This is a schedule of items for a task order solicitation to provide trail maintenance and construction services on the Morgan Trail for the U.S. Forest Service. The base bid includes restoration, drainage maintenance, brush cutting, logging out danger trees, erosion control work, and construction of new four-foot wide trail sections on approximately 8,000 linear feet and 1,120 linear feet of existing and new trail, respectively. It also includes installation of six-inch by six-inch pressure-treated timbers, shell rock for hardening drainage approaches and grade dips, and various sizes of culvert pipe. Optional bid items include the construction and installation of a horse-friendly gate and signage or an accessible kissing gate. Pricing is provided on a per linear foot, tonnage, or lump sum basis for the various line items. The related federal contract opportunity lists the solicitation number as 12445223R0026 for the National Forests in North Carolina 2023 Trail Indefinite Delivery/Indefinite Quantity multiple award contract.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM NO. DESCRIPTION MEASURE UNIT Quantity Unit Price TOTALS

910, 920, 930

Trail Maintenance - Existing Trail Restoration, Drainage Maintenance, Brush Cutting, Logging Out, Danger Tree Removal, Obliteration, Erosion Control

DQ LF 8,000

910, 920, 930 New 4 ft. Wide Trail Construction DQ LF 1,120

932, 995 6" X 6" PT timbers for check steps & tread hardening retainers at drainage approaches DQ LF 380

913, 932, 991 Shell rock - for hardening drainage approaches & grade dip ramps DQ TON 48

921-a 18-inch CMP culvert DQ LF 26

921-b 30-inch CMP culvert DQ LF 18

SUB-TOTAL BASE BID

940, 950, 995 OPTION 1: Horse Friendly Gate & Signage (constructed, installed) DQ LS

940, 950, 995 OPTION 2: Accessible Kissing Gate (constructed, installed) DQ LS 1

SUB-TOTAL OPTIONAL BID

Any other work required by the specifications or detail drawings will be considered incidental to the above items and no additional payment will be made.

TOTAL BID:

Trail IDIQ - TASK ORDER - Schedule of Items BASE BID Morgan Trail (#718)

OPTION(S) BID Morgan Trail (#718)