J03 Stephan Booster WM_Specs.pdf

PDF 2 MB Posted

Attached to
RFP Stephan Booster Station & WM Replace Federal contract opportunity
Solicitation number
RFP75H70125R00046
Issued by
Department of Health and Human Services Indian Health Service

About this file

This document is a detailed specifications and project manual for the Stephan Booster Station and Water Main Replacement project for the Crow Creek Reservation in Buffalo County, South Dakota, prepared by the Great Plains Area Indian Health Service in February 2025.

The project involves constructing approximately 9,900 feet of 6-inch water main, installing a buried pre-packaged Stephan water booster station, implementing SCADA controls, connecting existing water service lines, building a gravel access road, abandoning the existing booster station, and purchasing and installing a 45kW generator. The solicitation is set aside for Indian Small Business Economic Enterprises and will be awarded as a Firm Fixed-Price contract using Lowest Price Technically Acceptable evaluation criteria. The project is located in the Fort Thompson Community and includes comprehensive specifications for water distribution, excavation, concrete work, electrical systems, cathodic protection, and site restoration. Key components include detailed technical requirements for pipe installation, booster station equipment, electrical infrastructure, and comprehensive testing and quality assurance protocols.

View the file

Other files for this federal contract opportunity

Other files attached to RFP Stephan Booster Station & WM Replace, newest first.
File Type Posted
B05-A01 QA SBSWM Repl.pdf PDF
J04 Map of Project Location.pdf PDF
J07 IHS IEE Representation Form.pdf PDF
J02 Stephan Booster WM_Plans.pdf PDF
J05 Wage Det SD20250007 14Mar2025.pdf PDF
J06 Self Performed Calculation Sheet.docx DOCX document
J09 Past Performance Questionnaire.docx DOCX document
RFP 25R00046 Stephan Booster Station WM Replace.pdf PDF
J08 Company Specialized Experience Form Construction.pdf PDF
J10 WH-347 Exp 31Jan2028.pdf PDF
J01 SOW SBSWM Repl.pdf PDF
J11 Release of Claims.docx DOCX document
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS FOR

PROJECTS

GP-21-Z28 & GP-23-T29

STEPHAN BOOSTER STATION & WATER MAIN REPLACEMENT

CROW CREEK RESERVATION

BUFFALO COUNTY, SOUTH DAKOTA

FEBRUARY 2025

SPECIFICATIONS FOR

PROJECTS

GP-21-Z28 & GP-23-T29

STEPHAN BOOSTER STATION & WATER LINE REPLACEMENT

CROW CREEK RESERVATION

BUFFALO COUNTY, SOUTH DAKOTA

FEBRUARY 2025

Great Plains Area Indian Health Service Revised 02/2025

Summary 01100-1

SECTION 01100 – SUMMARY

PART 1 - GENERAL

SUMMARY

The work to be performed under this contract shall consist of furnishing the following to perform the work outlined in these specifications and as indicated by Project Drawings:

Tools Equipment Materials Labor Supplies Manufactured articles All transportation to complete the work Temporary facilities

Location of Work: Fort Thompson Community, Buffalo County, South Dakota on the Crow Creek Reservation

Incidentals Items: All work, materials, and services not expressly listed as being provided by others or not expressly called for in the contract but are necessary for the completion of the work in good faith, shall be furnished, installed, and performed by the contractor.

SUMMARY OF WORK TO BE DONE BY CONTRACTOR

This project includes the construction of approximately 9,900 feet of 6-inch water main, a buried pre-packaged Stephan water booster station, SCADA controls and integration at the Stephan booster station, the Fort Thompson elevated water storage tank, and the water treatment plant, connection of existing water service lines to the new water main, gravel access road, abandonment of the existing water booster station, and the purchase and installation of a 45kW generator as indicated in the specifications and shown on the plans.

ADDITIONAL INFORMATION

For information regarding contracting issues, contact the Contract Officer (CO).

Comply with all Tribal regulations related to the completion of the work including the acquisition of necessary permits and the payment of Tribal taxes.

END OF SECTION

Summary 01100-2

This Page Intentionally Left Blank

Price and Payment 01270 -1

SECTION 01270 – PRICE AND PAYMENT

GENERAL

SUMMARY

Work covered by this section includes method of measurement and basis of payment for all divisions included.

Payment for the various items of the Bid Schedules shall include all compensation to be received by the Contractor for furnishing all tools, equipment, materials, labor, supplies, manufactured articles, transportation, and temporary facilities required to complete the work in accordance with contract documents including incidentals.

Respective prices and payment shall constitute full compensation for all work completed including incidentals.

All items not expressly listed as being provided by others that are necessary for the completion of work shall be furnished and installed by the Contractor.

ESTIMATED QUANTITIES

All quantities stipulated in the bid schedule or other contract documents are approximate and are to be used: (1) as a basis for estimating the probable cost of the work and (2) for the purpose of comparing the bids submitted.

The Contractor shall be paid for actual quantities installed based on the quantities measured in the field. The actual amounts of work completed and materials furnished may differ from estimated quantities. The Contractor shall make no claim for damages, anticipated profits, or otherwise, on account of differences between the estimated amounts and the actual amount of work performed and materials furnished.

SURVEY AND MEASUREMENTS

All quantity measurements shall be the responsibility of the Contractor and will be verified by the Contracting Officers Representative.

All measurements and subsequent payments will be based on completed and accepted work performed in strict accordance with the plans, specifications, and other contract documents.

BID SCHEDULE ITEMS

GENERAL

Payment shall be full compensation to complete the work items in good faith, including incidental work.

In addition to the basis of payment described under each item, the unit price bid shall be full compensation for all of the following:

Price and Payment 01270 -2

General requirements in Division 01, but not limited to the following.

a. Submittals.

b. Record drawings.

c. Warranties.

Specific requirements in Division 02 through 16, including but not limited to the following (unless otherwise expressly defined as a line item in the bid schedule):

a. Erosion control.

b. Clearing and grubbing.

c. Removal and replacement of obstructions.

d. Associated trenching, excavation and backfill including the removal of any nuisance water, bedding, haunching, and compaction.

e. Disposal of any excess material.

f. Traffic control.

g. Rough grading.

h. Finish work, where called for, including finish grading, topsoiling, and landscaping.

BID ITEMS

A. Schedule A: Water Main and Booster Station Replacement

1. Mobilization, Demobilization, and Submittals

a. Measurement: By the job.

b. Basis of Payment: Includes labor, tools, equipment, materials, and all other incidentals necessary to transport and set up all equipment, materials, provide all submittals, permits, construction schedule, and all other paperwork required for construction start-up. This includes compensation for mobilizing equipment to the site, establishing a site office, furnishing bonds and insurance, payment of applicable Tribal taxes and permits, and payment of all applicable state and federal taxes and duties. Pay item also includes the provisions necessary to remove all equipment, and materials brought to the site by the Contractors(s).

2. 6-inch SDR-21 PVC Water Main

a. Measurement: By the lineal foot based on the horizontal length installed and measured over the centerline of the pipe.

b. Basis of Payment: Includes all pipe, elbows, fittings, labor, tools, equipment and materials required to construct the water mains, including excavation, dewatering, trenching, laying and jointing pipe, backfill and compaction, flushing, disinfection, pressure testing, detectable warning tape, tracer wire system including access boxes, removal and replacement of fences, culverts, protection and/or replacement or repair of utilities which may be impaired by work, disposal of excess excavated material, thrust restraints, preparation of seed bed and seeding, and all other incidentals required to complete the work as specified.

Price and Payment 01270 -3

3. STA. 0+00 Connection to Existing System

b. Basis of Payment: Includes labor, tools, equipment, excavation, backfill and compaction, connection to existing 6-inch water main with 6 x 6-inch tee, 6-inch gate valves, valve boxes, thrust blocks, couplings, and all other incidentals required to complete the work as specified and as shown on the plans.

4. 6-inch DR-14 (305 psi) C900 PVC Water Main and materials required to construct the water mains, including excavation, dewatering, trenching, laying and jointing pipe, backfill and compaction, flushing, disinfection, pressure testing, detectable warning tape, tracer wire system including access boxes, removal and replacement of fences, culverts, protection and/or replacement or repair of utilities which may be impaired by work, disposal of excess excavated material, thrust restraints, preparation of seed bed and seeding, and all other incidentals required to complete the work

5. New Stephan Booster Station

b. Basis for Payment: Includes all labor, tools, equipment, equipment shipment, excavation, borrow, backfill and compaction, packaged booster station, structural fill, concrete support pad, sump pump discharge piping w/discharge concrete pad, chain link fence w/gate, power line to new site, electrical and control lines and conduit, grading, landscaping, seeding, crushed rock cover (2-foot past fence) w/10-mil poly sheeting, landscape edging, and all other incidentals which may be required to complete the work as specified.

6. Impressed Current Cathodic Protection System excavation, backfill and compaction, design plans and preparation of installation drawings for the level control vault by a National Association of Corrosion Engineer (NACE) certified engineer, all materials and equipment to construct the anodes, cathodes, installation of the Cathodic protection system according to manufacturer’s recommendations, supply and installation of NEMA 4X FRP rectifier box, all geotechnical work including mobilizing equipment to the site, establishing a site office, furnishing bonds and insurance, payment of applicable Tribal taxes and permits, and payment of all applicable state and federal taxes and duties, drilling of boreholes based on the design plan recommendations, backfilling and compaction of boreholes, Price and Payment 01270 -4 and all other incidentals required to complete the work for a complete system

7. Abandonment of Existing Booster Station excavation, removal of the existing booster station, proper disposal of offsite the existing booster station and equipment, removal and disposal of the SCADA pole, electrical disconnect, and fencing around the existing booster station, borrow material (if necessary), backfill and compaction, grading site and water diversion berm to match existing landscape, landscaping, topsoil, seeding, and all other incidentals which may be required to complete the work

8. SCADA

SCADA controls, and components at the Water Treatment Plant, Stephan booster station site and the Fort Thompson water storage tank, SCADA radios, wiring, conduit, antenna modifications at the Fort Thompson water storage tank, new antenna and mast at the Stephan booster station site, meter disconnect enclosures, circuit breaker panels beneath meter disconnect enclosures, lightning arrestors, integration at the Water Treatment plant to ensure that the tank site, booster site, and water treatment plant communicate, and all other incidentals which may be required to complete the work as specified in order for an operable SCADA system.

9. Booster Station Gravel Access Road

a. Measurement: By the cubic yard.

b. Basis for Payment: Includes gravel (approximately 70 cubic yards spread in 3-inch depth), and compaction from the state highway 47 approach to the new Stephan booster station as indicated on the plans. This bid item also includes the 12” corrugated metal pipe (CMP) culvert w/flared ends. This work also includes all other incidentals which may be required to complete the work as specified.

10. Air Release Pit

a. Measurement: By each installed.

compaction, combination air release valve assembly, pit and cover, insulation, bronze ball valve with fittings and all other incidentals required to complete the work as specified.

Price and Payment 01270 -5

11. 6-inch Gate Valve w/Box compaction, gate valve, extension stem, gate valve box, centering device, valve box adapter, locking lid, one pentagon key, one socket wrench for valve extension stem, polyethylene encasement, tracing wire modifications, utility markers and all other incidentals required to complete the work as specified.

12. Fire Hydrant w/Gate Valve & Box compaction, hydrant, gate valve and box, tee, thrust blocks, piping, gravel, polyethylene encasement, concrete pad w/gravel, utility markers, and all other incidentals required to complete the work as specified. Provide one hydrant wrench to the utility department under each contract.

13. STA. 99+12 Connection to Existing System compaction, connection to existing 6-inch water main, 6-inch gate valves, valve boxes, thrust blocks, coupling, and all other incidentals required to complete the work as specified and as shown on the plans. Fire hydrant w/gate valve & box will be paid for under a separate bid item.

B. Schedule B: Water Service Line Construction

1. 1-inch Curb Stop

b. Basis of Payment: Includes all labor, tools, equipment, excavation, backfill and compaction, curb stop, box, stationary rod, concrete pad w/gravel, utility marker, one combination key and one pentagon wrench per contract, and all other incidentals required to complete the work as specified.

2. 1-1/4-inch Corporation Stop

b. Basis of Payment: Includes all labor, tools, equipment, excavation, backfill and compaction, corporation stop, couplings, service clamps or saddles and all other incidentals required to complete the work as specified.

3. 1-1/4-inch Curb Stop

Price and Payment 01270 -6

4. 1-1/4-inch DR-7 (335 psi) PE Water Service Line and materials required to construct the water service line, including excavation, dewatering, trenching, laying and jointing pipe, backfill and compaction, flushing, disinfection, pressure testing, detectable warning tape, removal and replacement of fences, culverts, protection and/or replacement or repair of utilities which may be impaired by work, disposal of excess excavated material, thrust restraints, and all other incidentals required to complete the work as

5. 1-1/2-inch Corporation Stop

6. 1-1/2-inch Curb Stop

7. 1-1/2-inch DR-7 (335 psi) PE Water Service Line dewatering, trenching, laying and jointing pipe, backfill and compaction, flushing, disinfection, pressure testing, detectable warning tape, removal and replacement of fences, culverts, protection and/or replacement or repair of utilities which may be impaired by work, disposal of excess excavated material, Price and Payment 01270 -7

8. 2-inch Corporation Stop

9. 2-inch Curb Stop

10. 2-inch DR-7 (335 psi) PE Water Service Line dewatering, trenching, laying and jointing pipe, backfill and compaction, flushing, disinfection, pressure testing, detectable warning tape, removal and replacement of fences, culverts, protection and/or replacement or repair of utilities which may be impaired by work, disposal of excess excavated material,

11. Meter Pit compaction, final grading, seeding, meter pit, inlet angle shut-off, remote readout, double check valve, pressure regulator, coiled polybutylene tubing, insulation, locking lid, fittings, external connections including fittings on either side of the meter pit to connect to the existing water service line (if applicable), and all other incidentals required to complete the work as specified.

12. Exploratory Digging

a. Measurement: By the hour.

b. Basis for Payment: Two (2) hours of exploratory digging shall be included to locate each water service line and be included as incidental to reconnecting the water service lines to the new water main. Time in excess of two (2) hours of exploratory digging to locate the water service line per water service line

Price and Payment 01270 -8 connection shall be paid for per hour as Exploratory Digging. This includes but is not limited to all excavation, inspection of existing facilities, and repairs as directed by the Project Engineer, backfilling, site cleanup, and all other incidentals required to complete the work as specified.

C. Schedule C: Skid Mounted Standby Generator

1. 45 KW Standby Generator Equipment

b. Basis of Payment: Includes full compensation for material and labor to supply a new, complete, and operational propane standby generator with weatherproof extreme weather kit enclosure shipped to the site. The payment for equipment shall also include supplying (1) automatic transfer switch, and a new 1,000-gallon propane tank delivered to the site.

2. 45 KW Standby Generator Installation

b. Basis of Payment: This payment also includes full compensation for all other materials and labor necessary to connect the supplied generator, propane tank, filling of the propane tank with propane for startup testing, and automatic transfer switch. This includes wiring the generator and automatic transfer switch to complete an operational generator; including installation of the concrete pads (includes compacted gravel below concrete pads), gas line, and installation of all electrical wiring per NEC requirements. This payment also includes full compensation for mobilizing equipment to the site, furnishing bonds and insurance, payment of applicable Tribal taxes and permits, and payment of all applicable state and federal taxes and duties.

PART 3 – EXECUTION (N/A)

Project Management And Coordination 01310 - 1

SECTION 01310 – PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

SUMMARY

Section includes the preconstruction conference, construction schedule, working hours/days, coordination requirements and progress meetings.

PRE-CONSTRUCTION CONFERENCE

Required after award of contract and prior to start of construction.

Representatives from the following shall attend.

Prime Contractor Subcontractor(s) Project Engineer and/or Technical Representative Owner’s Representative Appropriate State/Federal Agencies or other Funding Agencies TERO Representative, if applicable

The Project Engineer will arrange a date that is mutually acceptable to all parties planning to attend.

Contractor shall notify subcontractors of time and date of meeting.

CONSTRUCTION SCHEDULE

Present Project Engineer with a written preliminary construction schedule containing start and completion dates of the major items at the preconstruction meeting.

Notify the Project Engineer three full working days in advance of any construction.

Communicate major changes to the schedule to the Project Engineer in writing.

WORKING HOURS/DAYS

Perform all work during regularly scheduled working hours, unless approved by Project Engineer.

Working hours shall be defined as 7 AM to 5 PM Monday through Friday, with the exception of holidays.

No work will be allowed on Saturday, Sunday, Federal holidays, and Tribal holidays without the Project Engineer’s consent.

Holidays include, but are not limited to, New Year’s Day, President’s Day, Martin Luther King Jr Day, Memorial Day, Juneteenth Day, Independence Day, Labor

Project Management And Coordination 01310 - 2

Day, Columbus Day, Veterans Day, Thanksgiving Day and Christmas Day, or on any other holidays declared by the Project Engineer.

Holidays that fall on Saturday will be observed on the preceding Friday; holidays that fall on Sunday will be observed on the following Monday. No construction will be permitted on those days.

Project Engineer has the option to approve overtime or holiday work upon the Contractor’s request not less than 48 hours in advance of the work to be performed. Overtime and holiday requests that exceed a ten (10) hour work shift for a time period exceeding two days will not be approved by the Project Engineer.

COORDINATION WITH OTHER REQUIREMENTS

Coordinate work with other contractors (i.e., roads, building, etc.) in the area as necessary to complete the work specified.

Coordinate work with local utilities (i.e., water and sewer, power, telephone). All buried utilities may not be shown on the plans.

Contractor is responsible for having utilities marked prior to construction and field verify utility location.

PROGRESS MEETINGS

Project Engineer will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

Progress meetings will be scheduled throughout progress of the Work at maximum monthly intervals. Frequency of meetings will be determined from Work meeting construction schedule or when Project Engineer deems it necessary.

Representatives from the following shall attend:

Prime Contractor Subcontractor(s) Project Engineer and/or Technical Representative Owner’s Representative

Submittal Procedures 01330 - 1

SECTION 01330 – SUBMITTAL PROCEDURES

PART 1 - GENERAL

SUMMARY

This section includes information on submittal procedures. Materials requiring a submittal are listed in the appropriate specification section.

SUBMITTAL PROCEDURES

Submit one electronic pdf copy or three paper hard copies of submittals to the Project Engineer, unless requested otherwise.

Attach an acceptable submittal cover sheet for all submittal packages.

List all submittals included in the package in the appropriate location.

Signed cover sheet indicating all submittals have been reviewed prior to submission.

Identify each cut sheet or shop drawing with the following information:

Contract number Supplier Pertinent specification section number Pertinent drawing and detail number

Submit the following information, as applicable:

Manufacturer’s cut sheets indicating compliance with references (e.g. applicable ASTM, AWWA standards).

Laboratory results, as applicable.

Dimensional drawings or shop drawings, as applicable.

Other information necessary for the Project Engineer to determine compliance with the specifications.

Identify variations from the contract documents and product or system limitations that may be detrimental to successful performance of the completed work.

Revise and resubmit submittals as required and identify all changes made since previous submittal.

Distribute copies of reviewed submittals to concerned parties (i.e. suppliers, sub-contractors). Instruct parties to promptly report inability to comply with requirements.

Submit written communication of any inability to comply with the Project Engineer’s comments.

Submittal Procedures 01330 - 2

Submit information to the Project Engineer at least three weeks in advance of the work to be performed.

Approval of submittals must be provided by the Project Engineer prior to installation of materials and process of any payments for the materials.

Approval of any submittal does not relieve responsibility for completion of the work in accordance to the plans and specifications.

Quality Requirements 01430 - 1

SECTION 01430 – QUALITY REQUIREMENTS

PART 1 - GENERAL

SUMMARY

This section includes prerequisites and procedures, installer qualifications, control of installation, and manufacturers’ field services to ensure the quality of the work.

SUBMITTALS

Contractor Name and License Number

Subcontractor(s) Name and License Number

Name or names of the “Competent Person” in charge of safety on the jobsite, as defined by the OSHA Industry Standard 29 CFR 1926.

INSTALLER QUALIFICATIONS

Perform Work under the direction of personnel licensed by the state and/or reservation having jurisdiction.

If Work being completed is not regulated by the state and/or reservation, submit literature from the manufacturer, independent representative of the manufacturer, and/or supplier indicating the Contractor or Subcontractor’s ability to complete installation based on past experience or formal training.

CONTROL OF INSTALLATION

Review materials for acceptability, in accordance with the approved submittals, when delivered to the site.

Store and handle materials to prevent damage.

Review materials, services, and workmanship to ensure that Work is performed in accordance with the specifications.

Comply fully with manufacturers’ instructions.

Should manufacturers’ instructions conflict with contract documents, request clarification from Project Engineer before proceeding.

Should the finished product or method of completion differ in any way from the manufacturer’s written instructions or the specifications, request approval in writing from the Project Engineer before proceeding.

Correct defective Work to the satisfaction of the Project Engineer.

Quality Requirements 01430 - 2

MANUFACTURER’S FIELD SERVICES

Provide reports on observations and documentation of workmanship to the Project Engineer within 30 days of visit for review where manufacturers’ field services are provided.

WARRANTY

Provide a minimum one (1) year warranty for all materials and labor, covering defects in the materials or deficiencies resulting from contractor installation.

Provide additional warranties as required under other sections.

Warranty takes affect starting the date of substantial completion.

Staking and Construction Surveying 01720 - 1

SECTION 01720 – STAKING AND CONSTRUCTION SURVEYING

PART 1 - GENERAL

SUMMARY

This section outlines the staking and surveying work related to provide reference points in the field. Section clarifies staking provided to the Contractor and Contractor’s responsibilities.

Construction Surveys establish “control stakes” for basic line and grade used for project construction.

Control stakes are used to check work for contract compliance.

Set supplemental “working stakes” from control stakes when needed.

Working stakes are used to perform the work and are provided by the contractor.

STAKING PROVIDED TO THE CONTRACTOR

Water Main, Force Main and Appurtenance Staking

Offset of Horizontal or Centerline staking (approximately every 100 feet).

Appurtenance (gate valve, fittings, fire hydrant, etc.) staking on center.

Sewer Main and Appurtenance Staking.

Manhole staking on center with two offsets including elevations.

Project Benchmarks

Hubs for vertical control will be placed at various points throughout project.

Hubs for horizontal control (at least one per project).

CONTRACTOR’S RESPONSIBILITY

Notify the Project Engineer at least fourteen (14) calendar days in advance of the times and places that staking will be needed.

Set supplementary staking, grade staking, offsets, cut stakes, temporary bench marks, and control points necessary for contractor to complete the work in accordance with the plans and specifications.

Provide all staking materials for contractor supplementary staking to include hubs, lath, flagging, paint and other material needed to provide construction staking.

Staking and Construction Surveying 01720 - 2

Request clarification from the Project Engineer regarding conflicts before proceeding with installation of facilities.

Preserve all offset and reference staking, until such time as the pipeline or other facilities are installed.

Reference stakes needing replacement due to Contractor error or negligence must be replaced by Contractor, at no cost to the contract.

All permanent survey points/markers (i.e., property corners) and bench marks not directly in the line of work shall be preserved.

Replace all permanent survey markers disturbed or destroyed using a Professional Land Surveyor, at no cost to the contract.

Provide evidence of reestablishment of permanent survey markers to the Project Engineer and copy of stamped and approved monument re-establishment documentation from the appropriate jurisdiction (state, BIA, etc.).

Closeout Procedures 01770 - 1

SECTION 01770 – CLOSEOUT PROCEDURES

PART 1 - GENERAL

SUMMARY

Section includes information on substantial completion, closeout procedures, final inspection and final payment.

SUBSTANTIAL COMPLETION

Water Main: Water main construction is considered substantially complete once the work has been installed in accordance with the specifications, backfilled and compacted in place, successfully pressure tested, and passed bacteriological testing, at which point the completed system is connected to the existing system and ready to be consumed.

CLOSEOUT PROCEDURES

Submit a written request to Owner and Engineer that the work is substantially complete and request that the Engineer through the Owner issue a certificate of substantial completion.

At the same time submit to the Owner and Engineer an initial draft of punch list items to be completed or corrected before payment.

Provide warranties, approved Operation & Maintenance Manuals, and approved record documents (e.g., as-built drawings) to the Project Engineer within ten (10) days after date of substantial completion or 5 working days prior to the pre-final inspection (whichever is sooner).

Submit written certification that work is fully completed in accordance with contract documents and ready for final inspection at least five (5) working days prior to final inspection.

PRE-FINAL CLEANING

Complete pre-final clean-up prior to inspection.

Remove waste and surplus materials, rubbish, and construction facilities from the site.

PRE-FINAL INSPECTION

A pre-final inspection of the facilities shall be conducted, at a minimum, by the Project Engineer and the Contractor.

Inspect all facilities installed under the Contract.

Closeout Procedures 01770 - 2

Complete the requirements listed in Closeout Procedures Section 1.2 prior to the pre-final inspection.

PRE-FINAL PUNCH LIST

Any deficiencies noted at the pre-final inspection will be communicated to the Contractor through a letter from the Contract Manager or the Project Engineer.

After Substantial Completion promptly begin work on the punch list of items to be completed or corrected prior to final inspection.

Correct all deficiencies identified prior to scheduling a Final Inspection.

Full payment will not be made until all requirements of this section are met.

Contractor shall submit written certification that all pre-final punch list items have been completed in accordance to the contract documents and ready for final inspection at least five (5) working days prior to final inspection.

FINAL INSPECTION

Final inspection of all the facilities provided will be conducted, at a minimum, with the Owner, Federal Funding Agency(s), Project Engineer, and the Contractor.

Scheduling of the final inspection will not be allowed until all deficiencies listed in the pre-final punch list are corrected to the Project Engineer’s satisfaction.

FINAL PAYMENT

Deficiencies noted during the pre-final inspection will be communicated to the Contractor through a letter from the Contract Manager or Project Engineer.

Correction of all deficiencies will be required prior to the final payment being processed.

Final Payment will follow the procedures outlined in Section 01270 Price and Payment and require the Contractor to sign a release of claims for the contract.

Project Record Documents 01781 - 1

SECTION 01781 – PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

SUMMARY

This section describes the requirements for closeout submittals including, record drawings, warranty information and general operation and maintenance information.

DELIVERY

Provide all closeout submittals meeting these requirements and any specific requirements of each section.

Closeout submittals must be received prior to final payment

All closeout submittals must be received in a correct and complete manner before final payment can be made. If material is deficient, the deficiencies will be indicated in punch lists.

DEFINITIONS

Record Drawing: A drawing showing the actual installation of facilities, showing changes from the plans, and showing detail enough that future persons can readily locate all objects.

Ties: Measurements from permanent easily located objects to an installed object.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION

RECORD DRAWINGS

Provide record data in one of the following manners:

On a set of project drawings, neatly draw tie measurements and changes from the original design.

On separate 8½ X 11 sheets, neatly draw site sketches, structure sketches, etc., indicating the necessary information.

Provide three (3) swing tie measurements to all buried utility objects that may need to be located in the future, including, but not limited to:

Gate valves Corporation stops

Project Record Documents 01781 - 2

Curb stops Water main fittings Couplings to existing water systems.

Cleanouts Sewer wyes Utility crossings Septic tank manholes and access covers.

Corners of drainfields

Provide offset measurements for buried utilities (e.g., water main) installed parallel to roads or other known utilities.

Provide revised elevation data for all items that have elevations shown on the plan drawings, including, but not limited to, the following:

Manhole inverts (inlet and outlet) Manhole rims Lift station invert Lift station top Lift station pipe penetrations Float elevations Septic tank elevations Depth of installation of Individual septic systems Elevations of pipe entering and leaving structures Elevation of sewer service line stub (if terminated at right of way) Variations from the minimum depth of bury Other elevations indicated on profiles

Provide installed bid schedule items quantities for individual facilities on 8½ X 11 sheets.

Depending on the type of contract, standard forms may be supplied for use by the Contractor.

WARRANTIES

Submit all warranty information regarding the materials installed in accordance with that products’ particular section.

OPERATION AND MAINTENANCE INFORMATION

Submit all operation and maintenance information as included in the packaging from the manufacturer regarding the materials installed.

Additional project specific operation and maintenance requirements are listed in applicable sections.

Site Clearing 02230 - 1

SECTION 02230 – SITE CLEARING

PART 1 - GENERAL

SUMMARY

This section covers clearing, stripping and grubbing within the proposed areas of the Work.

RELATED WORK

Section 02300 – Earthwork

Section 02315 – Excavation, Trenching and Backfill

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION

CLEARING AND GRUBBING

Obtain necessary permit from Owner prior to cutting any trees or brush (if applicable).

Consult with the Project Engineer and Owner to designate a temporary area for stockpiling all cleared brush and trees.

Ensure all stockpiled material does not adversely affect drainage nor cause damage to abutting property.

Remove all ground vegetation and other extraneous material from the construction area to a depth of 6 inches and stockpile in the designated area.

Remove and dispose of all trees, stumps, brush, debris, and all other obstructions as needed in an approved manner off site.

Do not burn, bury, and/or leave debris within the Work areas.

If possible, within right-of-way and property lines, extend clearing and grubbing a minimum of 10 feet beyond all proposed structures unless otherwise directed by the Engineer.

Site Clearing 02230 - 2

Earthwork 02300 - 1

SECTION 02300 – EARTHWORK

PART 1 - GENERAL

SUMMARY

This section includes rough and finished site grading of all areas disturbed during construction.

RELATED WORK

Section 02230 – Site Clearing

Section 02315 – Excavation, Trenching and Backfill

Section 02370 – Temporary Erosion and Sediment Control

Section 02920 – Topsoiling, Seeding, Fertilizing, and Mulching

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION

ROUGH GRADING

Grade the area in the vicinity of the excavation to prevent surface water from flowing into the excavation.

Maintain existing drainage.

FINISH GRADING

Grade site to true grades as specified on the plans after all structures and piping have been installed.

Provide a smooth transition between adjacent existing grades and new grades.

Grade sites for effective drainage away from structures and to prevent ponding.

Dress and trim all slopes.

Drag all disturbed areas utilizing a box drag or by another attachment or method submitted to and approved by the Project Engineer.

Hand rake areas inaccessible to mechanical means.

Earthwork 02300 - 2

Remove all objectionable foreign matter, wood, metal, and stones over 2-inches in diameter and dispose of by an approved method off site.

Excavation, Trenching, and Backfill 02315 - 1

SECTION 02315 – EXCAVATION, TRENCHING AND BACKFILL

PART 1 - GENERAL

SUMMARY

This section includes excavation, trenching and backfill necessary for the construction of the facilities as indicated on the plans including, but not limited to:

water mains and service lines, sewer mains and service lines, concrete manholes, septic tanks, and other structures.

RELATED WORK

Section 02230 – Site Clearing

Section 02300 – Earthwork

Section 02316 – Rock Excavation

Section 2400 – Boring, Jacking & Directional Drilling

Section 02510 – Water Distribution

Section 02511 – Water Service Lines

Section 02705 – Road Restoration

Section 02920 – Topsoiling, Seeding, Fertilizing, and Mulching

REFERENCES

Manual on Uniform Traffic Control Devices

ASTM D698 – Test Methods for Moisture Density Relations of Soils and Soil- Aggregate Mixtures Using 5.5 lb. Rammer and 12-in. Drop [Standard Proctor Test]

ASTM D2321 – Underground Installation of Flexible Thermoplastic Sewer Pipe

ASTM D2487 – Classification of Soils for Engineering Purposes [Unified Soil Classification System]

SUBMITTALS

Imported Bedding Sieve Analysis

Polystyrene Insulation

Compaction Method

Excavation, Trenching, and Backfill 02315 - 2

Detectable Warning Tape

DEFINITIONS

Bedding, Haunching and Initial Backfill zones as defined herein and on the standard pipe trench detailed drawing.

Soil Materials as summarized and defined in ASTM D2321 and ASTM D2487.

PART 2 - PRODUCTS

BEDDING, HAUNCHING AND INITIAL BACKFILL MATERIAL

Native material if acceptable to Project Engineer.

Imported Bedding: Consists of sand, sandy gravel, or fine gravel having a maximum size of ¾-inch and a maximum Plasticity Index of 6.

INSULATION

Rigid extruded polystyrene insulation board, 2 inches thick, having a minimum compressive strength of 25 psi. Dow Chemical Styrofoam, or approved equal with a minimum R-value of 4.5 per inch.

Width:

4 feet for mains up to 12 inches (nominal diameter).

3 feet for mains and service lines up to 6-inches (nominal diameter).

WARNING TAPE

Detectable 3 inches wide.

Printed with “Caution Buried Water Line Below” for water mains and service lines.

Printed with “Caution Buried Sewer Line Below” for sewer mains, sewer force mains, and service lines.

PART 3 - EXECUTION

GENERAL

Trenching and excavation work shall be done in accordance with proper emphasis on safety as determined by the Contractor to conform to recommended safety standards such as OSHA 1910 and 1926.

A Competent Person, as defined by OSHA 1926, shall be on site at all times when excavation work is being completed.

Excavation, Trenching, and Backfill 02315 - 3

Provide suitable sheeting, shoring, and bracing as required in conformance with OSHA regulations.

In accordance with the contract, obtain all permits from appropriate road agency for construction within road right of way.

Repair damage resulting from settlement, slides, cave-ins, water pressure, and other causes.

Provide adequate signs, barricades, fences and amber lights and take all necessary precautions to protect the work and the safety of the public in all construction areas.

Placement of construction signs and barricades shall conform to the most current version of the “Manual on Uniform Traffic Control Devices.”

Protect barricades and obstructions at night by amber signal lights that burn from sunset to sunrise. Barricades shall also be of substantial construction, painted white or with reflective paint to increase their visibility at night.

Perform work without obstruction to traffic or inconvenience to the general public and the residents in the vicinity of the work.

The maximum open trench allowed during the day at each location shall not exceed 200 feet, with no open trench allowed overnight unless specifically approved.

Road Crossing

Comply with all construction and material requirements of roadway authorities having jurisdiction.

Maintain one lane of traffic open at all times.

Cleared trees, brush, or rocks prior to or during construction is considered incidental to excavation work.

EXCAVATION

Remove trees and stumps from excavation and site.

Remove and stockpile existing topsoil.

Install facilities as staked, centered in excavation, unless otherwise approved by Project Engineer.

Maintain surface drainage away from trenching or excavation.

Remove unsuitable foundation materials from excavation as shown on the plans or as authorized by the Project Engineer.

Maintain a minimum 1-foot clearance between outer surface of structure being installed and wall of excavation.

Rock encountered shall be classified, excavated, and measured in accordance with Section 02316.

Excavation, Trenching, and Backfill 02315 - 4

TRENCHING

Bottom width:

No less than 12 inches or more than 24 inches wider than the outside diameter of the pipe.

Where a chain or wheel trencher is approved for use in a rural area, the trench width shall be 4 to 6 inches greater than the outside diameter of the pipe.

Depth: Provide minimum cover as specified, or depths shown on plans.

BEDDING

If existing soil cannot provide uniform, stable bearing support, over-excavate a minimum of 4 inches below bottom of pipe or structure and provide imported bedding material as directed by the Project Engineer.

If unsuitable soil is encountered a price for imported bedding material will be negotiated if not included in bid schedule.

Unauthorized over excavation shall be backfilled with acceptable bedding material at the Contractor’s expense.

HAUNCHING AND INITIAL BACKFILL

General

Provide complete and uniform bearing and support for the pipe, including allowance for bell holes, or structure.

Work material under and around the pipe to ensure full pipe support.

Prevent movement of the pipe during placement of material.

Avoid contact between the pipe and mechanical compaction equipment.

Where a trencher is approved, backfill the trench from surface with selected material, free from large clods and all stones larger than 3 inches.

No frozen clods, saturated, foreign, or organic materials will be allowed.

Hand compact in 6-inch lifts from the bottom of the trench to 12 inches above the pipe crown.

BACKFILL & COMPACTION

All buried material shall be inspected by technical representative prior to backfilling.

Backfill remainder of excavation with native material, free from large clods, stones 8 inches or larger, organic material or frost chunks.

All backfill shall be compacted in the specified lifts utilizing mechanical equipment designed for compaction. Compaction methods utilizing mechanical equipment not designed for compaction will not be approved.

Excavation, Trenching, and Backfill 02315 - 5

All methods of compaction shall be approved prior to construction.

Compact in 6-inch lifts to a density not less than the density of the surrounding undisturbed soil or not less than 90% of the maximum dry density, determined by

ASTM D698.

In cases where the Contractor performs unacceptable methods of compaction, the work on the project will cease until an acceptable method of compaction has been approved. The Owner has the right to delay work until soil samples along the project alignment are taken for the purpose of developing a proctor for testing the compaction of the soil backfilled in the trench.

Conform to Section 02705 for backfill requirements within roadways.

Compact with mechanical tamper, after initial backfill, to a density not less than 95% of the maximum dry density, determined by ASTM D698 for the entire depth of the trench through a roadway or driveway.

Backfill and compact around manholes, valve boxes, and other appurtenances in 6-inch lifts.

Compact with a mechanical tamper to a density not less than 90% of the maximum dry density, determined by ASTM D698.

Backfill around septic tanks in 12-inch lifts.

Compact in a manner that will not produce undue strain on the tank.

Repair any trenches improperly backfilled or where settlement occurs, then refill and compact.

Restore surface to the required grade and compaction. Conform to Section 02300 for rough grading, finish grading and site surface drainage.

Remove and dispose of all surplus backfill materials to a location approved by the Project Engineer.

WARNING TAPE INSTALLATION

Install warning tape over water, sewer or force mains and service lines in trench 2 feet below finished grade.

FROST PROTECTION

Place insulation in areas where water main, sewer service lines or water service lines cross a road, driveway, traveled path, or as indicated on the plans.

Center insulation over pipe or appurtenance with 1 foot of compacted fill between the pipe and the insulation.

Grade fill so insulation lays flat.

Excavation, Trenching, and Backfill 02315 - 6

Insulate with a minimum of one 2-inch layer of polystyrene.

If a minimum bury depth is specified, install one 2-inch-thick layer for each foot of backfill less than the required minimum bury depth.

Install 3 foot wide for pipes up to 6 inches in diameter and 4 feet wide for pipes up to 12 inches in diameter.

Extend insulation a minimum of 5 feet on each side of the road crossing.

Lap insulation by 6 inches or stagger by 6 inches if composed of two layers.

Minimum thickness for the first lift of backfill over the insulation is 8 inches.

Do not operate construction equipment directly on insulation. Do not compact first lift with backhoe-mounted compactor or any other large compaction equipment.

Compact remaining backfill using normal construction practices.

REMOVAL OF NUISANCE WATER

Remove nuisance water entering the trenches.

Nuisance water that can be removed through the use of sump or trash pumps is not considered dewatering.

Keep trenches free from water until waterlines, fittings, valves, sewer lines, manholes and other appurtenances are in place and sealed against the entrance of water.

Prevent all water, earth or any foreign material from entering any facility.

Keep trenches free from water until the facilities are in place, sealed against the entrance of water, and backfill has been placed and compacted above the water level.

LOCATE EXISTING UTILITIES

Field locate all existing underground utilities.

Utilize state “811” or “one-call” hotlines.

Contact all other utility owners not covered by the state “one-call” hotlines.

UTILITY CONFLICTS

Protect existing utilities from damage during excavation and backfilling operations.

Provide temporary support for existing water, gas, telephone, power, or other utility services that cross the trench until backfilling of trench is complete

Compact backfill to 90% of Standard Proctor Density under disturbed utilities.

Excavation, Trenching, and Backfill 02315 - 7

Repair or replace any damaged existing utilities, at no additional cost to the project.

Water and sewer main crossing and parallel installation

Maintain a 10-foot horizontal separation (O.D. to O.D.) for parallel mains.

Upon approval by the Project Engineer, water and sewer mains may be installed closer than 10 feet, provided all of the following conditions;

a. Vertical separation is 18 inches (O.D. to O.D.)

b. Water main is above the sewer main.

c. Separate trenches are maintained.

Maintain a minimum 18-inch vertical separation (O.D. to O.D.) for crossing mains with the water main above the sewer main.

a. Lay pipe with joints equidistant from the point of crossing.

If it is impossible to meet any of the above separation distances and deviations, one of the following methods shall be adhered to.

a. Sewer main shall be constructed to water main pressure pipe standards meeting a minimum pressure class of 150-psi.

b. Either the water main or the sewer main may be encased in a watertight carrier pipe that extends 10 feet on both sides of the crossing. The carrier pipe shall be of materials approved by the regulatory agency for use in water main construction.

c. The water main and sewer main installed shall be made of high-density polyethylene (HDPE) pipe to eliminate the joints and possibility of leaks. Both water and sewer main shall be pressure tested in accordance to Section 02510.

Water and sewer service crossing and parallel installation.

Maintain a 30-inch horizontal separation from water and sewer services.

Maintain a 12-inch vertical separation for crossing water and sewer services.

Water service line splices or joints will not be permitted within 10 feet of a sewer line crossing.

MOVING FENCES AND MINOR STRUCTURES

Remove and reset culverts, drainage pipes or other minor structures that fall within the alignment of the new construction, to their original location and grade.

Visit the project site and determine actual conditions with regard to the existence of old car bodies, abandoned houses, fences, driveways, trees, stumps, brush, sidewalks, approaches, and other miscellaneous obstacles to construction.

Unless specifically referenced in a bid item, no separate payment will be made for the removal or replacement of these items.

Excavation, Trenching, and Backfill 02315 - 8

RECORDS

Conform to as-built requirements in Section 01781.

Rock Excavation 02316 - 1

SECTION 02316 – ROCK EXCAVATION

PART 1 - GENERAL

SUMMARY

This section covers rock excavation necessary during construction.

RELATED WORK

Section 02315 – Excavation, Trenching, and Backfill

Section 02920 – Topsoiling, Seeding, Fertilizing, and Mulching

REFERENCES

US Department of Labor, Occupational Safety and Health Administration Standard

1910.109 – Explosives and Blasting Agents

SUBMITTALS

Contractor’s blasting license and/or blasting permit

Bedding material

DEFINITIONS

Solid Rock: Large masses of igneous, metamorphic, or sedimentary rock which, in the judgment of the Project Engineer, cannot be excavated without drilling, blasting, ripping equipment, or other specialized equipment not normally on the job site.

Loose Rock: Individual boulders and other detached stones having a volume of one cubic yard or more.

GENERAL

Inclusion of a bid item and estimated quantity for rock excavation in the bid schedule indicates that rock excavation is probable.

Exclusion of rock excavation from the bid schedule does not preclude the possibility that rock will be encountered; it indicates that rock excavation is not anticipated.

If unanticipated rock is encountered a price for rock excavation will be negotiated with the Contractor.

Rock Excavation 02316 - 2

QUALITY ASSURANCE

The materials and construction methods specified herein are minimum requirements.

Where the appropriate state/local require more stringent materials or execution methods, they shall apply.

Notify the Project Engineer of any planned deviation from these specifications before proceeding so any price changes or quantity adjustments may be made.

PART 2 - PRODUCTS

BEDDING MATERIAL

Refer to Section 02315.

PART 3 - EXECUTION

ROCK MEASUREMENT

Solid rock

Unit of measure is cubic yards.

Measure from top of rock to a point 6 inches below the invert of the pipe (or appurtenance) and 12 inches from each side of the pipe (or appurtenance).

Loose rock

Unit of measure is cubic yards.

Measurement includes only those rocks or boulders that are individually one cubic yard or more in volume.

EXCAVATION

Solid rock

Excavate to a depth of at least 6 inches deeper than the pipe (or appurtenance) invert.

a. A maximum 30-inch trench width is allowed.

Refill to the required elevation with bedding material.

a. Bedding material shall extend upward at least one half the diameter of the pipe (or appurtenance).

Loose rock

Excavate to provide 6 inches of clear space around pipe (or appurtenance).

Refill to the required elevation with bedding material.

Rock Excavation 02316 - 3

All rock which cannot be handled and compacted as earth shall be kept separate from other excavated materials and shall not be mixed with other backfill materials, except as approved by the Project Engineer.

Dispose of all rock excavated.

BLASTING

The Contractor is responsible for damage and injury caused by…