JUN 2026 Equipment Only Consolidation Schedule.pdf

PDF 211 KB Posted

Attached to
JUN 2026 Equipment Only Consolidation
Solicitation number
36A79726Q0011_1
Issued by

About this file

This document is a consolidation schedule for a June 2026 Equipment Only procurement managed by the NAC (National Acquisition Center). The schedule outlines the timeline for a Request for Offers (RFO) process applicable to all modalities, with key dates spanning from June 2026 through February 2027.

The procurement follows a structured timeline beginning with requirements submission to the NAC in FORCE by June 30, 2026, followed by publication of a Pre-Solicitation Notice on August 5, 2026, and posting of requirements and the RFO on August 12, 2026. Vendors have until August 26, 2026 to submit equipment-related questions to the NAC, with published responses provided via amendment by September 16, 2026. The offer submission deadline is October 14, 2026, after which customers receive vendor offers via shared drive on October 21, 2026 and submit technical evaluations and best value selections by November 12, 2026. The NAC assigns Contracting Officer (CO) workload on November 18, 2026, with a goal to award delivery orders by February 16, 2027, representing 90 days from CO assignment. All dates are noted as estimates subject to change.

View the file

Other files

File Type Posted
Memorandum for Training.pdf PDF
Vendor Workup Spreadsheet - 36A79726Q0011.xlsx XLSX spreadsheet
36A79726Q0011_1.docx DOCX document
VA Directive 6550 - New Appendix A - published Jun. 2023.pdf PDF
662B60031-757B60015.zip ZIP file
570B60012- 589B63022.zip ZIP file
402B61001-570B60011.zip ZIP file
Vendor Folders.zip ZIP file
JUN 2026 EQ Consolidation - RFO.pdf PDF
EQ JUN 2026 CONSOLIDATION - Schedule of Line Items with QA Template-.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JUN 2026 Equipment Only Consolidation Schedule

Dates* Milestone – All Modalities

6/30/2026 Requirements due to the NAC in FORCE

8/05/2026 Publish Pre-Solicitation Notice

8/12/2026 Post Requirements and Request for Offers (RFO)

8/26/2026 Vendors to submit Equipment Questions to NAC

9/16/2026 NAC Published Responses to Vendor Questions via Amendment

10/14/2026 Vendors to Submit Offers to NAC

10/21/2026 Customers Receive Vendor Offers via the Shared Drive

11/12/2026 Customers Submit Technical Evaluations (Best Value Selections)

11/18/2026 NAC Assigns CO Workload

2/16/2027 Goal to Award Delivery Orders (90 Days from Assignment)

*Dates are estimates and are subject to change

File details come from the government source that posted it. Updated .