The document is a Request for Proposals (RFP) issued by the Silverthorne Dillon Joint Sewer Authority (SDJSA) for a Participant EQR Inventory Audit in January 2025. The project involves auditing Equivalent Residential Units (EQRs) reported by five participants: the Towns of Dillon and Silverthorne, and the Districts of Buffalo Mountain, Dillon Valley, and Mesa Cortina. The audit will review existing documents, verify EQR assignments by comparing service address characteristics, and potentially conduct site visits for commercial or industrial properties. Proposers are required to submit detailed proposals by 3:00 P.M. on Wednesday, February 26th, 2025, with a projected contract award on Monday, April 11th, 2025, and project completion by Friday, May 27th, 2025.
The RFP requires proposers to provide comprehensive deliverables, including a preliminary and final report for each participant's service area, organized by residential and commercial/industrial service addresses. Proposers must submit detailed information including organizational background, references, project approach, personnel qualifications, and a fee schedule. The SDJSA will evaluate proposals based on completeness, proposer experience, personnel qualifications, and pricing. The selected firm must provide insurance coverage, including $2,000,000 in general liability and $1,000,000 in automobile liability, and obtain a Town of Silverthorne business license. The RFP emphasizes the need for an original work product and allows for potential oral interviews with up to three top-ranked proposers.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SDJSA EQR Audit Addendum #1.pdf | ||
| Exhibit F.pdf | ||
| SDJSA EQR Audit RFP Questions.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Silverthorne Dillon Joint Sewer Authority
Participant EQR Inventory Audit
REQUEST FOR PROPOSALS
January 2025
Silverthorne Dillon Joint Sewer Authority EQR Inventory Audit
Request for Proposals
Table of Contents
SECTION I: TERMS AND CONDITIONS
1. Invitation
2. Procurement Schedule
3. Form of Response
4. Selection Process
5. Inquiries
6. Addenda
7. Consideration of Proposals
8. Disclosure of Proposal Contents
9. Original Proposal
10. Investigation of Conditions
11. Withdrawal of Proposal
12. Single Proposal Response
13. Conflicts and Inconsistencies
14. Contract Award
15. News Releases
16. Cost of Proposal Preparation
SECTION II: SCOPE OF SERVICES
1. Background
2. Scope Description
3. Deliverable items
SECTION III: SUBMITTAL FORMS
1. PROPOSAL SUBMITTAL CHECKLIST
2. ATTACHMENT A
SECTION I: TERMS AND CONDITIONS
1. Invitation
Qualified individuals, firms or consortiums are invited to submit a proposal to the Silverthorne
Dillon Joint Sewer Authority (“hereinafter referred to as “SDJSA”) for professional services to
Audit the EQRs currently used by the SDJSA and its five participants, and to recommend changes to those values where discrepancies between recorded values and EQRs in use are found.
The purpose of this solicitation is to bind a competent, experienced professional into a formal
Agreement with the SDJSA to perform the work described in this Request for Proposals and the attachments hereto.
Proposers are cautioned to read the entire Request for Proposals, noting all submittal requirements, including both substance and format. Failure to provide all requested information in the manner required might be cause for rejection of the proposal at the sole discretion of the SDJSA.
This invitation should not be construed as a commitment of any kind on the part of the SDJSA, nor does it commit the SDJSA to pay for any costs incurred in the submission of a proposal package, nor for any costs incurred prior to the execution of a formal Agreement.
2. Procurement Schedule
To be considered, proposals must be received by the SDJSA as shown in the table below:
Advertise RFP Week of January 29th, 2025
Deadline for SDJSA’s response to Procedural and Technical
Questions
3:00 P.M. Wednesday, February 12th, 2025
RFP Due 3:00 P.M. Wednesday, February 26th, 2025
The Proposal shall be delivered via email, and clearly identified as such in the subject line, to the
SDJSA, care of the SDJSA Operations Superintendent, Jason Kruckeberg at jkruckeberg@silverthorne.org.
Any proposal received after that time shall not be considered. Prospective proposers are advised that the SDJSA shall make a good faith effort to adhere to the schedule shown in Section I.3, page five of this RFP, “Form of Response”.
However, SDJSA shall be under no obligation to comply with the schedules shown. All prospective proposers or other interested parties known to the SDJSA may be notified equally of changes made to this schedule by the SDJSA within a reasonable time after such changes are made.
In no event shall any proposer have any redress to the SDJSA, be it financial or otherwise, if the mailto:jkruckeberg@silverthorne.org
SDJSA alters this schedule in any way. Responsibility for submitting the proposal to the SDJSA on or before the above stated time shall remain solely and strictly that of the proposer. The SDJSA shall in no way be responsible for delays in the delivery of any proposal via email. The SDJSA shall not be responsible for premature opening of proposals that are not marked properly as described above.
3. Form of Response
This subsection contains detailed instructions to which proposers must adhere in the preparation and submittal of proposals to the SDJSA.
Proposal: The proposer shall provide a digital PDF format version of the proposal to SDJSA by the date and time shown in the above schedule unless otherwise notified by the SDJSA.
Proposers are advised that proposal content and completeness are most important, and that clear and effective presentations are preferred, with unnecessarily elaborate, decorative, or extraneous materials discouraged. Each section within the proposal shall be clearly labeled for easy reference.
The proposal shall contain the following information and attachments:
Cover Letter: Identify the proposer’s name; mailing address; telephone number and contact person(s). The letter must be signed by the proposer and must be limited to two (2) pages.
Consortiums, joint ventures, or teams submitting proposals, although permitted and encouraged, will not be considered unless it is established that all contractual responsibility rests solely with one firm or one legal entity, which shall not be a subsidiary or affiliate with limited resources; and the entity responsible for execution on behalf of the team shall be indicated.
Organizational Information: Provide a statement of the proposer’s corporate status and background, including but not necessarily limited to the following: Legal status; organizational structure; current list of Owners, officers, and principals; management philosophy; brief history;
type(s) of business conducted; business locations and facilities; customer base; and ability to obtain the required insurance. This must be limited to four (4) pages
References: List completed projects, preferably similar in nature, within the past (5) years. Include references from previous project Owners with names and telephone numbers.
List any other projects similar in size, preferably in Colorado, that have been performed by the proposer. Provide the following information for each reference:
Client Name: ______________________________________
Address: ______________________________________
Contact Person: __________________________Telephone: (___) _____________
Project Dates: _______________________________
Project Description ________________________________________________
Original Project Budget: ______________________________
Final Project Cost: ______________________________
Explanation of variation from original budget to final project cost:
Project Manager and Personnel: Describe the qualifications, experience, and availability of the proposer’s candidate for project manager. Proposers are advised that failure to provide and maintain the individuals selected as project manager and project superintendent as indicated in the proposal may constitute cause for cancellation of contract award or termination of any Agreement between the SDJSA and the proposer. Additionally, describe the key personnel who will contribute to the
Project, including project managers with appropriate expertise in related projects. Such descriptions shall include, but not necessarily be limited to name and job title, years of experience, qualifications, expertise, and availability. Include resumes. Include information on how the
Project Manager will communicate and relay information to the team, and how they may be proactive in collaboratively solving project issues.
Project Approach: Describe the approach that the proposer would take in completing the project to meet the SDJSA’s needs. Project approach should be concise. Processes and elements should be described in this section of the proposal. Any other creative or innovative ideas should be described in this section.
Project Schedule: The proposer shall provide an estimated schedule that includes constraints, critical issues, meeting dates, review periods and delivery. The proposer should provide a schedule that they can realistically accomplish with the goal of completing the project by schedule below. If the proposer is not able to meet the following schedule, then an alternate schedule may be proposed with an explanation as to why it was necessary.
Below is a list of approximate milestone dates developed by the SDJSA.
Award Contract Monday, April 11th, 2025
Sign and Execute Contract Thursday, April 28th, 2025
Present Preliminary Report Wednesday, May 25th, 2025
Complete Contract, Present Final
Report
Friday, May 27th, 2025
Fee Schedule: Proposal shall include a fee for each task described in Section II “Scope of
Services”.
The Proposer shall identify any other required services and associated costs not included above that the Proposer believes are necessary to successfully complete the project.
The Proposer shall identify and recommend any Additional Related Services available and their associated costs.
Each proposer shall certify that its price proposal shall remain valid for a period of at least one hundred and twenty (120) days. In the event that a contract award by the SDJSA is delayed beyond the 120-day period, any such award shall be conditioned upon the proposer's acceptance.
Financial Information: Provide a statement of the proposer’s financial condition relative to the performance of this Project, specifically addressing ability to finance and maintain cash flow during the Project. The SDJSA may require the proposer to provide additional information to satisfy this requirement.
Statement of Insurance: The Proposer must provide the minimum insurance coverage levels as shown below and give evidence of same with copies of certificate(s) of insurance or letter(s) of intent to provide insurance from competent provider(s) doing business in the State of Colorado with an “A” rating as shown in the most recent edition of “Best’s Insurance Reports.”
o Worker's Compensation insurance to cover obligations imposed by applicable laws for any employee of Proposer or a sub-consultant engaged in the performance of work under this
Agreement. Evidence of qualified self-insured status may be substituted for the Workmen's
Compensation requirements of this Paragraph.
o General Liability insurance with minimum combined single limits of $2,000,000. The policy shall be applicable to all premises and operations. The policy shall include coverage for bodily injury, broad form property damage (including completed operations), personal injury (including coverage for contractual and employees' acts), blanket contractual, products, and completed operations. The policy shall contain a “severability of interests” provision.
o Comprehensive Automobile Liability insurance with minimum combined single limits for bodily injury and property damage of not less than $1,000,000 each occurrence and
$1,000,000 aggregate with respect to each of Consultant's owned, hired, or non-owned vehicles assigned to or used in performance of this Agreement. The policy shall contain a
“severability of interests” provisions.
Qualifications and Requirements:
1. The proposer must obtain a Town of Silverthorne business license prior to starting work on this project.
Attachment A: Acknowledgment of Receipt of RFP Packet, and Addenda: This form must be completed and signed by the proposer and attached to the proposal.
In the event the proposer intends to borrow any funds to finance any portion of the work pertaining to the Project, a letter of intent from the bank or other lending agency must be attached, indicating the minimum amount which will be loaned and the applicable percentage rate of interest to be charged. The letter of intent may contain the qualification that the loan will only be consummated upon award of a contract by the SDJSA.
Proposer may request in their proposal that any financial information submitted to establish the financial capability, price proposal, overhead rates, and other aspects of the proposer’s fiscal condition shall be handled as confidential data and utilized on a "need-to-know" basis for proposal evaluation. The SDJSA shall then make reasonable efforts to avoid disclosure to parties unrelated to the proposal evaluation process.
Any proposal not submitted in this format shall be deemed to be non-responsive and shall not be considered further by the SDJSA. The signer of the proposal must declare that the only person(s), company or parties interested in the contract as principals are named herein; that it is, in all respects, fair and in good faith without collusion or fraud; and that the signer of the proposal has the authority to bind the principal Proposer.
4. Selection Process
Each responsive proposal received by the SDJSA shall be evaluated in a consistent manner as described in this subsection. A responsive proposal is one that complies with all material aspects of the solicitation, both as to the method and timeliness of submission, and as to the substance of any resulting contract. Prospective proposers are required to submit all required forms, attachments, insurance certificates, and other information as required in the RFP.
SDJSA will review all responsive proposals. The proposals will be evaluated based on completeness, experience of proposer at this type of work, personnel proposed to work on the job, fee price and structure.
The SDJSA may identify up to three (3) proposers who are considered to be best qualified to perform the work required by the SDJSA, that may be invited to participate in oral interviews for the purpose of clarifying and confirming offerings and assertions made in the proposals.
The SDJSA reserves the right to delay making an award, as may be necessary to permit proper study and analysis of all proposals received, or to split award on proposals, or to reject any or all proposals received, and to make a pre-award survey to determine the capability of any or all proposers. The SDJSA reserves the right to reject any or all proposals and to negotiate matters of
Proposer performance, project schedule and other issues not directly related to the proposal price submitted prior to awarding a contract. The SDJSA further reserves the right to cancel the procurement process at any time during the evaluation process for any reason whatsoever.
5. Inquiries
Proposers may make inquiries in writing to SDJSA at any time prior to Wednesday, February
15th, 2025, 3:00 p.m. Any written question from a proposer regarding the meaning or interpretation of the RFP, work scope, etc., must be submitted to the SDJSA prior to the above-specified date. All clarifications given to any prospective proposer shall be similarly furnished to all prospective proposers in summary form as an addendum. No technical assistance shall be given by the SDJSA to any Proposer in preparation of its proposal.
Written inquiries shall only be directed to:
Jason Kruckeberg
Silverthorne Dillon Joint Sewer Authority jkruckeberg@silverthorne.org
P.O. Box 1309
Silverthorne, CO 80498
6. Addenda
Any or all changes, additions, or clarifications in connection with this RFP shall be issued by the
SDJSA in the form of written addenda. Each proposer must sign the “Acknowledgment of
Receipt of RFP Addenda” form (Attachment B) and submit the executed form with its proposal.
Oral comments, responses and/or representations shall not be binding upon the SDJSA.
7. Consideration of Proposals
The SDJSA reserves all rights to investigate the qualifications of all individuals and firms under consideration; to perform a financial audit of one or more firms; to confirm any part of the information furnished in a proposal, and to require further evidence of managerial, financial, or professional capabilities which are considered necessary for the successful performance of work described in this RFP. The SDJSA reserves the right to reject any or all proposals and to waive minor irregularities in proposals received.
8. Disclosure of Proposal Contents
All proposals and supporting documents, except such information that discloses proprietary or financial information submitted in response to qualification statements, becomes public information held in custody of the SDJSA after the proposal submittal date given in this RFP. The
SDJSA assumes no liability for the use or disclosure of technical or cost data submitted by any proposer.
However, if a proposal contains information that the respondent does not want disclosed to the public, or used for any purpose other than the evaluation of this offer, all such information must be indicated with the following or similar statement:
"The information contained on pages [indicate which pages] shall not be duplicated, used in whole or in part for any purpose other than to evaluate the proposal provided except that if a contract is awarded to this firm as a result of the submission of such information, the SDJSA shall have the right to duplicate, use or disclose this information to the extent provided in the contract. This restriction does not limit the
SDJSA’s right to use the information contained herein if also obtained from another source."
mailto:jkruckeberg@silverthorne.org
All such nondisclosure items specified in the proposal shall be subject to disclosure as provided in
Part 2 of Article 72 of Title 24, C.R.S. ("The Colorado Public Records Act") or as otherwise provided by law.
9. Original Proposal
The successful proposal must be an original work product of the submitting individual, firm, or team. Copying, paraphrasing, or otherwise using significant portions of the work product of another organization when presenting a proposal to the SDJSA shall not be permitted. Failure to adhere to this instruction may result in the rejection of the proposal.
10. Investigation of Conditions
All proposers are encouraged to review this RFP carefully and to investigate all conditions involved in the execution of work. The selected firm shall not be allowed additional compensation for items on which it has failed to inform itself prior to the opening of proposals.
11. Withdrawal of Proposal
After the time that proposals are due as prescribed herein, no proposal may be withdrawn for a period of one hundred and twenty (120) calendar days. Negligence on the part of a proposer in preparing its proposal shall not confer a right of withdrawal after the date proposals are due and received by the SDJSA.
12. Single Proposal Response
In the event that only one (1) proposal is received in response to this RFP, the SDJSA may require assistance from this single responsive and responsible proposer in the preparation of a proposal price analysis in order to determine whether the single proposal received by the SDJSA is fair and reasonable.
13. Conflicts and Inconsistencies
In the event of a conflict or inconsistency between any portions of the RFP and attachments, including drawings, specifications, is found prior to the date proposals are due, the SDJSA shall resolve such conflict or inconsistency and provide written notice of the single interpretation to all known proposers by written addendum.
14. Contract Award
The SDJSA maintains the right, but shall be under no obligation, to award a contract to the responsive and responsible proposer whose offer is deemed by the SDJSA to be most advantageous to the SDJSA as determined by capability, qualifications, and other factors set forth herein.
Proposers are hereby advised that contract award is subject to approval by a resolution of the
Silverthorne Town Council acting as the Governing Board of the Lead Agency for the Silverthorne
Dillon Joint Sewer Authority.
15. News Releases
Written approval by the SDJSA is required prior to any public disclosure regarding this RFP or any subsequent awards.
16. Cost of Proposal Preparation
The SDJSA shall not be liable for any costs or expenses incurred for the preparation of proposals submitted in response to this RFP or for any other cost incurred prior to execution of a formal agreement. Proposers shall not include such expenses as part of the price proposed. The SDJSA shall be held harmless and free from all liability, claims or expenses whatsoever incurred by, or on behalf of, any person or organization responding to this RFP.
SECTION II: SCOPE OF SERVICES
1. Background
The Silverthorne Dillon Joint Sewer Authority was established in 1971 between five
Participants: the Towns of Dillon and Silverthorne, and the Districts of Buffalo Mountain, Dillon
Valley, and Mesa Cortina. The Joint Authority Agreement uses an EQR definition to quantify usage of the SDJSA assets and establish fair billing to the Participants for wholesale wastewater conveyance and treatment services. While the defining parameters of an EQR are subject to revision, the application of an EQR to a use or property remains consistent as described in
Schedule F. A periodic review and inventory audit of EQRs reported by Participants to the
SDJSA and Lead Agency by a Third Party has been used to verify proper billing and capacity allotments of the SDJSA facilities and assets by the Participants.
2. Scope Description
1. Audit EQRs reported in use by reviewing existing documents available online and as may be available through the SDJSA or Participants. Resources may include billing lists provided by Participants to the Auditor for the purpose of establishing EQR assignments, public records that indicate characteristics of properties that define EQRs in use, e.g. data from the Summit County Assessor’s Office, and previous audits. Residential EQRs are to be audited by comparison of service address bed/bath counts to data recorded by the
Summit County Assessor. Commercial or Industrial EQRs may require site visits if records are incomplete. Identify discrepancies between recorded EQRs and Audited
EQRs based on data review.
2. Meetings with Staff. The proposer shall meet with JSA staff as necessary to provide a comprehensive report with recommendations and data. The proposals shall include the estimated number of meetings that the proposer thinks are needed to provide a comprehensive report.
3. Review and evaluate existing EQR assignments in Schedule F. Identify and propose EQR assignments for uses discovered by audit but not specified in Schedule F.
3. Deliverable items
1. Preliminary Report – This deliverable is a draft report that includes the initial findings and recommendations along with all the supporting data associated with the study to date.
Each Participant shall have an individual report for its service area organized in sections by service address type: Residential, or Commercial/Industrial. Submittals shall be searchable electronic format, either MS Office Suite or OCR compatible PDF.
2. Final Report - This deliverable is a final report that includes all the final findings and recommendations along with all the supporting data associated with the study. This report will include any changes and/or edits resulting from the review of the Preliminary
Report.
SECTION III: SUBMITTAL FORMS
1. PROPOSAL SUBMITTAL CHECKLIST
This form must be completed and returned with the proposal submittal.
Attachment Description Initials
Cover Letter (signed)
Organizational Information
References
Project Management and Personnel
Project Approach
Project Schedule
Fee Schedule
Financial Information
Statement of Insurance
Qualifications and Requirements
Acknowledgment of Receipt of RFP Packet and Addenda
Printed Name
Title of Proposer
Signature
Date:
2. ATTACHMENT A
ACKNOWLEDGMENT OF RECEIPT OF RFP PACKET AND ADDENDA
The undersigned hereby acknowledges receipt of the Silverthorne Dillon Joint Sewer Authority
Request for Proposals (RFP) packet, and the following addenda issued during the procurement process.
Addendum #1: ______________________________________ dated ___________
Addendum #2: ______________________________________ dated ___________
Addendum #3: ______________________________________ dated __________
Failure to acknowledge receipt of the proposal packet below, and all addenda may cause the proposal to be considered non-responsive to this solicitation.
Name of Proposer: _______________________________
Signature of Proposer:_______________________________
Date: ___________________________________