This Statement of Objectives document outlines requirements for the renovation of Buildings 51424 and 51428 located at Fort Huachuca, Arizona. The contractor shall provide design/build services including demolition of existing asbestos tile and gas space heaters, design and construction of a new HVAC system, electrical system upgrades including new panels and wiring, plumbing upgrades, fire suppression system installation, fire alarm installation, interior and exterior finishes, fencing, paving, and signage. The contractor must prepare designs, schedules, safety plans and provide materials, equipment, and labor to complete the project within 240 calendar days of the Notice to Proceed. The document specifies technical requirements for the renovations and provides attachments including existing building layouts, asbestos reports, and pictures.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT

SOO: Renovate 51424 / 51428 Modification #0

STATEMENT OF OBJECTIVES

Work Order Number:

TAU 00266-9J Renovate BLDG. 51424 Work Order Number:

FEE 18075-8J Renovate BLDG. 51428

Date: 6 JUN 2023 DPW Project Manager: George W. Bittorf

*NOTE: Abbreviations can be referenced on page #12 *

1.0 Project Background

1.01 Buildings 51424 and 51428 were placed in service on 11/30/1972, The Air conditioning for building 51424 is cooled by 4 small, roof top, Air evaporation units and one large roof top Air evaporation unit. The Air conditioning for building 51428 has 4 small water evaporator chiller units ducted through the windows. The surrounding asphalt pavement needs to be removed, regraded, and resurfaced to insure proper drainage around the buildings. Additionally, the project will include repairs, renovations, and upgrades to defined areas in the building.

2.0 Project Objectives

2.01 The Contractor shall provide design/build services and furnish all labor, material, equipment, supervision, transportation, permits, fees, licenses, and utilities necessary renovate Buildings 51424 and 51428. located at Fort Huachuca, AZ. A non-specific Design Criteria listing for the project is provided in Section 4.0 below. The Contractor shall prepare a more detailed description outlining their Contract Execution Overview (technical approach, labor hours, materials/equipment, self-performance/sub-Contractor), tentative schedule, and previous experience for this type of work. The Contractor shall field verify the area of work before submitting their proposal. This proposal shall generalize the major work elements and be all inclusive. The Government will rely on the Contractor's expertise and experience to successfully complete the project.

3.0 Proposal Requirements

3.01 Technical Approach. The Contractor proposal technical approach section must address each of the line items listed in Section 4.0, Design Criteria. This section must include a description of the steps and methods by which each item will be completed. The description must adhere to the details outlined in pertinent UFGS and UFC specifications, providing a clear understanding of the requirements to a competent, qualified person.

3.02 Materials/Quantities/Equipment. The Contractor proposal’s Materials, Quantities, and Equipment section must provide a clear and detailed list of all building materials and estimated quantities, as well as the equipment to be used in the execution of the project. These items must be presented in a manner that a competent, qualified person can understand what materials, estimated quantities and equipment will be used during the execution phase of the project.

3.02.01 Materials shall include items such as mechanical fasteners, hardware, devices, valves, piping, sealants, structural members, and all other permanently installed materials at the project location.

3.02.02 Equipment shall consist of all tools, machinery, motorized or engine driven equipment, and all other non-permanent items which will not be left on site.

3.03 Labor Hours. The Contractor proposal labor hours section must give a detailed breakdown of labor hours, to include estimated number of hours assigned to each trade or supervisory position, providing a clear understanding of the division of labor can be determined. In addition, the total labor hours estimated for the project should be listed.

3.03 Tentative Schedule. The Contractor Proposal Tentative Schedule section must provide a detailed estimate of all activities to be conducted during the project period of performance. Scheduled actions must be listed in a logical order to demonstrate a clear timeline of the proposed project activities.

4.0Design Criteria

4.01 Demolition

4.01.01 The contractor shall Remove all existing asbestos tile in Buildings 51424 and 51428.

4.01.02 The contractor shall prepare a Demolition Plan and submit proposed salvage, demolition, and removal procedures for approval before work is started. Demolition must be completed in compliance with UFGS 02 41 00 DEMOLITION AND

DECONSTRUCTION.

4.01.03 The work includes demolition, identified items and materials, and removal of resulting rubbish and debris from Government property daily, unless otherwise directed. The contractor shall verify each workday that the facility will be available and capable of undergoing construction activities.

4.01.04 Asbestos Containing Material and Lead Base Paint testing has been completed by the Government.

4.02 Design Criteria shall be performed in accordance with the project plans, specifications, and all applicable codes. In the event of a conflict between the contract specifications and the plans, the specifications shall take precedence.

4.03 The following list is not detailed and is considered as a Design-Build Contract.

Construction services shall include incidental and ancillary components, materials, and/or equipment accessories customarily required by code, guideline, or industry standard practice to make the work complete and operational.

4.04 Design: Design and renovate the workspace and office space, in Buildings 51424 and 51428 per the proposed floor plan. Design new asphalt pavement to insure proper drainage. Design shall be in accordance with the Unified Facilities Criteria (UFC).

Submit 35%, 65%, and 95% designs to the Government for review.

4.04.01 The Contractor shall remove the existing asphalt surface and subbase material.

Recontour the subgrade to establish positive drainage away from the buildings.

Replace 9” of subbase material, compact, seal, and resurface with 3” of 1 ½” asphalt binder base course and 2” of asphalt wearing course.

4.04.02 Renovation: The Contractor shall renovate workspace and office spaces. The office spaces shall be configured per the floor plan provided.

4.04.03 The Contractor shall construct, install, remove, or relocate walls, electrical, communications (telephone and internet), plumbing, AC/ductwork, and associated items, as required to modify the layout of the existing buildings, per the proposed floor plan.

4.04.04 The Contractor shall, remove and install, new LED light fixtures throughout workspace and office space areas in both buildings.

4.05 Mechanical: Remove existing AC evaporative units and gas space heaters. Replace the gas space heaters with new infra-red gas heaters and replace the gas water heater.

4.05.01Design and Install a new Energy Efficient, AC system. Install new ductwork, dampers, registers, grilles, thermostats, and associated items, for the new offices and in the workspace of the building.

4.06 Electrical: The Contractor shall replace all electrical panels, and breakers. New Panels and main disconnect switch will be connected to the new 800Amp 480V- 3 phase service. The Contractor shall install new panel labeling and 6 extra fuses for the main disconnect switch.

4.06.01 The Contractor shall perform wire continuity testing for the circuits that remain untouched except at the panel.

4.06.02 The Contractor shall submit an RFI if there is any issue with the 480V service for further resolution.

4.06.03 The Contractor shall install new backup power devices as required by Code.

4.06.04 The Contractor shall install a new, dedicated 100-amp panel for the

Communications room and perform wiring as required.

4.06.05 Provide one line wiring diagram from transformer to panels after completion.

The one-line diagram shall show all disconnects and equipment in use.

4.06.06 Provide updated panel schedules.

4.06.07 Provide Arc Flash analysis (including calculations). All electrical panels shall be labeled for Arc Flash compliance.

4.06.08 Provide electrical floor plan, noting the circuit breaker source on outlets, lights fixtures, and other devices. Provide labels to all electrical devices.

4.06.09 The Contractor shall mark and label, empty, abandoned electrical conduits and junction boxes in place.

4.07Handicap access: The Contractor shall provide Handicap access to the building.

4.07.01 The Contractor shall provide and install ADA compliant, workstation, and restroom in the building according to UFC 3-120-01, 1 March 2014.

4.08Additional Construction:

4.08.01 Demo existing walls as indicated on the attached drawings.

4.08.02 Construct new walls as shown on the included drawings.

4.08.03 Install new 2 X 2 drop ceiling with metal grid.

4.08.04 Remove and replace existing windows with new insulated replacement windows that conform to the historical décor of the current building.

4.08.05 Remove and replace existing rollup garage doors with new insulated rollup garage doors with motorized openers including remotes.

4.09Fire Suppression: Install a new fire sprinkler system for the entire building.

4.09.01 Install a fire sprinkler/fire suppression system in accordance with the NFPA

914, NFPA 25, NFPA13, and NFPA 24, except where specifically modified by UFC 3-600-01 as written in UFC 3- 600-01, Chapter 9-6.1.2.

4.09.02 Establish and connect a new water supply of sufficient size for the new fire suppression system.

4.10 Fire Alarm System & Emergency Egress:

4.10.01 Remove the current fire alarm system. Provide and install a complete and fully functioning fire alarm system that covers the entire building. This facility is considered public space and the LOC and AC shutdowns, (green buttons), are to be code compliant. The AHJ is the Fort Huachuca Fire Department.

4.10.02 The Contractor shall procure and install a Knox box. The electronic process of procurement and installation may be used instead of paper requests. The Knox box location shall be coordinated with the tenant and the Fort Huachuca Fire Department.

4.10.03 The Contractor shall install smoke detectors, fire alarms, pull stations, emergency detection, lighting, exit signage, emergency AC shutoff, in accordance with NFPA 72 and a Mass Notification System (MNS) in accordance with UFC 4-021-01. The new fire alarm control panel (FACP) to interface with the existing Monaco D-21 via radio on Fort Huachuca. Factory painted red conduit, with red painted junction/back boxes, covers, and couplings shall be used in unfinished areas for all fire alarm systems and MNS.

Refer to UFC 3-600-01 for definitions of unfinished areas. The inside covers of all junction boxes in finished areas shall be identified as “Fire Alarm” and all conduit in finished areas shall have painted red bands 3/4- inches wide at 20 feet intervals and on both sides of all floors, wall, and ceiling penetrations as required and stated in UFC 3-600-01.

4.10.04 Provide five (5) keys to the Government for each fire alarm system panel, each MNS panel, and each LOC panel.

4.11 Finishes: All interior finishes and painting shall match the existing area décor.

4.11.01The exterior shall be sand blasted and painted with a waterproofing paint.

4.11.02 The interior perimeter walls shall also be painted with a waterproofing paint to ensure that the interior stays dry.

4.11.03 The interior office walls shall be painted with 1 coat primer; 2 coats finish Latex flat paint.

4.11.04 The garage floor shall be painted with a primer coat and an epoxy sealant paint.

4.12 Site Restoration: Upon completion of construction activities, replace, patch, and repair, all damaged caused by construction in order to complete the project.

4.12.01 Prior to the final inspection the Contractor shall make the building ready for occupancy. This includes a thorough cleaning of the entire building. The building should be free of dust and debris, floors mopped, carpets cleaned, walls and windows cleaned. The exterior of the building shall be free from all construction debris, landscaping returned to a state comparable to the start of the project.

4.13 Close-out Documents: Provide four (4) CDs with digital copies of the as-built drawings PDF and CAD/DWG formats) and Operation & Maintenance (O&M) manuals (PDF).

Provide four (4) copies of the O&M manuals (Facility, O&M, QAE, Engineering).

4.14 ENRD: NEPA form (#4067) has been filed.

5.0 Schedule

5.01 Notice to Proceed (NTP) shall be issued after verification of bond requirements IAW

FAR Part 28. Project shall be 100% complete and ready for final inspection no later than 240 calendar days after the NTP.

5.02 The Contractor’s proposed schedule shall be submitted with the proposal. A revised schedule shall be submitted at the time of the preconstruction conference for approval.

The schedule shall be in the form of a progress chart of suitable scale to indicate the percentage of work scheduled for completion at any given date during the period. The schedule shall take into consideration anticipated adverse weather that could preclude progress, long-lead equipment, or materials critical to the completion of the project, review periods for submittal items requiring Government review and approval, air quality control permitting process, and other events and milestones as necessary.

6.0 Occupancy

6.01 Buildings 51424 and 51428, in this contract will not be occupied during the construction.

7.0 Material, Standards, Codes, Regulations, and Workmanship (FAR 52.236-5, Material and Workmanship)

7.01 All materials and equipment shall be new unless otherwise specified. All work shall be completed in accordance with the plans and specifications, applicable industry standards, UFC, UFGS, NFPA, ASHRAE, NEC, SMACNA, NEBB, AABC, MUTCD, SDDCTEA, and AASHTO standards; federal, state, and local codes, regulations of EPA, OSHA, NEPA, and MSHA, if required; Network Enterprise Center (NEC) and SSVEC requirements; Fort Huachuca Energy Policy and Army Energy and Water Management Program. All Government permits, certifications, lead paint and asbestos analyses, if required, shall be obtained by the Contractor prior to commencement of work or prior to beginning construction, and are the specific responsibility of the Contractor (Federal, State, and local governments). Air quality control permitting efforts must be coordinated with DPW ENRD Air Quality Program prior to the start of any construction and prior to making any irrevocable decisions (i.e., purchasing equipment) related to equipment, activities, or processes, that have the potential to emit air pollutants such as combustion exhaust, dust, asbestos, evaporative emissions, refrigerant, etc. All certifications are the responsibility of the Contractor (potable water health certifications, gas weld certifications, refrigerant technician certifications, including asbestos removal certifications) and must be provided to the COR prior to final payment.

7.02 The provisions of Public Law 109-58 (Energy Policy Act of 2005) shall be totally incorporated. In the event of a conflict with industry standards, specifications will take precedence.

7.02.01 All AC, related systems must be the most energy efficient. Proper planning is necessary to ensure the design and construction of any new AC system is in accordance with the installation’s goals toward Energy Security, surety, and conservation. The Energy Branch must approve all designs prior to construction and all energy calculations must be included.

7.02.02 All lighting fixtures are to be LED. The Energy Branch must approve all designs prior to construction and all energy calculations must be included.

7.03 The Contractor shall obtain specific approval for all materials and equipment that vary from the standards established herein. All work shall be performed in a skillful and workman-like manner to current applicable industry standards and in accordance with manufacturer instructions. Work requiring certified craftsmen shall be performed by certified personnel. Proof of such certification, training, or other qualifications, shall be made available to the Government upon request. If the manufacturer of any product used in accomplishing this project has published an installation and/or operation manual, such manual shall be followed in its entirety. If any organization such as, but not limited to, APA or ANSI publish any construction guide, it will be followed as applicable to this project. If the manufacturer’s manual deviates from any established code, regulation, local requirement or this work proposal, such deviation shall be brought to the attention of the government representative before award, for written resolution. A revised proposal will be issued to specify such resolution and incorporated in any resulting award.

7.04 Commissioning of major systems (e.g., AC, fire protection, court room A/V) is required.

7.05 The Contractor shall comply with Federal directives by recycling at least 10% of construction waste.

7.06 The Contractor shall comply with all Federal, State, and Army Environmental requirements. Ensure Contractor responsibilities and operating limitations are noted in the proposal. Contractor shall keep all records required by Federal/State authorities and submit to the Government with their weekly report.

7.07 Air, water, asbestos, lead based paint and hazardous waste, among others, need to be covered in any construction, demolition, or renovation contract; thus, the Contractor is required to maintain all record-keeping and submit it to the appropriate government entity at the appropriate time, with a copy sent to the DPW COR.

8.0 Signage

8.01 The Contractor shall provide and install all Handicap, room, space, and workstation identification signage will be in accordance with the sign standards, change #4, from UFC 3-120-01, 1 March 2014. Room identification signs must be included in all public accessed facilities. The UFC has examples and sizes required for all locations.

8.01.02 The Contractor shall provide evacuation placards for the building showing location and Egress routes out the building. These evacuation placards will be placed at all interior locations as required by the Post Safety Office.

9.0 Door Locks

9.01 Exterior and interior doors requiring locks shall be provided with construction cores and keys by the Contractor. The using organization is required to acquire the permanent keys and cores through the Directorate of Public Works (DPW). The Contractor shall install new locks for all door locations.

10.0 Clean Up (FAR 52.236-12, Cleaning Up)

10.01 The Contractor shall always keep the work area, including storage areas, free from the accumulation of waste materials. All trash will be removed from the site daily. Upon completion of the project, all equipment, materials, and other items associated with the project shall be removed from the project site and the site shall be left clean. All waste products created during performance of the work shall be removed from the project site, packaged in an environmentally approved manner, and disposed of OFF-POST at an environmentally approved disposal site.

11.0 Utilities: Where available, onsite utilities will be provided to the Contractor. These utilities shall only be used in the performance and support of the project.

11.01 Any temporary or permanent connection to the utility system will be coordinated with the Contracting Officer Representative prior to hook-up. The Contractor shall complete the temporary connection and all temporary electrical work in accordance with applicable codes and standards. Temporary electrical wiring and devices shall comply with the current National Electrical Code. Temporary wiring and devices shall be removed at project completion. All temporary electrical work shall be at the Contractor’s expense.

11.02 Expansions/tie-ins to the potable water system and/or sewer collection system must be coordinated with the DPW. Some projects for expanding the potable water system and/or the sewer collection system will require an ADEQ 4.01 permit/NOI, prior to breaking ground.

12.0 Storage Areas/Lay Down Yards

12.01 The Contractor and the Contracting Officer’s Representative will agree on temporary storage areas and lay down yards in the general location of the project.

Request for proposed storage area shall be submitted with the proposal documents.

The Contractor shall be responsible for the safety, security, and maintenance associated with storage areas. Storage areas shall always be kept clean and have a neat and organized appearance. If the storage area is not maintained, the Contracting Officer may direct the Contractor to store materials off the installation. Storage areas and lay down yards shall be returned to the existing stable state, which may require re-seeding with native grass mixtures.

13.0 DD Form 1354 Worksheet Preparation

13.01 The Contractor shall prepare a DD FORM 1354 Information Worksheet near completion of the project and submit it to the Government prior to final inspection and acceptance. The Contractor may obtain a DD FORM 1354 Information worksheet from the DOC CS or the DPW COR.

14.0 Controlled Areas

14.01 There are no controlled, or secure, areas in the building. No escorts are required.

15.0 Waste Disposal and Borrow Pits

15.01 The Contractor shall comply with the Fort Huachuca Waste Disposal/Borrow Pit Plan and submit a project specific Environmental Protection/Borrow Pit Plan.

16.0 Contractor Quality Control (CQC)

16.01 The Contractor is responsible for quality control and shall establish and maintain an effective quality control system and shall include the following:

16.01.01 The Quality Control (QC) system shall consist of plans, procedures, and organization necessary to produce a product that complies with the specified requirements of this project. The system shall cover all construction activities, both on site and off site, and shall be coordinated with the proposed construction schedule.

16.01.02 The Contractor shall submit a Contractor Quality Control Plan, proposed to implement the specified requirements, to the COR for review and approval. The plan shall identify personnel, procedures, controls, instructions, tests, records, and forms to be used. Construction will be permitted to begin only after acceptance of the CQC plan. The plan shall include, as a minimum, the following to cover all construction operations and features.

16.01.02.1 A description of the CQC organization and lines of authority (e.g., Organization Chart).

16.01.02.2 Names, qualifications, duties, responsibilities, and authorities of CQC personnel.

16.01.02.3 Procedures for scheduling, reviewing, certifying, and managing submittals.

16.01.02.4 Procedures for conducting CQC inspections to include routine inspections, follow-up inspections on deficient work, pre-final inspections, and final inspections.

16.01.02.5 Procedures for tracking construction deficiencies from the time of identification through acceptable corrective action (e.g., Deficiency Tracking Log).

16.01.02.6 Documentation, reporting procedures, and proposed reporting format.

16.01.03 The Contractor shall maintain current records providing factual evidence that the required QC activities and/or tests have been performed. These records shall be furnished to the Government daily and within 24 hours after the date covered by the report (except when no work is performed; then one report shall be submitted for every seven days of no work). The reports shall include the work of subcontractors and suppliers and shall be on an acceptable form that includes, the following:

16.01.03.01 Contractor/subcontractor and their area of responsibility.

16.01.03.02 Work performed each day, on location, description, and by whom.

16.01.03.03 Weather conditions encountered.

16.01.03.04 Any delays encountered.

16.01.03.05 Test and/or control activities performed with results and references to specifications/drawings.

16.01.03.06 Materials received with statement of quantity and quality, acceptability, and storage.

16.01.03.07 Submittals and deliverables reviewed.

16.01.03.08 Job safety evaluations stating what was checked, results, and instructions or corrective actions taken.

16.01.03.09 Instructions given/received and conflicts in plans and or specifications.

16.01.03.10 Contractor’s verification statement that equipment and materials incorporated into the work and the workmanship comply with the specified requirements.

16.01.03.11 Air Quality Control – The Contractor shall comply with all requirements of the Fort Huachuca Air Quality Control Permit and other Clean Air Act regulations by submitting all required records, including but not limited to the following, as applicable, in accordance with applicable pre-construction/post- construction timelines, to the DPW ENRD Air Quality Program:

16.01.03.11.01 Detail equipment specifications, activity/process descriptions

16.01.03.11.02 Documentation of equipment that was installed in accordance with manufacturer.

16.01.03.11.03 Specifications of removed equipment.

16.01.03.11.04 Dust control logs.

16.01.03.11.05Fuel certifications.

16.01.03.11.06 Report of run times occurring during equipment installation (i.e., generator hour meter readings). EPA engine certifications.

16.01.03.11.07 Records of Asbestos NESHAP Notification for Renovation and Demolition Activities forms filed with the appropriate state/county entity and all supporting documentation.

16.01.03.11.08 Miscellaneous chemical usage.

16.01.03.11.09 Refrigerant loss and associated items

16.01.03.12 All reporting details must be coordinated with the Air Quality Program prior to the start of construction or activity/process.

17.0 Inspection

17.01 All work is subject to inspection and testing by the Government at all places and at all reasonable times before acceptance, in accordance with FAR 52.246-12, Inspection of Construction. Government inspections and tests do not relieve the Contractor of the responsibility for providing adequate quality control measures, nor does it constitute or imply Government acceptance of the work. The presence or absence of a Government inspector does not relieve the Contractor of complying with the specified requirements, nor is the Government inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

18.0 Accident Prevention

18.01 The Contractor shall comply with 29 CFR part 1926, 29 CFR part 1910, all state and local occupational safety and health requirements, and requirements of EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual.

18.02 The Contractor is responsible for accident prevention and safety and shall establish and maintain an effective system.

18.03 The plan shall be developed by a “qualified person” (EM 385-1-1, A-1, 1.a.) and be signed by a representative of the prime Contractor’s “corporate office authorized to obligate the company.” The plan shall meet the minimum basic outline requirements contained in EM 385-1-1, Appendix A. The plan shall be job-specific and shall include work to be performed by subcontractors and measures to be taken by the Contractor to control hazards associated with materials, services, or equipment provided by suppliers.

The accident prevention plan shall include procedures for frequent safety inspections, conducted by competent persons, of the work sites, material, and equipment to ensure compliance with the plan and other referenced standards. Unless otherwise approved, Quality Control personnel shall conduct and document daily safety inspections.

19.0 Submittals

19.01 The Contractor shall provide information and/or submit samples of materials that the Contractor contemplates incorporating in the work. All submittals shall be at the Contractor’s expense.

19.01.01 The following submittal items are required for this project:

Submittals required prior to construction (normally at PRECON) shall include:

19.01.01.01 Construction schedule:

19.01.01.02 Project designs, specifications, design analysis

19.01.01.03 Shop drawings

19.01.01.04 Submittal Register (ENG FORM 4025 and 4288)

18.02.01.05 Catalog cuts (equipment and materials)

18.02.01.06 Finish material samples and/or product data

19.02.01.07 Sub-Contractor personnel list (POC with phone number)

19.02.01.08 Quality Control, Accident Prevention, Disposal/Borrow Pit Plans

19.02.01.09 Permits and certifications (Dig Permit, NOIs, 4.01 permits, Hot Work)

19.02.01.10 Air Quality Control and other Environmental submittals as appropriate

19.01.02 Submittals required during the construction period shall include:

19.01.02.01 Monthly reports to COR

19.01.02.02 Air Quality Control Reports and other Environmental submittals

19.01.02.03 TAB reports – certified by NEBB Technician

19.01.02.04 Draft DD FORM 1354 Worksheet

19.01.02.05 Air Quality Control and other Environmental submittals as appropriate

19.01.03 Submittals required near the end of the project but before final inspection:

19.01.03.01 Final DD FORM 1354 Worksheet.

19.01.03.02 As-Built drawings (per contract requirements)

19.01.03.03 Certified Commissioning Reports

19.01.03.04 O&M manuals – 4 hard copies and 4 digital copies on 4 CDs

19.01.03.05 All required certifications (potable water piping, gas line joint fusion weld certification)

19.02.03.06 Training for shop personnel

19.02.03.07 Estimate quantity of all recycled wastes

19.02.03.08 Repair parts list and vendors

19.02.03.09 Maintenance paint

19.02.03.10 Air Quality Control and other Environmental submittals as appropriate (construction water used, Dust control records)

19.02 If any of the equipment/material submittals are disapproved, the Contractor shall resubmit the disapproved submittals for review and comment within five (5) working days of notification of their disapproval. This process shall continue until all equipment/materials are approved by the Government.

19.03 If Contractor uses, or installs, materials or equipment without approval, he does so at the risk of subsequent rejection and replacement at his cost.

20.0 Final Inspection and Acceptance

20.01 Final inspection and acceptance shall be conducted after the pre-final inspection is completed by the CQC representative and the pre-final inspection punch list items are completed by the Contractor. The CQC representative compiles the pre-final punch list immediately after the work is completed. The Government’s PM/COR/QA representative will sign for completion documents after the final inspection and its punch list items are corrected; and upon receipt of acceptable As- Built Drawings and any delayed work (seeding prior to rainy season, Air Conditioning Test, Adjustment and Balancing in summer months, etc.). Until all delayed work, Punch-list items, As- Built drawings and O&M Manuals are completed to the government’s satisfaction (delivered/approved/accepted as appropriate), the government may retain 10% of the total contract cost IAW FAR 52.232-5 (e).

21.0 Warranty Requirements

21.01 All work shall be covered under the one-year warranty of construction (FAR 52.246-

21, Warranty of Construction).

21.02 In addition to the one-year warranty of construction, the Contractor shall obtain all warranties that would normally be given in commercial practice and, upon final acceptance of the work (or before), provide a list to the Government of each warranted equipment item, feature of construction, or system. The list shall indicate the following:

21.02.01 Name of item.

21.02.02 Model and Serial Number.

21.02.03 Installed location.

21.02.04 Name and phone numbers of manufacturers or suppliers.

21.02.05 Names, addresses, and phone numbers of sources of spare parts.

21.02.06 Warranties and terms of warranty. Items with warranties extending beyond the one-year warranty shall be indicated with separate warranty expiration dates.

21.02.07 Start date and duration of warranty period.

21.02.08 Summary of maintenance procedures required to continue the warranty in force with cross-reference to specific pertinent operation and maintenance manuals as applicable.

21.03 The list shall include the status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, AC balancing, pumps, motors, transformers, and for all commissioned systems such as fire protection and alarm systems, sprinkler systems, lightning protection systems, etc.

21.04 At approximately four (4) and nine (9) months after acceptance, the Government may conduct warranty inspections. The inspections will be scheduled by the Government COR/Project Manager and conducted with the user, and, if possible, Contractor personnel attending. A list of deficiencies existing at the time will be compiled and furnished to the Contractor for correction.

Attachments: (“J” section of the contract package)

• J-1 Existing building layout with changes (51424 / 51428)

• J-2 Building 51424 asbestos reports (prior MAY 2023)

• J-3 Building 51428 asbestos reports (prior MAY 2023)

• J-4 Pictures

• J-5 As-Built Drawings

• J-6 Comm Box 51424

• J-7 Comm Box 51428

• J-8 Communication cable Map

• J-9 Technical exhibit 51424

• J-10 Technical exhibit 51428

SOO: Modification #0

Abbreviations

AABC - Associated Air Balance Council AASHTO - American Association of State Highway and Transportation Officials AC – Air Conditioning ADA - Americans w/ Disabilities Act of

1990 (US)

ADEQ - Arizona Department of Environmental Quality AHJ – Authority Having Jurisdiction ANSI - American National Standards Institute APA - American Planning Association ASHRAE - American Society of Heating, Refrigerating, & Air- Conditioning Engineers AZPDES - Arizona Pollutant Discharge Elimination System CAD - Computer-Aided Design CDs – Compact Disc’s CFR - Code of Federal Regulations COR – Contracting Officers Representative CQC - Construction Quality Control CS – Contract Specialist DD - Department of Defense DOC - Directorate of Contracting DPW – Directorate of Public Works DWG - Drawing(s) EM – Engineer Manual ENG- Engineer ENRD - Environmental and Natural Resource Division EPA – Environmental Protection Agency FACP - Fire Alarm Control Panel FAR - Federal Acquisition Regulation HVAC – Heating Ventilation and Air Conditioning IAW - In Accordance With LED - Light Emitting Diode LOC - Line of Communications MNS – Mass Notification System MSHA - Mine Safety and Health Administration MUTCD - Manual on Uniform Traffic Control Devices

NEBB - National Environmental Balancing Bureau NEC – National Electric Code NEC – Network Enterprise Center NEPA - National Environment Protection Agency NESHAP - National Emission Standards for Hazardous Air Pollutants NFPA – National Fire Protection Association NOI – Notice of Intent OSHA – Occupational Safety and Health Association PDF - Portable Document Format PM – Project Manager POC – Point of Contact QAE - Quality Assurance Engineer/Evaluator QC – Quality Control SDDCTEA - Surface Deployment and Distribution Command Transportation Engineering Agency SMACNA - Sheet Metal and Air Conditioning Contractors National Association SSVEC - Sulphur Springs Valley Electric Cooperative TAB – Testing and Balancing UFC - Unified Facilities Criteria UFGS - Unified Facilities Guide Specifications O&M – Operations and Maintenance

STATEMENT OF OBJECTIVES
*NOTE: Abbreviations can be referenced on page #12 *
2.0 Project Objectives
3.0 Proposal Requirements
4.0Design Criteria
4.01 Demolition
4.01.01 The contractor shall Remove all existing asbestos tile in Buildings 51424 and 51428.
4.01.02 The contractor shall prepare a Demolition Plan and submit proposed salvage, demolition, and removal procedures for approval before work is started. Demolition must be completed in compliance with UFGS 02 41 00 DEMOLITION AND DECONSTRUCTION.
4.01.03 The work includes demolition, identified items and materials, and removal of resulting rubbish and debris from Government property daily, unless otherwise directed. The contractor shall verify each workday that the facility will be available a...
4.01.04 Asbestos Containing Material and Lead Base Paint testing has been completed by the Government.
5.0 Schedule
6.0 Occupancy
8.0 Signage
9.0 Door Locks
11.0 Utilities: Where available, onsite utilities will be provided to the Contractor. These utilities shall only be used in the performance and support of the project.
12.0 Storage Areas/Lay Down Yards
14.0 Controlled Areas
15.0 Waste Disposal and Borrow Pits
16.0 Contractor Quality Control (CQC)
17.0 Inspection
18.0 Accident Prevention
19.0 Submittals