J2. Morgan Trail SOW.pdf

PDF 7 MB Posted

Attached to
NFsNC 2023 Trail IDIQ Federal contract opportunity
Solicitation number
12445223R0026
Issued by
Department of Agriculture Forest Service

About this file

This document outlines a statement of work for a trail maintenance and construction task order under the NFsNC 2023 Trail IDIQ contract solicited by the Department of Agriculture Forest Service. Work includes maintenance of approximately 1.5 miles of the Morgan Trail as well as relocation of 0.2 miles of trail. Maintenance tasks encompass activities such as brush cutting, drainage installation, grade dip construction, and culvert replacement. The relocation section requires construction of a new 4-foot wide trail along the flagged centerline that meets accessibility and drainage standards. Additional scope includes installation of a horse gate and kissing fence. Bidders must visit the site and submit pricing for the base and option items by the specified response date.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA Forest Service – Region 8 Uwharrie National Forest Uwharrie Ranger District

MorganTrail Relocation & Maintenance

Project

Trail Maintenance and Construction

November 2022

Morgan Trail Maintenance & Relocation November 2022 Page 1

Attachment: Task Order for NFsNC Trail Maintenance and Construction Contract

Contract number:

Task Order # Task Order Name: Morgan Trail Relocation & Maintenance Project

Location The subject trail is located on the Uwharrie National Forest, northwest of Troy, North Carolina.

Scope of Work and Design Criteria

Work to be performed Work includes existing trail maintenance, new trail construction (relocation of existing trail segment), hardened drainage crossing construction (shell rock with pressure-treated timber retainers), and gate/fence construction (option bid items).

Specifications All trail maintenance, new trail, and structure construction required under this contract must be done in accordance with Standard Specifications for Construction of Trails and Trail Bridges on Forest Service Projects (10/30/2014), NFsNC Trail IDIQ contract documents, Forest Service agency standards, Trail Log and Project Drawings.

Trail Maintenance Perform trail maintenance for the trail length as specified in the Trail Log and Schedule of Items. Trail maintenance shall include, but not be limited to, existing tread restoration (de-berming, out-sloping, drainage maintenance, hazard tree removal, brush cutting, trail obliteration, etc.). All work outlined in the trail log for which there is no separate pay item shall be incidental to Trail Maintenance.

Grading operations shall be conducted as required to remove ruts, potholes, and corrugations, remove berm, and out-slope or crown trail tread to drain, as the terrain dictates. All suitable dislodged material shall be smoothly redistributed over the entire traveled way and firmly packed. The trail shall be graded to establish cross-slope or crown and provide positive drainage. Mud-holes shall be drained & filled with suitable material, compacted, and graded to drain.

Suitable soils have migrated from the original trail and are often found within the disturbed trail corridor (e.g., in drainage ways & trail-side berms). Reclaim, conserve, and use all suitable on-site material from maintenance and construction operations for specified work. Suitable on-site material shall include soil that is free of duff with a recognizable granular structure, having the same character as the trail surface and rock that can be accommodated in the trail structure. The trail shall be de-bermed, drainage ways shall be cleared and these suitable soils shall be ‘pulled in’ and used in trail tread grading and for the construction of rolling grade dip ramps.

Frequent hardened rolling grade dips with lead-off ditches are required. At numerous locations, the trail log states “add grade dip”; this statement refers to the repair, re-construction and/or construction of grade dips and associated lead-off ditches. When specified in the trail log, harden grade dip ramps with rock. Rock for

Morgan Trail Maintenance & Relocation November 2022 Page 2 hardening rolling grade dip ramps shall be imported shell rock available at Causey Construction in Asheboro NC (336-736-9725) or equal.

A minimum of 50 grade dips per mile is required. To achieve positive drainage on some sections of trail, berm punch-throughs with new grade dips and lead-off ditches may be required. The term ‘grade dip’ is synonymous with the term ‘drain dip’. All existing grade dips will need to be cleaned, repaired or re-constructed and new grade dips will need to be added. When out-sloping, installing and/or rebuilding drainage structures, assure drainage from the entire width of trail.

Suitable moisture content (MC) for trail grading shall be within the range of five percent (5%) to fifteen percent (15%) by weight. Unless authorized, no grading may be performed while the moisture content is outside this range.

Below 5% MC, the trail bed visually appears to contain little, if any, moisture. Heavy dusting is present.

Wetting precipitation has not occurred in the recent past. Unacceptable results below 5% MC would be indicated by extreme powdering and dusting.

Above 15% MC, the trail bed appears over-saturated, contains standing water, or may be rutting slightly.

Recent heavy precipitation has occurred. Unacceptable results above 15% MC would indicate clumping, rutting and inability to spread material.

Unacceptable results below 5% and above 15% MC would indicate inability to obtain maximum compaction of material.

No grading or other maintenance operations shall be performed during periods of freeze/thaw or when the ground is frozen.

Compaction of trail bed and associated earthwork within the trail, (e.g., grade dips) shall be performed with the material moisture content suitable for optimum compaction. The entire width of the trail shall be uniformly and thoroughly compacted. Complete compaction is obtained when no noticeable displacement of material is observed.

When properly compacted, the entire trail width shall be smooth and dressed to produce a uniform cross-slope with a surface free of hollows, depressions, and projections. The entire trail tread width shall hold together under normal use.

Acceptable results of grading operations shall be a trail bed that is firm, smooth, and finished to width and provides positive drainage from trail tread, without berms or undercutting at shoulders. No roots or rocks (exceeding maximum obstacle height as specified in design criteria) shall be protruding from the graded surface. Roots that exceed obstacle height shall be covered with suitable soil.

Abandoned Trail Obliteration A 0.2 mile section of the existing trail is to be relocated, and the abandoned trail “obliterated” to discourage continued use. The abandoned section of trail shall be blocked using brush, rocks, logs, or any other material along the trail appropriate for use in this manner. Obliteration shall be done for the full-width of the trail, and for a distance of 100 linear feet on each end at a minimum. Acceptable results of obliteration shall be a closed trail that is no longer noticeable or accessible to users from any point, including locations along the new, relocated trail. Additional brushing in may be required to achieve this result. Do not cross

Morgan Trail Maintenance & Relocation November 2022 Page 3 white flagged area to transport brush from new trail to abandoned trail. Transport brush be bringing it in from either end of abandoned trail.

Danger Tree Removal The Contractor shall remove trees and snags that are broken off or that are in a leaning, unstable position over the trail-way. Standing dead and danger trees within the clearing area and within 15 ft. of either side of the trail centerline shall be removed (i.e., a 30 ft. wide corridor centered on the trail centerline).

New Trail Construction (Relocation) Construct new 4 ft. wide full-bench, outsloped, side-hill trail as flagged. Pink flagging along centerline with 50’ corridor for varying. Do not disturb area flagged in white ribbon.

New trail construction includes clearing, grubbing, grading and compaction, drainage installation, smooth transitions to existing trail, etc. All work required to construct 4 ft. wide Class 3 pack and saddle/biking/hiking trail meeting Forest Service Standards is included.

Meander trail tread as necessary to drain. Install frequent grade reversals, grade dips and lead-off ditches to build sustainable, well-drained tread.

Transition grade smoothly to match existing trails on both ends where new trail connects to existing trail.

Preferred maximum grade of new trail shall be 10%. Allowable maximum grade for short runs (less than 50 LF continuous) shall be 15%.

Hardened Drainage Crossing with Retainers Where called for in trail log, harden the trail tread at approaches to drainage crossings with rock encased in 6” x 6” pressure-treated timber retainers. Harden grade dip ramps shell rock, where called for in the trail log. Before installing hardened tread surfacing, remove organic materials, grade, shape and compact mineral soil as required. All imported material must be approved by COR prior to placement.

Rock for hardening retained drainage crossing approaches (and rolling grade dip ramps) shall be imported shell rock available at Causey Construction in Asheboro NC (336-736-9725) or equal.

Erosion Prevention and Sedimentation Control All work shall be performed and maintained to prevent erosion and sediment migration to area waters and habitats. If the work creates potential for soil erosion or silt migration, the contractor will be responsible for implementing best management practices prior to soil disturbance (e.g., installing silt fence, straw bales or other suitable containment).

Prior to grading activities, remove and stockpile duff. After grading activities are complete, naturalize the trail corridor by scattering the saved duff on and alongside the newly restored trail (on any disturbed or scattered soils). The intent is for the duff to naturalize the newly restored trailway and to provide erosion prevention. Do not create a berm with the duff. Do not place materials in stream channels, drainage-ways, ditches, culvert inlets, or other locations where they would prevent the free flow of water away from the trail tread.

Morgan Trail Maintenance & Relocation November 2022 Page 4

Barricade (Gate & Fence) Construction – See Project Drawings The task order includes two option bid items for a horse-friendly gate and an accessible kissing fence at Sta. 90+00. The purpose of this gate and fence is to prevent motorized vehicles (motorbikes, ATVs, etc.)

from accessing the trail while allowing horses to access the trail by stepping over the gate, and allowing bikers, pedestrians (with strollers, etc.) to access the trail by going through the kissing fence.

Access Access may be an issue for certain types of equipment. It is the Bidder’s responsibility to view the project trail to assess the full range of construction needs, analyze access points, constraints, and the logistics of transporting imported materials.

Additionally, Contractors shall:

• Review the project site on the ground prior to submitting a bid.

• Lay out and flag dip locations, structures, and hazard trees. The Forest Service COR shall approve lay out and hazard tree felling prior to ground disturbing work or tree felling.

• Post temporary trail closure signs when work includes use of heavy equipment, felling trees, or poses a safety risk to users.

• If notified, stop work on all or certain sections of the project due to weather conditions, evidence of archeological sites or sensitive species.

Order of Precedence Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:

1 – The Statement of Work and the Schedule (excluding the specifications) 2 – Representations and Other Instructions 3 – Contract Clauses 4 – Other Documents, Exhibits, and Attachments 5 – The Specifications 6 – Drawings

Inspection Date: September 19, 2022 Inspector Names: Terry Savery and Kathryn Moore

Morgan Trail Maintenance Length: 8,000 LF (about 1.5 miles) Morgan Trail Relocation Length: 1,117 LF (about 0.2 miles) Abandoned Trail Obliteration: 100 LF (brush in 50 LF on each end)

General: Coordinate with the Uwharrie District Ranger Office to obtain gate keys, if required. The address is 789 Biscoe Road, Troy, NC. The phone number is (910) 576-6391.

Morgan Trail (TR-718) work begins at the intersection with Burl Tree Way Trail (TR-717) about 100 LF from NFSR-576 (Moccasin Creek Rd). This location is marked with signage (see attached map).

The trail log and trail maintenance work begins at this intersection. Station distances were measured with a surveyor’s wheel. The new trail (relocation) section centerline was flagged with pink flagging. The new trail location can depart from the flag-line when necessary to optimize drainage, within a 100 ft. corridor (i.e., 50 ft. to either side of the flag-line). Do not cross into white-flagged “no work” areas adjacent to this https://www.google.com/search?q=nantahala+ranger+district+phone&ludocid=11932898366007185361&sa=X&ved=2ahUKEwiIo-GTs8H2AhXNp3IEHVjlCJgQ6BN6BAgeEAI

Morgan Trail Maintenance & Relocation November 2022 Page 5

100 ft. corridor. Morgan Trail crosses OHV trails and are coincident to those OHV trails in several places for a total distance of 53 LF. These OHV trail segments are “no work” sections therefore this length has been subtracted from the total maintenance length line item.

Design Criteria The trail is native surface classified as a Trail Class 3 Pack & Saddle (Horse) trail. Hiking and bicycling are allowed uses. Typically, travel way widths on the maintenance sections of trail shall be perpetuated as existing (i.e., no need to narrow down the existing trail to design width) unless otherwise noted. The specified cross slope must be maintained over the entire trail width such that positive drainage exists from all sections of trail tread, regardless of width.

Design Tread Width – 4 ft.

Design Cross Slope – 5% Brush Cutting Height - 10 ft.

Brush Cutting Width – 8 ft.

Maximum Obstacle Height – 6 inches

Trail Log References:

The terms “left” and “right” are referenced proceeding up-station (i.e., beginning at Station 0+00 and proceeding to end of work)

GD – grade dip RGD = rolling grade dip HRGD = hardened rolling grade dip (i.e., rolling grade dip ramp surface hardened with rock) LOD = lead-off ditch DB = de-berm OS = out-slope DBH = diameter at breast height L – left R – right

The trail log is for reference purposes and illustrates some of the items of work to be accomplished. The intent of the logs is to give a general description of the trail. The trail log does not identify every work item. For example, some items of work, such as grade dip locations are specifically called out in the trail log, however not all locations where such items are required have been called out. There will be other locations where such work items will be required. Refer to the IDIQ contract instructions and specifications.

The Contractor shall visit the project site and view the work on the ground prior to submitting a bid. A detailed trail assessment log follows.

Morgan Trail Maintenance & Relocation November 2022 Page 6

Station Maintenance & Construction Need / Reference Points

Notes / Photos

-01+00 Photo: Moccasin Creek Rd.

(NFSR-576) intersects Burl Tree Trail (TR-717) here. The intersection of Burl Tree Trail with Morgan Trail is about 100 from the road.

Follow Burl Tree Trail to Sta.0+00 of Morgan Trail.

0+00 Begin typical trail maintenance at Station 0+00, where Morgan Trail intersects Burl Tree Trail.

Typical trail maintenance includes: brush cutting, logging out, danger tree removal, deberming, outsloping, rolling grade dip installation, etc.

0+00 Construct 3 check steps using 8

ft. long 6” x 6” pressure treated timbers spaced 12 ft. apart (min.) Anchor ends of check steps into side banks 1 ft. min.

24 LF 6” x 6” PT timbers for check steps

Morgan Trail Maintenance & Relocation November 2022 Page 7

0+44 Construct HRGD-R HRGD – Hardened Rolling Grade Dips will require approximately ½ TON of rock per grade dip (typical)

1+28 Construct hardened drainage crossing approach. Construct 10 LF, 6 ft. wide, hardened approach to drainage crossing.

Use 6” x 6” pressure treated retainers compacted mineral soil surfaced with shale rock ( l)

30 LF 6” x 6” PT timbers for rock retainers

1.65 TON rock

1+42 Ref: Center of drainage

1+57 Construct 10 LF, 6 ft. wide, hardened approach to drainage crossing.

30 LF 6” x 6” PT timbers for rock retainers

1.65 TON rock

2+00 Construct HRGD-R 3+43 Construct HRGD-R, OS-R

4+87 Use suitable material to cover exposed roots.

4+97 Construct HRGD-R

5+91 Photo facing back-station

6+55 Construct HRGD-R

8+81

Construct HRGD-R

9+68 Construct 10 LF, 6 ft. wide, hardened approach on each of drainage (total of two hardened approaches).

60 LF 6” x 6” PT timbers for rock retainers

3.3 TON rock

Morgan Trail Maintenance & Relocation November 2022 Page 8

9+78

Ref: center of drainage.

9+87 Maintain trail-right, block trail-left by brushing in.

10+20 Construct HRGD-R

Obliterate braided trail-L by brushing in approx. 25 LF.

10+65 Construct HRGD-R

10+75 Install 2 - 10 ft. long, 6”x 6” check steps, 12 ft. apart (min).

Anchor into banks. Fill in over roots at Sta. 10+85. Reduce root obstacle height to 6” maximum.

20 LF 6” x 6” PT timbers for check steps

11+15 to 11+71

Entrenched trail. Use suitable material obtained from grading operations to build up and outslope trail tread

35.427265, -80.043417

12+51 Construct HRGD-R

13+57 Construct HRGD-R. Block braided trail-L for 30 LF by brushing in

Morgan Trail Maintenance & Relocation November 2022 Page 9

14+53 Construct HRGD-R

15+10 Construct HRGD-R

16+06 Construct HRGD-R 16+28 Construct HRGD-R

16+71 Construct HRGD-R

17+51 Construct HRGD-R

18+22 Braided trail. Maintain trail-L, obliterate trail-R by brushing in.

OS-R.

18+91 Construct HRGD-R 19+66 Construct HRGD-R

20+31 Construct HRGD-R 21+34 Construct HRGD-R

Morgan Trail Maintenance & Relocation November 2022 Page 10

22+00 to 23+00

Trail goes left.

Ref: downed tree, slash on right

35.425257, -80.045102

Avoid impacting trailside environment here. Do not disturb quartz cobbles in the vicinity. Contain all work to the existing, already disturbed trail.

23+39 to 23+58

Trail intersects Rocky Mountain Loop OHV Trail (TR-92). Go left on OHV trail for approx. 20 ft.

No work required on OHV trail segment.

Turn right, continue Morgan Trail maintenance.

Morgan Trail Maintenance & Relocation November 2022 Page 11

23+95 Replace existing 30-inch CMP culvert with 18 LF-30-inch CMP culvert. Build up trail over culvert to achieve a minimum 1

ft. of cover. Re-construct banks at 2H:1V from trail tread down to new culvert inverts. Harden inlet slope with on-site area rock. Clear inlet and outlet channels for a minimum 100 LF (200 LF total – incidental to trail maintenance).

23+95 Outlet of existing 30-inch CMP

18 LF-30” CMP

25+72 Construct HRGD-R

26+37 Install one 6”x6” 8 LF check step, anchor into side banks.

8 LF 6” x 6” PT timbers for check step

27+10 Construct HRGD-R

27+67 Construct HRGD-R

28+76 Construct HRGD-R

Morgan Trail Maintenance & Relocation November 2022 Page 12

29+84 to 30+40

Braided trail, maintain trail-left.

Use suitable material obtained in grading operations to fill, build up trail tread and outslope-left to drain. Obliterate user created trail- right by brushing in.

35.423840, -80.046642

30+67 Construct HRGD-L

31+71 Construct HRGD-R

32+29 Construct HRGD-R

32+76 Ref: center of drainage

Construct 10 LF, 6 ft. wide, hardened approaches on each side of drainage.

60 LF 6” x 6” PT timbers for rock retainers

3.3 TON rock

33+22 Construct HRGD-R

34+79 Construct HRGD-R

35+20 Cover roots with suitable material

Morgan Trail Maintenance & Relocation November 2022 Page 13

35+31 Construct HRGD-R 35+70 Construct HRGD-R

35+85 Cover roots with suitable material

36+20 Construct HRGD-R 37+55 Construct HRGD-R

38+75 Construct HRGD-R

39+15 Construct HRGD-R

39+96 Obliterate / brush in braided trail-right for approx. 40 LF

42+19 Construct HRGD-R

42+50 Remove old plastic debris from trail area. Install 20 LF hardened crossings (10 LF each side of drainage.

60 LF 6” x 6” PT timbers for rock retainers

3.3 TON rock

42+78 Ref: center of drainage.

42+91 End hardening. Maintain trail-R, obliterate trail-L Photo view toward Dutch John Rd. (NFSR-553)

Replace existing 18-inch HDPE culvert at road with 26 LF-18-inch CMP. Regrade to provide 1

ft. min. cover. Install three 10 LF, 6” x 6” check steps below to hold material above. Start check steps at 6’ from culvert location.

Space check steps at a min. of 12’ apart.

30 LF 6” x 6” PT timbers for check steps

26 LF-18” CMP

43+30 HRGD-L. Harden grade dip with area rock.

Morgan Trail Maintenance & Relocation November 2022 Page 14

43+65 Photo taken from road back toward proposed trail hardening.

43+65 Turn left for a short distance to continuation of Morgan Trail on opposite side of road.

44+27 Continue Morgan Trail maintenance.

45+37 Construct HRGD-R 46+04 OS-R. Construct ditch on right.

Remove plastic debris from trail area (about 20 LF)

46+24 Build up trail 46+36 Construct HRGD-R 47+87 Construct HRGD-R 49+16 Construct HRGD-R 50+39 Construct HRGD-R 50+99 Existing 8 LF-18” HDPE culvert, good condition. Add suitable material to build up trail tread over existing culvert to obtain 1

ft. min. cover. Clean inlet & outlet of culvert and clear drainage channel for 50 LF on both inlet and outlet sides (incidental to trail maintenance).

51+35 Obliterate user-created trail, right.

52+30 Remove 3 hazard trees, left

Morgan Trail Maintenance & Relocation November 2022 Page 15

52+80 Construct HRGD-L 52+97 Install one 10 ft. long 6” x 6” check step, anchor into banks.

Use suitable material to cover roots at 53+00

10 LF 6” x 6” PT timbers for check steps

54+17 Ref: intersection with Rocky Mt.

Loop OHV Trail. Go right to continue Morgan Trail

No work required on OHV segment of trail

54+33 Continue Morgan Trail maintenance

54+62 Begin new Morgan Trail construction, left. Obliterate original Morgan Trail ahead.

54+62 Begin Trail Relocation. Pink flagging indicates approximate center line of new trail. Avoid area delineated with white flagging.

Coordinate with COR prior to beginning relocation construction and abandonment of existing trail.

35.41853, -80.048119

54+62 New Trail Construction Contractor to field locate and stake proposed trail relocation.

Notify COR for approval prior to construction.

Begin Trail Relocation. Pink flagging indicates approximate center line of new trail.

AVOID DISTURBING WHITE-

FLAGGED AREAS.

With the exception of white-flagged areas, the new trail can depart from flagged centerline by 50 ft. Construct new trail to fit terrain, optimize positive drainage.

Construct new 4 ft. wide full-bench, outsloped, side-hill trail as flagged.

Length = 1,120 LF New trail construction includes clearing, grubbing, grading and compaction, drainage installation, smooth transitions to existing trail, etc.

All work required to construct 4 ft. wide Class 3 equestrian / hiking / biking trail meeting Forest Service Standards is included.

Construct full bench, side-hill, outsloped trail tread. Meander trail tread as necessary to drain. Install frequent grade reversals, grade dips and lead-off ditches to build sustainable, well-drained tread.

Transition grade smoothly to match existing trail on both ends where new trail connects to existing trail.

Maximum grade: 10%

Block existing trail (to be abandoned) by brushing in / obliterating 100 LF minimum, full width on both ends. Obstruct visibility of abandoned trail completely (as viewed from new trail). Additional brushing along the length of the abandoned trail may be necessary to accomplish this. Bring in brush material from either end. Do not drag brush material across white-flagged area between the two trails.

65+79

End new trail construction.

Construct smooth transition from new trail to existing trail.

35.416322, -80.047478

Morgan Trail Maintenance & Relocation November 2022 Page 16

65+79 End of Morgan Trail Relocation at Dickey Bell OHV Trail (TR-92).

Photo taken back-station toward existing trail to be abandoned.

65+79 End of Morgan Trail Relocation.

Cross Dickey Bell OHV Trail to continuation of Morgan Trail.

Continue maintenance.

No work is required on OHV Trail.

Morgan Trail Maintenance & Relocation November 2022 Page 17

67+26 to 67+96

Large berm removal – right. OS- R.

70 LF of large berm removal.

Berm is approximately 3 ft. high, 4 ft. wide. Construct grade dips and lead off ditches, outsloped tread with berm removed. Berm removal is incidental to trail maintenance.

Fill, compact suitable material over roots.

Install six- 8’ long check steps anchored into bank at 12 ft.

(min) intervals.

48 LF 6” x 6” PT timbers for check steps

68+35 Construct HRGD-R 68+73 Construct HRGD-R 69+12 Braided Trail. Maintain trail-left.

Brush in trail-right.

72+28 De-berm, out-slope, construct

RGD-L

72+95 Construct HRGD-L

75+02 Construct HRGD-R

75+74 Logout

76+74 Logout

77+80 Construct HRGD-R

78+27 Large berm, right. De-berm and out-slope-right.

79+54 Construct HRGD-R. Trail is very rocky through this section.

80+34 Construct HRGD-R. Roll off large root wad on right.

81+09 Construct HRGD-R. Continue de-berming, out-slope-right.

Compact loose rocky soil

82+82 Construct HRGD-R

84+20 to 84+50

Heavy deberming

Morgan Trail Maintenance & Relocation November 2022 Page 18

84+73 Construct HRGD-R

84+76 Use suitable material to fill in around, cover roots

84+96 Install 8 ft. long check step, anchor into banks.

8 LF 6” x 6” PT timbers for check step

85+94 Construct HRGD-R

87+63 Use suitable material to fill in around, cover roots

88+20 Construct HRGD-R, brush-in, obliterate braided trail on right.

Maintain trail-left.

88+61 to 89+20

Construct S-curve, taking trail up onto already disturbed trail sides and berms, to reduce grade at this location.

Coordinate with COR prior to trail shift onto cut banks.

35.410999, -80.04776 Avoid white flagged areas

89+73 Ref: Ditch 89+86 Cross road. Ref: NFSR-553 centerline

90+00

91+20

91+70

Intersection with FSR-553.

Install / construct gate and fence to block unauthorized vehicular access and allow horses, bikes, hikers.

See Project Drawings.

All clearing, grubbing, tree felling/removal, and grading required for installation/construction of the gate and fence shall be incidental to those pay items.

After gate/fence construction, continue tread & drainage work on descent to natural rocky ford.

End work at ford. Note: the Intersection with Berner Trail (TR-721) is on the other side of rocky ford.