JFK Midrise Elevator Bank 3 Replacement SOW 2023 04 20.pdf
PDF 176 KB Posted
- Attached to
- JFK Mid-Rise Bank 3 Replacement Federal contract opportunity
- Solicitation number
- 47PB0023R0035
About this file
This statement of work and related federal contract opportunity outline requirements for replacing three elevators in the John F. Kennedy Federal Office Building in Boston, Massachusetts. The General Services Administration Public Buildings Service New England Region is seeking proposals to provide all labor, materials, tools, equipment, and supervision to remove and fully replace elevators 7, 8, and 9 that serve midrise floors 1 through 15. Offerors must complete the work within 15 months of the notice to proceed using the specifications and drawings dated December 2, 2022. The estimated price range for the contract is between $1,000,000 and $5,000,000. The solicitation number is 47PB0023R0035. The pre-proposal site visit will be held on May 17, 2023 and questions are due by May 24, 2023, with proposals due June 8, 2023.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 0003 SF 30 Solicitation Amendment 47PB0023R0035 2023 06 09.pdf | ||
| Solicitation Amendment 2023 06 06.pdf | ||
| 0001 SF 30 Solicitation Amendment 47PB0023R0035 2023 05 30.pdf | ||
| JFK Revised Final SpecsElev Upgrades 2023 04 07.pdf | ||
| SF 1442 47PB0023R0035 Form 2023 04 21.pdf | ||
| GSA527-21 2023 04 20.pdf | ||
| SBSA GC Agreement 2023 04 13.pdf | ||
| SBSA GC Solicitation 2023 05 05.pdf | ||
| GC Reps and Certs March 2023 04 21.pdf | ||
| Past Performance Questionnaire 2023 04 21.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. General Services Administration Public Buildings Service New England Region
SCOPE OF WORK
JFK Mid-rise Bank 3 Elevator Replacement
April 20, 2023
1. 1 Project Location
John F. Kennedy Federal Office Building 15 Sudbury Street Boston MA, 02203
1. 2 Project Points of Contact
Sebastian Asaro, Contracting Officer Phone: (646)398-0455 Sebastian.asaro@gsa.gov
Barry Wood, Project Manager Cell: (617) 304-5145 Barry.Wood@gsa.gov
Adam Katzman Phone (617) 283-2420 Adam.Katzman@gsa.gov
1. 3 Project Duration
Once the Notice to Proceed (NTP) has been given, the Contractor has Fifteen (15) Months to complete the project. The Contractor shall schedule all labor/work, materials, orders, deliveries, security clearances, etc. in a timely manner to ensure approved schedule is always maintained.
mailto:Sebastian.asaro@gsa.gov mailto:Barry.Wood@gsa.gov mailto:Adam.Katzman@gsa.gov
U.S. General Services Administration Public Buildings Service New England Region
1.4 Scope of Work
A. Summary
1) The Contractor shall provide all labor, material/supplies and equipment to support the removal and full replacement of the mid-rise, Bank 3 elevators at the JFK FOB in Boston MA. The replacement consists of three (3) elevators cars 7, 8, & 9 that serve the midrise floors of one (1) through (15). The drawings and specifications included in the solicitation, 47PB0023R0035 , include scope to replace all Twenty-Six (26) elevators. The contractor shall utilize the drawings & details that are specific to a full systems replacement of the (3) elevators identified in this SOW. The requirements include all provisions to replace the elevators and as follows:
B. Scope Package Requirements:
1) Specifications: The Contractor shall provide the work as specified in the 100% design document specifications.
a. Specification Title: Comprehensive Elevator & Escalator Upgrades
i. Dated: December 2, 2022.
2) Drawings: The Contractor shall provide the work as Illustrated in the 100% Design Document Drawings:
a. Drawing Set Title: Comprehensive Elevator & Escalator Upgrades
i. Dated: December 2, 2022.
b. Drawing sheet number specific to the scope follows:
i. G-000 – Cover Sheet
ii. G-001 – Elevator Location Plan
iii. D-001 – Abbreviation, Symbols, and General Demolition Notes
iv. D-102 – Passenger Elevators 7-13 Demolition Plans &
Elevations
v. D-201 – Passenger Elevators 1-13 Car Demolition Plans &
Elevations
vi. A-001 – Abbreviations, Symbols and Code Summary
vii. A-102 – Passenger Elevators 7-13 New Plans & Elevations
viii. A-201 – Passenger Car Interior Finishes
ix. A-202 – Passenger Car Interior Finishes
x. S-000 – Structural General Notes
xi. S-001 – Special Tests & Inspections
xii. S-200 – Typical Concrete Details
xiii. S-201 – Concrete Repair Details
xiv. E-001 – Electrical Symbols & Abbreviations
xv. E-102 – Passenger Elevators Cars 7-13 Electrical Plan
| SCOPE OF WORK |
| 1. 1 Project Location |
| 1. 2 Project Points of Contact |
| 1. 3 Project Duration |
| 1.4 Scope of Work |
File details come from the government source that posted it. Updated .