J.4 Section 834 - Drainage structure maintenance -Minarets Road Repairs.pdf
PDF 121 KB Posted
- Attached to
- Scenic Byway Creek Fire Road Repair- Phase 1
- Solicitation number
- 12970223B0004
- Issued by
-
Department of Agriculture Forest Service
About this file
This document contains a federal contract opportunity solicitation and related technical specifications. The solicitation is for Phase I of the Scenic Byway Creek Fire Road Repairs project in the Sierra National Forest, Madera County, California. The work consists of furnishing all labor, materials, equipment, tools, transportation, and supplies necessary to repair the first 5 miles of Minarets Road. The technical specifications provide requirements for drainage structure maintenance along Minarets Road, including cleaning culverts, catch basins, and inlet and outlet channels. Payment for drainage structure maintenance will be made on a per mile basis. This procurement is set aside for small businesses only and is to be awarded as a firm-fixed-price contract.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
834 DRAINAGE STRUCTURE MAINTENANCE (8/96)
1. DESCRIPTION
This work consists of cleaning and reconditioning culverts and other drainage structures.
2. MAINTENANCE REQUIREMENTS
a. Drainage structures, inlet structures, culverts, catch basins, and inlet and outlet channels shall be cleaned when required by the Government. Catch basins shall be cleaned by removing the material within 10 feet.
b. The transition from the ditchline to the catch basin shall be cleaned a distance of ten
(10) feet. Inlet channels shall be cleaned for a distance of ten (10) feet of debris that obstructs water flow or could move down and plug the culvert inlet. Outlet channels and lead-off ditches shall be cleaned. Debris and vegetation shall be removed and placed so as to not enter the channel or ditch or obstruct traffic.
c. Cleaning and reconditioning is limited to the first four (4) feet of inlet and outlet determined along the top of the structure. Ordered reconditioning of culvert inlet or outlet shall be by field methods such as jacking out or cutting away damaged metal which obstructs flow. Damage or obstructions which are not field corrected under the requirements of this Section shall be reported to the Government.
d. Removal of brush and trees less than six (6) inches in diameter is incidental.
Brush and trees shall be disposed of by cutting into lengths of four (4) feet or less and scattered on fill slopes or outside the roadway limits.
3. MEASUREMENT
a. Measurement for maintenance will be “by the mile”, measured by slope distance along the centerline of the roadway. Measurement will be to the nearest one-tenth mile. No separate measurement will be made for any of the elements of work described in the foregoing
4. PAYMENT
a. Quantities as determined above will be paid at the contract unit price.
b. Payment will be made under:
Pay Unit Pay Item
834(01) Drainage Structure Maintenance, Mile