This is a Performance Work Statement (PWS) for mini-split system replacement and electrical system upgrade at the Western Oregon Service Unit (Chemawa Health Center) in Salem, Oregon.

The project objectives are to provide fully operational electrical and HVAC infrastructure in the Pod 2 Server Room to support upgraded IT equipment without overheating, in compliance with applicable codes and standards. The work must be completed within 30 calendar days after receipt of the Notice to Proceed, with commencement required within 10 calendar days. Key deliverables include: installation of sixteen (16) dedicated 208/240V, 20-amp circuits with NEMA L6-20R twist-lock receptacles, each served by individual 2-pole breakers; removal and proper disposal of the existing 1-ton Daikin mini-split system (model RK12NMVJU); and installation of a new approximately 36,000 BTU/hr (3-ton), variable-capacity mini-split heat pump system with a minimum 17 SEER efficiency rating. The contractor must evaluate existing 208/240V electrical sources and provide all upstream infrastructure as needed, which may include a 480V feeder breaker, step-down transformer, and new subpanel. Electrical work must maintain continuous server room operations, protect patient care activities, and comply with NFPA 70, NFPA 70E, Oregon electrical codes, and NEC. HVAC work must comply with EPA Section 608 refrigerant handling requirements, UMC, and IBC standards. The contractor is responsible for field-verified load calculations, shop drawings, safety planning, infection control coordination, and final commissioning with O&M training. All refrigerant work requires EPA 608 certification, electrical work requires Oregon licensing, and electrical design must be prepared by or supervised by an Oregon-licensed electrical contractor with commercial power distribution experience.

View the file

Other files for this federal contract opportunity

Other files attached to Western Oregon POD2 Server Room Upgrades, newest first.
File Type Posted
A11 Pre-Solicitation SAM notice DRAFT.pdf PDF
J04 US DOL WD OR20260104 Dated 1-2-2026.pdf PDF
J02 Map Server Rm Location.pdf PDF
B01 75H70126Q00023 - Rev.pdf PDF
J03 Ktr Price Schedule - Pod 2.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement

Mini-Split System Replacement and Electrical System Upgrade

Overview

Site Location

The Western Oregon Service Unit (WOSU) is in Salem, Oregon, approximately 43 miles south of Portland, Oregon (Attachment A). The project location and physical address are below.

Western Oregon Service Unit

Chemawa Health Center 3750 Chemawa Rd. NE Salem, Oregon 97305

Background

The Pod 2 Server Room is a small interior equipment closet—approximately 64 square feet— with no exterior walls. All heat in the space is generated by the equipment itself; envelope heat gain is minimal compared to equipment load.

The room is undergoing an IT equipment upgrade as part of the IHS Cisco Refresh Project.

Incoming network switches are larger and draw significantly more power than the units they replace, which has two direct consequences for the building infrastructure:

1. The existing electrical system does not provide the quantity or type of circuits required by the new equipment. Sixteen (16) dedicated 208/240V, 20-amp circuits with NEMA L6- 20R twist-lock receptacles are required to serve the new switch power connections. The building’s primary distribution is 480V; existing 208/240V panel capacity in the vicinity of the server room shall be evaluated before assuming new step-down infrastructure is required.

2. The existing 1-ton Daikin mini-split (model RK12NMVJU) has proven inadequate for the current equipment load, resulting in recurring overheating events. The incoming equipment will substantially increase the room's heat load. The estimated design load following the upgrade is approximately 36,000 BTU/hr (3 tons), requiring an appropriately sized replacement to meet that demand.

The IT equipment upgrade itself, network switch installation, cabling, and configuration, is being performed separately by IHS IT staff and is not part of this contract.

Objective

The objective of this project is to provide a fully operational electrical and HVAC infrastructure in the Pod 2 Server Room capable of reliably supporting the upgraded IT equipment without overheating, in compliance with all applicable codes and standards. The Contractor's scope is limited to the electrical and mechanical work described in this PWS.

Period of Performance

The Contractor shall commence work within 10 calendar days after receipt of the Notice to Proceed (NTP) and complete all work within 30 calendar days after NTP, unless otherwise modified by the Contracting Officer.

Work Summary

The following work is required to achieve the project objective:

• A site visit shall be conducted to verify existing conditions prior to the submittal of any design documents or shop drawings.

• Field-verified load calculations shall be provided for both electrical and HVAC systems prior to installation.

• Existing 208/240V electrical sources in the vicinity of the server room shall be evaluated.

All upstream electrical infrastructure required to supply sixteen (16) new 20-amp branch circuits shall be provided, which may include a 480V feeder breaker, step-down transformer, and new subpanel if no suitable existing source is identified. The determination of required scope and routing is the Contractor's responsibility.

• The existing 1-ton Daikin mini-split system (outdoor unit, model RK12NMVJU, and associated interior head) shall be removed from service and properly disposed of.

• A new approximately 36,000 BTU/hr (3-ton), variable-capacity mini-split heat pump system shall be installed, with at least one (1) wall-mounted interior head in the server room, associated refrigerant line sets, condensate management, controls, and all required electrical connections and roofing penetrations.

• Sixteen (16) new dedicated 20-amp, 208/240V, NEMA L6-20R twist-lock receptacle circuits shall be installed in the server room.

• All work shall be coordinated to maintain continuous server room operations and to protect patient care activities throughout the project.

Technical Requirements

A. Codes, References, and Standards

Work under this contract shall be performed in compliance with the codes, references, and standards listed below.

1. EPA Section 608 - Refrigerant Recovery and Handling

2. NFPA 70- National Electrical Code (NEC), current adopted edition

3. NFPA 70E- Standard for Electrical Safety in the Workplace

4. Uniform Mechanical Code (UMC)

5. International Building Code (IBC)

6. Applicable State of Oregon electrical and mechanical codes

7. Manufacturer's installation specifications and requirements

B. Submittals

The Contractor shall provide submittals on the items listed below. COR approval is required before proceeding with the portion of the work to which the submittal applies.

1. Pre-Work

• Project schedule, including all work activities, sequencing, and any anticipated power interruptions

• Safety and Accident Prevention Plan, including Hazardous Materials

Inspection findings (see Hazard Inspection section)

• Field-verified electrical and HVAC load calculations

• Infection Control Risk Assessment (ICRA)

• Interim Life Safety Measures (ILSM) Plan

• Written plan for maintaining continuous server room operations and cleanliness during construction

• Shop drawings showing locations of all new receptacles and circuit routing within the server room; location and configuration of any new upstream electrical equipment (transformer, subpanel, or panel modifications);

HVAC equipment placement, interior head location(s), refrigerant line routing, and condensate discharge routing

• Equipment and material data sheets (cut sheets) for all items to be installed, including:

o HVAC outdoor unit and interior head(s) o Refrigerant type and safety data sheet o Condensate pump(s) o Thermostat / wall control o Electrical receptacles (NEMA L6-20R) and branch circuit breakers o Step-down transformer and subpanel, if applicable o Roofing sealant and penetration materials, if applicable o Drywall repair materials, if applicable

2. Post Work / Closeout

• Start-Up Report

• Warranties (minimum five (5) years on all HVAC equipment)

• Operation and Maintenance (O&M) Manuals for all installed equipment

• As-built circuit schedule mapping each L6-20R receptacle to its panel, breaker number, and equipment designation

• As-built drawings reflecting final installed conditions, including receptacle locations, circuit routing, and HVAC equipment placement

• O&M training documentation

C. Equipment/Material Specifications

Electrical

Sixteen (16) dedicated branch circuits, each rated at 20 amperes, 208/240V (or equivalent as required to serve equipment and confirmed by field conditions), with NEMA L6-20R twist-lock receptacles, are required in the server room. Each circuit shall be served by an individual 2-pole breaker. No sharing of circuits between power supply connections is acceptable.

Branch circuits shall be distributed across panel phases and sections to maintain equipment resiliency consistent with manufacturer redundancy requirements. The intent is to ensure that no single breaker, phase, or panel section failure results in the loss of all power supply connections to a single switch chassis.

The Contractor shall evaluate existing electrical infrastructure in the vicinity of the server room to determine the most appropriate and cost-effective power source for the new branch circuits. If the existing 208/240V panel capacity is available and sufficient, it shall be used. If no suitable source exists, all required upstream infrastructure shall be provided, which may include a 480V feeder breaker, step-down transformer, and new three-phase subpanel. Upstream equipment shall be sized to the estimated coincident room demand of approximately 10,000 watts, with appropriate NEC demand factors, load diversity, and future capacity margin. The arithmetic sum of branch circuit breaker ratings shall not be used as the basis for feeder or transformer sizing.

A complete, labeled panel schedule shall be provided, and the circuit directory updated to reflect all new circuits, receptacle locations, and equipment served.

HVAC

A new approximately 36,000 BTU/hr (3-ton) mini-split heat pump system, capable of maintaining a stable server room temperature under full equipment load, is required. The system shall be Daikin or an approved equal, with a minimum efficiency rating of 17

SEER.

The system shall be variable-capacity (inverter-driven). Fixed-speed or single-stage systems are not acceptable; the small, enclosed room environment makes stable temperature control without short cycling a critical performance requirement. The system shall be capable of stable operation at low sensible loads without hunting or short cycling.

At least one (1) wall-mounted interior head shall be installed within the server room, positioned to provide effective airflow distribution across equipment racks. The Contractor shall propose the number and placement of interior heads appropriate to the room size and configuration, subject to COR approval. Placement shall be shown on shop drawings prior to installation.

The interior head(s) shall be equipped with condensate pump(s). Condensate shall be routed to an approved discharge location in a manner that eliminates any risk of dripping or leaking over server racks, electrical equipment, or active cabling.

The system shall include a wall control or thermostat with a digital display and manual temperature setpoint capability.

As-equal products will be evaluated based on the following salient characteristics:

• Rated cooling capacity of approximately 36,000 BTU/hr

• Variable-capacity / inverter-driven compressor

• Minimum 17 SEER efficiency rating

• UL Listed

• Wall-mounted interior head(s) suitable for server room installation

Equipment Load Table

The following table represents the design-basis heat load for the Pod 2 Server Room following the equipment upgrade. Because the room is an interior space with no exterior walls, envelope heat gain is minimal compared to equipment load, and the design load is driven entirely by equipment heat dissipation. Values marked "Estimated" reflect engineering judgment based on measured Command Line Interface (CLI) data from the existing switches and published Cisco platform specifications; field verification is required during the load calculation phase.

Equipment Qty Unit Load

(W) Total Load

(W) Basis

Cisco Catalyst 9410R Switches 2 ~3,000-

3,500 ~6,000- 7,000

Estimated - scaled from measured chassis internal power dissipation (excluding PoE) on existing Catalyst 4500 VSS pair ~1,196W internal on active chassis, adjusted for 8-blade vs. 5-blade configuration with margin

Tripp Lite UPS

(SU3000LCD2UHV) 1 1,600 1,600

Confirmed—LCD display reading under operational load

ScriptPro System (existing, no change) 1 ~500 ~500

Estimated: existing 110V circuit; no modifications to this system

C9300 Switch (replacing 2960-X) 1 ~200 ~200

Estimated; served from existing UPS; no new circuit required

Miscellaneous / Allowance ~500

Allowance for lighting, incidentals, and load growth

Design Basis Total ~10,000W

HVAC Design Load 36,000 BTU/hr (3 tons)

Includes safety factor for load growth and estimation uncertainty

Note on PoE Load: The Catalyst 9410R switches supply Power over Ethernet (PoE) to phones, wireless access points, and downstream devices located throughout the facility - not within the server room. Of the 2,205W measured on the active existing chassis, approximately 1,009W was inline PoE load delivered to downstream devices outside the room. Because this power is dissipated outside the server room, it does not contribute to the room's cooling load. Equipment load values in the table above reflect chassis internal power dissipation (excluding PoE delivered to remote devices), consistent with the measured CLI data methodology used to establish the design basis. This is the technical basis for the 3-ton HVAC design load; switch power supply nameplate ratings and Cisco's published maximum BTU figures are not used as the design basis.

Performance Outcomes

The following outcomes are required. The Contractor is responsible for determining the methods, sequencing, and means necessary to achieve them while maintaining continuous clinic operations and protecting patient care activities.

Electrical

• Sixteen (16) dedicated 208/240V, 20-amp circuits with NEMA L6-20R twist-lock receptacles shall be installed and operational in the server room, each served by an individual 2-pole breaker.

• Branch circuits shall be distributed across panel phases and sections to maintain switch power supply redundancy consistent with manufacturer requirements.

• All required upstream electrical infrastructure – evaluated and determined during the site visit – shall be complete and code-compliant prior to energizing new circuits.

• Shop drawings showing receptacle locations, circuit routing, and the location and configuration of all upstream electrical equipment shall be submitted and approved prior to installation.

• Panel schedules and circuit directories shall be updated to reflect all new circuits, with each receptacle traceable to its panel, breaker, and equipment designation in a final as-built circuit list.

• All existing circuits shall remain operational and undisturbed unless a specific outage has been scheduled and approved by the COR in advance.

• All work shall comply with NFPA 70E and facility Lockout/Tagout (LOTO) procedures;

a Job Hazard Analysis (JHA) / Activity Hazard Analysis (AHA) shall be submitted as required.

• Racks, cabling, and active equipment shall be protected from dust and debris throughout.

Egress and equipment cooling airflow shall not be obstructed. All disturbed finishes shall be restored to match pre-construction conditions.

HVAC

• The existing 1-ton Daikin mini-split system (outdoor unit, model RK12NMVJU, and associated interior head) shall be removed and disposed of in accordance with EPA Section 608 requirements. These units shall not be reused.

• A new approximately 36,000 BTU/hr (3-ton), variable-capacity, wall-mounted mini-split heat pump system (17 SEER or better) shall be installed and fully operational, with interior head(s) within the server room positioned to provide effective airflow across equipment racks.

• Shop drawings showing interior head placement, refrigerant line routing, and condensate discharge routing shall be submitted and approved prior to installation.

• The system shall demonstrate stable temperature control under full equipment load with the room door closed, with no short cycling behavior.

• Condensate shall be collected and discharged without risk of leaks or drips over server equipment, cabling, or electrical infrastructure.

• All rooftop penetrations and equipment interfaces shall be sealed and watertight upon completion.

• The system shall be commissioned per the manufacturer's startup requirements; a startup report shall be provided.

• Facility staff shall receive a demonstration of system operation, controls, and basic troubleshooting prior to closeout.

• All removed equipment, debris, and waste shall be transported to an EPA-approved disposal or recycling facility, as applicable.

Coordination and Protection of Operations

• Site access shall be coordinated with the Facility Manager a minimum of three (3) business days in advance of each work activity.

• Work adjacent to the AIIRS negative-pressure room shall be coordinated to avoid disruption. If the AIIRS room is activated during construction, the Contractor shall pause relevant activities as directed by the COR (not to exceed 60 minutes per occurrence).

• Any required power interruptions shall be scheduled and approved by the COR in advance. A written schedule identifying all anticipated interruptions shall be submitted prior to commencement of work.

• Server room operations shall remain functional throughout, except during specific approved outages. A written plan demonstrating how this will be achieved shall be submitted and approved before any work begins.

• All work outside of normal business hours shall be approved by the COR a minimum of 48 hours in advance.

• The work area shall be restored to a condition equal to or better than pre-construction upon completion.

Quality Assurance

• All refrigerant work shall be performed by a technician holding a valid EPA 608 Certification.

• All HVAC equipment shall be UL-listed. Only standard or premium-grade equipment will be accepted.

• All electrical work shall be performed by electricians licensed under applicable State of Oregon requirements.

• Electrical design documents – including load calculations, circuit layout, and any upstream infrastructure design – shall be prepared by or under the direct supervision of an Oregon-licensed electrical contractor with demonstrated experience in commercial power distribution.

• System functionality shall be demonstrated to the COR and Facility Manager prior to final acceptance.

• Deficiencies identified during the joint final inspection shall be corrected within fifteen

(15) calendar days of notification.

Kickoff Meeting

A kickoff meeting with the COR and Facility Manager is required prior to commencement of any work, to review project scope, schedule, site access, and coordination requirements.

Infection Control

The Infection Control Checklist shall be reviewed and evaluated in consultation with the Infection Control Officer on a weekly basis.

Activities generating dust - including cutting, drilling, and demolition - shall be controlled using methods specified in the attached Infection Control Project Risk Assessment Approval Checklist.

The Contractor's dust control methods shall be evaluated and approved by the Infection Control Officer prior to commencement of any such activities.

Interim Life Safety Measures Plan

The Contractor shall obtain advance approval from the IHS Safety Officer before modifying or temporarily disabling any life safety system, including exit path modifications or temporary alarm disabling. Approved interim measures shall be in place before any such modifications occur.

Hazard Inspection

Work will take place in and around a facility constructed in 1976 with a major remodel in 2017.

A comprehensive facility-wide hazardous materials survey has not been conducted.

As part of the Safety and Accident Prevention Plan, all work areas shall be inspected for hazardous materials prior to commencement of work, including assessment for Asbestos Containing Materials (ACMs) by a State Licensed Asbestos Inspector consistent with 40 CFR Part 61, Subpart M (Asbestos NESHAP). Inspection findings shall be included in the Safety and Accident Prevention Plan submittal. Discovery of confirmed or suspected hazardous materials shall be reported to the COR immediately, and a Contract Modification shall be negotiated before affected work proceeds.

Closeout Meeting

A closeout meeting with the COR and Facility Manager shall be conducted upon completion of all work. Written meeting minutes shall be recorded and provided by the Contractor.