J.3 Statement of Work and Specs (34 Pages).pdf

PDF 301 KB Posted

Attached to
Sunbeam Dam Stairs
Solicitation number
1240LT25Q0029
Issued by

About this file

This document is a comprehensive Statement of Work (SOW) and technical specifications for the Sawtooth NRA Sunbeam Dam Stair Replacement project, detailing a federal construction contract for the USDA Forest Service. The project involves removing and replacing a large set of existing stairs at the Sunbeam Dam Interpretive Site in Custer County, Idaho, located approximately 13 miles east of Stanley and accessed from State Highway 75.

The technical specifications cover multiple critical aspects of the construction, including archaeological protection, site preparation, concrete work, earthwork, and aggregate base course requirements. Key technical requirements include: removing the existing stairs, pouring concrete landings and piers, constructing new steel stairs with handrails, protecting archaeological resources, maintaining proper erosion control, and adhering to strict environmental guidelines. The project has an estimated start date of July 7th, 2025, with a contract duration of 100 calendar days. Contractors must follow detailed specifications for materials, compaction, grading, and construction tolerances, with particular attention to protecting the surrounding natural environment and maintaining archaeological site integrity.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1

Section C - Description/Specifications/Statement of Work

GENERAL SPECIFICATIONS

GAOA Sawtooth NRA Sunbeam Dam Stair Replacement Final Submittal – 2/13/2023

1.1 SCOPE OF CONTRACT

A. This project removes and replaces a large set of stairs at the Sunbeam Dam Interpretive Site in the Sawtooth National Recreation Area.

B. The work includes removing the existing stairs, pouring concrete landings and piers, and constructing new steel stairs with handrails.

C. Quantities associated with these options are identified in the Schedule of Items.

1.2 PROJECT LOCATION

A. The project is located in the Sawtooth National Recreation Area of the Sawtooth National Forest, Custer County, Idaho, in Section 20, T11N, R15E. It is located approximately 13 miles east of Stanley, Idaho. The project site is accessed from State Highway 75.

1.3 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. The stairs will be closed to the public during construction, but the interpretive site and restroom will remain open to the public during construction; When large equipment will be present the contract may temporarily close the site up to 8 hours.

The Forest Service will issue a closure order for the site. The Contractor will be responsible for signing and limiting public access.

2. Contractor will provide all materials and labor necessary to protect streams, wet or dry, during construction activities. The Contractor will be required to submit a erosion control and stream protection plan and receive approval from the COR, in writing, prior to the beginning of construction. The erosion control and stream protection plan shall cover all disturbed areas, including borrow, stockpile, fueling, and staging areas used during construction activities to avoid or minimize downslope transport of sediment into the Salmon River and Yankee Fork

3. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.

4. Refuel and service equipment only in designated areas located more than 300-ft slope distance from the ordinary high-water mark of adjacent streams.

5. If work is to occur after August 15th the CO, with input from the Sawtooth NRA fish biologist, shall work with the contractor to confirm the proposed work poses no likelihood to adversely impact spawning Chinook Salmon.

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2

6. Utilities are not available at the site for construction purposes.

7. Toilet facilities are available at the site.

1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Idaho Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed to adequately keep the public from entering the job site. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.

1.5 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work) on site.

B. No overnight camping will be allowed on site.

1.6 INSPECTION OF WORKSITE

A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.7 START DATE

A. Estimate July 7th, 2025

1.8 CONTRACT TIME

A. Base Bid: 100 Calendar Days

1.9 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to or are included in payment for other pay items in this contract. These items are considered incidental, and no additional compensation will be made.

SECTION 011500 - ARCHEOLOGICAL PROTECTION

SECTION 011900 - MOBILIZATION

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3

SECTION 024113 - SELECTIVE SITE DEMOLITION

SECTION 033000 - CAST-IN-PLACE CONCRETE

SECTION 312000 - EARTHWORK

SECTION 321204 - CRUSHED AGGREGATE BASE OR SURFACE COURSE

END OF SECTION C

February 2025

ARCHEOLOGICAL PROTECTION 011500-1

USDA FOREST SERVICE, R4

GAOA Sawtooth NRA Sunbeam Dam Stair Replacement

SECTION 011500 - ARCHEOLOGICAL PROTECTION

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of protecting archeological resources contained in soil deposits.

1.2 DEFINITIONS

A. Resources: Prehistoric, historic, and recent 20th century artifacts, including charcoal, human bones, ash, fire rocks, and building materials that indicate the presence of past human occupation.

B. Archeologically Sensitive Areas: Areas that have been determined to contain significant in-the-ground archeological resources.

C. Nonsensitive Areas: Areas that have a low likelihood of containing significant in-the-ground archeological resources.

D. Archeological Monitor: Representative of the Government designated to record and collect cultural resources for compliance with Government regulations to protect in-the-ground resources.

1.3 SUBMITTALS

A. 14 days before start of ground-disturbing site work, submit a Daily Work Schedule, detailing construction work in archeologically sensitive areas. Key schedule to drawings and include the following information.

1. Starting and ending dates of ground-disturbing construction.

2. Locations of temporary facilities, such as barriers, field offices, staging areas, sanitary facilities, borrow pits, and haul and access roads.

3. Types of construction, such as clearing, topsoil stripping, structure of trench excavation, landscaping, and post construction clean up.

4. Methods and equipment used for each type of construction.

5. Plan for relocating work in the event of temporary work stoppages at each archeologically sensitive area.

1.4 QUALITY ASSURANCE

A. At least one week before on-site work begins, Contractor shall meet with Contracting Officer (CO) and Archeological Monitor to discuss Daily work Schedule and equipment and special methods to be used in archeologically sensitive areas. Contractor shall ensure that approved Daily Work Schedule is followed throughout construction.

ARCHEOLOGICAL PROTECTION 011500-2

PART 2 - PRODUCTS

PART 3 - EXECUTION

3.1 OBSERVATION

A. Archeological Monitor will observe all ground-disturbing site work, including construction of temporary facilities, at all archeologically sensitive areas, from a safe location mutually agreed on by Contractor and Monitor. As new ground is broken, Monitor will examine excavated materials, using construction layout centerline and perimeter staking as a reference point to record locations of findings.

3.2 DISCOVERY OF RESOURCES

A. If Archeological Monitor discovers resources, immediate relocation of the work to a nonsensitive area may be required to allow Monitor to take soil samples and record resources. While Archeological Monitor is documenting resources in sensitive areas, Contractor shall relocate work to nonsensitive areas where monitoring is not normally required.

B. If resources are discovered while Archeological Monitor is absent, stop work immediately and report the discovery to the Contracting Officer.

3.3 WORK STOPPAGE

A. The Contractor shall plan, schedule, and execute the work to prevent stoppage at one area from stopping all work at the construction site.

END OF SECTION 011500

MOBILIZATION 011900-1

GAOA Sawtooth NRA Sunbeam Dam Stair Replacement

SECTION 011900 - MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

1.2 MEASUREMENT AND PAYMENT

A. The measurement shall be lump sum for mobilization. Payment shall be as follows:

1. Bond premiums will be reimbursed after receipt of the evidence of payment.

2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

5. Progress payments for mobilization and preparatory work shall be subject to retainage.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 011900

SELECTIVE SITE DEMOLITION 024113-1

GAOA Sawtooth NRA Sunbeam Dam Stair Replacement

SECTION 024113 - SELECTIVE SITE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. This work consists of the removal and disposal of stairs, posts, chains, and any other obstructions that are not designated or permitted to remain. Except in areas to be excavated, the resulting trenches, holes, and pits shall be backfilled.

B. Materials removed shall become the property of CONTRACTOR.

1.2 MEASUREMENT AND PAYMENT

A. Measurement shall be Lump Sum Quantity for all items contained within project.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 General.

A. Contractor shall raze, remove, and dispose of all structures and obstructions which are identified in the project.

3.2 PROTECTION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

B. Remove temporary barricades and protections where hazards no longer exist.

END OF SECTION 322706

April 2015

CAST-IN-PLACE CONCRETE 033000-1

GAOA Sawtooth NRA Sunbeam Dam Stair Replacement

SECTION 033000 - CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section specifies cast-in place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes.

1.2 DEFINITIONS

A. Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash and other pozzolans, ground granulated blast-furnace slag, and silica fume; subject to compliance with requirements.

1.3 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Design Mixtures: For each concrete mixture. Indicate amounts of mixing water to be withheld for later addition at Project site.

C. Steel Reinforcement Shop Drawings when project design requires special consideration.

D. Field quality-control test reports.

1.4 MEASUREMENT AND PAYMENT

A. Concrete Landing - Measurement shall be Lump Sum Quantity. There will be no volumetric measurement of concrete. This item will be measured as each structure, complete with earthwork, reinforcing steel, and aggregate base course in place and finished as shown on the drawings and accepted by the contracting officer.

B. Concrete Piers - Measurement shall be Lump Sum Quantity. There will be no volumetric measurement of concrete. This item will be measured as each structure, complete with earthwork, reinforcing steel, and aggregate base course in place and finished as shown on the drawings and accepted by the contracting officer.

PART 2 - PRODUCTS

2.1 FORM-FACING MATERIALS

A. Smooth-Formed Finished Concrete: Form-facing panels that will provide continuous, true, and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number of joints.

1. Plywood, metal, or other approved panel materials.

CAST-IN-PLACE CONCRETE 033000-2

2. Exterior-grade plywood panels, suitable for concrete forms, complying with DOC PS 1, and as follows:

a. Structural 1, B-B or better; mill oiled and edge sealed.

b. B-B (Concrete Form), Class 1 or better; mill oiled and edge sealed.

B. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved material. Provide lumber dressed on at least two edges and one side for tight fit.

C. Forms for Cylindrical Columns, Pedestals, and Supports: Metal, glass-fiber-reinforced plastic, paper, or fiber tubes that will produce surfaces with gradual or abrupt irregularities not exceeding specified formwork surface class. Provide units with sufficient wall thickness to resist plastic concrete loads without detrimental deformation.

D. Form-Release Agent: Commercially formulated form-release agent that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces.

2.2 STEEL REINFORCEMENT

A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60 , deformed.

B. Plain-Steel Wire: ASTM A 82, as drawn.

C. Deformed-Steel Wire: ASTM A 496.

2.3 REINFORCEMENT ACCESSORIES

A. Joint Dowel Bars: ASTM A 615/A 615M, Grade 60, plain-steel bars, cut bars true to length with ends square and free of burrs.

B. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded wire reinforcement in place. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice," of greater compressive strength than concrete and as follows:

1. For concrete surfaces exposed to view where legs of wire bar supports contact forms, use CRSI Class 1 plastic-protected steel wire or CRSI Class 2 stainless-steel bar supports.

2.4 CONCRETE MATERIALS

A. Cementitious Material: Use the following cementitious materials, of the same type, brand, and source, throughout Project:

1. Portland Cement: ASTM C 150, Type II.

B. Normal-Weight Aggregates: ASTM C 33, graded, from a single source.

1. Maximum Coarse-Aggregate Size: 1 inch (25 mm) nominal.

2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.

CAST-IN-PLACE CONCRETE 033000-3

C. Water: ASTM C 94/C 94M and potable.

D. Fly ash, ground iron blast-furnace slag, or silica fume may partially replace cement in any mix as follows:

1. Fly Ash:

a. Class F – Not more than 20 percent of the minimum mass of portland cement may be replaced with class F fly ash.

b. Class C – Not more than 25 percent of the minimum mass of portland cement may be replaced with class C fly ash.

2. Ground Iron Blast-Furnace Slag: Not more than 25 percent of the minimum mass of portland cement may be replaced with ground iron blast-furnace slag.

3. Silica Fume (microsilica): Not more than 10 percent of the minimum mass of portland cement may be replaced with silica fume.

4. Additionally, fly ash, slag, and silica fume will constitute no more than 50 percent of the total replacement weight.

2.5 ADMIXTURES

A. Air-Entraining Admixture: ASTM C 260.

B. Chemical Admixtures: Provide admixtures certified by manufacturer to be compatible with other admixtures and that will not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.

1. Retarding Admixture: ASTM C 494/C 494M, Type B.

C. Color Pigment: ASTM C 979, synthetic mineral-oxide pigments or colored water-reducing admixtures; color stable, nonfading, and resistant to lime and other alkalis.

1. Color: Pebble 651 by Davis Colors, or approved equal.

2. Color Pigment shall not exceed 6% by weight of the cement.

D. Synthetic Fiber: Monofilament or fibrillated polypropylene fibers engineered and designed for use in concrete pavement, complying with ASTM C 1116, Type III, 1/2 to 1-1/2 inches long.

2.6 VAPOR RETARDERS

A. Plastic Vapor Retarder: ASTM E 1745, Class C, or polyethylene sheet, ASTM D 4397, not less than 10 mils (0.25 mm) thick. Include manufacturer's recommended adhesive or pressure-sensitive joint tape.

B. Fine-Graded Granular Material: Clean mixture of crushed stone, crushed gravel, and manufactured or natural sand; ASTM D 448, Size 10, with 100 percent passing a 3/8-inch (9.5-mm) sieve, 10 to 30 percent passing a No. 100 (0.15-mm) sieve, and at least 5 percent passing No. 200 (0.075-mm) sieve; complying with deleterious substance limits of ASTM C 33 for fine aggregates.

CAST-IN-PLACE CONCRETE 033000-4

2.7 CURING MATERIALS

A. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. when dry.

B. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

C. Water: Potable.

D. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B, dissipating or nondissipating. Liquid Membrane-Forming Compounds. Material shall be certified by curing compound manufacturer to not interfere with bonding of floor covering.

2.8 RELATED MATERIALS

A. Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber or ASTM D 1752, cork or self-expanding cork.

B. Semirigid Joint Filler: Two-component, semirigid, 100 percent solids, epoxy resin with a Type A shore durometer hardness of 80 per ASTM D 2240.

C. Bonding Agent: ASTM C 1059, Type II, non-redispersible, acrylic emulsion or styrene butadiene.

D. Epoxy Bonding Adhesive: ASTM C 881, two-component epoxy resin, capable of humid curing and bonding to damp surfaces, of class suitable for application temperature and of grade to suit requirements, and as follows:

1. Types IV and V, load bearing, for bonding hardened or freshly mixed concrete to hardened concrete.

2.9 REPAIR MATERIALS

A. Repair Underlayment: Cement-based, polymer-modified, self-leveling product that can be applied in thicknesses from 1/8 inch (3.2 mm) and that can be feathered at edges to match adjacent floor elevations.

1. Cement Binder: ASTM C 150, portland cement or hydraulic or blended hydraulic cement as defined in ASTM C 219.

2. Primer: Product of underlayment manufacturer recommended for substrate, conditions, and application.

3. Aggregate: Well-graded, washed gravel, 1/8 to 1/4 inch (3.2 to 6 mm) or coarse sand as recommended by underlayment manufacturer.

4. Compressive Strength: Not less than 4100 psi (29 MPa) at 28 days when tested according to ASTM C 109/C 109M.

B. Repair Overlayment: Cement-based, polymer-modified, self-leveling product that can be applied in thicknesses from 1/8 inch (3.2 mm) and that can be feathered at edges to match adjacent floor elevations.

CAST-IN-PLACE CONCRETE 033000-5

1. Cement Binder: ASTM C 150, portland cement or hydraulic or blended hydraulic cement as defined in ASTM C 219.

2. Primer: Product of topping manufacturer recommended for substrate, conditions, and application.

3. Aggregate: Well-graded, washed gravel, 1/8 to 1/4 inch (3.2 to 6 mm) or coarse sand as recommended by topping manufacturer.

4. Compressive Strength: Not less than 5000 psi (34.5 MPa) at 28 days when tested according to ASTM C 109/C 109M.

2.10 CONCRETE MIXTURES, GENERAL

A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, according to ACI 301.

1. Use a qualified independent testing agency for preparing and reporting proposed mixture designs based on laboratory trial mixtures.

B. Limit water-soluble, chloride-ion content in hardened concrete to 0.06 percent by weight of cement.

C. Admixtures: Use admixtures according to manufacturer's written instructions.

D. Color Pigment: Add color pigment to concrete mixture according to manufacturer's written instructions and to result in hardened concrete color consistent with approved mockup.

2.11 CONCRETE MIXTURES FOR BUILDING ELEMENTS

1. Synthetic Fiber: Uniformly disperse in concrete mixture at manufacturer's recommended rate, but not less than 1.0 lb/cu. yd. (0.60 kg/cu. m).

2.12 FABRICATING REINFORCEMENT

A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."

2.13 CONCRETE MIXING

A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M and ASTM C 1116, and furnish batch ticket information.

1. When air temperature is between 85 and 90 deg F (30 and 32 deg C), reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F (32 deg C), reduce mixing and delivery time to 60 minutes.

B. Project-Site Mixing: Measure, batch, and mix concrete materials and concrete according to ASTM C 94/C 94M. Mix concrete materials in appropriate drum-type batch machine mixer.

CAST-IN-PLACE CONCRETE 033000-6

1. For mixer capacity of 1 cu. yd. (0.76 cu. m) or smaller, continue mixing at least 1- 1/2 minutes, but not more than 5 minutes after ingredients are in mixer, before any part of batch is released.

2. For mixer capacity larger than 1 cu. yd. (0.76 cu. m), increase mixing time by 15 seconds for each additional 1 cu. yd. (0.76 cu. m).

3. Provide batch ticket for each batch discharged and used in the Work, indicating Project identification name and number, date, mixture type, mixture time, quantity, and amount of water added. Record approximate location of final deposit in structure.

PART 3 - EXECUTION

3.1 FORMWORK

A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads.

B. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117.

C. Limit concrete surface irregularities, designated by ACI 347R as abrupt or gradual, as follows:

1. Class A, 1/8 inch (3.2 mm) for smooth-formed finished surfaces.

2. Class B, 1/4 inch (6 mm) for rough-formed finished surfaces.

D. Construct forms tight enough to prevent loss of concrete mortar.

E. Fabricate forms for easy removal without hammering or prying against concrete surfaces.

Provide crush or wrecking plates where stripping may damage cast concrete surfaces.

Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical.

1. Install keyways, reglets, recesses, and the like, for easy removal.

2. Do not use rust-stained steel form-facing material.

F. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and slopes in finished concrete surfaces. Provide and secure units to support screed strips; use strike-off templates or compacting-type screeds.

G. Provide temporary openings for cleanouts and inspection ports where interior area of formwork is inaccessible. Close openings with panels tightly fitted to forms and securely braced to prevent loss of concrete mortar. Locate temporary openings in forms at inconspicuous locations.

H. Chamfer or round exterior corners and edges of permanently exposed concrete.

I. Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and bulkheads required in the Work. Determine sizes and locations from trades providing such items.

CAST-IN-PLACE CONCRETE 033000-7

J. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, and other debris just before placing concrete.

K. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment.

L. Coat contact surfaces of forms with form-release agent, according to manufacturer's written instructions, before placing reinforcement.

3.2 EMBEDDED ITEMS

A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

1. Install anchor rods, accurately located, to elevations required and complying with tolerances in Section 7.5 of AISC's "Code of Standard Practice for Steel Buildings and Bridges."

3.3 REMOVING AND REUSING FORMS

A. General: Formwork for sides of beams, walls, columns, and similar parts of the Work that does not support weight of concrete may be removed after cumulatively curing at not less than 50 deg F (10 deg C) for 48 hours after placing concrete, if concrete is hard enough to not be damaged by form-removal operations and curing and protection operations are maintained.

1. Leave formwork for beam soffits, joists, slabs, and other structural elements that supports weight of concrete in place until concrete has achieved at least 70 percent of its 28-day design compressive strength.

2. Remove forms only if shores have been arranged to permit removal of forms without loosening or disturbing shores.

B. Clean and repair surfaces of forms to be reused in the Work. Split, frayed, delaminated, or otherwise damaged form-facing material will not be acceptable for exposed surfaces.

Apply new form-release agent.

C. When forms are reused, clean surfaces, remove fins and laitance, and tighten to close joints. Align and secure joints to avoid offsets. Do not use patched forms for exposed concrete surfaces unless approved by Contracting Officer.

3.4 VAPOR RETARDERS

A. Plastic Vapor Retarders: Place, protect, and repair vapor retarders according to ASTM E 1643 and manufacturer's written instructions.

1. Lap joints 6 inches (150 mm) and seal with manufacturer's recommended tape.

3.5 STEEL REINFORCEMENT

CAST-IN-PLACE CONCRETE 033000-8

A. General: Comply with CRSI's "Manual of Standard Practice" for placing reinforcement.

1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder before placing concrete.

B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials that would reduce bond to concrete.

C. Accurately position, support, and secure reinforcement against displacement. Locate and support reinforcement with bar supports to maintain minimum concrete cover. Do not tack weld crossing reinforcing bars.

D. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.

3.6 JOINTS

A. General: Construct joints true to line with faces perpendicular to surface plane of concrete.

B. Construction Joints: Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by the Contracting Officer.

1. Place joints perpendicular to main reinforcement. Continue reinforcement across construction joints, unless otherwise indicated. Do not continue reinforcement through sides of strip placements of floors and slabs.

2. Use a bonding agent at locations where fresh concrete is placed against hardened or partially hardened concrete surfaces.

C. Contraction Joints in Slabs-on-Grade: Form weakened-plane contraction joints, sectioning concrete into areas as indicated. Construct contraction joints for a depth equal to at least one-fourth of concrete thickness as follows:

1. Grooved Joints: Form contraction joints after initial floating by grooving and finishing each edge of joint to a radius of 1/8 inch (3.2 mm). Repeat grooving of contraction joints after applying surface finishes. Eliminate groover tool marks on concrete surfaces.

2. Sawed Joints: Form contraction joints with power saws equipped with shatterproof abrasive or diamond-rimmed blades. Cut 1/8-inch- (3.2-mm-) wide joints into concrete when cutting action will not tear, abrade, or otherwise damage surface and before concrete develops random contraction cracks. No Sawed Joints are allowed on concrete exposed to freezing.

D. Expansion Joints in Slabs-on-Grade: After removing formwork, install joint-filler strips at slab junctions with vertical surfaces, such as column pedestals, foundation walls, grade beams, and other locations, as indicated.

1. Extend joint-filler strips full width and depth of joint, terminating flush with finished concrete surface, unless otherwise indicated.

2. Install joint-filler strips in lengths as long as practicable. Where more than one length is required, lace or clip sections together.

CAST-IN-PLACE CONCRETE 033000-9

3.7 CONCRETE PLACEMENT

A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections have been performed.

B. Do not add water to concrete during delivery, at Project site, or during placement unless approved by the Contracting Officer.

C. Before test sampling and placing concrete, water may be added at Project site, subject to limitations of ACI 301.

D. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete will be placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation.

1. Deposit concrete in horizontal layers of depth to not exceed formwork design pressures and in a manner to avoid inclined construction joints.

2. Consolidate placed concrete with mechanical vibrating equipment according to

ACI 301.

3. Do not use vibrators to transport concrete inside forms. Insert and withdraw vibrators vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 inches (150 mm) into preceding layer. Do not insert vibrators into lower layers of concrete that have begun to lose plasticity. At each insertion, limit duration of vibration to time necessary to consolidate concrete and complete embedment of reinforcement and other embedded items without causing mixture constituents to segregate.

E. Deposit and consolidate concrete for floors and slabs in a continuous operation, within limits of construction joints, until placement of a panel or section is complete.

1. Consolidate concrete during placement operations so concrete is thoroughly worked around reinforcement and other embedded items and into corners.

2. Maintain reinforcement in position on chairs during concrete placement.

3. Screed slab surfaces with a straightedge and strike off to correct elevations.

4. Slope surfaces uniformly to drains where required.

5. Begin initial floating using bull floats or darbies to form a uniform and open-textured surface plane, before excess bleedwater appears on the surface. Do not further disturb slab surfaces before starting finishing operations.

F. Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.

1. When average high and low temperature is expected to fall below 40 deg F (4.4 deg C) for three successive days, maintain delivered concrete mixture temperature within the temperature range required by ACI 301.

2. Do not use frozen materials or materials containing ice or snow. Do not place concrete on frozen subgrade or on subgrade containing frozen materials.

CAST-IN-PLACE CONCRETE 033000-10

3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs.

G. Hot-Weather Placement: Comply with ACI 301 and as follows:

1. Maintain concrete temperature below 90 deg F (32 deg C) at time of placement.

Chilled mixing water or chopped ice may be used to control temperature, provided water equivalent of ice is calculated to total amount of mixing water. Using liquid nitrogen to cool concrete is Contractor's option.

2. Fog-spray forms, steel reinforcement, and subgrade just before placing concrete.

Keep subgrade uniformly moist without standing water, soft spots, or dry areas.

3.8 FINISHING FORMED SURFACES

A. As-cast concrete texture imparted by form-facing material, arranged in an orderly and symmetrical manner with a minimum of seams. Repair and patch tie holes and defects.

Remove fins and other projections that exceed specified limits on formed-surface irregularities.

B. Rubbed Finish: Apply the following to smooth-formed finished as-cast concrete where indicated:

1. Grout-Cleaned Finish: Wet concrete surfaces and apply grout of a consistency of thick paint to coat surfaces and fill small holes. Mix one part portland cement to one and one-half parts fine sand with a 1:1 mixture of bonding admixture and water.

Add white portland cement in amounts determined by trial patches so color of dry grout will match adjacent surfaces. Scrub grout into voids and remove excess grout.

When grout whitens, rub surface with clean burlap and keep surface damp by fog spray for at least 36 hours.

C. Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar unformed surfaces adjacent to formed surfaces, strike off smooth and finish with a texture matching adjacent formed surfaces. Continue final surface treatment of formed surfaces uniformly across adjacent unformed surfaces, unless otherwise indicated.

3.9 MISCELLANEOUS CONCRETE ITEMS

A. Filling In: Fill in holes and openings left in concrete structures, unless otherwise indicated, after work of other trades is in place. Mix, place, and cure concrete, as specified, to blend with in-place construction. Provide other miscellaneous concrete filling indicated or required to complete the Work.

B. Curbs: Provide monolithic finish to interior curbs by stripping forms while concrete is still green and by steel-troweling surfaces to a hard, dense finish with corners, intersections, and terminations slightly rounded.

C. Equipment Bases and Foundations: Provide machine and equipment bases and foundations as shown on Drawings. Set anchor bolts for machines and equipment at correct elevations, complying with diagrams or templates from manufacturer furnishing machines and equipment.

CAST-IN-PLACE CONCRETE 033000-11

3.10 CONCRETE PROTECTING AND CURING

A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and ACI 301 for hot-weather protection during curing.

B. Evaporation Retarder: Apply evaporation retarder to unformed concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h (1 kg/sq. m x

h) before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.

C. Formed Surfaces: Cure formed concrete surfaces, including underside of beams, supported slabs, and other similar surfaces. If forms remain during curing period, moist cure after loosening forms. If removing forms before end of curing period, continue curing for the remainder of the curing period.

D. Unformed Surfaces: Begin curing immediately after finishing concrete. Cure unformed surfaces, including floors and slabs, concrete floor toppings, and other surfaces.

E. Cure concrete according to ACI 308.1, by one or a combination of the following methods:

1. Moisture Curing: Keep surfaces continuously moist for not less than seven days with the following materials:

a. Water.

b. Continuous water-fog spray.

c. Absorptive cover, water saturated, and kept continuously wet. Cover concrete surfaces and edges with 12-inch (300-mm) lap over adjacent absorptive covers.

2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches (300 mm), and sealed by waterproof tape or adhesive. Cure for not less than seven days. Immediately repair any holes or tears during curing period using cover material and waterproof tape.

a. Moisture cure or use moisture-retaining covers to cure concrete surfaces to receive floor coverings.

b. Moisture cure or use moisture-retaining covers to cure concrete surfaces to receive penetrating liquid floor treatments.

c. Cure concrete surfaces to receive floor coverings with either a moisture-retaining cover or a curing compound that the manufacturer certifies will not interfere with bonding of floor covering used on Project..

3. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating and repair damage during curing period.

CAST-IN-PLACE CONCRETE 033000-12

a. After curing period has elapsed, remove curing compound without damaging concrete surfaces by method recommended by curing compound manufacturer unless manufacturer certifies curing compound will not interfere with bonding of floor covering used on Project.

3.11 CONCRETE SURFACE REPAIRS

A. Defective Concrete: Repair and patch defective areas when approved by Contracting Officer. Remove and replace concrete that cannot be repaired and patched to Contracting Officer's approval.

B. Patching Mortar: Mix dry-pack patching mortar, consisting of one part portland cement to two and one-half parts fine aggregate passing a No. 16 (1.18-mm) sieve, using only enough water for handling and placing.

C. Repairing Formed Surfaces: Surface defects include color and texture irregularities, cracks, spalls, air bubbles, honeycombs, rock pockets, fins and other projections on the surface, and stains and other discolorations that cannot be removed by cleaning.

1. Immediately after form removal, cut out honeycombs, rock pockets, and voids more than 1/2 inch (13 mm) in any dimension in solid concrete, but not less than 1 inch (25 mm) in depth. Make edges of cuts perpendicular to concrete surface. Clean, dampen with water, and brush-coat holes and voids with bonding agent. Fill and compact with patching mortar before bonding agent has dried. Fill form-tie voids with patching mortar or cone plugs secured in place with bonding agent.

2. Repair defects on surfaces exposed to view by blending white portland cement and standard portland cement so that, when dry, patching mortar will match surrounding color. Patch a test area at inconspicuous locations to verify mixture and color match before proceeding with patching. Compact mortar in place and strike off slightly higher than surrounding surface.

3. Repair defects on concealed formed surfaces that affect concrete's durability and structural performance as determined by Contracting Officer.

D. Repairing Unformed Surfaces: Test unformed surfaces, such as floors and slabs, for finish and verify surface tolerances specified for each surface. Correct low and high areas. Test surfaces sloped to drain for trueness of slope and smoothness; use a sloped template.

1. Repair finished surfaces containing defects. Surface defects include spalls, popouts, honeycombs, rock pockets, crazing and cracks in excess of 0.01 inch (0.25

mm) wide or that penetrate to reinforcement or completely through unreinforced sections regardless of width, and other objectionable conditions.

2. After concrete has cured at least 14 days, correct high areas by grinding.

3. Correct localized low areas during or immediately after completing surface finishing operations by cutting out low areas and replacing with patching mortar.

Finish repaired areas to blend into adjacent concrete.

4. Correct other low areas scheduled to receive floor coverings with a repair underlayment. Prepare, mix, and apply repair underlayment and primer according

CAST-IN-PLACE CONCRETE 033000-13

to manufacturer's written instructions to produce a smooth, uniform, plane, and level surface. Feather edges to match adjacent floor elevations.

5. Correct other low areas scheduled to remain exposed with a repair topping. Cut out low areas to ensure a minimum repair topping depth of 1/4 inch (6 mm) to match adjacent floor elevations. Prepare, mix, and apply repair topping and primer according to manufacturer's written instructions to produce a smooth, uniform, plane, and level surface.

6. Repair defective areas, except random cracks and single holes 1 inch (25 mm) or less in diameter, by cutting out and replacing with fresh concrete. Remove defective areas with clean, square cuts and expose steel reinforcement with at least a 3/4-inch (19-mm) clearance all around. Dampen concrete surfaces in contact with patching concrete and apply bonding agent. Mix patching concrete of same materials and mixture as original concrete except without coarse aggregate. Place, compact, and finish to blend with adjacent finished concrete. Cure in same manner as adjacent concrete.

7. Repair random cracks and single holes 1 inch (25 mm) or less in diameter with patching mortar. Groove top of cracks and cut out holes to sound concrete and clean off dust, dirt, and loose particles. Dampen cleaned concrete surfaces and apply bonding agent. Place patching mortar before bonding agent has dried.

Compact patching mortar and finish to match adjacent concrete. Keep patched area continuously moist for at least 72 hours.

E. Perform structural repairs of concrete, subject to Contracting Officer's approval, using epoxy adhesive and patching mortar.

F. Repair materials and installation not specified above may be used, subject to Contracting Officer's approval.

3.12 FIELD QUALITY CONTROL

A. Testing and Inspecting: Contractor will engage a qualified independent testing and inspecting agency to perform field tests and inspections and prepare test reports.

B. Concrete Tests: Testing of composite samples of fresh concrete obtained according to ASTM C 172 shall be performed according to the following requirements:

1. Testing Frequency: See Table 3.6 in Section 014100. A composite sample set consists of one slump test, one air entrainment test, and one temperature test.

2. Slump: ASTM C 143/C 143M; one test at point of placement for each composite sample. Perform additional tests when concrete consistency appears to change or water is added.

3. Air Content: ASTM C 231, pressure method, for normal-weight concrete; one test for each composite sample.

4. Concrete Temperature: ASTM C 1064/C 1064M; one test for each composite sample.

5. Compression Test Specimens: ASTM C 31/C 31M. Cast and laboratory cure one set of three standard cylinder specimens for each composite sample.

CAST-IN-PLACE CONCRETE 033000-14

a. Compressive-Strength Tests: ASTM C 39/C 39M; test one of three laboratory-cured specimens at 7 days and one specimen at 28 days. If either previous tests fail, test third specimen at 28 days.

b. Strength of each batch delivered will be satisfactory if 28-day compressive-strength tests equals or exceeds specified compressive strength.

C. Test results shall be reported in writing to Contracting Officer and Contractor within 48 hours of testing. Reports shall contain project identification name and number, date of concrete placement, name of concrete testing and inspecting agency, location of concrete batch in work, design compressive strength at 28 days, concrete mixture proportions and materials, compressive breaking strength, and type of break for both 7- and 28-day tests.

D. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.

E. Correct deficiencies in the work that test reports and inspections indicate does not comply with the Contract Documents.

END OF SECTION 033000

EARTHWORK 312000-1

GAOA Sawtooth NRA Sunbeam Dam Stair Replacement

SECTION 312000 - EARTHWORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Preparing subgrades for slabs-on-grade

2. Excavating and backfilling for piers

1.2 DEFINITIONS

A. Backfill: Soil materials used to fill an excavation.

B. Borrow or Select Borrow: Satisfactory soil material used for embankment, backfill, or fill construction that is either imported from off-site or excavated from designated locations at the site.

C. Excavation: Removal of material encountered above subgrade elevations and to lines and dimensions indicated.

1. Additional Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions as directed by Contracting Officer. Additional excavation and replacement material will be paid for according to Contract provisions for changes in the Work.

2. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions without direction of the Contracting Officer.

Unauthorized excavation, as well as remedial work directed by Contracting Officer, shall be without additional compensation.

3. Unclassified Excavation: Excavation to subgrade elevation and to lines and dimensions indicated regardless of the character of surface and subsurface conditions encountered, including rock, soil materials, and obstructions.

D. Fill: Soil materials used to raise existing grades.

E. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below the ground surface.

F. Subgrade: Surface or elevation remaining after completing excavation, or top surface of a fill or backfill immediately below subbase, aggregate base, drainage fill, initial or subsequent backfill, or topsoil materials.

G. Utilities include on-site underground pipes, conduits, ducts, and cables, as well as underground services within building.

EARTHWORK 312000-2

1.3 SUBMITTALS

A. Contractor shall submit to the Contracting Officer for approval source of aggregates and backfill materials and certified sieve analysis. Materials from Government Sources are exempt from this requirement.

1.4 MEASUREMENT AND PAYMENT

A. There will be no separate measurement or payment for work in this Section. Payment will be included in the contract unit price as shown on the Schedule of Items.

PART 2 - PRODUCTS

2.1 BACKFILL MATERIALS, GENERAL

A. Excavated material may be processed and used for backfill if the Contractor can show compliance with the material specified herein to the satisfaction of the Contracting Officer. If excavated material is not sufficient to meet requirements, Contractor shall import needed material.

B. Satisfactory Soils: ASTM D 2487 soil classification groups GW, GP, GM, SW, SP, and SM, or a combination of these group symbols; free of rock or gravel larger than 3 inches (75 mm) in any dimension, debris, waste frozen materials, vegetation, and other deleterious matter.

C. Unsatisfactory Soils: ASTM D 2487 soil classification groups GC, SC, ML, MH, CL, CH, OL, OH, and PT, or a combination of these group symbols.

1. Unsatisfactory soils also include satisfactory soils not maintained within 2 percent of optimum moisture content at time of compaction.

D. Backfill and Fill: Satisfactory soil materials.

1. Remove rocks over 8 inches in maximum dimension, ice or frozen earth, muck, debris, and earth with high void content.

2. Remove rocks over 4 inches in maximum dimension for backfill placed within 12 inches of foundation.

2.2 ENGINEERED FILL

A. Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; with at least 90 percent passing a 1 1/2 inch sieve and not more than 12 percent passing a No. 200 sieve.

PART 3 - EXECUTION

3.1 LOCATION, ALIGNMENT AND GRADE

A. The location of all structures shall be staked out and grades established by the Contractor.

Locations shall be approved by the Contracting Officer before excavation is started.

EARTHWORK 312000-3

3.2 PREPARATION

A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout and other hazards created by earthwork operations.

B. Provide erosion-control measures to prevent erosion or displacement of soils and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways.

3.3 DEWATERING

A. Prevent surface water and ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area.

B. Protect subgrades from softening, undermining, washout, and damage by rain or water accumulation.

1. Reroute surface water runoff away from excavated areas. Do not allow water to accumulate in excavations. Do not use excavated trenches as temporary drainage ditches.

2. Install a dewatering system to keep subgrades dry and convey ground water away from excavations. Maintain until dewatering is no longer required.

3.4 EXPLOSIVES

A. Do not use explosives.

B. Explosives: Obtain written permission from authorities having jurisdiction before bringing explosives to Project site or using explosives on Project site.

1. Do not damage adjacent structures, property, or site improvements or weaken the bearing capacity of rock subgrade when using explosives.

3.5 EXCAVATION SUPPORT AND PROTECTION

A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards that could develop during excavation.

B. Design, furnish, install, monitor, and maintain excavation support and protection system capable of supporting excavation sidewalls and resisting soil and hydrostatic pressures and superimposed and construction loads.

C. The contractor shall meet State General…

This is the start of the file's text. The full file is on GovTribe.