | 25,360.00 | 45.25 | 28,688.50 | 53.00 | 33,602.00 | 25,360.00 | 34,870.00 |
| 52 | 0759-0106000F | CONCRETE CURBS, LOW PROFILE MOUNTABLE CURB | FOOT | 18 | 50.00 | 900.00 | 69.00 | 1,242.00 | 95.00 | 1,710.00 | 70.00 | 1,260.00 | 110.00 | 1,980.00 | 352.00 | 6,336.00 | 1,242.00 | 6,336.00 |
| 53 | 0759-0110000F | CONCRETE CURBS, STANDARD CURB | FOOT | 304 | 45.00 | 13,680.00 | 45.00 | 13,680.00 | 35.00 | 10,640.00 | 40.00 | 12,160.00 | 46.00 | 13,984.00 | 59.00 | 17,936.00 | 10,640.00 | 17,936.00 |
| 54 | 0759-0122000J | CONCRETE ISLANDS | SQFT | 370 | 25.00 | 9,250.00 | 18.00 | 6,660.00 | 25.00 | 9,250.00 | 20.00 | 7,400.00 | 20.00 | 7,400.00 | 63.00 | 23,310.00 | 6,660.00 | 23,310.00 |
| 55 | 0759-0126000J | CONCRETE DRIVEWAYS | SQFT | 215 | 20.00 | 4,300.00 | 33.00 | 7,095.00 | 25.00 | 5,375.00 | 26.00 | 5,590.00 | 58.25 | 12,523.75 | 43.00 | 9,245.00 | 5,375.00 | 12,523.75 |
| 56 | 0759-0127000J | CONCRETE DRIVEWAYS, REINFORCED | SQFT | 730 | 30.00 | 21,900.00 | 35.00 | 25,550.00 | 30.00 | 21,900.00 | 26.00 | 18,980.00 | 41.50 | 30,295.00 | 44.00 | 32,120.00 | 18,980.00 | 32,120.00 |
| 57 | 0759-0128000J | CONCRETE WALKS | SQFT | 3280 | 11.00 | 36,080.00 | 14.00 | 45,920.00 | 15.00 | 49,200.00 | 14.00 | 45,920.00 | 23.00 | 75,440.00 | 16.00 | 52,480.00 | 45,920.00 | 75,440.00 |
| 58 | 0759-0154100E | EXTRA FOR NEW CURB RAMPS | EACH | 12 | 2,000.00 | 24,000.00 | 2,200.00 | 26,400.00 | 1,750.00 | 21,000.00 | 1,900.00 | 22,800.00 | 2,600.00 | 31,200.00 | 1,400.00 | 16,800.00 | 16,800.00 | 31,200.00 |
| 59 | 0759-0510000J | TRUNCATED DOMES ON NEW SURFACES | SQFT | 155 | 50.00 | 7,750.00 | 50.00 | 7,750.00 | 35.00 | 5,425.00 | 45.00 | 6,975.00 | 55.00 | 8,525.00 | 33.00 | 5,115.00 | 5,115.00 | 8,525.00 |
| 60 | 0855-0102100E | BI-DIRECTIONAL YELLOW TYPE I MARKERS | EACH | 89 | 15.00 | 1,335.00 | 9.50 | 845.50 | 9.00 | 801.00 | 8.50 | 756.50 | 10.25 | 912.25 | 8.71 | 775.19 | 756.50 | 912.25 |
| 61 | 0855-0102100E | BI-DIRECTIONAL WHITE TYPE I MARKERS | EACH | 33 | 15.00 | 495.00 | 9.50 | 313.50 | 9.00 | 297.00 | 8.50 | 280.50 | 10.25 | 338.25 | 8.71 | 287.43 | 280.50 | 338.25 |
| 62 | 0865-0160000F | THERMOPLASTIC, EXTRUDED OR SPRAYED, SURFACE, NON-PROFILED | FOOT | 6662 | 1.50 | 9,993.00 | 2.15 | 14,323.30 | 2.00 | 13,324.00 | 2.25 | 14,989.50 | 2.35 | 15,655.70 | 2.00 | 13,324.00 | 13,324.00 | 15,655.70 |
| 63 | 0867-0103500E | PAVEMENT LEGEND, TYPE AB: ARROWS | EACH | 6 | 375.00 | 2,250.00 | 415.00 | 2,490.00 | 400.00 | 2,400.00 | 400.00 | 2,400.00 | 450.00 | 2,700.00 | 384.37 | 2,306.22 | 2,306.22 | 2,700.00 |
| 64 | 0867-0131000E | PAVEMENT LEGEND, TYPE B-HS: BICYCLE LANE STENCIL | EACH | 6 | 350.00 | 2,100.00 | 415.00 | 2,490.00 | 400.00 | 2,400.00 | 400.00 | 2,400.00 | 450.00 | 2,700.00 | 384.37 | 2,306.22 | 2,306.22 | 2,700.00 |
| 65 | 0867-0145100J | PAVEMENT BAR, TYPE B-HS | SQFT | 604 | 15.00 | 9,060.00 | 21.00 | 12,684.00 | 19.00 | 11,476.00 | 20.00 | 12,080.00 | 23.00 | 13,892.00 | 19.27 | 11,639.08 | 11,476.00 | 13,892.00 |
| 66 | 0867-0174000E | PAVEMENT LEGEND, TYPE B-HS : BICYCLE DETECTOR STENCIL | EACH | 1 | 500.00 | 500.00 | 333.00 | 333.00 | 325.00 | 325.00 | 325.00 | 325.00 | 360.00 | 360.00 | 307.50 | 307.50 | 307.50 | 360.00 |
| 67 | 0868-0100000J | GREEN BICYCLE LANE, PREFORMED THERMOPLASTIC FILM | SQFT | 75 | 15.00 | 1,125.00 | 20.00 | 1,500.00 | 18.00 | 1,350.00 | 19.00 | 1,425.00 | 21.00 | 1,575.00 | 17.94 | 1,345.50 | 1,345.50 | 1,575.00 |
| 68 | 0902-0101000E | CROSSWALK CLOSURE SUPPORTS | EACH | 4 | 1,300.00 | 5,200.00 | 1,350.00 | 5,400.00 | 1,000.00 | 4,000.00 | 1,400.00 | 5,600.00 | 1,100.00 | 4,400.00 | 940.00 | 3,760.00 | 3,760.00 | 5,600.00 |
| 69 | 0905-0100000A | REMOVE EXISTING SIGNS | LS | 1 | 1,200.00 | 1,200.00 | 555.00 | 555.00 | 300.00 | 300.00 | 500.00 | 500.00 | 350.00 | 350.00 | 300.00 | 300.00 | 300.00 | 555.00 |
| 70 | 0920-0100000A | SIGN SUPPORT FOOTINGS | LS | 1 | 2,000.00 | 2,000.00 | 4,100.00 | 4,100.00 | 2,500.00 | 2,500.00 | 6,000.00 | 6,000.00 | 2,350.00 | 2,350.00 | 1,950.00 | 1,950.00 | 1,950.00 | 6,000.00 |
| 71 | 0930-0114000A | PERFORATED STEEL SQUARE TUBE SLIP BASE SIGN SUPPORTS | LS | 1 | 3,100.00 | 3,100.00 | 3,400.00 | 3,400.00 | 3,000.00 | 3,000.00 | 5,000.00 | 5,000.00 | 3,450.00 | 3,450.00 | 2,900.00 | 2,900.00 | 2,900.00 | 5,000.00 |
| 72 | 0930-0117000A | PERFORATED STEEL SQUARE TUBE ANCHOR SIGN SUPPORTS | LS | 1 | 1,000.00 | 1,000.00 | 525.00 | 525.00 | 1,250.00 | 1,250.00 | 1,900.00 | 1,900.00 | 1,250.00 | 1,250.00 | 1,050.00 | 1,050.00 | 525.00 | 1,900.00 |
| 73 | 0940-0201000J | SIGNS, STANDARD SHEETING, EXTRUDED ALUMINUM | SQFT | 88 | 35.00 | 3,080.00 | 29.00 | 2,552.00 | 30.00 | 2,640.00 | 37.50 | 3,300.00 | 31.00 | 2,728.00 | 26.50 | 2,332.00 | 2,332.00 | 3,300.00 |
| 74 | 0970-0100000A | POLE FOUNDATIONS | LS | 1 | 1,500.00 | 1,500.00 | 3,000.00 | 3,000.00 | 6,300.00 | 6,300.00 | 2,000.00 | 2,000.00 | 3,600.00 | 3,600.00 | 17,000.00 | 17,000.00 | 2,000.00 | 17,000.00 |
| 75 | 0970-0105000A | SWITCHING, CONDUIT, AND WIRING | LS | 1 | 3,700.00 | 3,700.00 | 7,500.00 | 7,500.00 | 8,250.00 | 8,250.00 | 15,000.00 | 15,000.00 | 8,450.00 | 8,450.00 | 12,000.00 | 12,000.00 | 7,500.00 | 15,000.00 |
| 76 | 0987-0100000A | TELECOMMUNICATIONS, MATERIAL | LS | 1 | 30,600.00 | 30,600.00 | 23,000.00 | 23,000.00 | 10,500.00 | 10,500.00 | 9,000.00 | 9,000.00 | 26,565.00 | 26,565.00 | 8,300.00 | 8,300.00 | 8,300.00 | 26,565.00 |
| 77 | 0987-0110000A | TELECOMMUNICATIONS, INSTALLATION | LS | 1 | 20,400.00 | 20,400.00 | 32,000.00 | 32,000.00 | 24,000.00 | 24,000.00 | 45,000.00 | 45,000.00 | 38,640.00 | 38,640.00 | 41,000.00 | 41,000.00 | 24,000.00 | 45,000.00 |
| 78 | 0990-0101000A | TRAFFIC SIGNAL INSTALLATION, JOHNSON CK BLVD & 79TH PL | LS | 1 | 506,000.00 | 506,000.00 | 447,000.00 | 447,000.00 | 476,000.00 | 476,000.00 | 440,000.00 | 440,000.00 | 502,302.00 | 502,302.00 | 432,200.00 | 432,200.00 | 432,200.00 | 502,302.00 |
| 79 | 1011-0200000A | BIORETENTION POND, WATER QUALITY FACILITY | LS | 1 | 46,000.00 | 46,000.00 | 58,000.00 | 58,000.00 | 61,500.00 | 61,500.00 | 65,000.00 | 65,000.00 | 14,000.00 | 14,000.00 | 63,000.00 | 63,000.00 | 14,000.00 | 65,000.00 |
| 80 | 1030-0108000R | PERMANENT SEEDING | ACRE | 0.12 | 20,000.00 | 2,400.00 | 13,000.00 | 1,560.00 | 12,500.00 | 1,500.00 | 12,500.00 | 1,500.00 | 48,300.00 | 5,796.00 | 14,000.00 | 1,680.00 | 1,500.00 | 5,796.00 |
| 81 | 1030-0118000e | WETLAND PLANTS, PLUGS | EACH | 1607 | 1.25 | 2,008.75 | 1.10 | 1,767.70 | 3.00 | 4,821.00 | 1.00 | 1,607.00 | 3.75 | 6,026.25 | 5.00 | 8,035.00 | 1,607.00 | 8,035.00 |
| 82 | 1040-0101000K | TOPSOIL | CUYD | 64 | 100.00 | 6,400.00 | 50.00 | 3,200.00 | 50.00 | 3,200.00 | 45.00 | 2,880.00 | 84.50 | 5,408.00 | 94.00 | 6,016.00 | 2,880.00 | 6,016.00 |
| 83 | 1040-0153000E | SHRUBS, #1 CONTAINER | EACH | 29 | 18.00 | 522.00 | 13.00 | 377.00 | 15.00 | 435.00 | 13.00 | 377.00 | 18.00 | 522.00 | 37.00 | 1,073.00 | 377.00 | 1,073.00 |
| 84 | 1040-0171000E | WETLAND PLANTS, #1 CONTAINER | EACH | 218 | 12.00 | 2,616.00 | 13.00 | 2,834.00 | 15.00 | 3,270.00 | 13.00 | 2,834.00 | 18.00 | 3,924.00 | 37.00 | 8,066.00 | 2,834.00 | 8,066.00 |
| 85 | 1040-0190000K | BARK MULCH | CUYD | 15 | 220.00 | 3,300.00 | 66.00 | 990.00 | 65.00 | 975.00 | 65.00 | 975.00 | 90.00 | 1,350.00 | 96.00 | 1,440.00 | 975.00 | 1,440.00 |
| 86 | 1050-0162000F | TYPE CL-4R CHAIN LINK FENCE WITH BLACK PVC COATING | FOOT | 85 | 60.00 | 5,100.00 | 80.00 | 6,800.00 | 45.00 | 3,825.00 | 45.00 | 3,825.00 | 52.00 | 4,420.00 | 72.00 | 6,120.00 | 3,825.00 | 6,800.00 |
| 87 | 1050-0162000F | TYPE CL-6R CHAIN LINK FENCE WITH BLACK PVC COATING AND SCREENING PICKETS | FOOT | 139 | 110.00 | 15,290.00 | 95.00 | 13,205.00 | 65.00 | 9,035.00 | 68.00 | 9,452.00 | 78.50 | 10,911.50 | 88.00 | 12,232.00 | 9,035.00 | 13,205.00 |
| 88 | 1050-0198000E | 12 FOOT X 48 INCH CHAIN LINK DOUBLE GATES | EACH | 1 | 3,500.00 | 3,500.00 | 3,100.00 | 3,100.00 | 2,400.00 | 2,400.00 | 2,400.00 | 2,400.00 | 2,800.00 | 2,800.00 | 2,850.00 | 2,850.00 | 2,400.00 | 3,100.00 |
| 89 | 1070-0100000E | SINGLE MAILBOX SUPPORTS | EACH | 2 | 1,200.00 | 2,400.00 | 1,335.00 | 2,670.00 | 750.00 | 1,500.00 | 1,000.00 | 2,000.00 | 1,450.00 | 2,900.00 | 950.00 | 1,900.00 | 1,500.00 | 2,900.00 |
| 90 | 1070-0102000E | MAILBOX CONCRETE COLLARS | EACH | 1 | 750.00 | 750.00 | 720.00 | 720.00 | 350.00 | 350.00 | 500.00 | 500.00 | 785.00 | 785.00 | 950.00 | 950.00 | 350.00 | 950.00 |
| 91 | 1070-0103000E | REMOVE AND REINSTALL MAILBOX SUPPORTS | EACH | 1 | 1,500.00 | 1,500.00 | 1,550.00 | 1,550.00 | 500.00 | 500.00 | 1,000.00 | 1,000.00 | 1,690.50 | 1,690.50 | 1,600.00 | 1,600.00 | 500.00 | 1,690.50 |
| 92 | 1170-0109000F | 1 INCH COPPER WATER SERVICE LINE | FOOT | 127 | 75.00 | 9,525.00 | 115.00 | 14,605.00 | 55.00 | 6,985.00 | 70.00 | 8,890.00 | 95.00 | 12,065.00 | 103.00 | 13,081.00 | 6,985.00 | 14,605.00 |
| 93 | 0280-0111020H | CONCRETE WASH OUT FACILITY | EACH | 1 | 1,500.00 | 1,500.00 | 3,700.00 | 3,700.00 | 1,500.00 | 1,500.00 | 1,800.00 | 1,800.00 | 0.00 | 0.00 | 6,500.00 | 6,500.00 | 0.00 | 6,500.00 |
| $1,645,052.75 | $1,714,494.04 | $1,833,291.00 | $1,847,677.50 | $1,959,099.95 | $2,128,912.44 | LOW | HIGH | |||||||||||
| Engineers Est | $1,645,052.75 | Engineers Estimate | Westech Construction | Corpac Construction Co | Moore Excavation | Dirt & Agg interchange | Kodiak Pacific Construction | |||||||||||
| Westech Construction | $1,714,494.04 | |||||||||||||||||
| Corpac Const. | $1,833,291.00 | Bid item 22 quantity changed during bid | Bid amount said | $ 1,962,199.95 | Bid amount said | $ 2,104,612.44 | ||||||||||||
| Moore Ex | $1,847,677.50 | Bid item 93 added during bid | Missing Bid Item 93 amount in bid schedule | Bid Item 19 bid schedule not carried out correctly | ||||||||||||||
| Drit and Agg | $1,959,099.95 | Bid Item 33 in bid schedule not carried out correctly | ||||||||||||||||
| Kodiak | $2,128,912.44 |
Compare to Estimate
| SE JOHNSON CREEK BLVD: 79TH PL - 82ND AVE | ||||||||||||||
| Westech Construction | Estimate | |||||||||||||
| Item # | Spec | |||||||||||||
| Sec | Description | Unit | Quantity | Unit Price | Total Price | Unit Price | Total Price | Maximum | Minimum | |||||
| 1 | 0210-0100000A | MOBILIZATION | LS | 1 | 171,000.00 | $171,000.00 | 135,000.00 | $ 135,000.00 | $ 171,000.00 | $ 135,000.00 | ||||
| 2 | 0221-0100000A | TEMPORARY PROTECTION AND DIRECTION OF TRAFFIC | LS | 1 | 22,000.00 | $22,000.00 | 41,000.00 | $ 41,000.00 | $ 41,000.00 | $ 22,000.00 | ||||
| 3 | 0222-0102000J | TEMPORARY SIGNS | SQFT | 200 | 33.30 | $6,660.00 | 24.00 | $ 4,800.00 | $ 6,660.00 | $ 4,800.00 | ||||
| 4 | 0222-0162000E | SEQUENTIAL ARROW SIGNS | EACH | 1 | 1,345.00 | $1,345.00 | 5,000.00 | $ 5,000.00 | $ 5,000.00 | $ 1,345.00 | ||||
| 5 | 0223-0168000T | FLAGGERS | HOUR | 800 | 80.00 | $64,000.00 | 50.00 | $ 40,000.00 | $ 64,000.00 | $ 40,000.00 | ||||
| 6 | 0224-0104000E | TEMPORARY BARRICADES, TYPE II | EACH | 4 | 36.00 | $144.00 | 80.00 | $ 320.00 | $ 320.00 | $ 144.00 | ||||
| 7 | 0224-0105000E | TEMPORARY BARRICADES, TYPE III | EACH | 2 | 99.00 | $198.00 | 150.00 | $ 300.00 | $ 300.00 | $ 198.00 | ||||
| 8 | 0224-0145000E | TEMPORARY PLASTIC DRUMS | EACH | 26 | 22.00 | $572.00 | 50.00 | $ 1,300.00 | $ 1,300.00 | $ 572.00 | ||||
| 9 | 0225-0153000F | TEMPORARY STRIPING | FOOT | 2700 | 1.60 | $4,320.00 | 1.00 | $ 2,700.00 | $ 4,320.00 | $ 2,700.00 | ||||
| 10 | 0225-0154000F | STRIPE REMOVAL | FOOT | 3250 | 1.60 | $5,200.00 | 0.50 | $ 1,625.00 | $ 5,200.00 | $ 1,625.00 | ||||
| 11 | 0228-0141600F | PEDESTRIAN CHANNELIZING DEVICES | FOOT | 300 | 5.50 | $1,650.00 | 10.00 | $ 3,000.00 | $ 3,000.00 | $ 1,650.00 | ||||
| 12 | 0280-0100000A | EROSION CONTROL | LS | 1 | 10,000.00 | $10,000.00 | 3,000.00 | $ 3,000.00 | $ 10,000.00 | $ 3,000.00 | ||||
| 13 | 0280-0113000F | SEDIMENT FENCE | FOOT | 485 | 8.00 | $3,880.00 | 4.00 | $ 1,940.00 | $ 3,880.00 | $ 1,940.00 | ||||
| 14 | 0280-0114040E | INLET PROTECTION, TYPE 4 | EACH | 14 | 46.00 | $644.00 | 125.00 | $ 1,750.00 | $ 1,750.00 | $ 644.00 | ||||
| 15 | 0280-0110010E | CONSTRUCTION ENTRANCE, TYPE 1 | EACH | 1 | 2,700.00 | $2,700.00 | 750.00 | $ 750.00 | $ 2,700.00 | $ 750.00 | ||||
| 16 | 0280-0111010E | TIRE WASH FACILITY, TYPE 1 | EACH | 1 | 6,500.00 | $6,500.00 | 750.00 | $ 750.00 | $ 6,500.00 | $ 750.00 | ||||
| 17 | 0290-0100000A | POLLUTION CONTROL PLAN | LS | 1 | 1,100.00 | $1,100.00 | 1,000.00 | $ 1,000.00 | $ 1,100.00 | $ 1,000.00 | ||||
| 18 | 0294-0100000A | HEALTH AND SAFETY PLAN | LS | 1 | 2,200.00 | $2,200.00 | 2,500.00 | $ 2,500.00 | $ 2,500.00 | $ 2,200.00 | ||||
| 19 | 0294-0200010M | CONTAMINATED SOIL DISPOSAL | TON | 138 | 112.00 | $15,456.00 | 100.00 | $ 13,800.00 | $ 15,456.00 | $ 13,800.00 | ||||
| 20 | 0294-0500000A | LEAD COMPLIANCE PLAN | LS | 1 | 5,500.00 | $5,500.00 | 2,500.00 | $ 2,500.00 | $ 5,500.00 | $ 2,500.00 | ||||
| 21 | 0295-0100000F | REMOVE ASBESTOS MATERIAL, FRIABLE | FOOT | 5 | 61.00 | $305.00 | 300.00 | $ 1,500.00 | $ 1,500.00 | $ 305.00 | ||||
| 22 | 0295-0200000F | REMOVE ASBESTOS MATERIAL, NON-FRIABLE | SQFT | 2750 | 3.50 | $9,625.00 | 5.00 | $ 13,750.00 | $ 13,750.00 | $ 9,625.00 | ||||
| 23 | 0305-0100000A | CONSTRUCTION SURVEY WORK | LS | 1 | 20,000.00 | $20,000.00 | 40,000.00 | $ 40,000.00 | $ 40,000.00 | $ 20,000.00 | ||||
| 24 | 0310-0100000F | REMOVAL OF PIPES | FOOT | 248 | 10.25 | $2,542.00 | 30.00 | $ 7,440.00 | $ 7,440.00 | $ 2,542.00 | ||||
| 25 | 0310-0104000E | REMOVAL OF INLETS | EACH | 3 | 1,555.00 | $4,665.00 | 500.00 | $ 1,500.00 | $ 4,665.00 | $ 1,500.00 | ||||
| 26 | 0310-0106000A | REMOVAL OF STRUCTURES AND OBSTRUCTIONS | LS | 1 | 9,000.00 | $9,000.00 | 27,000.00 | $ 27,000.00 | $ 27,000.00 | $ 9,000.00 | ||||
| 27 | 0310-0109000A | REMOVAL OF BUILDINGS | LS | 1 | 24,000.00 | $24,000.00 | 40,000.00 | $ 40,000.00 | $ 40,000.00 | $ 24,000.00 | ||||
| 28 | 0310-0119000F | ASPHALT PAVEMENT SAW CUTTING | FOOT | 1030 | 3.25 | $3,347.50 | 5.00 | $ 5,150.00 | $ 5,150.00 | $ 3,347.50 | ||||
| 29 | 0320-0100000A | CLEARING AND GRUBBING | LS | 1 | 4,000.00 | $4,000.00 | 12,000.00 | $ 12,000.00 | $ 12,000.00 | $ 4,000.00 | ||||
| 30 | 0330-0105000K | GENERAL EXCAVATION | CUYD | 793 | 70.00 | $55,510.00 | 60.00 | $ 47,580.00 | $ 55,510.00 | $ 47,580.00 | ||||
| 31 | 0331-0109000J | 18 INCH SUBGRADE STABILIZATION | SQYD | 114 | 19.00 | $2,166.00 | 65.00 | $ 7,410.00 | $ 7,410.00 | $ 2,166.00 | ||||
| 32 | 0350-0105000J | SUBGRADE GEOTEXTILE | SQYD | 946 | 1.69 | $1,598.74 | 2.00 | $ 1,892.00 | $ 1,892.00 | $ 1,598.74 | ||||
| 33 | 0390-0119000K | GROUTED RIPRAP | CUYD | 190 | 65.00 | $12,350.00 | 20.00 | $ 3,800.00 | $ 12,350.00 | $ 3,800.00 | ||||
| 34 | 0415-0100000F | MAINLINE VIDEO INSPECTION | FOOT | 331 | 9.00 | $2,979.00 | 5.00 | $ 1,655.00 | $ 2,979.00 | $ 1,655.00 | ||||
| 35 | 0415-0400000E | SERVICE LINE LATERAL VIDEO INSPECTION | EACH | 1 | 275.00 | $275.00 | 750.00 | $ 750.00 | $ 750.00 | $ 275.00 | ||||
| 36 | 0445-030006BF | 6 INCH SANITARY SEWER PIPE, 10 FT DEPTH | FOOT | 52 | 340.00 | $17,680.00 | 150.00 | $ 7,800.00 | $ 17,680.00 | $ 7,800.00 | ||||
| 37 | 0445-035012AF | 12 INCH STORM SEWER PIPE, 5 FT DEPTH | FOOT | 331 | 175.00 | $57,925.00 | 130.00 | $ 43,030.00 | $ 57,925.00 | $ 43,030.00 | ||||
| 38 | 0445 | 6 INCH STORM SEWER CLEANOUT | EACH | 1 | 1,275.00 | $1,275.00 | 500.00 | $ 500.00 | $ 1,275.00 | $ 500.00 | ||||
| 39 | 0470-0101000E | CONCRETE STORM SEWER MANHOLES | EACH | 1 | 6,800.00 | $6,800.00 | 7,000.00 | $ 7,000.00 | $ 7,000.00 | $ 6,800.00 | ||||
| 40 | 0470-0315000E | CONCRETE INLETS, TYPE GB-2 | EACH | 5 | 2,250.00 | $11,250.00 | 2,900.00 | $ 14,500.00 | $ 14,500.00 | $ 11,250.00 | ||||
| 41 | 0490-0100000E | ADJUSTING BOXES | EACH | 2 | 320.00 | $640.00 | 500.00 | $ 1,000.00 | $ 1,000.00 | $ 640.00 | ||||
| 42 | 0490-0102000E | ADJUSTING CATCH BASINS | EACH | 1 | 1,200.00 | $1,200.00 | 1,000.00 | $ 1,000.00 | $ 1,200.00 | $ 1,000.00 | ||||
| 43 | 0490-0104000E | CONNECTION TO EXISTING STRUCTURES | EACH | 2 | 2,300.00 | $4,600.00 | 2,000.00 | $ 4,000.00 | $ 4,600.00 | $ 4,000.00 | ||||
| 44 | 0490-0120000E | MINOR ADJUSTMENT OF MANHOLES | EACH | 4 | 2,400.00 | $9,600.00 | 1,500.00 | $ 6,000.00 | $ 9,600.00 | $ 6,000.00 | ||||
| 45 | 0620-0123000J | COLD PLANE PAVEMENT REMOVAL, 4 INCHES DEEP | SQYD | 3363 | 6.50 | $21,859.50 | 7.00 | $ 23,541.00 | $ 23,541.00 | $ 21,859.50 | ||||
| 46 | 0640-0100000M | AGGREGATE BASE | TON | 740 | 75.00 | $55,500.00 | 45.00 | $ 33,300.00 | $ 55,500.00 | $ 33,300.00 | ||||
| 47 | 0295-0200000F | REMOVE ASBESTOS MATERIAL, FRIABLE | SQFT | 470 | 19.00 | $8,930.00 | 25.00 | $ 11,750.00 | $ 11,750.00 | $ 8,930.00 | ||||
| 48 | 0744-0302000M | LEVEL 3, 1/2 INCH ACP MIXTURE | TON | 1052 | 130.00 | $136,760.00 | 125.00 | $ 131,500.00 | $ 136,760.00 | $ 131,500.00 | ||||
| 49 | 0748-0103000J | 6 INCH ASPHALT CONCRETE PAVEMENT REPAIR | SQYD | 500 | 118.00 | $59,000.00 | 50.00 | $ 25,000.00 | $ 59,000.00 | $ 25,000.00 | ||||
| 50 | 0749-0100000E | EXTRA FOR ASPHALT APPROACHES | EACH | 5 | 685.00 | $3,425.00 | 2,000.00 | $ 10,000.00 | $ 10,000.00 | $ 3,425.00 | ||||
| 51 | 0759-0103000F | CONCRETE CURBS, CURB AND GUTTER | FOOT | 634 | 42.95 | $27,230.30 | 40.00 | $ 25,360.00 | $ 27,230.30 | $ 25,360.00 | ||||
| 52 | 0759-0106000F | CONCRETE CURBS, LOW PROFILE MOUNTABLE CURB | FOOT | 18 | 69.00 | $1,242.00 | 50.00 | $ 900.00 | $ 1,242.00 | $ 900.00 | ||||
| 53 | 0759-0110000F | CONCRETE CURBS, STANDARD CURB | FOOT | 304 | 45.00 | $13,680.00 | 45.00 | $ 13,680.00 | $ 13,680.00 | $ 13,680.00 | ||||
| 54 | 0759-0122000J | CONCRETE ISLANDS | SQFT | 370 | 18.00 | $6,660.00 | 25.00 | $ 9,250.00 | $ 9,250.00 | $ 6,660.00 | ||||
| 55 | 0759-0126000J | CONCRETE DRIVEWAYS | SQFT | 215 | 33.00 | $7,095.00 | 20.00 | $ 4,300.00 | $ 7,095.00 | $ 4,300.00 | ||||
| 56 | 0759-0127000J | CONCRETE DRIVEWAYS, REINFORCED | SQFT | 730 | 35.00 | $25,550.00 | 30.00 | $ 21,900.00 | $ 25,550.00 | $ 21,900.00 | ||||
| 57 | 0759-0128000J | CONCRETE WALKS | SQFT | 3280 | 14.00 | $45,920.00 | 11.00 | $ 36,080.00 | $ 45,920.00 | $ 36,080.00 | ||||
| 58 | 0759-0154100E | EXTRA FOR NEW CURB RAMPS | EACH | 12 | 2,200.00 | $26,400.00 | 2,000.00 | $ 24,000.00 | $ 26,400.00 | $ 24,000.00 | ||||
| 59 | 0759-0510000J | TRUNCATED DOMES ON NEW SURFACES | SQFT | 155 | 50.00 | $7,750.00 | 50.00 | $ 7,750.00 | $ 7,750.00 | $ 7,750.00 | ||||
| 60 | 0855-0102100E | BI-DIRECTIONAL YELLOW TYPE I MARKERS | EACH | 89 | 9.50 | $845.50 | 15.00 | $ 1,335.00 | $ 1,335.00 | $ 845.50 | ||||
| 61 | 0855-0102100E | BI-DIRECTIONAL WHITE TYPE I MARKERS | EACH | 33 | 9.50 | $313.50 | 15.00 | $ 495.00 | $ 495.00 | $ 313.50 | ||||
| 62 | 0865-0160000F | THERMOPLASTIC, EXTRUDED OR SPRAYED, SURFACE, NON-PROFILED | FOOT | 6662 | 2.15 | $14,323.30 | 1.50 | $ 9,993.00 | $ 14,323.30 | $ 9,993.00 | ||||
| 63 | 0867-0103500E | PAVEMENT LEGEND, TYPE AB: ARROWS | EACH | 6 | 415.00 | $2,490.00 | 375.00 | $ 2,250.00 | $ 2,490.00 | $ 2,250.00 | ||||
| 64 | 0867-0131000E | PAVEMENT LEGEND, TYPE B-HS: BICYCLE LANE STENCIL | EACH | 6 | 415.00 | $2,490.00 | 350.00 | $ 2,100.00 | $ 2,490.00 | $ 2,100.00 | ||||
| 65 | 0867-0145100J | PAVEMENT BAR, TYPE B-HS | SQFT | 604 | 21.00 | $12,684.00 | 15.00 | $ 9,060.00 | $ 12,684.00 | $ 9,060.00 | ||||
| 66 | 0867-0174000E | PAVEMENT LEGEND, TYPE B-HS : BICYCLE DETECTOR STENCIL | EACH | 1 | 333.00 | $333.00 | 500.00 | $ 500.00 | $ 500.00 | $ 333.00 | ||||
| 67 | 0868-0100000J | GREEN BICYCLE LANE, PREFORMED THERMOPLASTIC FILM | SQFT | 75 | 20.00 | $1,500.00 | 15.00 | $ 1,125.00 | $ 1,500.00 | $ 1,125.00 | ||||
| 68 | 0902-0101000E | CROSSWALK CLOSURE SUPPORTS | EACH | 4 | 1,350.00 | $5,400.00 | 1,300.00 | $ 5,200.00 | $ 5,400.00 | $ 5,200.00 | ||||
| 69 | 0905-0100000A | REMOVE EXISTING SIGNS | LS | 1 | 555.00 | $555.00 | 1,200.00 | $ 1,200.00 | $ 1,200.00 | $ 555.00 | ||||
| 70 | 0920-0100000A | SIGN SUPPORT FOOTINGS | LS | 1 | 4,100.00 | $4,100.00 | 2,000.00 | $ 2,000.00 | $ 4,100.00 | $ 2,000.00 | ||||
| 71 | 0930-0114000A | PERFORATED STEEL SQUARE TUBE SLIP BASE SIGN SUPPORTS | LS | 1 | 3,400.00 | $3,400.00 | 3,100.00 | $ 3,100.00 | $ 3,400.00 | $ 3,100.00 | ||||
| 72 | 0930-0117000A | PERFORATED STEEL SQUARE TUBE ANCHOR SIGN SUPPORTS | LS | 1 | 525.00 | $525.00 | 1,000.00 | $ 1,000.00 | $ 1,000.00 | $ 525.00 | ||||
| 73 | 0940-0201000J | SIGNS, STANDARD SHEETING, EXTRUDED ALUMINUM | SQFT | 88 | 29.00 | $2,552.00 | 35.00 | $ 3,080.00 | $ 3,080.00 | $ 2,552.00 | ||||
| 74 | 0970-0100000A | POLE FOUNDATIONS | LS | 1 | 3,000.00 | $3,000.00 | 1,500.00 | $ 1,500.00 | $ 3,000.00 | $ 1,500.00 | ||||
| 75 | 0970-0105000A | SWITCHING, CONDUIT, AND WIRING | LS | 1 | 7,500.00 | $7,500.00 | 3,700.00 | $ 3,700.00 | $ 7,500.00 | $ 3,700.00 | ||||
| 76 | 0987-0100000A | TELECOMMUNICATIONS, MATERIAL | LS | 1 | 23,000.00 | $23,000.00 | 30,600.00 | $ 30,600.00 | $ 30,600.00 | $ 23,000.00 | ||||
| 77 | 0987-0110000A | TELECOMMUNICATIONS, INSTALLATION | LS | 1 | 32,000.00 | $32,000.00 | 20,400.00 | $ 20,400.00 | $ 32,000.00 | $ 20,400.00 | ||||
| 78 | 0990-0101000A | TRAFFIC SIGNAL INSTALLATION, JOHNSON CK BLVD & 79TH PL | LS | 1 | 447,000.00 | $447,000.00 | 506,000.00 | $ 506,000.00 | $ 506,000.00 | $ 447,000.00 | ||||
| 79 | 1011-0200000A | BIORETENTION POND, WATER QUALITY FACILITY | LS | 1 | 58,000.00 | $58,000.00 | 46,000.00 | $ 46,000.00 | $ 58,000.00 | $ 46,000.00 | ||||
| 80 | 1030-0108000R | PERMANENT SEEDING | ACRE | 0.12 | 13,000.00 | $1,560.00 | 20,000.00 | $ 2,400.00 | $ 2,400.00 | $ 1,560.00 | ||||
| 81 | 1030-0118000e | WETLAND PLANTS, PLUGS | EACH | 1607 | 1.10 | $1,767.70 | 1.25 | $ 2,008.75 | $ 2,008.75 | $ 1,767.70 | ||||
| 82 | 1040-0101000K | TOPSOIL | CUYD | 64 | 50.00 | $3,200.00 | 100.00 | $ 6,400.00 | $ 6,400.00 | $ 3,200.00 | ||||
| 83 | 1040-0153000E | SHRUBS, #1 CONTAINER | EACH | 29 | 13.00 | $377.00 | 18.00 | $ 522.00 | $ 522.00 | $ 377.00 | ||||
| 84 | 1040-0171000E | WETLAND PLANTS, #1 CONTAINER | EACH | 218 | 13.00 | $2,834.00 | 12.00 | $ 2,616.00 | $ 2,834.00 | $ 2,616.00 | ||||
| 85 | 1040-0190000K | BARK MULCH | CUYD | 15 | 66.00 | $990.00 | 220.00 | $ 3,300.00 | $ 3,300.00 | $ 990.00 | ||||
| 86 | 1050-0162000F | TYPE CL-4R CHAIN LINK FENCE WITH BLACK PVC COATING | FOOT | 85 | 80.00 | $6,800.00 | 60.00 | $ 5,100.00 | $ 6,800.00 | $ 5,100.00 | ||||
| 87 | 1050-0162000F | TYPE CL-6R CHAIN LINK FENCE WITH BLACK PVC COATING AND SCREENING PICKETS | FOOT | 139 | 95.00 | $13,205.00 | 110.00 | $ 15,290.00 | $ 15,290.00 | $ 13,205.00 | ||||
| 88 | 1050-0198000E | 12 FOOT X 48 INCH CHAIN LINK DOUBLE GATES | EACH | 1 | 3,100.00 | $3,100.00 | 3,500.00 | $ 3,500.00 | $ 3,500.00 | $ 3,100.00 | ||||
| 89 | 1070-0100000E | SINGLE MAILBOX SUPPORTS | EACH | 2 | 1,335.00 | $2,670.00 | 1,200.00 | $ 2,400.00 | $ 2,670.00 | $ 2,400.00 | ||||
| 90 | 1070-0102000E | MAILBOX CONCRETE COLLARS | EACH | 1 | 720.00 | $720.00 | 750.00 | $ 750.00 | $ 750.00 | $ 720.00 | ||||
| 91 | 1070-0103000E | REMOVE AND REINSTALL MAILBOX SUPPORTS | EACH | 1 | 1,550.00 | $1,550.00 | 1,500.00 | $ 1,500.00 | $ 1,550.00 | $ 1,500.00 | ||||
| 92 | 1170-0109000F | 1 INCH COPPER WATER SERVICE LINE | FOOT | 127 | 115.00 | $14,605.00 | 75.00 | $ 9,525.00 | $ 14,605.00 | $ 9,525.00 | ||||
| 93 | 0280-0111020H | CONCRETE WASH OUT FACILITY | EACH | 1 | 3,700.00 | $3,700.00 | 1,500.00 | $ 1,500.00 | $ 3,700.00 | $ 1,500.00 | ||||
| $1,714,494.04 | $ 1,645,052.75 | $ 1,714,494.04 | $ 1,645,052.75 |
3 lowest Bid Analysis
| SE JOHNSON CREEK BLVD: 79TH PL-82ND AVE | ||||||||||||||||||||
| Bid Opening June 10, 2025 | ||||||||||||||||||||
| Engineers Estimate | Westech Construction | % OVR/UND. | % OVR/UND. | ITEM % OF | Corpac Construction | Moore | ||||||||||||||
| Item # | Spec | |||||||||||||||||||
| Sec | Description | Unit | Quantity | Unit Price | Total Price | Unit Price | Total Price | Low Bidder | ||||||||||||
| to Engr. Estimate | 3 Lowest Bidders | |||||||||||||||||||
| Average | Lowest Bid | |||||||||||||||||||
| to Total Bid | Unit Price | Total Price | Unit Price | Total Price | ||||||||||||||||
| 1 | 0210-0100000A | MOBILIZATION | LS | 1 | 135,000.00 | 135,000.00 | 171,000.00 | $ 171,000.00 | 26.67% | -3.18% | 9.97% | 1 | 183,330.00 | $ 183,330.00 | 175,000.00 | $ 175,000.00 | 1 | |||
| 2 | 0221-0100000A | TEMPORARY PROTECTION AND DIRECTION OF TRAFFIC | LS | 1 | 41,000.00 | 41,000.00 | 22,000.00 | 22,000.00 | -46.34% | -160.61% | 1.28% | 2 | 75,000.00 | 75,000.00 | 75,000.00 | 75,000.00 | 2 | |||
| 3 | 0222-0102000J | TEMPORARY SIGNS | SQFT | 200 | 24.00 | 4,800.00 | 33.30 | 6,660.00 | 38.75% | 8.61% | 0.39% | 3 | 25.00 | 5,000.00 | 33.00 | 6,600.00 | 3 | |||
| 4 | 0222-0162000E | SEQUENTIAL ARROW SIGNS | EACH | 1 | 5,000.00 | 5,000.00 | 1,345.00 | 1,345.00 | -73.10% | -1.49% | 0.08% | 4 | 750.00 | 750.00 | 2,000.00 | 2,000.00 | 4 | |||
| 5 | 0223-0168000T | FLAGGERS | HOUR | 800 | 50.00 | 40,000.00 | 80.00 | 64,000.00 | 60.00% | 0.00% | 3.73% | 5 | 78.00 | 62,400.00 | 82.00 | 65,600.00 | 5 | |||
| 6 | 0224-0104000E | TEMPORARY BARRICADES, TYPE II | EACH | 4 | 80.00 | 320.00 | 36.00 | 144.00 | -55.00% | -39.81% | 0.01% | 6 | 50.00 | 200.00 | 65.00 | 260.00 | 6 | |||
| 7 | 0224-0105000E | TEMPORARY BARRICADES, TYPE III | EACH | 2 | 150.00 | 300.00 | 99.00 | 198.00 | -34.00% | -42.76% | 0.01% | 7 | 100.00 | 200.00 | 225.00 | 450.00 | 7 | |||
| 8 | 0224-0145000E | TEMPORARY PLASTIC DRUMS | EACH | 26 | 50.00 | 1,300.00 | 22.00 | 572.00 | -56.00% | -115.15% | 0.03% | 8 | 50.00 | 1,300.00 | 70.00 | 1,820.00 | 8 | |||
| 9 | 0225-0153000F | TEMPORARY STRIPING | FOOT | 2700 | 1.00 | 2,700.00 | 1.60 | 4,320.00 | 60.00% | 5.21% | 0.25% | 9 | 0.20 | 540.00 | 2.75 | 7,425.00 | 9 | |||
| 10 | 0225-0154000F | STRIPE REMOVAL | FOOT | 3250 | 0.50 | 1,625.00 | 1.60 | 5,200.00 | 220.00% | -42.71% | 0.30% | 10 | 3.75 | 12,187.50 | 1.50 | 4,875.00 | 10 | |||
| 11 | 0228-0141600F | PEDESTRIAN CHANNELIZING DEVICES | FOOT | 300 | 10.00 | 3,000.00 | 5.50 | 1,650.00 | -45.00% | -266.67% | 0.10% | 11 | 25.00 | 7,500.00 | 30.00 | 9,000.00 | 11 | |||
| 12 | 0280-0100000A | EROSION CONTROL | LS | 1 | 3,000.00 | 3,000.00 | 10,000.00 | 10,000.00 | 233.33% | -1.67% | 0.58% | 12 | 15,500.00 | 15,500.00 | 5,000.00 | 5,000.00 | 12 | |||
| 13 | 0280-0113000F | SEDIMENT FENCE | FOOT | 485 | 4.00 | 1,940.00 | 8.00 | 3,880.00 | 100.00% | 35.42% | 0.23% | 13 | 3.50 | 1,697.50 | 4.00 | 1,940.00 | 13 | |||
| 14 | 0280-0114040E | INLET PROTECTION, TYPE 4 | EACH | 14 | 125.00 | 1,750.00 | 46.00 | 644.00 | -63.20% | -78.26% | 0.04% | 14 | 75.00 | 1,050.00 | 125.00 | 1,750.00 | 14 | |||
| 15 | 0280-0110010E | CONSTRUCTION ENTRANCE, TYPE 1 | EACH | 1 | 750.00 | 750.00 | 2,700.00 | 2,700.00 | 260.00% | -18.21% | 0.16% | 15 | 1,875.00 | 1,875.00 | 5,000.00 | 5,000.00 | 15 | |||
| 16 | 0280-0111010E | TIRE WASH FACILITY, TYPE 1 | EACH | 1 | 750.00 | 750.00 | 6,500.00 | 6,500.00 | 766.67% | 35.90% | 0.38% | 16 | 3,500.00 | 3,500.00 | 2,500.00 | 2,500.00 | 16 | |||
| 17 | 0290-0100000A | POLLUTION CONTROL PLAN | LS | 1 | 1,000.00 | 1,000.00 | 1,100.00 | 1,100.00 | 10.00% | -9.09% | 0.06% | 17 | 1,500.00 | 1,500.00 | 1,000.00 | 1,000.00 | 17 | |||
| 18 | 0294-0100000A | HEALTH AND SAFETY PLAN | LS | 1 | 2,500.00 | 2,500.00 | 2,200.00 | 2,200.00 | -12.00% | 13.64% | 0.13% | 18 | 1,500.00 | 1,500.00 | 2,000.00 | 2,000.00 | 18 | |||
| 19 | 0294-0200010M | CONTAMINATED SOIL DISPOSAL | TON | 138 | 100.00 | 13,800.00 | 112.00 | 15,456.00 | 12.00% | -0.30% | 0.90% | 19 | 100.00 | 13,800.00 | 125.00 | 17,250.00 | 19 | |||
| 20 | 0294-0500000A | LEAD COMPLIANCE PLAN | LS | 1 | 2,500.00 | 2,500.00 | 5,500.00 | 5,500.00 | 120.00% | 45.45% | 0.32% | 20 | 1,500.00 | 1,500.00 | 2,000.00 | 2,000.00 | 20 | |||
| 21 | 0295-0100000F | REMOVE ASBESTOS MATERIAL, FRIABLE | FOOT | 5 | 300.00 | 1,500.00 | 61.00 | 305.00 | -79.67% | -9.84% | 0.02% | 21 | 85.00 | 425.00 | 55.00 | 275.00 | 21 | |||
| 22 | 0295-0200000F | REMOVE ASBESTOS MATERIAL, NON-FRIABLE | SQFT | 2750 | 5.00 | 13,750.00 | 3.50 | 9,625.00 | -30.00% | -142.86% | 0.56% | 22 | 15.00 | 41,250.00 | 7.00 | 19,250.00 | 22 | |||
| 23 | 0305-0100000A | CONSTRUCTION SURVEY WORK | LS | 1 | 40,000.00 | 40,000.00 | 20,000.00 | 20,000.00 | -50.00% | -6.67% | 1.17% | 23 | 19,000.00 | 19,000.00 | 25,000.00 | 25,000.00 | 23 | |||
| 24 | 0310-0100000F | REMOVAL OF PIPES | FOOT | 248 | 30.00 | 7,440.00 | 10.25 | 2,542.00 | -65.83% | -144.72% | 0.15% | 24 | 35.00 | 8,680.00 | 30.00 | 7,440.00 | 24 | |||
| 25 | 0310-0104000E | REMOVAL OF INLETS | EACH | 3 | 500.00 | 1,500.00 | 1,555.00 | 4,665.00 | 211.00% | 37.73% | 0.27% | 25 | 650.00 | 1,950.00 | 700.00 | 2,100.00 | 25 | |||
| 26 | 0310-0106000A | REMOVAL OF STRUCTURES AND OBSTRUCTIONS | LS | 1 | 27,000.00 | 27,000.00 | 9,000.00 | 9,000.00 | -66.67% | -153.70% | 0.52% | 26 | 34,500.00 | 34,500.00 | 25,000.00 | 25,000.00 | 26 | |||
| 27 | 0310-0109000A | REMOVAL OF BUILDINGS | LS | 1 | 40,000.00 | 40,000.00 | 24,000.00 | 24,000.00 | -40.00% | -29.86% | 1.40% | 27 | 54,500.00 | 54,500.00 | 15,000.00 | 15,000.00 | 27 | |||
| 28 | 0310-0119000F | ASPHALT PAVEMENT SAW CUTTING | FOOT | 1030 | 5.00 | 5,150.00 | 3.25 | 3,347.50 | -35.00% | -53.85% | 0.20% | 28 | 5.75 | 5,922.50 | 6.00 | 6,180.00 | 28 | |||
| 29 | 0320-0100000A | CLEARING AND GRUBBING | LS | 1 | 12,000.00 | 12,000.00 | 4,000.00 | 4,000.00 | -66.67% | -91.67% | 0.23% | 29 | 7,500.00 | 7,500.00 | 11,500.00 | 11,500.00 | 29 | |||
| 30 | 0330-0105000K | GENERAL EXCAVATION | CUYD | 793 | 60.00 | 47,580.00 | 70.00 | 55,510.00 | 16.67% | 7.14% | 3.24% | 30 | 45.00 | 35,685.00 | 80.00 | 63,440.00 | 30 | |||
| 31 | 0331-0109000J | 18 INCH SUBGRADE STABILIZATION | SQYD | 114 | 65.00 | 7,410.00 | 19.00 | 2,166.00 | -70.77% | -108.77% | 0.13% | 31 | 35.00 | 3,990.00 | 65.00 | 7,410.00 | 31 | |||
| 32 | 0350-0105000J | SUBGRADE GEOTEXTILE | SQYD | 946 | 2.00 | 1,892.00 | 1.69 | 1,598.74 | -15.50% | -7.30% | 0.09% | 32 | 2.25 | 2,128.50 | 1.50 | 1,419.00 | 32 | |||
| 33 | 0390-0119000K | GROUTED RIPRAP | CUYD | 190 | 20.00 | 3,800.00 | 65.00 | 12,350.00 | 225.00% | -7.69% | 0.72% | 33 | 95.00 | 18,050.00 | 50.00 | 9,500.00 | 33 | |||
| 34 | 0415-0100000F | MAINLINE VIDEO INSPECTION | FOOT | 331 | 5.00 | 1,655.00 | 9.00 | 2,979.00 | 80.00% | -62.96% | 0.17% | 34 | 22.00 | 7,282.00 | 13.00 | 4,303.00 | 34 | |||
| 35 | 0415-0400000E | SERVICE LINE LATERAL VIDEO INSPECTION | EACH | 1 | 750.00 | 750.00 | 275.00 | 275.00 | -63.33% | -151.52% | 0.02% | 35 | 1,500.00 | 1,500.00 | 300.00 | 300.00 | 35 | |||
| 36 | 0445-030006BF | 6 INCH SANITARY SEWER PIPE, 10 FT DEPTH | FOOT | 52 | 150.00 | 7,800.00 | 340.00 | 17,680.00 | 126.67% | 12.75% | 1.03% | 36 | 250.00 | 13,000.00 | 300.00 | 15,600.00 | 36 | |||
| 37 | 0445-035012AF | 12 INCH STORM SEWER PIPE, 5 FT DEPTH | FOOT | 331 | 130.00 | 43,030.00 | 175.00 | 57,925.00 | 34.62% | -14.29% | 3.38% | 37 | 145.00 | 47,995.00 | 280.00 | 92,680.00 | 37 | |||
| 38 | 0445 | 6 INCH STORM SEWER CLEANOUT | EACH | 1 | 500.00 | 500.00 | 1,275.00 | 1,275.00 | 155.00% | -6.54% | 0.07% | 38 | 1,800.00 | 1,800.00 | 1,000.00 | 1,000.00 | 38 | |||
| 39 | 0470-0101000E | CONCRETE STORM SEWER MANHOLES | EACH | 1 | 7,000.00 | 7,000.00 | 6,800.00 | 6,800.00 | -2.86% | -22.79% | 0.40% | 39 | 9,750.00 | 9,750.00 | 8,500.00 | 8,500.00 | 39 | |||
| 40 | 0470-0315000E | CONCRETE INLETS, TYPE GB-2 | EACH | 5 | 2,900.00 | 14,500.00 | 2,250.00 | 11,250.00 | -22.41% | -54.81% | 0.66% | 40 | 4,000.00 | 20,000.00 | 4,200.00 | 21,000.00 | 40 | |||
| 41 | 0490-0100000E | ADJUSTING BOXES | EACH | 2 | 500.00 | 1,000.00 | 320.00 | 640.00 | -36.00% | -42.71% | 0.04% | 41 | 850.00 | 1,700.00 | 200.00 | 400.00 | 41 | |||
| 42 | 0490-0102000E | ADJUSTING CATCH BASINS | EACH | 1 | 1,000.00 | 1,000.00 | 1,200.00 | 1,200.00 | 20.00% | -11.11% | 0.07% | 42 | 800.00 | 800.00 | 2,000.00 | 2,000.00 | 42 | |||
| 43 | 0490-0104000E | CONNECTION TO EXISTING STRUCTURES | EACH | 2 | 2,000.00 | 4,000.00 | 2,300.00 | 4,600.00 | 15.00% | -71.01% | 0.27% | 43 | 4,500.00 | 9,000.00 | 5,000.00 | 10,000.00 | 43 | |||
| 44 | 0490-0120000E | MINOR ADJUSTMENT OF MANHOLES | EACH | 4 | 1,500.00 | 6,000.00 | 2,400.00 | 9,600.00 | 60.00% | 19.44% | 0.56% | 44 | 2,000.00 | 8,000.00 | 1,400.00 | 5,600.00 | 44 | |||
| 45 | 0620-0123000J | COLD PLANE PAVEMENT REMOVAL, 4 INCHES DEEP | SQYD | 3363 | 7.00 | 23,541.00 | 6.50 | 21,859.50 | -7.14% | -41.03% | 1.27% | 45 | 8.00 | 26,904.00 | 13.00 | 43,719.00 | 45 | |||
| 46 | 0640-0100000M | AGGREGATE BASE | TON | 740 | 45.00 | 33,300.00 | 75.00 | 55,500.00 | 66.67% | 17.78% | 3.24% | 46 | 45.00 | 33,300.00 | 65.00 | 48,100.00 | 46 | |||
| 47 | 0295-0200000F | REMOVE ASBESTOS MATERIAL, FRIABLE | SQFT | 470 | 25.00 | 11,750.00 | 19.00 | 8,930.00 | -24.00% | 28.07% | 0.52% | 47 | 15.00 | 7,050.00 | 7.00 | 3,290.00 | 47 | |||
| 48 | 0744-0302000M | LEVEL 3, 1/2 INCH ACP MIXTURE | TON | 1052 | 125.00 | 131,500.00 | 130.00 | 136,760.00 | 4.00% | -1.28% | 7.98% | 48 | 135.00 | 142,020.00 | 130.00 | 136,760.00 | 48 | |||
| 49 | 0748-0103000J | 6 INCH ASPHALT CONCRETE PAVEMENT REPAIR | SQYD | 500 | 50.00 | 25,000.00 | 118.00 | 59,000.00 | 136.00% | 18.08% | 3.44% | 49 | 72.00 | 36,000.00 | 100.00 | 50,000.00 | 49 | |||
| 50 | 0749-0100000E | EXTRA FOR ASPHALT APPROACHES | EACH | 5 | 2,000.00 | 10,000.00 | 685.00 | 3,425.00 | -65.75% | -89.05% | 0.20% | 50 | 2,200.00 | 11,000.00 | 1,000.00 | 5,000.00 | 50 | |||
| 51 | 0759-0103000F | CONCRETE CURBS, CURB AND GUTTER | FOOT | 634 | 40.00 | 25,360.00 | 42.95 | 27,230.30 | 7.38% | -7.06% | 1.59% | 51 | 55.00 | 34,870.00 | 40.00 | 25,360.00 | 51 | |||
| 52 | 0759-0106000F | CONCRETE CURBS, LOW PROFILE MOUNTABLE CURB | FOOT | 18 | 50.00 | 900.00 | 69.00 | 1,242.00 | 38.00% | -13.04% | 0.07% | 52 | 95.00 | 1,710.00 | 70.00 | 1,260.00 | 52 | |||
| 53 | 0759-0110000F | CONCRETE CURBS, STANDARD CURB | FOOT | 304 | 45.00 | 13,680.00 | 45.00 | 13,680.00 | 0.00% | 11.11% | 0.80% | 53 | 35.00 | 10,640.00 | 40.00 | 12,160.00 | 53 | |||
| 54 | 0759-0122000J | CONCRETE ISLANDS | SQFT | 370 | 25.00 | 9,250.00 | 18.00 | 6,660.00 | -28.00% | -16.67% | 0.39% | 54 | 25.00 | 9,250.00 | 20.00 | 7,400.00 | 54 | |||
| 55 | 0759-0126000J | CONCRETE DRIVEWAYS | SQFT | 215 | 20.00 | 4,300.00 | 33.00 | 7,095.00 | 65.00% | 15.15% | 0.41% | 55 | 25.00 | 5,375.00 | 26.00 | 5,590.00 | 55 | |||
| 56 | 0759-0127000J | CONCRETE DRIVEWAYS, REINFORCED | SQFT | 730 | 30.00 | 21,900.00 | 35.00 | 25,550.00 | 16.67% | 13.33% | 1.49% | 56 | 30.00 | 21,900.00 | 26.00 | 18,980.00 | 56 | |||
| 57 | 0759-0128000J | CONCRETE WALKS | SQFT | 3280 | 11.00 | 36,080.00 | 14.00 | 45,920.00 | 27.27% | -2.38% | 2.68% | 57 | 15.00 | 49,200.00 | 14.00 | 45,920.00 | 57 | |||
| 58 | 0759-0154100E | EXTRA FOR NEW CURB RAMPS | EACH | 12 | 2,000.00 | 24,000.00 | 2,200.00 | 26,400.00 | 10.00% | 11.36% | 1.54% | 58 | 1,750.00 | 21,000.00 | 1,900.00 | 22,800.00 | 58 | |||
| 59 | 0759-0510000J | TRUNCATED DOMES ON NEW SURFACES | SQFT | 155 | 50.00 | 7,750.00 | 50.00 | 7,750.00 | 0.00% | 13.33% | 0.45% | 59 | 35.00 | 5,425.00 | 45.00 | 6,975.00 | 59 | |||
| 60 | 0855-0102100E | BI-DIRECTIONAL YELLOW TYPE I MARKERS | EACH | 89 | 15.00 | 1,335.00 | 9.50 | 845.50 | -36.67% | 5.26% | 0.05% | 60 | 9.00 | 801.00 | 8.50 | 756.50 | 60 | |||
| 61 | 0855-0102100E | BI-DIRECTIONAL WHITE TYPE I MARKERS | EACH | 33 | 15.00 | 495.00 | 9.50 | 313.50 | -36.67% | 5.26% | 0.02% | 61 | 9.00 | 297.00 | 8.50 | 280.50 | 61 | |||
| 62 | 0865-0160000F | THERMOPLASTIC, EXTRUDED OR SPRAYED, SURFACE, NON-PROFILED | FOOT | 6662 | 1.50 | 9,993.00 | 2.15 | 14,323.30 | 43.33% | 0.78% | 0.84% | 62 | 2.00 | 13,324.00 | 2.25 | 14,989.50 | 62 | |||
| 63 | 0867-0103500E | PAVEMENT LEGEND, TYPE AB: ARROWS | EACH | 6 | 375.00 | 2,250.00 | 415.00 | 2,490.00 | 10.67% | 2.41% | 0.15% | 63 | 400.00 | 2,400.00 | 400.00 | 2,400.00 | 63 | |||
| 64 | 0867-0131000E | PAVEMENT LEGEND, TYPE B-HS: BICYCLE LANE STENCIL | EACH | 6 | 350.00 | 2,100.00 | 415.00 | 2,490.00 | 18.57% | 2.41% | 0.15% | 64 | 400.00 | 2,400.00 | 400.00 | 2,400.00 | 64 | |||
| 65 | 0867-0145100J | PAVEMENT BAR, TYPE B-HS | SQFT | 604 | 15.00 | 9,060.00 | 21.00 | 12,684.00 | 40.00% | 4.76% | 0.74% | 65 | 19.00 | 11,476.00 | 20.00 | 12,080.00 | 65 | |||
| 66 | 0867-0174000E | PAVEMENT LEGEND, TYPE B-HS : BICYCLE DETECTOR STENCIL | EACH | 1 | 500.00 | 500.00 | 333.00 | 333.00 | -33.40% | 1.60% | 0.02% | 66 | 325.00 | 325.00 | 325.00 | 325.00 | 66 | |||
| 67 | 0868-0100000J | GREEN BICYCLE LANE, PREFORMED THERMOPLASTIC FILM | SQFT | 75 | 15.00 | 1,125.00 | 20.00 | 1,500.00 | 33.33% | 5.00% | 0.09% | 67 | 18.00 | 1,350.00 | 19.00 | 1,425.00 | 67 | |||
| 68 | 0902-0101000E | CROSSWALK CLOSURE SUPPORTS | EACH | 4 | 1,300.00 | 5,200.00 | 1,350.00 | 5,400.00 | 3.85% | 7.41% | 0.31% | 68 | 1,000.00 | 4,000.00 | 1,400.00 | 5,600.00 | 68 | |||
| 69 | 0905-0100000A | REMOVE EXISTING SIGNS | LS | 1 | 1,200.00 | 1,200.00 | 555.00 | 555.00 | -53.75% | 18.62% | 0.03% | 69 | 300.00 | 300.00 | 500.00 | 500.00 | 69 | |||
| 70 | 0920-0100000A | SIGN SUPPORT FOOTINGS | LS | 1 | 2,000.00 | 2,000.00 | 4,100.00 | 4,100.00 | 105.00% | -2.44% | 0.24% | 70 | 2,500.00 | 2,500.00 | 6,000.00 | 6,000.00 | 70 | |||
| 71 | 0930-0114000A | PERFORATED STEEL SQUARE TUBE SLIP BASE SIGN SUPPORTS | LS | 1 | 3,100.00 | 3,100.00 | 3,400.00 | 3,400.00 | 9.68% | -11.76% | 0.20% | 71 | 3,000.00 | 3,000.00 | 5,000.00 | 5,000.00 | 71 | |||
| 72 | 0930-0117000A | PERFORATED STEEL SQUARE TUBE ANCHOR SIGN SUPPORTS | LS | 1 | 1,000.00 | 1,000.00 | 525.00 | 525.00 | -47.50% | -133.33% | 0.03% | 72 | 1,250.00 | 1,250.00 | 1,900.00 | 1,900.00 | 72 | |||
| 73 | 0940-0201000J | SIGNS, STANDARD SHEETING, EXTRUDED ALUMINUM | SQFT | 88 | 35.00 | 3,080.00 | 29.00 | 2,552.00 | -17.14% | -10.92% | 0.15% | 73 | 30.00 | 2,640.00 | 37.50 | 3,300.00 | 73 | |||
| 74 | 0970-0100000A | POLE FOUNDATIONS | LS | 1 | 1,500.00 | 1,500.00 | 3,000.00 | 3,000.00 | 100.00% | -25.56% | 0.17% | 74 | 6,300.00 | 6,300.00 | 2,000.00 | 2,000.00 | 74 | |||
| 75 | 0970-0105000A | SWITCHING, CONDUIT, AND WIRING | LS | 1 | 3,700.00 | 3,700.00 | 7,500.00 | 7,500.00 | 102.70% | -36.67% | 0.44% | 75 | 8,250.00 | 8,250.00 | 15,000.00 | 15,000.00 | 75 | |||
| 76 | 0987-0100000A | TELECOMMUNICATIONS, MATERIAL | LS | 1 | 30,600.00 | 30,600.00 | 23,000.00 | 23,000.00 | -24.84% | 38.41% | 1.34% | 76 | 10,500.00 | 10,500.00 | 9,000.00 | 9,000.00 | 76 | |||
| 77 | 0987-0110000A | TELECOMMUNICATIONS, INSTALLATION | LS | 1 | 20,400.00 | 20,400.00 | 32,000.00 | 32,000.00 | 56.86% | -5.21% | 1.87% | 77 | 24,000.00 | 24,000.00 | 45,000.00 | 45,000.00 | 77 | |||
| 78 | 0990-0101000A | TRAFFIC SIGNAL INSTALLATION, JOHNSON CK BLVD & 79TH PL | LS | 1 | 506,000.00 | 506,000.00 | 447,000.00 | 447,000.00 | -11.66% | -1.64% | 26.07% | 78 | 476,000.00 | 476,000.00 | 440,000.00 | 440,000.00 | 78 | |||
| 79 | 1011-0200000A | BIORETENTION POND, WATER QUALITY FACILITY | LS | 1 | 46,000.00 | 46,000.00 | 58,000.00 | 58,000.00 | 26.09% | -6.03% | 3.38% | 79 | 61,500.00 | 61,500.00 | 65,000.00 | 65,000.00 | 79 | |||
| 80 | 1030-0108000R | PERMANENT SEEDING | ACRE | 0.12 | 20,000.00 | 2,400.00 | 13,000.00 | 1,560.00 | -35.00% | 2.56% | 0.09% | 80 | 12,500.00 | 1,500.00 | 12,500.00 | 1,500.00 | 80 | |||
| 81 | 1030-0118000e | WETLAND PLANTS, PLUGS | EACH | 1607 | 1.25 | 2,008.75 | 1.10 | 1,767.70 | -12.00% | -54.55% | 0.10% | 81 | 3.00 | 4,821.00 | 1.00 | 1,607.00 | 81 | |||
| 82 | 1040-0101000K | TOPSOIL | CUYD | 64 | 100.00 | 6,400.00 | 50.00 | 3,200.00 | -50.00% | 3.33% | 0.19% | 82 | 50.00 | 3,200.00 | 45.00 | 2,880.00 | 82 | |||
| 83 | 1040-0153000E | SHRUBS, #1 CONTAINER | EACH | 29 | 18.00 | 522.00 | 13.00 | 377.00 | -27.78% | -5.13% | 0.02% | 83 | 15.00 | 435.00 | 13.00 | 377.00 | 83 | |||
| 84 | 1040-0171000E | WETLAND PLANTS, #1 CONTAINER | EACH | 218 | 12.00 | 2,616.00 | 13.00 | 2,834.00 | 8.33% | -5.13% | 0.17% | 84 | 15.00 | 3,270.00 | 13.00 | 2,834.00 | 84 | |||
| 85 | 1040-0190000K | BARK MULCH | CUYD | 15 | 220.00 | 3,300.00 | 66.00 | 990.00 | -70.00% | 1.01% | 0.06% | 85 | 65.00 | 975.00 | 65.00 | 975.00 | 85 | |||
| 86 | 1050-0162000F | TYPE CL-4R CHAIN LINK FENCE WITH BLACK PVC COATING | FOOT | 85 | 60.00 | 5,100.00 | 80.00 | 6,800.00 | 33.33% | 29.17% | 0.40% | 86 | 45.00 | 3,825.00 | 45.00 | 3,825.00 | 86 | |||
| 87 | 1050-0162000F | TYPE CL-6R CHAIN LINK FENCE WITH BLACK PVC COATING AND SCREENING PICKETS | FOOT | 139 | 110.00 | 15,290.00 | 95.00 | 13,205.00 | -13.64% | 20.00% | 0.77% | 87 | 65.00 | 9,035.00 | 68.00 | 9,452.00 | 87 | |||
| 88 | 1050-0198000E | 12 FOOT X 48 INCH CHAIN LINK DOUBLE GATES | EACH | 1 | 3,500.00 | 3,500.00 | 3,100.00 | 3,100.00 | -11.43% | 15.05% | 0.18% | 88 | 2,400.00 | 2,400.00 | 2,400.00 | 2,400.00 | 88 | |||
| 89 | 1070-0100000E | SINGLE MAILBOX SUPPORTS | EACH | 2 | 1,200.00 | 2,400.00 | 1,335.00 | 2,670.00 | 11.25% | 22.97% | 0.16% | 89 | 750.00 | 1,500.00 | 1,000.00 | 2,000.00 | 89 | |||
| 90 | 1070-0102000E | MAILBOX CONCRETE COLLARS | EACH | 1 | 750.00 | 750.00 | 720.00 | 720.00 | -4.00% | 27.31% | 0.04% | 90 | 350.00 | 350.00 | 500.00 | 500.00 | 90 | |||
| 91 | 1070-0103000E | REMOVE AND REINSTALL MAILBOX SUPPORTS | EACH | 1 | 1,500.00 | 1,500.00 | 1,550.00 | 1,550.00 | 3.33% | 34.41% | 0.09% | 91 | 500.00 | 500.00 | 1,000.00 | 1,000.00 | 91 | |||
| 92 | 1170-0109000F | 1 INCH COPPER WATER SERVICE LINE | FOOT | 127 | 75.00 | 9,525.00 | 115.00 | 14,605.00 | 53.33% | 30.43% | 0.85% | 92 | 55.00 | 6,985.00 | 70.00 | 8,890.00 | 92 | |||
| 93 | 0280-0111020H | CONCRETE WASH OUT FACILITY | EACH | 1 | 1,500.00 | 1,500.00 | 3,700.00 | 3,700.00 | 146.67% | 36.94% | 0.22% | 93 | 1,500.00 | 1,500.00 | 1,800.00 | 1,800.00 | 93 | |||
| 1,645,052.75 | 1,714,494.04 | 4.22% | -4.90% | 100.00% | 1,833,291.00 | 1,847,677.50 |
| Engineers Estimate | Westech Construction | % OVR/UND. | % OVR/UND. | ITEM % OF | Corpac Construction | Moore Excavation | ||||
| 4.2% | Low Bidder | |||||||||
| to Engr. Estimate | 3 Lowest Bidders | |||||||||
| Average | Lowest Bid | |||||||||
| to Total Bid | 6.9% |