This amendment to a solicitation provides additional details for a federal contract opportunity involving the modernization of three elevators in the JFK Mid-Rise Bank located in Boston, MA. The General Services Administration seeks a contractor to modernize elevators 7, 8, and 9 and integrate them onto a new dispatching system while ensuring the four remaining elevators can continue independent operation and integrate at a later date. The estimated price range for the modernization is between $1,000,000 and $5,000,000. The solicitation number is 47PB0023R0035 and responses were due by June 8, 2023. The amendment addresses questions received and requires the contractor to isolate the three modernized elevators from the existing group, install new wiring for the three car group, and provide for future integration of all seven elevators onto a destination dispatching system.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
1. Does the facility have a plan to modernize the additional three elevators within this bank subsequent to elevators 7, 8 and 9? This elevator bank consists of six total elevators that all work in tandem with one another. The current procurement calls for the modernization of three of the six elevators. While funding is an obvious constraint, it is typical for all elevators within a bank to be modernized simultaneously so they are all the same make, model and vintage, and also so they can properly interface with one another. We can make that happen with an interface cross-cancellation panel between the six cars, but that’s typically not a long-term solution.
o GSA Response - The GSA does intend to modernize the other four elevators in the mid-rise bank when funding becomes available. Due to the current funding constraints the GSA has determined that separating the (3 ELEVATORS THE ARE TO BE MODERNIZED) from the existing 7 elevator group is in the best interest of the government. This decision would require the contractor to ensure the 4 existing elevators run on the same dispatching algorithm they have been since installation and would require upgrading the 3 elevators on a new system. The contractor shall include provisions for the 4 remaining elevators to be modernized to tie into the dispatching panel that is installed for the new system and to ensure that each system runs independently of the other.
2. Would the facility still like a price for Alternate No. 3 related to destination dispatching?
o Similar to question #1, destination dispatching only works if every elevator within the group is of the same make and model. If the plan is to modernize just three of the six elevators it is not practical, or potentially even possible, to implement destination dispatch.
o GSA Response - The GSA is not requesting an alternate price to include destination dispatching for all 7 elevators. The elevators shall run on standard group dispatching vs Destination dispatching. Once all the 7 elevators are upgraded then destination dispatching can be deployed. The base contract should have the full destination controls set in place and the work shall support the GSA requirement to switch from standard dispatching to destination dispatching when a future contract is awarded to modernize the additional 4 cars in the midrise.
As a result of the RFI request the following scope is required to support work for cars 7,8 & 9:
The Contractor shall remove the Triplex from the existing 7 car group.
• These cars will be completely modernized and function as a stand group when it refers to dispatching.
o Isolate and install new wiring for new 3 car group. No cross-cancellation panel will be provided to tie all 7 elevator in back.
o All work for car 7-9 shall be as specified in contract documents.
o Dispatching to be Destination based as specified.
o Group dispatcher to have provisions for all 7 elevators in mid-rise bank to be tied in at a later date.
o Cars 7-9 & 10-13 to work independently of each other until tied in together at a later date.
The contractor shall provide the required work to ensure that Cars 10-13 are independent of the scope in this solicitation:
• These cars are to be isolated into a 4 car group with existing equipment and dispatching.
• These newly formed 4 car group will not communicate with the newly modernized elevators 7-9 for the time being.
• Once modernization of elevators 10-13 occurs the Mid-Rise bank will once again consist of a 7 car group with Destination Dispatching.
| topmostSubform[0]: |
| Page1[0]: |
| Code[0]: 1PQC |
| Copies[0]: 1 |
| CheckBox9[0]: 1 |
| Code[2]: 1PQC |
| NameandTitleOfficer[0]: Sebastian Asaro, Contracting Officer |
| Is[0]: 1 |
| CheckBox10[0]: Off |
| NameandAddress[0]: |
| DateSigned[1]: |
| Pages[0]: 3 |
| AmendmentNo[0]: 0003 |
| Dated10B[0]: |
| ModificationNo[0]: |
| AdministeredBy[0]: Acquisition Management Division (1PQ) Contract Operations Branch (1PQC), GSA/PBS |
10 Causeway Street, Rm 1100 Boston, MA 02222-1077 USA
| FacilityCode[0]: | |
| CheckBox13B[0]: Off | |
| CheckBox13D[0]: Off | |
| ReqNumber[0]: EQ1PSKM-23-0033 | |
| Dated9B[0]: 5/8/2023 | |
| 2023-06-09T12:33:47-0400 | |
| SEBASTIAN ASARO |
| C13[0]: |
| Description[0]: The purpose of this amendment is to |
1. Incorporate the government's response to RFI'S dated 06/09/2023.
2. All other terms and conditions remain unchanged.
| NotExtended[0]: 1 |
| Code[1]: |
| AmendmentNo[1]: 47PB0023R0035 |
| ContractIDCode[0]: |
| DateSigned[0]: |
| CheckBox11[0]: 1 |
| Page[0]: 1 |
| AccountingData[0]: |
| CopiesReturned[0]: 1 |
| CheckBox13A[0]: Off |
| IsNot[0]: Off |
| EffectiveDate[0]: 6/9/2023 |
| A13[0]: |
| ProjectNo[0]: RMA12726 |
| CheckBox13C[0]: Off |
| Extended[0]: Off |
| D13[0]: |
| IssuedBy[0]: Acquisition Management Division (1PQ) Contract Operations Branch (1PQC), GSA/PBS |
10 Causeway Street, Rm 1100 Boston, MA 02222-1077 USA NameandTitleSigner[0]:
File details come from the government source that posted it. Updated .