JA Typhoon Sinlaku Additional Stone_Redacted.pdf
PDF 488 KB Posted
- Solicitation number
- N40192-26-JARS-009
About this file
This is a Justification and Approval (J&A) for Use of Other Than Full and Open Competition issued by Naval Facilities Engineering Systems Command (NAVFAC) Marianas on September 30, 2026.
The document authorizes a sole-source contract modification to Tutor Perini Corporation Nan Inc. A Joint Venture (TPC-NAN JV) under existing contract N62742-22-D-1314-N4019225F4003 for critical emergency waterfront stabilization repairs at Apra Harbor, Guam. The modification value is $19,624,552.00 in fiscal year 2026 funding and represents approximately three percent of the total contract value. The work involves procuring and placing additional critical armor stone to mitigate active breaches and stabilization damage to the Glass Breakwater caused by Typhoon Sinlaku (April 2026), with a period of performance not expected to exceed one year. The Glass Breakwater, approximately 2.9 miles long, is the Navy's longest and largest breakwater and is strategically critical to military logistics, operations, and mission readiness in the Indo-Pacific region, serving as the only marine passage for Department of Defense operations in the region.
The J&A invokes 10 U.S.C. § 3406(c)(1) (Unusual and Compelling Urgency) as statutory authority, citing the critical need to complete emergency stabilization repairs before the peak 2026 typhoon season (late August through mid-November) to prevent catastrophic breakwater failure. The incumbent contractor, already mobilized and performing ongoing repairs from Typhoon Mawar damage, is best suited for timely execution. The Contracting Officer determined the cost fair and reasonable based on evaluation against an Independent Government Estimate and historically competitive rates from the existing contract. Future permanent restoration phases will be competed to the maximum extent practicable once the site is stabilized.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND MARIANAS
PSC 455, BOX 195
FPO AP 96540-2937
IN REPLY REFER TO:
Ser: N40192-26-JARS-009 30 September 2026
JUSTIFICATION AND APPROVAL
FOR USE OF OTHER THAN FULL AND OPEN COMPETITION
1. Contracting Activity
Naval Facilities Engineering Command (NAVFAC Marianas), Naval Base Guam (NBG), Resident Officer in Charge of Construction (ROICC) Guam, South.
2. Description of the Action Being Approved
Award a contract modification on a sole-source basis to Tutor Perini Corporation Nan Inc. A Joint Venture (TPC-NAN JV) under contract N62742-22-D-1314-N4019225F4003, the contractor currently performing waterfront and breakwater repairs at Apra Harbor, Guam, for damage sustained from Typhoon Mawar in May 2023. This contract modification is for critical emergency waterfront stabilization repairs at Apra Harbor for damage caused by Typhoon Sinlaku using $19,624,552.00 fiscal year 2026 (FY26) funding.
This modification will be executed under the authority of 10 U.S.C. § 3406(c)(1), Unusual and Compelling Urgency. This period of performance for this modification is not expected to exceed one year.
3. Description of Supplies/Services
This modification covers additional work required to make immediate emergency waterfront stabilization repairs for damage caused by Typhoon Sinlaku to the Glass Breakwater in April 2026. Following Typhoon Sinlaku, the Government took immediate action through an initial modification to authorize placement of 20k tons of stone needed for emergency repairs based on initial assessments and procure a survey to understand the extent of the damage. However, before the full scope of repairs could be determined, Guam was impacted by a second storm, Typhoon Bavi, in July 2026. Due to the short time frame between Typhoon Sinlaku and Typhoon Bavi, it took the designers time to identify and segregate requirements attributable to the emergency repairs under each storm. Based on the results of the survey, it was determined that additional armor stone is required to complete stabilization requirements as tied to Typhoon Sinlaku. This FY26 emergency waterfront stabilization repair constitutes a bona fide need of FY26 and its estimated value is $19,624,552.00 which is approximately three (3) percent (%) of the total contract value. Under this modification, the contractor shall procure/place additional critical armor stone to mitigate active breaches caused by Typhoon Sinlaku.
4. Statutory Authority Permitting Other Than Full and Open Competition
The statutory authority permitting other than full and open competition is 10 U.S.C. § 3406(c) as implemented by FAR 16.507-6(b)(1): the agency need for the supplies or services is so urgent that providing a fair opportunity would result in unacceptable delays.
5. Rationale Justifying Use of Cited Statutory Authority
The Glass Breakwater is a rubble-mound gravity coastal structure initially constructed circa 1946 to provide a safe harbor to Outer Apra Harbor and Inner Apra Harbor. Apra Harbor is strategic to the Indo-Pacific region for military logistics, operations, and mission readiness. The Glass Breakwater provides safe passage for all marine vessels and safe harbor for all waterfront structures within Apra Harbor. This critical infrastructure provides coastal defense from sea state conditions in the Philippine Sea that would otherwise render safe passage in Apra Harbor inoperable. This breakwater, at approximately 2.9 miles long, is the longest and largest breakwater owned by the Navy and one of the largest breakwaters owned by the DoD.
Historically, the breakwater has been repaired or modernized after significant wave events. The last repair project on the breakwater was competitively awarded in 2025, to TPC-NAN JV, after Typhoon Mawar, and has not yet been completed.
In its deteriorated condition, Glass Breakwater is progressing towards failure as defined by the United States Army Corps of Engineers (USACE). In its current condition approximately one-third of the breakwater has outside of the breakw further deterioration was discovered which indicated the breakwater contin damage criteria despite the lack of significant weather events. This progression towards failure indicates the breakwater is at significant risk of partial breach, which will eventually lead to full breach.
Due to the high potential and frequency of storms within this region, another storm could emerge at any time, expediting further breakwater damage, and thereby limiting the military logistics and operations in the region. Since Typhoon Mawar, Guam has been narrowly missed by numerous storms. According to e typhoon season for Guam runs from late June through December (when Pacific Ocean the water temperatures are at their warmest), with the peak of the typhoon season occurring between late August through mid-November. In their annual seasonal forecast National Oceanic and Atmospheric Administration (NOAA) predicts an above-average 2026 typhoon season due to El Nino. As such, it is imperative that Glass Breakwater maintains its coastal defense capabilities to ensure accessible marine passage through Apra Harbor. This is in the best interest of the United States.
This modification is a mission critical project for additional emergency waterfront stabilization repairs for damage caused by Typhoon Sinlaku, which are in addition to the stabilization repairs currently being performed by TPC-NAN JV under contract N62742-22-D-1314-N4019225F4003. As detailed in Section 3, the timeframe to execute the repairs caused by Typhoon Sinlaku was impacted by the need to analyze the extent of damage and repair requirements following Typhoon Bavi, which hit Guam soon after Typhoon Sinlaku. Now complete and with the appropriate FY26 funds aligned to these validated requirements, immediate execution of this modification is required to prevent catastrophic failure of the breakwater during the remainder of the peak 2026 typhoon season.
Any delay in completing the emergency waterfront stabilization repairs for damage caused by Typhoon Sinlaku will delay all successive construction activities and will not be recoverable. Delay in executing the emergency waterfront stabilization repairs the subject of this modification will result in serious injury financial and operational to the Government, i.e., will negatively impact progress on the current Glass Breakwater repair project, which in turn affects military logistics, operations, and mission readiness in the Indo-Pacific region, as Apra Harbor serves as the only marine passage for the Department of Defense (DoD) he Indo-Pacific.
The incumbent contractor, TPC-NAN JV, is already mobilized and performing repair work on the Glass Breakwater and is best suited to timely complete the emergency stabilization repairs, the subject of this modification, thereby mitigating the threat to military readiness, national security and port safety at Apra Harbor, Guam. In addition to the foregoing, Glass Breakwater has physical constraints prohibiting the efficient and effective presence of multiple contractors. Finally, the emergency waterfront stabilization repairs required under this modification were not required at the time of award of contract N62742-22-D- 1314-N4019225F4003 and are now required to mitigate further damage to the Glass Breakwater.
6. Description of Efforts Made to Solicit Offers from as Many Offerors as Practicable.
Due to the unusual and compelling urgency, standard synopsizing was not conducted. Soliciting other sources is not practicable for the reasons stated above.
7. Determination of Fair and Reasonable Cost
The Contracting Officer has determined the anticipated cost of $19,624,552.00 to the Government for the emergency stabilization repairs required under this modification to the Glass Breakwater, and covered by this J&A, will be determined fair and reasonable based on the evaluation of the proposal against the Independent Government Estimate (IGE) and historically competitive rates established under contract N62742-22-D-1314-N4019225F4003.
8. Actions to Remove Barriers to Future Competition
This J&A will not be used as a basis to circumvent competition for future, non-urgent requirements. Future permanent restoration phases will be competed to the maximum extent practicable once the site is stabilized.
ACQUISITION VALUED OVER $10,000,000 BUT NOT EXCEEDING $100,000,000
ECHELON IV COMMANDING OFFICER APPROVAL
Upon the basis of the above justification, I hereby approve, as Echelon IV Commanding Officer, Competition Advocate, the solicitation of the proposed procurement described herein using other than full and open competition, pursuant to the authority of 10 U.S.C. § 3406(c), Unusual and Compelling Urgency.
CAPT Alan Eichelman, P.E.
Signature Commanding Officer, NAVFAC Marianas