About this file
This is a schedule of items for a task order solicitation to provide trail maintenance and construction services on the Morgan Trail for the U.S. Forest Service. The base bid includes restoration, drainage maintenance, brush cutting, logging out danger trees, erosion control work, and construction of new four-foot wide trail sections on approximately 8,000 linear feet and 1,120 linear feet of existing and new trail, respectively. It also includes installation of six-inch by six-inch pressure-treated timbers, shell rock for hardening drainage approaches and grade dips, and various sizes of culvert pipe. Optional bid items include the construction and installation of a horse-friendly gate and signage or an accessible kissing gate. Pricing is provided on a per linear foot, tonnage, or lump sum basis for the various line items. The related federal contract opportunity lists the solicitation number as 12445223R0026 for the National Forests in North Carolina 2023 Trail Indefinite Delivery/Indefinite Quantity multiple award contract.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_12445223R0026_Amd_0002.pdf | ||
| Sol_12445223R0026_Amd_0001.pdf | ||
| J4. Morgan Trail Reroute Environmental Map.pdf | ||
| J5. MorganTrail Drawings.pdf | ||
| J7. Trail IDIQ 2023-Standard Trail Design Parameters.pdf | ||
| J3. Morgan Trail Reroute Decision Memo Map.pdf | ||
| J11. Wage Determination - Madison County (1).pdf | ||
| J12. Wage Determination - Madison County (2).pdf | ||
| Sol_12445223R0026.pdf | ||
| J2. Morgan Trail SOW.pdf | ||
| J6. Trail IDIQ 2023 - Standard Trail Specifications.pdf | ||
| J8. Trail IDIQ 2023 - Standard Trail Plans.pdf | ||
| J9. Contractor Performance Report.docx | DOCX document | |
| J13. Wage Determination - Madison County (3).pdf | ||
| J10. Wage Determination - Madison County (4).pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEM NO. DESCRIPTION MEASURE UNIT Quantity Unit Price TOTALS
910, 920, 930
Trail Maintenance - Existing Trail Restoration, Drainage Maintenance, Brush Cutting, Logging Out, Danger Tree Removal, Obliteration, Erosion Control
DQ LF 8,000
910, 920, 930 New 4 ft. Wide Trail Construction DQ LF 1,120
932, 995 6" X 6" PT timbers for check steps & tread hardening retainers at drainage approaches DQ LF 380
913, 932, 991 Shell rock - for hardening drainage approaches & grade dip ramps DQ TON 48
921-a 18-inch CMP culvert DQ LF 26
921-b 30-inch CMP culvert DQ LF 18
SUB-TOTAL BASE BID
940, 950, 995 OPTION 1: Horse Friendly Gate & Signage (constructed, installed) DQ LS
940, 950, 995 OPTION 2: Accessible Kissing Gate (constructed, installed) DQ LS 1
SUB-TOTAL OPTIONAL BID
Any other work required by the specifications or detail drawings will be considered incidental to the above items and no additional payment will be made.
TOTAL BID:
Trail IDIQ - TASK ORDER - Schedule of Items BASE BID Morgan Trail (#718)
OPTION(S) BID Morgan Trail (#718)
Morgan Trl SOI