Job_Order_Contract_(JOC)_for_Pavement_Maintenance_and_Repair_Services_at_John_Wayne_Airport_(Addendum_#1_Revision).pdf
PDF 481 KB Posted
- Attached to
- Job Order Contract (JOC) for Pavement Maintenance and Repair Services at John Wayne Airport
- Solicitation number
- IFB# 080-2775902-SV
- Issued by
- Orange County, San Francisco City, California
About this file
The document is an Invitation for Bids (IFB) issued by the County of Orange, OC Public Works Procurement Services for a Job Order Contract (JOC) for Pavement Maintenance and Repair Services at John Wayne Airport. The solicitation seeks competitive sealed bids from pre-qualified contractors to provide pavement maintenance and repair services for a one-year contract period, with the total contract amount yet to be specified. The mandatory pre-bid meeting is scheduled for Tuesday, February 25, 2025, at 10:00 am, and bids are due on Monday, March 10, 2025, at 2:00 pm. Bidders must have a current California Class A Contractor's license and submit their bids electronically through the county's e-procurement portal. The contract bids will remain valid for 180 days after the closing date.
The pricing structure for this contract involves an Adjustment Factor system, where contractors will quote four different adjustment factors that will be applied against prices in the Construction Task Catalog®. The awarded contract will utilize a complex award formula that weighs different adjustment factors for John Wayne Airport custom standards and assemblies, both during normal working hours and outside normal working hours. Contractors must pay a 1% JOC System License Fee to The Gordian Group to access their Job Order Contracting software and complete the bidding process. The county reserves the right to reject any and all bids, make multiple awards, and will require successful bidders to comply with various safety, permitting, and contractual requirements, including providing an Injury and Illness Prevention Program and adhering to specific storm water and environmental regulations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
County of Orange, OC Public Works IFB # undefined
Job Order Contract (JOC) for Job Order Contract (JOC) for Pavement Maintenance and Repair Services at
John Wayne Airport
COUNTY OF ORANGE
undefined
PROCUREMENT SERVICES
601 N. Ross St., 4th Floor
Santa Ana, CA 92701
Date: Monday, February 24, 2025
INVITATION FOR BIDS
FOR: JOB ORDER CONTRACT (JOC) FOR PAVEMENT
MAINTENANCE AND REPAIR SERVICES AT JOHN WAYNE AIRPORT
BID MUST BE RECEIVED BEFORE:
March 10, 2025 / 2:00 pm
IFB IFB# 080-2775902-SV
Procurement Services Regular Office Hours:
8:00 AM to 5:00 PM
Monday through Friday
The office is closed between 12:00 PM and 1:00 PM
Job Order Contract (JOC) for ____________________________
1. General Information
1.1. Important Notice
The County of Orange has attempted to provide all information available. It is the responsibility of each Bidder to review, evaluate, and where necessary, request any clarification prior to submission of a bid. If any person contemplating submitting a bid in response to this IFB is in doubt as to the true meaning of any part of the solicitation documents attached hereto or finds discrepancies in or omissions from the specifications, they must submit a request for clarification/interpretation through the County's online bidding system at https://procurement.opengov.com/portal/ocgov.
If clarification or interpretation of this solicitation is considered necessary by County, an addendum shall be issued and the information will be provided through the County's online bidding system. Any interpretation of, or correction to, this solicitation will be made only by addendum issued by the County through the County's online bidding system. It is the responsibility of each
Bidder to periodically check the County's online bidding system to ensure that they have received and reviewed any and all addenda to this solicitation. The County will not be responsible for any other explanations, corrections to, or interpretations of the documents, including any oral information.
All questions or requests for interpretation must be received by 2:00 pm on Thursday, February 27, 2025.
1.2. Lobbying
Orange County does not require and neither encourages nor discourages the use of lobbyists or other consultants for the purpose of securing business.
2. General Instructions and Provisions
2.1. Bid Submission
Before submitting a bid, Bidders shall carefully examine the solicitation contents, including the
Contract Terms and Conditions and Scope of Work. Bidders shall include in their bid response a monetary sum to cover the cost of all items included in the Contract.
2.2. Mandatory Pre-Bid Meeting Webinar
All Bidders must be in attendance at the Pre-Bid Webinar Meeting in order to continue in the bidding process. The Pre-Bid Webinar Meeting will be conducted one time only. Attendance will be taken at the webinar meeting, at the beginning and the end of the meeting. Attendance during entire webinar is required.
A. PRE-BID INFORMATION
DATE: Tuesday, February 25, 2025
TIME: 10:00 am – NO ONE WILL BE ADMITTED AFTER 10:10 am
LOCATION: MEETING LINK WILL BE SENT TO THOSE WHO RSVP
https://procurement.opengov.com/portal/ocgov
B. Please RSVP your attendance through the e-procurement portal by close of business day on February 24 2005.
C. The purpose of the Pre-Bid Meeting will be to discuss the Job Order Contract (JOC) concept, and discuss JOC from a Contractor’s perspective. For Contractors who are new to the JOC process, a training workshop will be part of the Pre-Bid Meeting.
o The County strongly encourages a responsible managing officer from the
Contractor’s office to attend this meeting. Bidders may request one (1) CD which contains the Construction Task Catalog® and the Technical Specifications.
2.3. Bid Submittal
This is a fully electronic Invitation for Bid (IFB). Bidders must submit their bid through the
County’s online bidding system to be considered responsive. Only electronic bids will be accepted, no exceptions. Once the Bid Due Date and Time has lapsed, bidders, the public and County staff are able to immediately see the results on OpenGov Procurement.
All bids are due no later than the due date and time specified within this solicitation. Late bids will not be accepted regardless of reason.
No person, firm or corporation shall be allowed to make or file or be interested in more than one bid, for the Job Order Contract. A person, firm or corporation who has submitted a sub-bid to a
Bidder, or who has quoted prices on materials to a Bidder, is not hereby disqualified from submitting a sub-bid or quoting prices to other Bidders.
Bidders shall take all responsibility for any errors or omissions in their bids. Any discrepancies in numbers or calculations shall be interpreted to reflect the lowest price to the County.
The County shall not be liable for any expenses incurred by potential Bidders in the preparation or submission of their bids. Pre-contractual expenses are not to be included in the Contractor’s
Pricing Sheet. Pre-contractual expenses are defined as, including but not limited to, expenses incurred by Bidder in:
A. Preparing its bid in response to this IFB;
B. Submitting that bid to the County;
C. Negotiating with the County any matter related to the bid; and, D. Any other expenses incurred by the Bidder prior to the date of the award and execution, if any, of the Contract.
2.4. Bonds
Bonds shall be secured from an admitted surety company authorized to conduct surety insurance in California and satisfactory to County Counsel and County Risk Management and in accordance with the General Conditions.
A. Bid Bond: Bidder will be required to furnish a bid bond in an amount not less than 10% of the total Contract amount. Original bid security documents shall be received at the following address before 2:00 p.m. on the bid closing date or submittals shall be deemed non-responsive:
County of Orange/County Administration South Building
601 N. Ross St., 4th Floor
Santa Ana, CA 92701
Attn: Suchitra Vattyam
B. Labor and Material Payment Bond and a Faithful Performance Bond: The successful Bidder, immediately upon award, will be required to furnish a Faithful
Performance Bond and a Labor and Material Payment Bond in an amount of $6,000,000.
Sample bonds can be found attached to this IFB.
2.5. Contractor’s License
No bid may be considered from a Bidder who, at the time the bids are opened, is not licensed to perform the project in accordance with Division 3, Chapter 9, of the Business and Professions
Code of the State of California (see California Business and Professions Code, Section 7000, et seq). However, if federal funds are involved, the Bidder must be properly licensed at the time of award (Public Contract Code 20103.5).
Bidders shall be required to meet any other legal, license or certificate requirements that are necessary to enable them to perform the services specified in this solicitation.
2.6. Bid Protest & Appeal
Any bidder, respondent, or contractor who alleges an error or impropriety in the solicitation or award of a contract may submit a grievance or protest to the awarding department and the following procedures will apply.
A. Procedure
1. Prior to the filing of an Agenda Staff Report (ASR) for award of Contract, the DPA shall send a Notice of Intent to Award a Contract to all participating vendors and submit a copy to the Clerk of the Board. This Notice shall initiate the protest period as follows:
2. Bidders will have five (5) business days from the date of the notice in which to file a protest concerning the award of the Contract.
3. Protests relating to a proposed Contract award which are received after the five (5) business day deadline will not be considered by the County.
4. During the five (5) business day period, bid information is subject to public disclosure.
5. Upon expiration of the five (5) business day period or proper resolution of a protest/appeal, the department may move forward with the Contract award or if necessary, filing the item for approval by the Board of Supervisors.
B. Protest Process
1. In the event of a timely protest, the County shall not proceed with the solicitation or award of the Contract until the DPA, or the Director renders a decision on the protest.
2. Upon receipt of a timely protest, the DPA will within ten (10) business days of the receipt of the protest, issue a decision in writing which shall state the reasons for the actions taken.
3. The County may, after providing written justification to be included in the procurement file, make the determination that an immediate award of the Contract is necessary to protest the substantial interest of the County. The award of a Contract shall in no way compromise the protestor’s right to protest procedures outlined herein.
4. If the protestor disagrees with the decision of the DPA, the protestor may submit a written appeal to the Office of the Director requesting an appeal, in accordance with the process stated below.
C. Appeal Process
1. If the protesting Bidder wishes to appeal the decision of the DPA, the protesting bidder must submit, within three (3) business days from receipt of the DPA’s decision, a written appeal to the Office of the Director.
2. Within fifteen (15) business days, the Office of the Director will conduct a third-party review of all materials in connection with the grievance, assess the merits of the protest and provides a written determination that shall contain his or her decision.
3. The decision of the Director will be final and there shall be no right to any administrative appeals of this decision.
2.7. Acceptance/Rejection/Award
A. Bids submitted in response to this IFB may become subject to public disclosure. The
County shall not be liable in any way for disclosure of any such records. Additionally, all bids shall become the property of the County.
B. Bids will be reviewed by the County for responsiveness to all requirements. The County has the right to reject any bid deemed unresponsive or lacking the resources or experience to adequately perform the services described herein, and is therefore not a responsible bidder.
C. Only those responsible, responsive bids meeting all solicitation requirements and specifications shall be further reviewed for consideration for award. Award shall be based on the lowest, responsive, responsible bid.
Please take notice, non-acceptance of County of Orange terms and conditions will result in a bid being deemed non-responsive. The County will not accept any other terms, conditions, or provisions contrary to those contained within this solicitation.
D. Final award determination based upon the lowest responsive, responsible bid, may also include a review of successful Bidder’s qualifications, experience, and resources;
Bidder’s ability to meet the requirements and perform the services specified in this solicitation; Bidder’s references and past performance; and Bidder’s acceptance of
County of Orange terms and conditions.
E. Awarded Contractor will be required to sign a Contract upon award. If Contractor is a corporation, signature will be provided in accordance with the corporation’s code as specified in this solicitation.
2.8. Rights Reserved to County
The County reserves the right to:
A. Waive, at its discretion, any irregularity or formality, which the County deems immaterial.
B. Make multiple awards to Bidders for services requested in this solicitation, at its sole discretion, to serve the best interests of the County.
C. Accept or reject all bids received as a result of this solicitation at its sole discretion and to solicit for new bids, as the best interests of the County may require;
D. Withdraw or cancel this solicitation at any time without prior notice and furthermore makes no representation that any Contract will be awarded to any bidder responding to this solicitation;
2.9. W-9 Requirements
Department of the Treasury, Internal Revenue Service Form W-9 Requirement: Effective
June 3, 2006, all Contractors, entering into a contract with the County, who are not already established in the Countywide Accounting and Personnel System (CAPS) as an Auditor-
Controller vendor, will be required to submit to the County a federal Form W-9, or form W-8 for foreign vendors.
In order to comply with this County requirement, within ten days of notification of selection of award of Contract but prior to official award of Contract, the selected Contractor agrees to furnish to the contract administrator, the County DPA, or the agency/department deputy purchasing agent the required W-9 or W-8.
3. Scope of Work
3.1. Scope of Work
Contractor shall provide all labor, materials, tools, equipment, utilities, vehicles, and transportation services required to provide Pavement Maintenance and Repair Services at John Wayne Airport under this Contract. Services may be provided, but may not be limited to, any facility or property which is owned, operated, or maintained by the County. Pavement Maintenance and Repair
Services at John Wayne Airport shall be provided in accordance with the following, which are incorporated herein by this reference.
A. Construction Task Catalog® & Technical Specifications Titled: Job Order Contracting;
Dated January 2025 (to be available for download after the Pre-Bid Meeting).
B. All other requirements identified specifically in A Job Order Detailed Scope of Work, which include but not limited to drawings, additional specifications, as-built records, sketches, written scope narratives, standard specification from other local, state and federal agencies.
C. California Building Code and other codes, ordinances, rules, regulations, orders and legal requirements of Agency Having Jurisdiction which bear on the performance of the work.
D. Secured Facilities: The Contractor may be required to have their employees, subcontractors and/or a suppliers submit applications and complete security clearances prior to commencing any work in a secured County facility. Contractor employees, subcontractors and/or suppliers will be required to submit to fingerprinting and personal background checks as part of the security clearance process.
3.2. Performance Requirements
A. There is no guaranteed minimum amount of work which will be ordered under this
Contract.
B. This is a Contract for work specified in individual Job Orders. Work ordered prior to but not completed by the expiration of the Contract period, and any additional work required as a result of unforeseen conditions encountered during construction up to six (6) months after the contract expiration date, will be completed with all provisions of this Contract still in force. Performance time for each Job Order issued under this Contract will be determined in accordance with the Contract. This performance time will be determined and agreed upon by both Parties for each individual Job Order. Contractor must self-perform 20% of the Work under this Contract for ‘A’ and ‘B’ licenses. Contractor must self-perform 75% of the Work under this Contract, unless otherwise approved by the
County, for ‘C’ licenses.
C. This is an indefinite-quantity Contract for the supplies or services specified and effective for the period stated. Work or performance shall be made only as authorized by Job
Orders issued in accordance with the ordering procedures clause. The Contractor agrees to furnish to the County when and if ordered, the supplies or services specified in the
Contract up to and including the quantity designated in the Job Orders issued as the maximum designated in the Contract.
3.3. Ordering Procedures
A. Joint Scope Meeting and Job Order Development
The County will issue, for each individual project, a Brief Scope of Work and Joint Scope Meeting invitation requesting the Contractor’s Superintendent and/or the County’s end user representative, to meet at the project site. Upon receipt of this notification, the Contractor agrees to respond to the County within two (2) working days by establishing verbal contact with the County. The
County, Contractor and other necessary parties will visit the proposed Work site and participate in a Joint Scope Meeting, which will include discussion and establishment of the following:
1. Detailed Scope of Work
2. Definition and refinement of requirements
3. Existing site conditions
4. Methods and alternatives for accomplishing Work
5. Requirements for plans, sketches, shop drawing(s), submittals, etc.
6. Tentative duration Work schedule
7. Preliminary quantity assumptions/estimates
8. Staging areas and site access
9. Special conditions regarding unique facility operations
10. Safety requirements
11. Hazardous Materials or site conditions
12. Other project requirements
As part of the required Joint Scope Meeting, the Contractor and the County will agree on a sequence of Work; means of access to the premises and building; space for storage of materials and equipment; Work and materials and use of approaches; use of corridors, stairways, elevators, and means of communications and the location of partitions, eating spaces, and restrooms for the
Contractor, for individual Job Orders. The Contractor agrees to be responsible for taking these factors into account when developing its Quotation.
The Detailed Scope of Work will be completed by the Contractor and submitted to the County for approval, prior to issuance of a Request for Quote. This Detailed Scope of Work must be submitted within forty-eight (48) hours or a mutually agreed upon time of the Joint Scope Meeting. If consultant services are required to clarify project requirements, they will be completed and submitted with the Scope of Work for County approval before a Request for Quote will be issued.
Unless waived in writing, the Contractor agrees to provide all documentation required to fully establish the Scope of Work including, but not limited to, shop drawings, sketches and/or specifications that comply with the Contract specifications and relate to the proposed project. This documentation will be provided for the purpose of defining scope, obtaining permits, and assisting the County in determining the best possible solution for repair and refurbishment issues. If the
County requests a change in the proposed Scope of Work, the Contractor agrees to submit a revised
Scope of Work reflecting all requested changes within forty-eight (48) hours.
B. Request for Quote
Once the project development stage and Joint Scope Meeting have produced a County approved
Detailed Scope of Work, the County will issue a Request for Quote (RFQ) to the Contractor. The
RFQ will include the Scope of Work approved by the County and other pertinent information with regards to scheduling, submittals, shop drawings and sketch requirements. The Contractor agrees to prepare and submit a Quote of Work.
C. Quote Development
The Contractor Quote agrees to be comprised of the following elements:
1. Detailed Cost Quote
a. Pre-Priced Work requirements: Pre-Priced Work requirements will identify the type and number of Work tasks required from the CTC. The price per unit set forth in the CTC shall serve as the base price for the purpose of the operation of this article. The Contractor’s Quote shall include support documentation to indicate that adequate engineering and planning for the requirement has been done, and that the Work tasks proposed are reasonable for the Scope of Work.
Documentation to be submitted with the Quote shall include, but not be limited to, shop drawings, calculations, Catalog® cuts, and specifications.
b. The total extended price for Pre-Priced Work requirements will be determined by multiplying the price per unit by the quantity required. The price offered in the
Quote will be determined by multiplying the total extended price by the appropriate Adjustment Factor.
2. Non-Pre-Priced Task Requirements
a. Units of Work not included in the CTC, but within the general scope and intent of this Contract, may be negotiated into this Contract as needs arise. Such Work requirements shall be incorporated into and made a part of this Contract for the
Job Order to which they pertain, and may be incorporated into the CTC if determined appropriate by the County at the negotiated price. Non-Pre-Priced
Tasks shall be separately identified and submitted in the Quote. Whether a Work requirement is Pre-Priced or Non-Pre-Priced is a final determination by the
County, binding and conclusive on the Contractor.
b. Information submitted in support of Non-Pre-Priced Tasks agree to include, but not be limited to, the following: complete specifications and technical data, including Work unit content, Work unit cost data, schedule requirements; quality control and inspection requirements. Pricing data submitted in support of Non-
Pre-Priced Tasks include a cost or price analysis report establishing the basis for selecting the approach proposed to accomplish the requirements. Unless otherwise directed by the County, cost data shall be submitted demonstrating that the
Contractor solicited and received three (3) bids. The Contractor shall not submit a quote or bid from any supplier or subcontractor that the Contractor is not prepared to use. The County may require additional quotes and bids if the suppliers or subcontractors are not acceptable for if the prices are not reasonable. The
Contractor agrees to provide an installed unit price (or demolition price if appropriate), which shall include all costs required to accomplish the Non-Pre-
Priced Task.
c. The final price submitted for Non-Pre-Priced (NPP) Tasks shall be calculated according to the following formula:
Contractor performed duties
A= The hourly rate for each trade classification not in the Construction Task
Catalog® multiplied by the quantity;
B= The rate for each piece of Equipment not in the Construction Task Catalog® multiplied by the quantity;
C= Lowest of three (3) independent quotes for all materials.
Total for a Non Pre-Priced Task performed with Contractor’s Own Forces =
(A+B+C) x Factor of 1.05
Subcontractor performed duties
If the Non Pre-Priced Task is to be subcontracted, the Contractor must submit three (3) independent quotes for the Work.
D= Lowest of three (3) Subcontractor quotes.
Total cost of Non-Pre-Priced Tasks performed by Subcontractors = D x Factor of
1.05.
After being used on three separate Job Orders, the unit price for the Non-Pre-
Priced Task may become fixed as a permanent Pre-Priced item, which will no longer require price justification.
The County’s determination as to whether a task is a Pre-Priced Task or a Non
Pre-Priced Task shall be final, binding and conclusive.
3. Total Fixed Cost of the Quote
The total fixed cost of the Quote shall be determined by adding the total Quote price offered for Pre-Priced and Non-Pre-Priced Work units.
4. Submittals
All documents, shop drawings, and “As-Built” drawings shall be prepared such that the drawings meet all the requirements of Local, State, and Federal regulations, codes and directives. The Contractor agrees to also provide as necessary, the forms, studies, and other documentation required by applicable codes and agencies.
The Contractor agrees to ensure that all engineering solutions conform strictly to the guides and criteria outlined in Contract specifications. In case of uncertainty of detail or procedure, the Contractor agrees to request additional instruction from the County.
The Contractor is responsible for producing complete, competent, properly coordinated, and thoroughly checked documents.
At the Contractor’s expense, as part of their Adjustment Factors, the documentation noted above, shall be prepared and reviewed as necessary to ensure its compliance with all applicable laws and regulations.
5. Work Duration Schedule
With each quote, the Contractor agrees to furnish a Gantt chart Work duration schedule showing the order in which the Contractor proposes to perform the Work, the durations in which the Contractor is to perform the Work, and the relative dates on which the Contractor contemplates starting and completing project tasks, including the acquisition of materials, fabrication, and equipment. The County may determine the level of detail and number of tasks required to be included on the schedule. Unless otherwise specified, the schedule shall be in the form of a Gantt chart Work duration schedule of suitable scale to indicate appropriately the percentage of Work scheduled for Completion. At the discretion of the County, the Contractor may be required to furnish a Critical Path Method (CPM) schedule.
The purpose of the Work Duration Schedule is to ensure adequate planning, coordination and execution of the Work, and to evaluate the progress of the Work.
The schedule indicates the dates for starting and completing various aspects of the
Work including, but not limited to, on-site construction activities as well as the submittal, approval, procurement, fabrication, and delivery of major items, materials and equipment. The schedule indicates phasing of Work activities as required. The schedule provides the Contractor’s initial plan for the Work based on its understanding of the Detailed Scope of Work, with the critical path highlighted.
a. Schedule Approval; all project schedules will be subject to the County’s review and approval. The use of any particular scheduling system shall be subject to the approval of the County.
b. Schedule Updates; the Contractor agrees to maintain the Work duration schedule updates on an ongoing basis and, when the County requests it, include the updates in its payment request. The Contractor may be required to submit a narrative report with each monthly update which shall include a description of current and anticipated problem areas, delaying factors and their impact, and an explanation of corrective action taken or proposed. Failure to do so may be considered a material breach of the Contract. Any additional or unanticipated costs or expense required to maintain the schedules shall be solely the Contractor’s obligation and
Contractor agrees not to charge the County.
c. Adjustment of the Work duration schedule; the Contractor agrees that whenever it becomes apparent to the County, from the current monthly status review meeting or the schedule, that phasing or Job Order milestone dates will not be met, it will take some or all of the following actions at no additional cost to the County.
i. Increase construction manpower in such quantities and crafts as will eliminate the backlog of Work.
ii. Increase the number of working hours per shift, shifts per working day.
iii. Reschedule the Work under the Job Order in conformance with all other requirements. The Contractor agrees to be liable for any additional cost incurred by the County for the adjustment of project schedules.
iv. Prior to proceeding with any of the above actions, the Contractor agrees to notify and obtain approval from the County’s Project Manager for the proposed schedule changes. If such actions are approved, the Contractor agrees to incorporate the revisions into the schedule.
6. Subcontractor’s List
The Quote represents the Contractor’s offer to do Work, and as such, in accordance with Sections 4100 to 4114, inclusive, of the Public Contract Code of the State of
California, the Contractor agrees to list, on the Subcontractor listing report, the name, business location and the California Contractor License number of each
Subcontractor that will perform Work, labor or render service on the Work in excess of one-half of one percent (1/2%) of the total Quote amount. Contractors and
Subcontractor which have been debarred from public works projects by the Labor
Commissioner may not perform Work under this Contract. The Contractor agrees to list project percentage of proposed Subcontractor and percentage of the project to be self-performed.
Contractor agrees to advise the County of any Subcontractor substitution(s) prior to commencement of subcontract Work and to only substitute Subcontractor as authorized under Public Contract Code sections 4100 et seq. Contractor may be subject to penalties in accordance to the above referenced sections for illegal
Subcontractor substitution.
Engineer, as a duly authorized officer, may consent to Subcontractor substitution requested by the Contractor subject to the limitations and notices prescribed in
Section 4107 of the Public Contract Code.
7. Electronic Quote
The Contractor agrees to transmit an electronic copy of the Quote, using the County furnished software, to the County.
8. Complete Quote
By submitting a signed Quote, the Contractor is agreeing to accomplish the Work outlined in the RFQ and the Detailed Scope of Work for that particular Job Order. It is the Contractor’s responsibility to include the necessary line items in the Quote prior to submitting it to the County. Errors and omissions in the Quotes shall be the responsibility of the Contractor. All costs associated with preparing Quotes shall be the responsibility of the Contractor. The County makes no commitment as to the award of individual Job Orders.
D. Quote Review
Each Quote received from the Contractor will be reviewed in detail for appropriateness of quantities and tasks selected. Submittals will be reviewed, as well as the Work duration schedule and list of Subcontractor. The County will evaluate the proposed Work units and may compare them with the independent County estimate of the same tasks to determine the reasonableness of approach, including the nature and number of Work units proposed. The County will determine whether the Contractor’s Quote is acceptable.
E. Project Approval
The County may issue a Job Order Authorization for the Work, to include the firm-fixed-price of the Job Order and the project duration. Contractor agrees that all clauses of this Contract are applicable to any Job Order issued hereunder.
The County reserves the right to reject a Contractor’s Quote based on unjustifiable quantities and/or methods, performance periods, inadequate documentation, or other inconsistencies or deficiencies on the Contractor’s part in the sole opinion of the County.
The County reserves the right to issue a unilateral Job Order authorization for the Work if a
Quote price cannot be mutually agreed upon. This is based upon unjustifiable quantities in the sole opinion of the County.
The County also reserves the right to not issue a Job Order Authorization if the County’s requirement is no longer valid or the project is not funded. In these instances, the Contractor has no right of claim to recover Quote expenses. The County may pursue continuing valid requirements by other means where Contract was not reached with the Contractor.
F. Quote Time Requirements
1. Quote Submittal
The Contractor agrees to respond to a Request for Quote within forty-eight (48) hours. Contractor’s response shall confirm receipt of the Request for Quote, and a mutually agreed upon date for submittal of Contractor’s detailed price Quote.
The Contractor agrees to make a thorough analysis of each Request for Quote and submit all requests for information to the County, in writing. All requests for information and the responses are to be documented in the Detailed Scope of
Work. The requests shall include supporting sketches or information necessary to properly convey requested information. Contractor shall submit recommended solution(s) review and consideration. The requests for information shall not extend the Quote due date unless mutually agreed to by the County.
2. Quote Review
The Contractor’s project manager or agent agrees to be available for Quote review meetings within twenty-four (24) hours of being notified by the County (via fax, e-mail, telephone, etc). After review of the Quote, the Contractor agrees to remove all inapplicable line items and adjust quantities as directed by the County.
3. Quote Modification
The Contractor will be granted only one opportunity to add new, valid line items that may have been omitted from its first Quote by submitting a second, revised
Quote. The Contractor agrees to submit the revised Quote within forty-eight (48) hours of the initial Quote review meeting, unless otherwise specified in writing. Upon review of the revised Quote, the Contractor agrees to remove all line items or adjust quantities deemed inappropriate by the County, and re-submit its
Quote within twenty-four (24) hours. No new line items may be added to the revised
Quote, nor may quantities be increased, nor modifiers added unless specifically agreed to in writing by the County’s subsequent Quote review.
4. Enforcement of Time Requirements
The Quote time requirements contained herein will be strictly enforced. Failure to comply may result in the Contractor being deemed non-responsive to the Request for
Quote. The County may cancel the Request for Quote from the Contractor and solicit another Contractor. The County may also deem the Contractor ineligible for any future JOC contracts.
3.4. Approval and Construction Procedures
A. Job Order Authorization (JOA)
Upon approval of the Scope of Work and the Contractor’s Quote, the County will issue a Job
Order Authorization to the Contractor. The Job Order Authorization will include the firm fixed price of the Job Order and the project duration. Once the Job Order Authorization has been issued the Contractor agrees to:
1. Initiate submission of required shop drawings and submittals to the County for review and approval.
2. Prepare a detailed Work duration schedule.
3. The Contractor agrees to not begin construction prior to the construction start date identified in the Notice to Proceed (NTP).
4. Upon issuance of the NTP, the County agrees to have the right to direct the
Contractor to withhold actual commencement of a Job Order in part or in whole, and the Contractor agrees to comply with such instructions. The Contractor agrees to be granted an extension of the completion time of the Job Order equal to the number of working days delay caused to County pursuant to Contractor's compliance with such instructions. The Contractor will not be entitled to any additional compensation due to the subject extension of the Completion time. The only compensation would be if a
Job Order is delayed in part, after Work has commenced, and the Contractor is required to perform additional Work to make the Work area safe or to perform additional scope as directed by the County. This additional Work will be considered additional Work and ordered as a separate Job Order.
B. Notice to Proceed (NTP)
Following the JOA and purchase order issuance, the County will issue a Notice to Proceed (NTP) that will provide the construction start date, the Work duration period, and the Substantial
Completion date. The Contractor agrees to begin and complete construction within the dates specified on the NTP. The County must approve all extensions of time in writing.
The County may also issue an Emergency NTP. In the event the County requires the Contractor to respond to an immediate request for work, a Job Order will be created and an Emergency NTP will be issued. The Contractor will be required to perform the Scope of Work included with the
Emergency NTP as directed by the County’s Project Manager or designee. The Detailed Scope of
Work, Quotation, Subcontractor Listing, Shop Drawings and required Non-Pre-Priced backup documentation will be submitted upon completion of the emergency work in accordance with the
Ordering Procedures detailed in Section III above.
C. Pre-Construction Meeting
No more than seven (7) days from the issuance of the NTP, unless the County grants additional time, the County will conduct a pre-construction meeting with the Contractor’s project manager, Subcontractors, and the end-user to determine the actual project schedule, project access requirements and to address and resolve any customer concerns.
D. Project Construction
The Contractor agrees to provide continuous on-site supervision on each Job Order, while progress on the project is being accomplished. The Contractor’s Project Manager will ensure:
1. Coordination and providing supervision to all Subcontractor and workers;
2. Posting of the prevailing wage scale;
3. Maintaining a copy of the Contractors safety program manual made available to all construction personnel;
4. Conducting weekly on-site safety meetings;
5. Completing the daily labor and construction progress log on a daily basis and submit copies to the County on a daily basis. Copies of the previous day’s reports must be submitted by 9:00AM of the following day.
a. Daily labor log is to include a listing of Subcontractor(s) and a count of workers by trade providing services for the day.
b. Construction progress log is to include a narrative of the Work provided by trade(s). Narrative agrees to include the various areas of the jobsite where Work was performed and any problems or conditions that were encountered.
c. In the event the Contractor fails to provide a daily log and/or construction progress log, the County may impose damages against the Contractor in the amount of fifty dollars ($50.00) for each log and deduct from the Contractor’s payment request, for each day the Contractor does not provide the documentation.
6. County may suspend Contractor operations if no Contractor Superintendent is observed. All delays caused by the suspension will be the responsibility of the
Contractor. No time extension or claims for cost(s) associated with the suspension will be granted by the County.
E. Changed Work
Changed Work (all added or deleted Work), as it pertains to the approved Detailed Scope of Work included in a specific Job Order, shall be either changes directed by the County or unforeseen site conditions, which were not evident during the Initial Joint Scope Meeting. This additional Work will be considered a subsequent Job Order, for that specific project, and will be ordered, approved and executed as per the procedures set forth in this Contract.
A credit for Tasks that have been deleted from the Detailed Scope of Work will be given at 100% of the value at which they were included in the original Quote. Credits for Pre-Priced and Non
Pre-Priced Tasks shall be calculated at the pre-set Unit Prices and multiplied by the appropriate
Adjustment Factors. A Supplemental Job Order will be issued detailing the credit(s) due the
County.
F. Project Completion
The Contractor agrees to schedule a final job walk with the County. If required, the County will prepare a list of incomplete items, the “Punch List”. The Contractor agrees to complete the “Punch
List” corrections and schedule a final project completion job walk. The County will sign the
“Punch List” as completed when determined, the project is finished. The Contractor agrees to submit the following along with its final payment request:
1. “Punch List” signed by the County;
2. Completed building inspection card;
3. All required warranties and maintenance requirements;
4. All record drawings or as-built drawings,
5. All required operation and maintenance manuals;
6. All keys and security entry cards;
7. Any other closeout items.
3.5. Contracts and Order of Precedence
In the event that any provision(s) in any component part of the Contract conflicts with any provision(s) of any other component part, the following order of precedence among the Contracts component parts shall govern:
A. Job Orders (including Scope of Work)
B. County -Contractor Contract
C. Project manual
D. Construction Task Catalog®
E. County Standard Plans
F. Technical Specifications
G. Green Book
3.6. Permits, Business Licenses, Inspections and Warranty
A. Except as noted, the Contractor agrees to obtain and pay for all permits required for the
Work. Further, the Contractor agrees to obtain and pay for all permits incidental to the
Work or made necessary by Contractor's operation. The Contractor agrees to obtain all building permits. The Contractor will be reimbursed for all direct costs of permits without mark-up. The Contractor must submit the direct cost of all permits and inspection in the
Quote as a Non-Pre-Priced Task. Any permit and/or inspection fees not included in the
Quote will not be reimbursed by the County. The County is not responsible for any re-inspection(s) required due to the Contractor’s failure to pass initial inspection(s).
B. The Contractor will be required to obtain a city business license to perform the Work in the appropriate city, as specific in the Job Order.
C. To comply with Section 3800 of the Labor Code of the State of California, the Contractor and all Subcontractors requiring a permit (building, plumbing, grading, and electrical, etc.) agree to file a workers' compensation certificate with the County.
D. Exclusive of off-site inspection specified to be the County's responsibility, the Contractor agrees to arrange and pay for all off-site inspection of the Work including certification thereof required by the specifications, drawings, or by governing authorities.
E. The County will provide on-site inspection of the Work and will arrange for off-site inspection when specified in the Detailed Scope of Work. All other required inspections will be the responsibility of the Contractor.
F. The County will inspect the Work for code compliance as part of permits pulled. The
County will provide this inspection at no additional cost for the first inspection and for re-inspection. If the Contractor is unable to correct defective Work after one re-inspection, the County may charge the Contractor for additional re-inspection.
G. In addition to any other warranties in this Contract, or those provided by manufactures the Contractor warrants that Work performed under this Contract conforms to the
Contract requirements and is free of any defect in equipment, material, or workmanship performed by the Contractor or any Subcontractor or supplier at any tier.
H. Corrections to Work may be required during the Work or the warranty period. The
County is expressly authorized at County's option to apply any sums withheld from progress payments toward the cost of such corrections.
I. This warranty shall continue for a period of one year from the date listed on the Notice of
Completion for the specific Job Order. If the County takes occupancy of any part of the
Work before Final Acceptance, a warranty covering that specific portion of the Work shall begin for a period of one year from the date the County takes occupancy. The
County will notify the Contractor in writing of the scope of any partial occupancy and the specific items under warranty.
J. The County will not pay any costs for licenses required in the performance of the Work.
The Contractor agrees to assume this responsibility in total.
K. As required by the Detailed Scope of Work for a specific Job Order, the County may be required to enter into Contracts with other Local, State and Federal Agencies to accomplish the subject Scope of Work. Agencies may include but are not limited
California Department of Fish and Game, US. Army Corps of Engineers, California
Regional Water Quality Control Board. The Contractor will be required to comply with the requirements set forth within the permit.
L. Best Management Practices (BMPs) may be required for specific Job Orders, which will be identified in the Detailed Scope of Work. All California Storm Water Quality
Association (CASQA) Construction BMPs may be viewed at www.cabmphandbooks.com. It is the Contractors responsibility to pay for all costs incurred by the specific BMPs. The County will not reimburse these costs.
M. As required by the Detailed Scope of Work, per a specific Job Order the following permits may apply and will be provided by the County:
1. NPDES Dewatering Permit
2. NPDS Municipal Storm Water Sewer System Permit http://www.cabmphandbooks.com/
3. NPDES General Construction Permit
4. Any site specific permits identified by County
N. If applicable, the NPDES Watering Permit shall be provided in accordance with the following:
1. Construction Related Dewatering & De Minimus Discharges, Santa Ana Region:
a. The County has been issued Municipal NPDES Permit No. CAS618030, Order
No. R8-2009-0030, from the California Regional Water Quality Control Board, Santa Ana Region. Section III.3.ii. of this permit authorizes de minimus types of discharges listed in the Santa Ana Regional Board’s General De Minimus Permit for Discharges to Surface Waters, Order No. R8-2009-0003, from County owned and/or operated facilities and activities (including construction), outside of the
Newport Bay watershed.
b. A copy of the County’s Municipal NPDES Permit (Order No. R8-2009-0030) may be found on the internet at:
http://www.waterboards.ca.gov/santaana/board_decisions/adopted_orders/orders
/2009/09_030_oc_stormwater_ms4_permit.pdf
c. A copy of the Santa Ana Regional Board’s General De Minimus Permit for
Discharges to Surface Waters (Order No. R8-2009-0003) may be found on the internet at:
http://www.waterboards.ca.gov/santaana/board_decisions/adopted_orders/orders
/2009/09_003_deminimus_permit_wdr.pdf
d. For de minimus discharges outside of the Newport Bay Watershed, the Contractor is hereby directed to read and thoroughly comply with the language in Section
III.3.ii. of the County’s Municipal NPDES Permit (Order No. R8-2009-0030) and to consult the General De Minimus Permit (Order No. R8-2009-0003) for the types of de minimus discharges which are covered.
O. National Pollutant Discharge Elimination System (NPDES) General Permit For Storm
Water Discharges Associated With Construction And Land Disturbance Activities Water
Quality Order 2009-0009-Dwq (CGP):
1. On September 2, 2009, the State Water Resources Control Board adopted Order No.
2009-0009-DWQ (Waste Discharge Requirements for Discharges of Storm Water
Runoff Associated with Construction Activities and Land Disturbance
Activities). Effective July 1, 2010, all dischargers are required to obtain coverage under the Construction General Permit Order 2009-0009-DWQ (CGP). Construction sites shall obtain permit coverage at the appropriate Risk Level as determined by the http://www.waterboards.ca.gov/santaana/board_decisions/adopted_orders/orders/2009/09_030_oc_stormwater_ms4_permit.pdf http://www.waterboards.ca.gov/santaana/board_decisions/adopted_orders/orders/2009/09_030_oc_stormwater_ms4_permit.pdf http://www.waterboards.ca.gov/santaana/board_decisions/adopted_orders/orders/2009/09_003_deminimus_permit_wdr.pdf http://www.waterboards.ca.gov/santaana/board_decisions/adopted_orders/orders/2009/09_003_deminimus_permit_wdr.pdf
Risk Assessment Procedures described in subsection f below. The Regional Water
Boards have the authority to require Risk Determination to be performed on projects currently covered under Water Quality Order No. 99-08-DWQ where they deem necessary.
A copy of these documents may be found on the internet at:
http://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/constpermit s/wqo_2009_0009_complete.pdf
2. Prior to commencing Work, the Contractor shall submit the required PRDs (Permit
Registration Documents) to the County Project Manager. If any of the required items are missing, the PRD submittal is considered incomplete and will be rejected. Upon receipt and acceptance of a complete PRD submittal, the County Project Manager will electronically submit these documents to State Water Board through the
California Integrated Water Quality System (CIWQS) Project’s Storm water Multi-
Application Reporting and Tracking (SMART) system to obtain coverage under the
General Permit.
3. Standard PRD Requirements
a. Notice of Intent
b. Risk Assessment (Standard or Site-Specific)
c. Site Map
d. SWPPP
e. Annual Fee
f. Signed Certification Statement
4. Additional Permit Registration Document (PRD) Requirements Related To
Construction Type
a. If Contractor proposes to implement an Active Treatment System (ATS) on a
Specific Job Order, Contractor shall submit:
i. Complete ATS Plan in accordance with Attachment F of the CGP at least 14 days prior to the planned operation of the ATS and a paper copy shall be available onsite during ATS operation.
ii. Certification proof that the preparation and design was accomplished by a qualified professional in accordance with Attachment F of the CGP.
b. Dischargers who are proposing an alternate Risk Justification shall submit:
i. Particle Size Analysis.
5. Exception to Standard PRD Requirements
a. Construction sites with less than one (1) acre of disturbance or an R value less than five (5) as determined in the CGP Risk Assessment from the Revised
Universal Soil Loss Equation (RUSLE) are not required to submit a SWPPP.
6. Description of PRDs
a. Notice of Intent (NOI) or Notice of Construction Activity (NOCA)
The Notice of Intent or Notice of Construction Activity must be filled out electronically on-line through the State’s SMART System. Contractor shall coordinate with the County Project Manager to provide the required information to fill out the NOI on-line form. Upon receipt of all required information
(including all items required below), County staff will electronically submit the
Project information through the SMART system.
b. Site Map(s) Includes
i. The project’s surrounding area (vicinity)
ii. Site layout
iii. Construction site boundaries
iv. Drainage areas
v. Discharge locations
vi. Sampling locations
vii. Areas of soil disturbance (temporary or permanent)
viii. Active areas of soil disturbance (cut or fill)
ix. Locations of all runoff BMPs
x. Locations of all erosion control BMPs
xi. Location of all sediment control BMPs
xii. ATS locations (if applicable)
xiii. Location of sensitive habitats, watercourses, or other features which are not to be disturbed
xiv. Locations of all post construction BMPs
xv. Location of storage areas for waste, vehicles, service, loading/unloading of materials, access (entrance/exits) points to construction site, fueling and water storage, water transfer for dust control and compaction practices
c. Storm Water Pollution Prevention Plan (SWPPP)
The Contractor will need to submit a site-specific SWPPP for review, approval, and certification by the County prior to submittal to the State’s SMART system and prior to start of mobilization and construction activity and will comply with the approved SWPPP and with any subsequent amendments to the SWPPP.
NO CONSTRUCTION ACTIVITY CAN BE…
This is the start of the file's text. The full file is on GovTribe.