JAN 2026 TKY Consolidation Schedule.pdf
PDF 201 KB Posted
- Attached to
- 6525--JAN 2026 Consolidation - HTME with Extended Installation Services (includes Turnkey Services)
- Solicitation number
- 36A79726Q0008
About this file
This document is a consolidation procurement schedule for HTME (Healthcare Technology Management Equipment) with Extended Installation Services, including Turnkey Services. The consolidation is managed by Michael Kuchyak and applies to all modalities within the program. The schedule outlines a two-phase acquisition approach: an equipment-only phase followed by a turnkey services phase that includes site visits and installation scopes.
The procurement timeline begins with requirements submission to the NAC (National Acquisition Center) by January 31, 2026, followed by publication of a Pre-Solicitation Notice on March 6, 2026, and the formal Request for Offers (RFO) on March 11, 2026. Vendors submit equipment-only questions by April 1, 2026, with responses published by April 22, 2026. Equipment offers are due May 20, 2026, and customers receive offers on May 27, 2026. Technical evaluations for equipment selection (best value basis) are due June 17, 2026, the same date as CO Engagements. Following site visits and turnkey scope discussions on July 15, 2026, vendors submit turnkey offers by August 26, 2026. Customers submit technical evaluations for turnkey services by September 9, 2026, with a goal to award delivery orders by October 14, 2026. All dates are estimates and subject to change.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| JAN 2026 TKY Schedule of Requirements w QA - Updated 4-22-26.xlsx | XLSX spreadsheet | |
| 36A79726Q0008 0001.docx | DOCX document | |
| 521B62001 - 578B68008.zip | ZIP file | |
| 605B60047 - 695B68003.zip | ZIP file | |
| Amendment 0001 - Continuation Page.pdf | ||
| NAC Turnkey Rubric - 2 Mar 2026.pdf | ||
| VA Directive 6550 - New Appendix A - published Jun. 2023.docx | DOCX document | |
| Vendor Folders.zip | ZIP file | |
| 460B68004 - 556B61003.zip | ZIP file | |
| 646B52002 - 695B68003.zip | ZIP file | |
| 578B58006 - 640B64047.zip | ZIP file | |
| JAN 2026 TKY Schedule of Requirements - Updated 3-11-26.xlsx | XLSX spreadsheet | |
| Memorandum for Training.pdf | ||
| Vendor Workup Spreadsheet - 36A79726Q0008.xlsx | XLSX spreadsheet | |
| JAN 2026 Extended Install and Turnkey Consolidation RFO.pdf | ||
| 36A79726Q0008_1.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JAN 2026 Consolidation - HTME with Extended Installation Services (includes Turnkey
Services) Schedule
Consolidation Manager - Michael Kuchyak
Dates* Milestone – All Modalities
1/31/2026 Requirements due to the NAC in FORCE
3/6/2026 Post Pre-Solicitation Notice
3/11/2026 Post Requirements and Request for Offers (RFO)
4/1/2026 Vendors to submit EQUIPMENT ONLY Questions to NAC
4/22/2026 NAC to Publish Responses to Vendor Questions via Amendment
5/20/2026 Vendors to Submit Equipment Offers to NAC
5/27/2026 Customers to Receive Vendor Offers via the Shared Drive
6/17/2026 Customers Submit Technical Evaluations (Best Value Selections) EQUIPMENT ONLY
6/17/2026 CO Engagements
7/15/2026 NAC CO communicates with Selected Vendors + Customers for site visits/Turnkey Scopes
8/26/2026 Vendors to Submit Turnkey Offers to NAC CO & Consolidation Manager
8/26/2026 NAC CO furnishes Turnkey offers to Customers
9/9/2026 Customers to submit Technical Evaluations for Turnkey to NAC CO
10/14/2026 Goal to Award Delivery Orders
*Dates are estimates and are subject to change