J05 Self Performed Calculation Sheet Pryor Clinic Constr.docx

DOCX document 28 KB Posted

Attached to
Pryor Clinic Expansion Construction in Pryor
Solicitation number
75H70126R00024
Issued by

About this file

This is a Self-Performed Calculation Sheet for the Pryor Clinic Expansion Construction project (Solicitation 75H70126R00024), an Indian Health Service construction solicitation set aside for Indian Small Business Economic Enterprises (ISBEE). The sheet is a mandatory worksheet that offerors must complete to demonstrate compliance with limitations on subcontracting requirements under FAR 52.219-14 and 13 CFR 125.6.

Offerors must calculate and document their self-performed work percentage by subtracting profit/fees, material costs, and payments to non-similarly situated entities from the total proposed price, then dividing the remaining self-performed costs by the total contract value. For general construction contracts, the prime contractor may not pay more than 85% of the government-paid amount to non-similarly situated firms, while special trade contractors are limited to 75%. The worksheet requires identification of all proposed prime contractor and subcontractors with their concern status (Small Business, 8(a), SDB, SDVOSB, HUBZone, EDWOSB, WOSB, or Large Business), work activities, and dollar values. Critically, work subcontracted to "similarly situated entities"—first-tier subcontractors holding the same small business program status that qualified the prime contractor—is excluded from the subcontracting limitation calculation. Offerors must sign and submit the calculation at proposal submission, with an additional signed submission required upon contract completion showing actual results achieved.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment J05. Self-Performed Calculation Sheet Solicitation Number: 75H70126R00024

SELF-PERFORMED CALCULATION SHEET

INSTRUCTIONS FOR CALCULATION OF SELF-PERFORMED WORK IAW “Limitations on Subcontracting” (FAR 52.219-14 (Oct 2022) and/or FAR 52.219-17) Offeror’s are to identify self-performance IAW CFR Title 13: Business Credit and Assistance, Chapter I, PART 125—GOVERNMENT CONTRACTING PROGRAMS § 125.6 Prime contractor performance requirements (limitations on subcontracting). https://www.ecfr.gov/current/title-13/chapter-I/part-125/section-125.6 SELF PERFORMED CALCULATIONS for Construction Firms, it will not pay more than 85% (75% for special trade contractors) of the amount paid by the government to it to firms that are not similarly situated. Any work that a similarly situated subcontractor further subcontracts will count towards the 85% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted. (See Page 3 for clarifications on “similar situated” entities).

OFFEROR’S SELF PERFORMANCE WORKSHEET:

Offeror’s are required to complete this Worksheet for this Proposal.

a) Offeror’s total proposed price (base + option(s))
$___________
b) Subtract profit or fees
$___________
c) Subtract cost of materials
$___________
d) Subtract Offeror’s total estimated cost of contract performance incurred for NON similar situated entities
$___________

e) Offeror’s total estimated cost of contract performance for similar situated entities (a-b-c-d=e)

f) Offeror’s percentage of “similar situated” entities work (e/a x 100% = %)
________%

List of Proposed Prime Contractor and Subcontractors, their work activities and value:

Prime Contractor/Subcontractor
Concern Status

(i.e., SB, 8(a), SDB, SDVOSB, HUBZone, etc.)

Work Activities
$ Value

(Can add additional sheet if necessary)

At completion of this Contract/Task Order, the awardee shall complete and submit the following calculations to the Contracting Officer for the actual results achieved.

a) Offeror’s total proposed price (base + option(s))
$___________
b) Subtract profit or fees
$___________
c) Subtract cost of materials
$___________
d) Subtract Offeror’s total estimated cost of contract performance incurred for NON similar situated entities
$___________

e) Offeror’s total estimated cost of contract performance for similar situated entities (a-b-c-d=e)

f) Offeror’s percentage of “similar situated” entities work (e/a x 100% = %)
________%

Signed at submission of Proposal:

Name: ___________________________________ Title: ______________________________________ Signature: _________________________________ Date: ______________________________________ Signed at completion of Contract/Task Order:

Name: ___________________________________ Title: ______________________________________ Signature: _________________________________ Date: ______________________________________

Definitions: “Concern Status” means the SBA determined status of the firm, the small business program status as that which qualified the prime contractor for the award, and that is considered small for the NAICS code the prime contractor assigned to the subcontract the subcontractor will perform. These include Small Business, 8(a) participants, Small Disadvantaged Businesses (SDB), HUBZone Small Business concerns, Service-Disabled Veteran-Owned Small Business (SDVOSB) concerns, and Economically Disadvantaged Women-Owned Small Business (EDWOSB) concerns and Women-Owned Small Business (WOSB) concerns eligible under the WOSB Program. If none of these apply, the concern would be a Large Business.

(FAR 52.219-14 Limitations on Subcontracting (Oct 2022)— “Similarly situated entity” means a first-tier subcontractor, including an independent contractor, has the same small business program status as that which qualified the prime contractor for the award, and that is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract. An example of a similarly situated entity is a first-tier subcontractor that is a HUBZone small business concern for a HUBZone setaside or sole source award under the HUBZone Program.]

(13 CFR 125.6) § 125.6 What are the prime contractor's limitations on subcontracting?

(a) General. In order to be awarded a full or partial small business set-aside contract with a value greater than the simplified acquisition threshold (as defined in the FAR at 48 CFR 2.101)” in paragraph (a) introductory text; and an 8(a) contract, an SDVOSB contract, a VOSB contract, a HUBZone contract, or a WOSB or EDWOSB contract pursuant to part 127 of this chapter, a small business concern must agree that:

(3) In the case of a contract for general construction, it will not pay more than 85% of the amount paid by the government to it to firms that are not similarly situated. Any work that a similarly situated subcontractor further subcontracts will count towards the 85% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(4) In the case of a contract for special trade contractors, no more than 75% of the amount paid by the government to the prime may be paid to firms that are not similarly situated. Any work that a similarly situated subcontractor further subcontracts will count towards the 75% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(c) Subcontracts to similarly situated entities. A small business concern prime contractor that receives a contract listed in paragraph (a) of this section and spends contract amounts on a subcontractor that is a similarly situated entity shall not consider those subcontracted amounts as subcontracted for purposes of determining whether the small business concern prime contractor has violated paragraph (a) of this section, to the extent the subcontractor performs the work with its own employees. Any work that the similarly situated subcontractor does not perform with its own employees shall be considered subcontracted SBA will also exclude a subcontract to a similarly situated entity from consideration under the ostensible subcontractor rule (§ 121.103(h)(4)). A prime contractor may no longer count a similarly situated entity towards compliance with the limitations on subcontracting where the subcontractor ceases to qualify as small or under the relevant socioeconomic status.

Example 1 to paragraph (c):

An SDVO SBC sole source contract is awarded in the total amount of $500,000 for hammers. The prime contractor is a manufacturer and subcontracts 51% of the total amount received, less the cost of materials ($100,000) or $204,000, to an SDVO SBC subcontractor that manufactures the hammers in the U.S. The prime contractor does not violate the limitation on subcontracting requirement because the amount subcontracted to a similarly situated entity (less the cost of materials) is excluded from the limitation on subcontracting calculation.

Example 2 to paragraph (c):

A competitive 8(a) BD contract is awarded in the total amount of $10,000,000 for janitorial services. The prime contractor subcontracts $8,000,000 of the janitorial services to another 8(a) BD certified firm. The prime contractor does not violate the limitation on subcontracting for services because the amount subcontracted to a similarly situated entity is excluded from the limitation on subcontracting.

Example 3 to paragraph (c):

A WOSB set-aside contract is awarded in the total amount of $1,000,000 for landscaping services. The prime contractor subcontracts $500,001 to an SDVO SBC subcontractor that is not also a WOSB under the WOSB program. The prime contractor is in violation of the limitation on subcontracting requirement because it has subcontracted more than 50% of the contract amount to an SDVO SBC subcontractor, which is not considered similarly situated to a WOSB prime contractor.