This is a Draft Specifications document prepared for the State of Rhode Island Department of Behavioral Healthcare, Developmental Disabilities and Hospitals (BHDDH) for the demolition of a former group residential building located at 22 Tartaglia Street in Johnston, Rhode Island. The project involves the complete demolition of an existing 3,200 square foot wood-framed structure and basement, with the footprint to be infilled and stabilized with temporary vegetation. The scope of work includes site demolition, structure removal, grading, erosion and sediment control, and protection of existing trees and vegetation. A pre-bid site visit is scheduled for October 16, 2026, at 12:00 PM EST at the project location. The contract is structured as a single prime contract with the contractor responsible for all necessary permitting and demolition activities.

The specifications establish comprehensive requirements for contractor qualifications, quality assurance and quality control procedures, temporary facilities and site management, environmental protection, and tree preservation. An asbestos determination survey completed on April 6, 2026, identified 26 suspect building materials represented by 52 bulk samples, all of which tested as non-asbestos containing. The contract documents incorporate applicable Rhode Island Building Code provisions, fire safety codes, and standards from organizations including ASTM, NFPA, and ICC. The contractor must comply with work hour restrictions (7:00 AM to 6:00 PM, Monday through Friday), maintain site security and erosion controls, provide temporary facilities including sanitary facilities, and submit payment applications with waivers of mechanic's lien as required. Project completion is anticipated with establishment of temporary vegetation and site stabilization following demolition.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

State of RI BHDDH

Johnston Group Home

Demolition Project

Draft Specifications May 1, 2026

PREPARED FOR:

Bristol Studio

412A Thames Street

Bristol RI, 02809

TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DOCUMENT 003126 - ASBESTOS DETERMINATION SURVEY

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 011000 - SUMMARY

SECTION 012900 - PAYMENT PROCEDURES

SECTION 014000 - QUALITY REQUIREMENTS

SECTION 014200 - REFERENCES

SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS

SECTION 015639 - TEMPORARY TREE AND PLANT PROTECTION

DIVISION 02 - EXISTING CONDITIONS

SECTION 024116 - STRUCTURE DEMOLITION

DIVISION 31 – EARTHWORK

SECTION 312213 - SITE GRADING

SECTION 312513 - EROSION AND SEDIMENT CONTROL

END OF TABLE OF CONTENTS

Draft Specifications State of RI BHDDH

Demolition Package

EXISTING HAZARDOUS MATERIAL

INFORMATION

003126 - 1

DOCUMENT 003126 - ASBESTOS DETERMINATION SURVEY

PART 1 - GENERAL

1.1 ASBESTOS DETERMINATION SURVEY

A. This Document with its referenced attachments is part of the Procurement and Contracting

Requirements for the Project. They provide Owner's information for Bidders' convenience and are intended to supplement rather than serve in lieu of Bidders' own investigations. They are made available for Bidders' convenience and information. This Document and its attachments are not part of the Contract Documents.

B. A survey and report for this Project titled “Asbestos Determination Survey”, prepared by

Brendon Cooney – MAC Services, dated April 6, 2026, is available for viewing as appended to this Document.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF DOCUMENT 003126

ASBESTOS DETERMINATION SURVEY

Conducted At:

Group Residential Building

22 Tartaglia Street

Johnston, RI 02919

Prepared For:

GMIarchitects – Bristol Studio

412A Thames Street

Briston, RI 02809

Attention: Damara Toohey

Prepared By:

Brendon Cooney – MA AI900689

MAC Services

21 Mill Pond Drive

Rochester, MA 02770

Reviewed By:

Joseph Cooney – RI AI00829

April 6, 2026

Asbestos Determination Survey

Table of Contents:

Page

Project Summary 3

Section I

A. Scope of Work 3-4

B. Description of Survey 4-5

Section II

Bulk Sample Analytical Summary 5

Tables

List of Tables: 5

Table 1: Suspect Building Materials 6-8

BULK Asbestos Sample Analytical Data 9-29

PROJECT SUMMARY

On March 23rd, 2026, MAC Services (MAC) conducted a limited asbestos determination survey for all accessible materials from the group residential building located at 22 Tartaglia Street in Johnston, RI.

The intent of the inspection was to conduct a NESHAP demolition inspection.

The survey focused on all suspected homogenous building materials. In total, there were fifty-two, (52), samples obtained representing twenty-six, (26), suspect building materials. All suspect building material samples collected were determined to be NON-asbestos containing. All sampled materials suspected of containing asbestos are listed in Table 1.

If during the renovation process any suspect looking materials not listed in this report are uncovered from layers below the surface of floors, walls and ceilings by demolition personnel, they must stop all activity around the uncovered material until it is determined if that suspect material is asbestos. MAC

Services is not responsible for any hidden or concealed items or building materials.

SECTION I

Section one of this report details the survey methodology and scope of investigation.

A. SCOPE OF WORK

The space specified for Asbestos Containing Building Material (ACBM) determination was inspected by

Massachusetts Licensed Inspector, Joseph Cooney, (AI000187), collected bulk samples, assessed the physical condition of the materials suspected of being asbestos containing, and completed the field survey forms. The inspector is experienced and has conducted previous asbestos surveys, specifications, asbestos air sample analysis, and monitoring as well as reporting of asbestos repair and removal projects.

Standardized forms were used to gather data, including chain of custody records to accompany samples to the laboratory.

Samples were collected adhering to AHERA regulations and guidelines which dictates that multiple samples per suspect material must be obtained depending on the material type and existing homogenous quantity, with each separate homogenous area of material sampled. Materials are broken down into three separate categories described as follows:

Surfacing Material (SM): is defined as material that is sprayed on, troweled on, or otherwise permanently applied to surfaces, such as acoustical plaster on ceilings, and fireproofing materials on structural members, or other materials on surfaces for acoustical, fireproofing, or other purposes.

Thermal System Insulation (TSI): are materials applied to pipes, fittings, boilers, breaching, tanks, ducts, or interior structural components to prevent heat loss or water condensation, or for other purposes.

Miscellaneous Material (MM): are interior and exterior building material on structural components, structural members or fixtures, such as floor and ceiling tiles, and vinyl sheeting and does not include surfacing material or thermal systems insulation.

Some definitions of terms are as follows:

A homogeneous material is a surfacing material, thermal system insulation material, or miscellaneous material that is uniform in color and texture.

A friable material is one which, when dry, may be crumbled, pulverized, or reduced to powder by hand pressure.

Non-friable materials typically contain bonding agents (e.g., cement, plastics, asphalt, and glue) that lock the asbestos fibers into the product. The inspector identified all visible flooring material that could potentially contain asbestos.

ACBM is an Asbestos Containing Building Material

AHERA stands for Asbestos Hazard Emergency Response Act

B. SAMPLING SURVEY

MAC has developed standard procedures to be used in order to randomly sample each material suspected of being asbestos containing. In order to classify any homogeneous material as a non-asbestos containing building material, a sufficient number of samples are collected and analyzed. All samples analyzed must show the lack of asbestos content (less than one percent asbestos) in order to be considered non-asbestos containing. If a material has trace amounts of asbestos (less than 1%) the material is not considered

‘Asbestos Containing’ and therefore, doesn’t have to be removed as asbestos containing, however, it must still be disposed of as asbestos containing.

Samples were taken and logged in on a chain of custody form and delivered to Asbestos Identification

Laboratory of Woburn, MA for analysis. The bulk samples were analyzed by polarized light microscopy

(PLM) (EPA Interim Method: Appendix A of Subpart F-40 CFR Part 763 and/or EPA 600/R-93/116).

Asbestos Identification Lab is licensed by the Commonwealth of Massachusetts (#AA 000208) for bulk asbestos analysis and is a NVLAP accredited laboratory.

CLASSIFICATION OF MATERIAL CONDITION

Where applicable, all identified asbestos containing material is classified as to physical condition as follows:

GOOD (G):

Asbestos containing building material in good condition at the time of the survey was whole and complete and typical of newer installation.

DAMAGED (D):

Asbestos containing building material in damaged condition at the time of the survey was generally complete but showed some signs of damage or deterioration. Material is classified as damaged when the damage or deterioration covers less than one tenth of the material's surface and is evenly distributed, or when it covers less than one quarter of the material's surface and is localized. This material typically needs attention but does not constitute emergency removal.

SIGNIFICANTLY DAMAGED (SD):

Asbestos containing building material is determined to be significantly damaged when at the time of the survey, the material was damaged or deteriorated, often with pieces missing. A material is classified as significantly damaged when the damage/deterioration covers more than one tenth of the material's surface and is evenly distributed, or when it covers more than one quarter of the material’s surface and is localized.

SECTION II

ANALYTICAL DATA

Fifty-two, (52), samples of materials suspected to be asbestos containing were collected and analyzed.

Analytical Data is presented on the following pages. All sampled materials suspected of containing asbestos are identified in Table 1. Twenty-six, (26), materials, represented by fifty-two, (52), samples obtained were determined to be non-asbestos containing. Multiple samples of each suspect material are required per the AHERA regulations.

Table 1:

"Suspect Homogeneous Building Materials", lists all building materials related to the planned renovations/demolition, suspected of containing asbestos. Asbestos containing materials are divided into the three categories established by the U.S. Environmental Protection Agency under the Asbestos Hazard

Emergency Response Act (AHERA): Thermal Systems Insulation (TSI) Surfacing Material (SM), and

Miscellaneous Material (MM). Each material is identified by the appropriate two-letter prefix.

TABLE 1

SUSPECT ASBESTOS CONTAINING BUILDING MATERIALS SAMPLED

Sample Field

ID

Description Location Color Material

Type

01A Textured Plaster Dining Area Ceiling White SM

01B Textured Plaster Basement Main Area Ceiling White SM

02A Gypsum Board Dining Area Ceiling Off White M

02B Gypsum Board Basement Storage Room Wall Off White MM

03A White Skim Coat

Plaster

Dining Area Wall White SM

03B White Skim Coat

Plaster

Basement Storage Room Wall White SM

04A Tan Stone Pattern

Linoleum

Kitchen Multi MM

04B Tan Stone Pattern

Linoleum

Hall at Exit Multi MM

05A Glue with 04A Kitchen Tan MM

05B Glue with 04B Hall at Exit Tan MM

06A 12”x12” Brown

Speck Pattern Floor

Tile

Bedroom next to Stairwell Light

Brown

MM

06B 12”x12” Brown

Speck Pattern Floor

Tile

Bedroom next to Stairwell Light

Brown

MM

07A Mastic with 06A Bedroom next to Stairwell Tan MM

07B Mastic with 06B Bedroom next to Stairwell Tan MM

08A 4” Brown Cove Base Bathroom near Stairwell Light

Brown

MM

08B 4” Brown Cove Base Bathroom near Stairwell Light

Brown

MM

09A Mastic with 08A Bathroom near Stairwell Tan MM

09B Mastic with 08B Bathroom near Stairwell Tan MM

10A 6”x6” Ceramic Tile

Grout

Bathroom next to Kitchen White MM

10B 6”x6” Ceramic Tile

Grout

Bathroom next to Kitchen White MM

11A 6”x6” Ceramic Tile

Glue

Bathroom next to Kitchen Off White MM

Description Location Color Material

Type

11B 6”x6” Ceramic Tile

Glue

Bathroom next to Kitchen Off White MM

12A 2”x6” White Ceramic

Tile Grout

Kitchen White MM

12B 2”x6” White Ceramic

Tile Grout

Kitchen White MM

13A 2”x6” White Ceramic

Tile Glue

Kitchen Off White MM

13B 2”x6” White Ceramic

Tile Glue

Kitchen Off White MM

14A Light Tan Stone

Pattern Linoleum

Corner Bedroom near Kitchen Multi MM

14B Light Tan Stone

Pattern Linoleum

Corner Bedroom near Kitchen Multi MM

15A Glue with 14A Corner Bedroom near Kitchen Grey MM

15B Glue with 14B Corner Bedroom near Kitchen MM

16A Brown Speck Pattern

Linoleum

Bedroom Across from (2) Bathrooms Multi MM

16B Brown Speck Pattern

Linoleum

Bedroom Across from (2) Bathrooms Multi MM

17A Glue with 16A Bedroom Across from (2) Bathrooms Tan MM

17B Glue with 16B Bedroom Across from (2) Bathrooms Tan MM

18A 4”x4” Ceramic Tile

Grout

Bathroom near Driveway Side Exit White MM

18B 4”x4” Ceramic Tile

Grout

Bathroom near Driveway Side Exit White MM

19A 4”x4” Ceramic Tile

Glue

Bathroom near Driveway Side Exit Tan MM

19B 4”x4” Ceramic Tile

Glue

Bathroom near Driveway Side Exit Tan MM

20A 1”x1” Ceramic Tile

Grout

Bathroom near Driveway Side Exit Grey MM

20B 1”x1” Ceramic Tile

Grout

Bathroom near Driveway Side Exit Grey MM

21A 1”x1” Ceramic Tile

Glue

Bathroom near Driveway Side Exit Grey MM

Description Location Color Material

Type

21B 1”x1” Ceramic Tile

Glue

Bathroom near Driveway Side Exit Grey MM

22A Carpet Glue Hall near Kitchen Tan MM

22B Carpet Glue Hall near Kitchen Tan MM

23A Epoxy Flooring Bathroom near Stairwell Multi MM

23B Epoxy Flooring Bathroom near Kitchen Multi MM

24A Grey Asphalt Roof

Shingle

Exterior – Roof at Front Black MM

24B Grey Asphalt Roof

Shingle

Exterior – Roof at Front Black MM

25A Black Tar Paper Exterior – Roof at Front Black MM

25B Black Tar Paper Exterior – Roof at Front Black MM

26A Black Vapor Barrier

Sheeting

Exterior – Behind Vinyl Siding at Rear

Corner

Black MM

26B Black Vapor Barrier

Sheeting

Exterior – Behind Vinyl Siding at Rear

Corner

Black MM

BULK ASBESTOS SAMPLE ANALYTICAL DATA

SUMMARY 011000 - 1

SECTION 011000 - SUMMARY

1.1 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Contractor's use of site and premises.

4. Work restrictions.

5. Specification and Drawing conventions.

6. Miscellaneous provisions.

B. Related Requirements:

1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

2. Section 015639 "Temporary Tree and Plant Protection" for protection of existing trees and plants on the project site.

1.2 DEFINITIONS

A. Work Package: A group of specifications, drawings, and schedules prepared by the design team to describe a portion of the Project Work for pricing, permitting, and construction.

1.3 PROJECT INFORMATION

A. Project Identification: State of Rhode Island BHDDH Group Home Demolition.

1. Project Location: 22 Tartaglia Street, Johnston, Rhode Island 02919.

2. Project Number: GMI# 25122.2

B. Owner: State of Rhode Island.

1. Owner's Representative: Jacob Lautman, Project Engineer.

C. Architect: GMI Architects.

1. Architect's Representative: Damara S. Toohey.

D. Contractor: To be determined.

SUMMARY 011000 - 2

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following:

1. Demolition of existing 3,200 sf wood-framed structure and basement and associated site elements. Footprint to be infilled as described in Civil Drawings. Existing trees and associated vegetation to be protected and maintained during demolition as described in

Civil Drawings.

2. Type of Contract: Building will be demolished under a single prime contract.

1.5 CONTRACTOR'S USE OF SITE AND PREMISES

A. Unrestricted Use of Site: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.

B. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1.6 WORK RESTRICTIONS

A. Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work to between 7:00 a.m. to 6:00 p.m., Monday through Friday, unless otherwise indicated. Work hours may be modified to meet Project requirements if approved by Owner and authorities having jurisdiction.

1. Weekend Hours: Same as week day hours.

C. Smoking and Controlled Substance Restrictions: Use of tobacco products , alcoholic beverages, and other controlled substances on Project site is not permitted.

D. Employee Identification: Provide identification tags for Contractor personnel working on

Project site. Require personnel to use identification tags at all times.

1.7 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

SUMMARY 011000 - 3

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.

3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.

4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 00 Contracting Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.

C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

D. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations scheduled on

Drawings and published as part of the U.S. National CAD Standard.

3. Keynoting: Materials and products are identified by reference keynotes referencing

Specification Section numbers found in this Project Manual.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

SECTION 012900 - PAYMENT PROCEDURES

1.1 SUMMARY

A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.

1.2 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of

Contractor's construction schedule.

1. Coordinate line items in the schedule of values with items required to be indicated as separate activities in Contractor's construction schedule.

2. Submit the schedule of values to Architect through Construction Manager at earliest possible date, but no later than seven days before the date scheduled for submittal of initial Applications for Payment.

B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification

Section.

1. Arrange schedule of values consistent with format of AIA Document G703.

2. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Provide multiple line items for principal subcontract amounts in excess of five percent of the

Contract Sum.

3. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

a. Differentiate between items stored on-site and items stored off-site.

4. Overhead Costs: Include total cost and proportionate share of general overhead and profit for each line item.

5. Schedule of Values Revisions: Revise the schedule of values when Change

Orders or Construction Change Directives result in a change in the Contract Sum.

Include at least one separate line item for each Change Order and Construction

Change Directive.

1.3 APPLICATIONS FOR PAYMENT

A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Architect and

Construction Manager and paid for by Owner.

B. Payment Application Times: The date for each progress payment is indicated in the

Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.

C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as form for Applications for Payment.

D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Construction

Manager will return incomplete applications without action.

1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.

2. Include amounts for work completed following previous Application for

Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.

3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

E. Transmittal: Submit three signed and notarized original copies of each Application for

Payment to Construction Manager by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

F. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from entities lawfully entitled to file a mechanic's lien arising out of the

Contract and related to the Work covered by the payment.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.

2. When an application shows completion of an item, submit conditional final or full waivers.

3. Owner reserves the right to designate which entities involved in the Work must submit waivers.

4. Submit final Application for Payment with or preceded by conditional final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.

5. Waiver Forms: Submit executed waivers of lien on forms acceptable to Owner.

G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule (preliminary if not final).

4. Products list (preliminary if not final).

5. Sustainable design action plans, including preliminary project materials cost data.

6. Schedule of unit prices.

7. Submittal schedule (preliminary if not final).

8. List of Contractor's staff assignments.

9. List of Contractor's principal consultants.

10. Copies of building permits.

11. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

12. Initial progress report.

13. Report of preconstruction conference.

14. Certificates of insurance and insurance policies.

15. Performance and payment bonds.

16. Data needed to acquire Owner's insurance.

H. Application for Payment at Substantial Completion: After Architect issues the

Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

I. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. AIA Document G706.

5. AIA Document G706A.

6. AIA Document G707.

7. Evidence that claims have been settled.

8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.

9. Final liquidated damages settlement statement.

PART 2 - PRODUCTS (Not Used)

PART 3 - PART 3 - EXECUTION (Not Used)

END OF SECTION

SECTION 014000 - QUALITY REQUIREMENTS

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for quality assurance and quality control.

B. Testing and inspection services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.

1. Specific quality-assurance and quality-control requirements for individual work results are specified in their respective Specification Sections. Requirements in individual Sections may also cover production of standard products.

2. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and quality-control procedures that facilitate compliance with the Contract Document requirements.

3. Requirements for Contractor to provide quality-assurance and quality-control services required by Architect, Owner, Commissioning Authority, Construction

Manager, or authorities having jurisdiction are not limited by provisions of this

Section.

1.3 DEFINITIONS

A. Experienced: When used with an entity or individual, "experienced," unless otherwise further described, means having successfully completed a minimum of five previous projects similar in nature, size, and extent to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

B. Field Quality-Control Tests and Inspections: Tests and inspections that are performed on-site for installation of the Work and for completed Work.

C. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, subcontractor, or sub-subcontractor, to perform a particular construction operation, including installation, erection, application, assembly, and similar operations.

1. Use of trade-specific terminology in referring to a Work result does not require that certain construction activities specified apply exclusively to specific trade(s).

D. Product Tests: Tests and inspections that are performed by a nationally recognized testing laboratory (NRTL) according to 29 CFR 1910.7, by a testing agency accredited according to NIST's National Voluntary Laboratory Accreditation Program (NVLAP), or by a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with specified requirements.

E. Source Quality-Control Tests and Inspections: Tests and inspections that are performed at the source (e.g., plant, mill, factory, or shop).

F. Testing Agency: An entity engaged to perform specific tests, inspections, or both. The term "testing laboratory" has the same meaning as the term "testing agency."

G. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work, to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

H. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work, to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Contractor's quality-control services do not include contract administration activities performed by Architect or

Construction Manager.

1.4 DELEGATED DESIGN SERVICES

A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract

Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Architect.

B. Delegated Design Services Statement: Submit a statement signed and sealed by the responsible design professional, for each product and system specifically assigned to

Contractor to be designed or certified by a design professional, indicating that the products and systems are in compliance with performance and design criteria indicated.

Include list of codes, loads, and other factors used in performing these services.

1.5 CONFLICTING REQUIREMENTS

A. Conflicting Standards and Other Requirements: If compliance with two or more standards or requirements is specified and the standards or requirements establish different or conflicting requirements for minimum quantities or quality levels, inform the Architect regarding the conflict and obtain clarification prior to proceeding with the

Work. Refer conflicting requirements that are different, but apparently equal, to

Architect for clarification before proceeding.

B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified is the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding.

1.6 INFORMATIONAL SUBMITTALS

A. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance"

Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

B. Schedule of Tests and Inspections: Prepare in tabular form and include the following:

1. Specification Section number and title.

2. Entity responsible for performing tests and inspections.

3. Description of test and inspection.

4. Identification of applicable standards.

5. Identification of test and inspection methods.

6. Number of tests and inspections required.

7. Time schedule or time span for tests and inspections.

8. Requirements for obtaining samples.

9. Unique characteristics of each quality-control service.

C. Reports: Prepare and submit certified written reports and documents as specified.

D. Permits, Licenses, and Certificates: For Owner's record, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.

1.7 REPORTS AND DOCUMENTS

A. Test and Inspection Reports: Prepare and submit certified written reports specified in other Sections. Include the following:

1. Date of issue.

2. Project title and number.

3. Name, address, telephone number, and email address of testing agency.

4. Dates and locations of samples and tests or inspections.

5. Names of individuals making tests and inspections.

6. Description of the Work and test and inspection method.

7. Identification of product and Specification Section.

8. Complete test or inspection data.

9. Test and inspection results and an interpretation of test results.

10. Record of temperature and weather conditions at time of sample-taking and testing and inspection.

11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements.

12. Name and signature of laboratory inspector.

13. Recommendations on retesting and reinspecting.

B. Manufacturer's Technical Representative's Field Reports: Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections. Include the following:

1. Name, address, telephone number, and email address of technical representative making report.

2. Statement on condition of substrates and their acceptability for installation of product.

3. Statement that products at Project site comply with requirements.

4. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.

5. Results of operational and other tests and a statement of whether observed performance complies with requirements.

6. Statement of whether conditions, products, and installation will affect warranty.

7. Other required items indicated in individual Specification Sections.

C. Factory-Authorized Service Representative's Reports: Prepare written information documenting manufacturer's factory-authorized service representative's tests and inspections specified in other Sections. Include the following:

1. Name, address, telephone number, and email address of factory-authorized service representative making report.

2. Statement that equipment complies with requirements.

3. Results of operational and other tests and a statement of whether observed performance complies with requirements.

4. Statement of whether conditions, products, and installation will affect warranty.

5. Other required items indicated in individual Specification Sections.

1.8 QUALITY ASSURANCE

A. Qualifications paragraphs in this article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.

B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units. As applicable, procure products from manufacturers able to meet qualification requirements, warranty requirements, and technical or factory-authorized service representative requirements.

C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

D. Installer Qualifications: A firm or individual experienced in installing, erecting, applying, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.

E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that is similar in material, design, and extent to those indicated for this Project.

F. Testing and Inspecting Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspection indicated, as documented in accordance with ASTM E329, and with additional qualifications specified in individual Sections; and, where required by authorities having jurisdiction, that is acceptable to authorities.

G. Manufacturer's Technical Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

H. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect, demonstrate, repair, and perform service on installations of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

1.9 QUALITY CONTROL

A. Owner Responsibilities: Where quality-control services are indicated as Owner's responsibility, Owner will engage a qualified testing agency to perform these services.

1. Owner will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged and a description of types of testing and inspection they are engaged to perform.

2. Payment for these services will be made from testing and inspection allowances specified in Section 012100 "Allowances," as authorized by Change Orders.

3. Costs for retesting and reinspecting construction that replaces or is necessitated by Work that failed to comply with the Contract Documents will be charged to

Contractor, and the Contract Sum will be adjusted by Change Order.

B. Contractor Responsibilities: Tests and inspections not explicitly assigned to Owner are

Contractor's responsibility. Perform additional quality-control activities, whether specified or not, to verify and document that the Work complies with requirements.

1. Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.

2. Engage a qualified testing agency to perform quality-control services.

a. Contractor will not employ same entity engaged by Owner, unless agreed to in writing by Owner.

3. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspection will be performed.

4. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service.

5. Testing and inspection requested by Contractor and not required by the Contract

Documents are Contractor's responsibility.

6. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.

C. Retesting/Reinspecting: Regardless of whether original tests or inspections were

Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the

Contract Documents.

D. Testing Agency Responsibilities: Cooperate with Architect, Commissioning Authority , Construction Manager, and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.

1. Notify Architect, Commissioning Authority, , Construction Manager, and

Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.

2. Determine the locations from which test samples will be taken and in which in-situ tests are conducted.

3. Conduct and interpret tests and inspections, and state in each report whether tested and inspected Work complies with or deviates from requirements.

4. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor.

5. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the Work.

6. Do not perform duties of Contractor.

E. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified in Section 013300

"Submittal Procedures."

F. Manufacturer's Technical Services: Where indicated, engage a manufacturer's technical representative to observe and inspect the Work. Manufacturer's technical representative's services include participation in preinstallation conferences, examination of substrates and conditions, verification of materials, observation of

Installer activities, inspection of completed portions of the Work, and submittal of written reports.

G. Contractor's Associated Requirements and Services: Cooperate with agencies and representatives performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:

1. Access to the Work.

2. Incidental labor and facilities necessary to facilitate tests and inspections.

3. Adequate quantities of representative samples of materials that require testing and inspection. Assist agency in obtaining samples.

4. Facilities for storage and field curing of test samples.

5. Delivery of samples to testing agencies.

6. Preliminary design mix proposed for use for material mixes that require control by testing agency.

7. Security and protection for samples and for testing and inspection equipment at

Project site.

H. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and quality-control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspection.

1. Schedule times for tests, inspections, obtaining samples, and similar activities.

I. Schedule of Tests and Inspections: Prepare a schedule of tests, inspections, and similar quality-control services required by the Contract Documents. Coordinate and submit concurrently with Contractor's Construction Schedule. Update and submit with each

Application for Payment.

1. Schedule Contents: Include tests, inspections, and quality-control services, including Contractor- and Owner-retained services, commissioning activities, and other Project-required services paid for by other entities.

2. Distribution: Distribute schedule to Owner, Architect, Commissioning Authority, Construction Manager, testing agencies, and each party involved in performance of portions of the Work where tests and inspections are required.

1.10 SPECIAL TESTS AND INSPECTIONS

A. Special Tests and Inspections: Owner will engage a qualified testing agency to conduct special tests and inspections required by authorities having jurisdiction as the responsibility of Owner, and as follows:

1. Verifying that manufacturer maintains detailed fabrication and quality-control procedures, and reviewing the completeness and adequacy of those procedures to perform the Work.

2. Notifying Architect, Commissioning Authority, , Construction Manager, and

Contractor promptly of irregularities and deficiencies observed in the Work during performance of its services.

3. Submitting a certified written report of each test, inspection, and similar quality-control service to Architect and Commissioning Authority, through Construction

Manager, with copy to Contractor and to authorities having jurisdiction.

4. Submitting a final report of special tests and inspections at Substantial

Completion, which includes a list of unresolved deficiencies.

5. Interpreting tests and inspections, and stating in each report whether tested and inspected Work complies with or deviates from the Contract Documents.

6. Retesting and reinspecting corrected Work.

PART 2 - PRODUCTS (Not Used)

PART 3 - PART 3 - EXECUTION

3.1 TEST AND INSPECTION LOG

A. Test and Inspection Log: Prepare a record of tests and inspections. Include the following:

1. Date test or inspection was conducted.

2. Description of the Work tested or inspected.

3. Date test or inspection results were transmitted to Architect.

4. Identification of testing agency or special inspector conducting test or inspection.

B. Maintain log at Project site. Post changes and revisionsas they occur. Provide access to test and inspection log for Architect's, Commissioning Authority's, and Construction

Manager's and authorities' having jurisdiction reference during normal working hours.

1. Submit log at Project closeout as part of Project Record Documents.

3.2 REPAIR AND PROTECTION

A. General: On completion of testing, inspection, sample-taking, and similar services, repair damaged construction and restore substrates and finishes.

1. Provide materials and comply with installation requirements specified in other

Specification Sections or matching existing substrates and finishes. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible. Comply with the Contract Document requirements for cutting and patching in Section 017300 "Execution."

B. Protect construction exposed by or for quality-control service activities.

C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.

REFERENCES 014200 - 1

SECTION 014200 - REFERENCES

PART 1 - GENERAL

1.1 DEFINITIONS

A. General: Basic Contract definitions are included in the Conditions of the Contract.

B. "Approved": When used to convey Architect's action on Contractor's submittals, applications, and requests, "approved" is limited to Architect's duties and responsibilities as stated in the Conditions of the Contract.

C. "Directed": A command or instruction by Architect. Other terms including "requested,"

"authorized," "selected," "required," and "permitted" have the same meaning as

"directed."

D. "Indicated": Requirements expressed by graphic representations or in written form on

Drawings, in Specifications, and in other Contract Documents. Other terms including

"shown," "noted," "scheduled," and "specified" have the same meaning as "indicated."

E. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work.

F. "Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations.

G. "Install": Unload, temporarily store, unpack, assemble, erect, place, anchor, apply, work to dimension, finish, cure, protect, clean, and similar operations at Project site.

H. "Provide": Furnish and install, complete and ready for the intended use.

I. "Project Site": Space available for performing construction activities. The extent of

Project site is shown on Drawings and may or may not be identical with the description of the land on which Project is to be built.

1.2 INDUSTRY STANDARDS

A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced.

Such standards are made a part of the Contract Documents by reference.

B. Publication Dates: Comply with standards in effect as of date of the Contract

Documents unless otherwise indicated.

1. For standards referenced by applicable building codes, comply with dates of standards as listed in building codes.

REFERENCES 014200 - 2

C. Copies of Standards: Each entity engaged in construction on Project should be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents.

1. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source.

1.3 ABBREVIATIONS AND ACRONYMS

A. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Abbreviations and acronyms not included in this list shall mean the recognized name of the entities indicated in Gale's "Encyclopedia of Associations:

National Organizations of the U.S." or in Columbia Books' "National Trade &

Professional Associations of the United States." The information in this list is subject to change and is believed to be accurate as of the date of the Contract Documents.

1. AABC - Associated Air Balance Council; www.aabc.com.

2. AAMA - American Architectural Manufacturers Association; (See FGIA).

3. AAPFCO - Association of American Plant Food Control Officials;

www.aapfco.org.

4. AASHTO - American Association of State Highway and Transportation

Officials; www.transportation.org.

5. AATCC - American Association of Textile Chemists and Colorists;

www.aatcc.org.

6. ABMA - American Bearing Manufacturers Association;

www.americanbearings.org.

7. ABMA - American Boiler Manufacturers Association; www.abma.com.

8. ACI - American Concrete Institute; (Formerly: ACI International);

www.concrete.org.

9. ACPA - American Concrete Pipe Association; www.concrete-pipe.org.

10. AEIC - Association of Edison Illuminating Companies, Inc. (The);

www.aeic.org.

11. AF&PA - American Forest & Paper Association; www.afandpa.org.

12. AGA - American Gas Association; www.aga.org.

13. AHAM - Association of Home Appliance Manufacturers; www.aham.org.

14. AHRI - Air-Conditioning, Heating, and Refrigeration Institute (The);

www.ahrinet.org.

15. AI - Asphalt Institute; www.asphaltinstitute.org.

16. AIA - American Institute of Architects (The); www.aia.org.

17. AISC - American Institute of Steel Construction; www.aisc.org.

18. AISI - American Iron and Steel Institute; www.steel.org.

19. AITC - American Institute of Timber Construction; www.plib.org.

20. AMCA - Air Movement and Control Association International, Inc.;

www.amca.org.

21. ANSI - American National Standards Institute; www.ansi.org.

22. AOSA - Association of Official Seed Analysts, Inc.; www.aosaseed.com.

23. APA - APA - The Engineered Wood Association; www.apawood.org.

24. APA - Architectural Precast Association; www.archprecast.org.

25. API - American Petroleum Institute; www.api.org.

26. ARI - Air-Conditioning & Refrigeration Institute; (See AHRI).

REFERENCES 014200 - 3

27. ARI - American Refrigeration Institute; (See AHRI).

28. ARMA - Asphalt Roofing Manufacturers Association; www.asphaltroofing.org.

29. ASCE - American Society of Civil Engineers; www.asce.org.

30. ASCE/SEI - American Society of Civil Engineers/Structural Engineering

Institute; (See ASCE).

31. ASHRAE - American Society of Heating, Refrigerating and Air-Conditioning

Engineers; www.ashrae.org.

32. ASME - ASME International; (American Society of Mechanical Engineers);

www.asme.org.

33. ASSE - American Society of Sanitary Engineering;…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .