J.2 Statement of Work (35 Pages).pdf

PDF 744 KB Posted

Attached to
PINEDALE ROOF REPLACEMENT Federal contract opportunity
Solicitation number
1240LT24Q0063
Issued by
Department of Agriculture Forest Service

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to replace the roofs on several government-owned dwellings in Pinedale, Wyoming and Big Piney, Wyoming.

The Base Bid includes removal and disposal of existing metal roofing, underlayment, roof accessories, soffits, fascia, trim and flashing, and installation of new self-adhering sheet underlayment, flashing, soffits, and standing seam metal roofing on the Pinedale dwellings. Optional Bid Items include repair of existing roof sheathing and replacement of existing asphalt shingle roofing with the same new roofing materials on two additional sites in Big Piney. The contract period of performance is from date of award through October 31, 2024. The Base Bid has a 45 calendar day period of performance, while the Option Bids have a 30 calendar day period of performance. The contract has specific measurement and payment terms, including unit price and lump sum payment methods. The work must be performed while the buildings remain occupied, with contractor responsibility for site access, safety, waste management, and other project logistics.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1

Replace Section C - Description/Specifications/Statement of Work

GENERAL SPECIFICATIONS

BRIDGER-TETON NATIONAL FOREST – PINEDALE RANGER DISTRICT

PINEDALE DWELLING ROOF REPLACEMENT PROJECT

05/01/2024

1.1 SCOPE OF CONTRACT

A. The Base Bid for this project includes all labor, materials and equipment to perform selective demolition and to provide and install sheet metal roofing for the Pinedale dwellings (or housing units). The facilities are owned by the United States Forest Service, Bridger-Teton National Forest.

1. Base Bid Item: Work includes but is not limited to: removal and disposal of the existing metal roofing, underlayment, roof accessories, soffits, fascia, trim and flashing. Provide and install full roof self-adhering sheet underlayment, flashing, soffits and standing seam metal roofing.

2. Optional Bid Items:

a. Repair existing roof sheathing at the dwellings in listed in the Base Bid Item.

Assumed to be 10% of total square footage but will be determined after initial demolition of existing metal roof.

b. Work includes but is not limited to: removal and disposal of the existing asphalt shingle roofing, underlayment, roof accessories, soffits, fascia, trim and flashing. Provide and install full roof self-adhering sheet underlayment, flashing, soffits and standing seam metal roofing at Sites 2A and 2B in Big Piney, WY.

1.2 PROJECT LOCATIONS

A. The Based Bid Item work will be conducted at the Pinedale dwellings located at the following locations:

1. 243 W Pine Street, Pinedale, WY 82941

2. 331 N Franklin Avenue, Pinedale, WY 82941

3. 332 N Franklin Avenue, Pinedale, WY 82941

B. The Option Bid Item work will be conducted at the Big Piney Bunkhouses located at the following locations:

1. Site #2A referenced in the Optional Bid Items is located at 10418 US-189, Big Piney, WY 83113, East of the Big Piney Ranger District Station and West of Site #2B.

2. Site #2B referenced in the Optional Bid Items is located at 10418 US-189, Big Piney, WY 83113, East of the Big Piney Ranger District Office. See Figure 3 - Vicinity Maps.

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2

Figure 1. VICINITY MAPS – 243 W Pine Street

Figure 2. VICINITY MAPS – 331 & 332 N Franklin Avenue

331 N Franklin Avenue 332 N Franklin Avenue

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3

Figure 3. VICINITY MAPS – Optional Bid Item Sites 2A & 2B

Site 2A

Site 2B

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-4

1.3 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. The site will be occupied during construction. The Contractor will be responsible for signing and limiting access to materials and construction areas for the public.

2. Use of Site: Verify locations for materials storage and construction with COR. Do not disturb portions of site beyond areas in which the COR specifies.

3. There is electrical service available for use at the site.

4. Water is available but limited at the site for construction purposes.

5. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.

6. Construction Hours – Hours of operation for the construction, demolition, excavation and subsequent cleanup shall be only between the hours between 7:00 a.m. and 7:00 p.m. Monday through Friday.

1.4 TEMPORARY ACCESS

A. Parking: Use designated areas for construction personnel or as approved by the

Contracting Officer. All other parking is prohibited.

1.5 WASTE MANAGEMENT AND DISPOSAL

A. Waste Management Plan: Submit a pdf copy of the plan within 14 days of date established for the Notice to Proceed.

B. The Contractor shall provide and maintain appropriate waste disposal containers or bins at the project site for the duration of the project construction. Verify with Contracting Officer’s Representative for placement of disposal containers and bins on the project site.

C. Waste material and debris shall be picked up and deposited in the waste disposal bins on a daily basis. Containers must be emptied on a weekly basis unless more frequent emptying is needed. Construction materials and debris shall not be allowed to become airborne or migrate into adjacent properties.

D. Burning or burying of construction waste material on site will not be permitted. Material shall be disposed of in accordance with the Waste Material Disposal specification.

1.6 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work) on site.

B. No overnight camping will be allowed on site.

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-5

1.7 NSPECTION OF WORKSITE

A. The contractor shall acknowledge they have taken the necessary steps to determine the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.8 PERIOD OF PERFORMANCE

A. Base Bid: 45 Calendar Days B. Option Bid: 30 Calendar Days

1.9 CONTRACT TIME

A. Date of award through October 31, 2024

1.10 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made:

Section 011250 - Measurement And Payment Section 011900 - Mobilization Section 013300 - Submittal Procedures Section 017320 - Selective Demolition Section 061600 - Sheathing Section 070150.19 - Preparation For Reroofing Section 074113.16 - Standing-Seam Metal Roof Panels Section 076200 - Sheet Metal Flashing And Trim

END OF SECTION C

MAY 2024

MEASUREMENT AND PAYMENT 011250-1

USDA FOREST SERVICE, R4

PINEDALE ROOF REPLACEMENT

SECTION 011250 - MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 SUMMARY

A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.

B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.

1.2 DETERMINATION OF QUANTITIES

A. The following measurements and calculations shall be used to determine contract quantities for payment.

1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.

2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.

3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.

4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.

5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.

6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.

B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."

MEASUREMENT AND PAYMENT 011250-2

1.3 UNITS OF MEASUREMENT

A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

1. Acre: Make longitudinal and transverse measurements for area computations horizontally.

2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.

3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.

4. Cubic Yard (CY): A measurement computed by one of the following methods:

a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.

Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

5. Each (EA): One complete unit, which may consist of one or more parts.

6. Gallons (GAL): The quantity shall be measured by any of the following methods:

a. Measured volume in container.

b. Metered volume by approved metering system.

c. Commercially package volume.

7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.

8. Linear Foot (LF): Measurement of work along its length from point-to-point;

parallel to the base or foundation. Do not measure overlaps.

9. Lump Sum (LS): One complete unit.

10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.

11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.

12. Square Foot (SF): Measured on a plane parallel to the surface being measured.

13. Square Yard (SY): Measured on a plane parallel to the surface being measured.

14. Ton: Measured as a short ton consisting of 2,000 pounds.

MEASUREMENT AND PAYMENT 011250-3

1.4 METHOD OF MEASUREMENT

A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.

2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:

a. As a result of changes in the work authorized by the CO.

b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.

4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.

5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 011250

MOBILIZATION 011900-1

PINEDALE ROOF REPLACEMENT

SECTION 011900 - MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

1.2 MEASUREMENT AND PAYMENT

A. The measurement shall be lump sum for mobilization. Payment shall be as follows:

1. Bond premiums will be reimbursed after receipt of the evidence of payment.

2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

5. Progress payments for mobilization and preparatory work shall be subject to retainage.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 011900

SUBMITTAL PROCEDURES 013300-1

PINEDALE ROOF REPLACEMENT

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.

B. See other specification section within this package for additional requirements on submittal.

1.2 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 14 days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

C. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

a. Project name.

b. Date.

SUBMITTAL PROCEDURES 013300-2

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. If more than one item is shown on submittal sheet, identify item.

D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

1.3 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit pdf copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

SUBMITTAL PROCEDURES 013300-3

C. Shop Drawings – Not Applicable

D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.

E. Samples: Prepare physical units of materials or products, including the following:

1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

2.2 INFORMATIONAL SUBMITTALS – NOT APPLICABLE

PART 3 - EXECUTION

3.1 GENERAL

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.

F. Requests for substitutions will only be considered if contractor submits the following:

1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.

Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.

2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.

SUBMITTAL PROCEDURES 013300-4

3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.

4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.

3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required submittals for the project - the table is to assist the Contractor and may not be all inclusive

– additional submittals may be required by specific specifications:

TABLE 013000-1

Spec.

Section Section Title Subsection Required Submittal

013300 Submittal Procedures 2.1D Construction Schedule

070150.19 Preparation for Reroofing 1.4A Photos or video

074113 Standing Seam Metal Roofing 1.3A Product Data 074113 Standing Seam Metal Roofing 1.3C Samples 074113 Standing Seam Metal Roofing 1.4B Warranty 076200 Sheet Metal Flashing and Trim 1.3A Product Data

END OF SECTION 013300

SELECTIVE DEMOLITION 017320-1

PINEDALE ROOF REPLACEMENT

SECTION 017320 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes demolition and removal of the following:

1. Selected portions of a building.

2. Repair procedures for selective demolition operations.

1.2 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.

B. Remove and Salvage: NOT APPLICABLE

C. Remove and Reinstall: NOT APPLICABLE

D. Existing to Remain: NOT APPLICABLE

1.3 MATERIALS OWNERSHIP

A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Government property, demolished materials shall become Contractor's property and shall be removed from Project site.

1.4 SUBMITTALS – NOT APPLICABLE

1.5 QUALITY ASSURANCE – NOT APPLICABLE

1.6 PROJECT CONDITIONS

A. Conduct selective demolition so Government operations will not be disrupted. Provide not less than 72 hours' notice to CO of activities that will affect Government operations.

B. Maintain access to existing building amenities, pathways, and other adjacent occupied or used facilities.

1. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the COR.

C. Government assumes no responsibility for condition of areas to be selectively demolished.

1. Conditions existing at time of inspection for bidding purpose will be maintained by Government as far as practical.

SELECTIVE DEMOLITION 017320-2

D. Hazardous Materials: Hazardous materials were found to be present in building to be selectively demolished. Follow procedures in Section 024230, Work Involving Asbestos.

1. Dispose of any fluorescent light tubes appropriately.

2. Do not disturb hazardous materials or items suspected of containing hazardous materials except under procedures specified elsewhere in the Contract Documents.

E. Storage or sale of removed items or materials on-site will not be permitted.

1.7 MEASUREMENT AND PAYMENT

A. There will be no separate measurement or payment for work in this section. Payment will be included at the contract unit price for items shown on the Schedule of Items.

PART 2 - PRODUCTS

2.1 REPAIR MATERIALS

A. Use repair materials identical to existing materials.

1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.

2. Use materials whose installed performance equal or surpasses that of existing materials.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped.

B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to CO.

3.2 PREPARATION

A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

1. Do not close or obstruct roads, without permission from CO. Provide alternate routes around closed or obstructed traffic ways if required by governing regulations.

2. Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction.

SELECTIVE DEMOLITION 017320-3

3. Protect existing site improvements, appurtenances, and landscaping to remain.

B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

C. Temporary Enclosures: Provide temporary enclosures for protection of existing building and construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.

3.3 POLLUTION CONTROLS – NOT APPLICABLE

3.4 SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.

1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

4. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

B. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse. Paint equipment to match new equipment.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by CO, items may be removed to a suitable, protected storage location during selective demolition [and cleaned] and reinstalled in their original locations after selective demolition operations are complete.

3.5 PATCHING AND REPAIRS

A. General: Promptly repair damage to adjacent construction caused by selective demolition operations.

SELECTIVE DEMOLITION 017320-4

B. Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.

1. Completely fill holes and depressions in existing masonry walls that are to remain with an approved masonry patching material applied according to manufacturer's written recommendations.

C. Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.

D. Floors and Walls: Where walls or partitions that are demolished extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish color, texture, and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.

E. Ceilings: Patch and repair existing ceilings as necessary to provide an even-plane surface of uniform appearance.

3.6 DISPOSAL OF DEMOLISHED MATERIALS

A. General: Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.

B. Burning: Do not burn demolished materials.

C. Disposal: Transport demolished materials off Government property and legally dispose of them.

END OF SECTION 017320

SHEATHING 061600--10

PINEDALE ROOF REPLACEMENT

SECTION 061600 - SHEATHING

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Roof sheathing.

1.2 SUBMITTALS

A. Product Data: For each type of process and factory-fabricated product. Indicate component materials and dimensions and include construction and application details.

1.3 DELIVERY, STORAGE, AND HANDLING

A. Stack plywood and other panels flat with spacers between each bundle to provide air circulation. Provide for air circulation around stacks and under coverings.

1.4 MEASUREMENT AND PAYMENT

A. There will be no separate measurement or payment for work in this section. Payment will be included in the contract unit price for items shown in the schedule of items.

PART 2 - PRODUCTS

2.1 WOOD PANEL PRODUCTS, GENERAL

A. Plywood: Either DOC PS 1 or DOC PS 2, unless otherwise indicated.

B. Oriented Strand Board: DOC PS 2.

C. Thickness: As needed to comply with requirements specified, but not less than thickness indicated in drawings.

D. Factory mark panels to indicate compliance with applicable standard.

2.2 ROOF SHEATHING

A. Plywood Roof Sheathing: APA Rated Sheathing, Exposure 1, Exterior sheathing.

1. Span Rating: Not less than 24/0.

2. Nominal Thickness: 5/8”

B. Oriented-Strand-Board Roof Sheathing: Exposure 1, Structural I sheathing.

1. Span Rating: Not less than 24/16.

SHEATHING 061600--9

2. Nominal Thickness: 5/8”

2.3 FASTENERS

A. General: Provide fasteners of size and type indicated that comply with requirements specified in this Article for material and manufacture.

B. Power-Driven Fasteners: NES NER-272.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Do not use materials with defects that impair quality of sheathing or pieces that are too small to use with minimum number of joints or optimum joint arrangement.

B. Cut panels at penetrations, edges, and other obstructions of work; fit tightly against abutting construction, unless otherwise indicated.

C. Securely attach to substrate by fastening as indicated, complying with the following:

1. NES NER-272 for power-driven fasteners.

2. Table 2304.9.1, "Fastening Schedule," in ICC's "International Building Code."

D. Coordinate roof sheathing installation with flashing and joint-sealant installation so these materials are installed in sequence and manner that prevent exterior moisture from passing through completed assembly.

E. Do not bridge building expansion joints; cut and space edges of panels to match spacing of structural support elements.

F. Coordinate sheathing installation with installation of materials installed over sheathing so sheathing is not exposed to precipitation or left exposed at end of the workday when rain is forecast.

3.2 WOOD STRUCTURAL PANEL INSTALLATION

A. General: Comply with applicable recommendations in APA Form No. E30S, "Engineered Wood Construction Guide," for types of structural-use panels and applications indicated.

B. Fastening Methods: Fasten panels as indicated below:

1. Roof Sheathing:

a. Nail to wood framing as indicated on Drawings.

b. Space panels 1/8 inch apart at edges and ends.

END OF SECTION 061600

PREPARATION FOR REROOFING 070150.19--14

PINEDALE ROOF REPLACEMENT

SECTION 070150.19 - PREPARATION FOR REROOFING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Full tear-off of entire roof system of dwellings.

1.2 ADDITIONAL BID ITEMS

A. Removal of any existing deteriorated sheathing.

1.3 PREINSTALLATION MEETINGS

A. Preliminary Roofing Conference: Before starting removal Work, conduct conference at Project site.

1.4 INFORMATIONAL SUBMITTALS

A. Photographs or Videotape: Show existing conditions of adjoining construction and site improvements, including exterior and interior finish surfaces, that might be misconstrued as having been damaged by reroofing operations.

1. Submit before Work begins.

1.5 FIELD CONDITIONS

A. Existing Roofing System:

1. Base Bid: Metal Roofs and Underlayment

2. Option Bid: Asphalt Shingle Roofs and Underlayment

B. Forest Service/Government will occupy portions of building immediately below reroofing area.

1. Conduct reroofing so Government's operations are not disrupted.

2. Provide Contracting Officers Representative with not less than 72 hours' written notice of activities that may affect Government's operations.

3. Coordinate work activities daily with Government so they have adequate advance notice to place protective dust and water-leakage covers over sensitive equipment and furnishings, shut down HVAC and fire-alarm or -detection equipment if needed, and evacuate occupants from below work area.

4. Before working over structurally impaired areas of deck, notify Government to evacuate occupants from below affected area.

PREPARATION FOR REROOFING 070150.19--13

a. Verify that occupants below work area have been evacuated before proceeding with work over impaired deck area.

C. Protect building to be reroofed, adjacent buildings, walkways, site improvements, exterior plantings, and landscaping from damage or soiling from reroofing operations.

D. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.

E. Conditions existing at time of inspection for bidding will be maintained by Government as far as practical.

F. Limit construction loads on existing roof areas to remain, and existing roof areas scheduled to be reroofed to 50 PSF for rooftop materials and equipment.

G. Weather Limitations: Proceed with reroofing preparation only when existing and forecasted weather conditions permit Work to proceed without water entering existing roofing system or building.

1. Remove only as much roofing in one day as can be made watertight in the same day. Watertight may include temporary measures.

1.6 MEASUREMENT AND PAYMENT

A. There will be no separate measurement or payment for work in this Section. Payment will be included in the contract unit price as shown on the Schedule of Items.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 PREPARATION

A. Seal or isolate windows that may be exposed to airborne substances created in removal of existing materials.

B. Shut off rooftop utilities and service piping before beginning the Work.

C. Coordinate with Government to shut down air-intake equipment in the vicinity of the Work.

1. Cover air-intake louvers before proceeding with reroofing work that could affect indoor air quality or activate smoke detectors in the ductwork.

D. During removal operations, have sufficient and suitable materials on-site to facilitate rapid installation of temporary protection in the event of unexpected rain.

3.2 ROOF TEAR-OFF

A. Notify COR each day of extent of roof tear-off proposed for that day and obtain authorization to proceed.

PREPARATION FOR REROOFING 070150.19--12

B. Lower removed roofing materials to ground and onto lower roof levels, using dust-tight chutes or other acceptable means of removing materials from roof areas.

C. Full Roof Tear-off: Where indicated on Drawings, remove existing roofing and other roofing system components down to the existing roof sheathing.

1. Remove base flashings and counter flashings.

2. Remove perimeter edge flashing.

3. Remove expansion-joint covers, where applicable.

4. Remove soffit and fascia, where applicable.

5. Remove flashings at pipes , and other penetrations.

3.3 DECK PREPARATION – NOT APPLICABLE

END OF SECTION 070150.19

STANDING-SEAM METAL ROOF PANELS 074113.16 -1

PINEDALE ROOF REPLACEMENT

SECTION 074113.16 - STANDING-SEAM METAL ROOF PANELS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Standing-seam metal roof panels.

1.2 ADDITIONAL BID ITEMS

A. Removal of any existing deteriorated sheathing, and replacement with new wood.

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings: Include fabrication and installation layouts of metal panels; details of edge conditions, joints, panel profiles, corners, anchorages, attachment system, trim, flashings, closures, and accessories; and special details.

C. Samples: For each type of metal panel indicated.

1.5 INFORMATIONAL SUBMITTALS

A. Product test reports.

B. Warranties: Sample of special warranties.

1.6 CLOSEOUT SUBMITTALS

A. Maintenance data.

1.7 QUALITY ASSURANCE

A. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by manufacturer.

1.8 WARRANTY

STANDING-SEAM METAL ROOF PANELS 074113.16 -2

A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of metal panel systems that fail in materials or workmanship within specified warranty period.

1. Warranty Period: One years from date of Substantial Completion.

B. Special Warranty on Panel Finishes: Manufacturer's standard form in which manufacturer agrees to repair finish or replace metal panels that show evidence of deterioration of factory-applied finishes within specified warranty period.

1. Finish Warranty Period: 15 years minimum from date of Substantial Completion.

a. Color fading in excess of 10 Hunter units per ASTM D 2244.

b. Chalking in excess of No. 6 rating per ASTM D 4214.

c. Failure of adhesion, peeling, checking, or cracking

1.9 BUY AMERICAN COMPLIANCE:

A. Materials provided under work of this Section shall comply with the following requirements:

1. Buy American Act of 1933 BAA-41 U.S.C §§ 10a – 10d.

1.10 MEASUREMENT AND PAYMENT

A. There will be no separate measurement or payment for work in this section. Payment will be included in the contract unit price for items shown in the schedule of items.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Structural Performance: Provide metal panel systems capable of withstanding the effects of the following loads, based on testing according to ASTM E1592:

1. Wind Loads: 3 second gust of 110 mph.

B. Wind-Uplift Resistance: Provide metal roof panel assemblies that comply with UL 580 for wind-uplift-resistance class indicated.

1. Uplift Rating: UL 90.

C. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes by preventing buckling, opening of joints, overstressing of components, failure of joint sealants, failure of connections, and other detrimental effects.

Base calculations on surface temperatures of materials due to both solar heat gain and nighttime-sky heat loss.

1. Temperature Change (Range): 120 deg F, ambient; 180 deg F

2.2 STANDING-SEAM METAL ROOF PANELS

STANDING-SEAM METAL ROOF PANELS 074113.16 -3

A. Provide factory-formed metal roof panels designed to be installed by lapping and interconnecting raised side edges of adjacent panels with joint type indicated and mechanically attaching panels to supports using concealed clips in side laps. Include clips, cleats, pressure plates, and accessories required for weathertight installation.

1. Steel Panel Systems: Unless more stringent requirements are indicated, comply with ASTM E1514.

B. Vertical-Rib, Snap-Joint, Standing-Seam Metal Roof Panels: Formed with vertical ribs at panel edges and intermediate stiffening ribs symmetrically spaced between ribs; designed for sequential installation by mechanically attaching panels to supports using concealed clips located under one side of panels, engaging opposite edge of adjacent panels, and snapping panels together.

1. Basis of Design Manufacturer: MBCI Metal Roof and Wall Systems, Lockseam.; Houston TX. Tel: (877) 713-6224; Email: info@mbci.com; Web:

www.mbci.com

2. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. ATAS International, Inc.

b. Drexel Metals.

c. Fabral; a brand of OmniMax International.

d. Garland Company, Inc. (The).

e. MBCI; Cornerstone Building Brands.

f. McElroy Metal, Inc.

g. Or approved equal

3. Metallic-Coated Steel Sheet: Zinc-coated (galvanized) steel sheet complying with ASTM A653/A653M, G90 coating designation, or aluminum-zinc alloy-coated steel sheet complying with ASTM A792/A792M, Class AZ50 coating designation;

structural quality. Prepainted by the coil-coating process to comply with

ASTM A755/A755M.

a. Nominal Thickness: 0.028 inch. 24 Gage

b. Exterior Finish: Two-coat fluoropolymer.

c. Color: As selected by COR from manufacturer's full range.

4. Clips: One-piece fixed or two-piece floating to accommodate thermal movement.

5. Material:

a. 0.028-inch- nominal thickness, zinc-coated (galvanized) or aluminum-zinc alloy-coated steel sheet.

6. Panel Coverage: 16 inches.

7. Panel Height: 1.25 inches - 1.75 inches.

mailto:info@ecoficientseries.com http://www.mbci.com/ http://www.specagent.com/Lookup?ulid=6905 http://www.specagent.com/Lookup?uid=123457235368 http://www.specagent.com/Lookup?uid=123457235354 http://www.specagent.com/Lookup?uid=123457235348 http://www.specagent.com/Lookup?uid=123457235349 http://www.specagent.com/Lookup?uid=123457235352

STANDING-SEAM METAL ROOF PANELS 074113.16 -4

2.3 UNDERLAYMENT MATERIALS

A. Synthetic Underlayment: UV-resistant polypropylene, polyolefin, or polyethylene polymer fabric with surface coatings or treatments to improve traction underfoot and abrasion resistance; evaluated and documented to be suitable for use as a roof underlayment under applicable codes by a testing and inspecting agency acceptable to authorities having jurisdiction.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

a. Carlisle Residential; a division of Carlisle Construction Materials.

b. Grace Construction Products; W.R. Grace & Co. -- Conn.

c. Owens Corning.

d. Or approved equal

B. Self-Adhering, High-Temperature Sheet Underlayment: Provide self-adhering, cold-applied, sheet underlayment, a minimum of 30 mils thick, consisting of slip-resistant, polyethylene-film top surface laminated to a layer of butyl or SBS-modified asphalt adhesive, with release-paper backing. Provide primer when recommended by underlayment manufacturer.

1. Thermal Stability: Stable after testing at 240 deg F; ASTM D1970.

2. Low-Temperature Flexibility: Passes after testing at minus 20 deg F;

ASTM D1970.

3. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. ATAS International, Inc.

b. Carlisle WIP Products; a brand of Carlisle Construction Materials.

c. GCP Applied Technologies Inc.

d. Henry Company.

e. Owens Corning.

f. Polyglass U.S.A., Inc.

g. Protecto Wrap Company.

h. SDP Advanced Polymer Productsc Inc.

i. Or approved equal

C. Synthetic Membrane Underlayment: ASTM D226/D226M, Type II (No. 30), asphalt-saturated organic felts.

D. Slip Sheet: Manufacturer's recommended slip sheet, if needed of type required for application.

2.4 MISCELLANEOUS MATERIALS

A. Miscellaneous Metal Subframing and Furring: ASTM C645; cold-formed, metallic-coated steel sheet, ASTM A653/A653M, G90 hot-dip galvanized coating designation or ASTM A792/A792M, Class AZ50 coating designation unless otherwise indicated.

http://www.specagent.com/Lookup?ulid=6898 http://www.specagent.com/Lookup?uid=123457005032 http://www.specagent.com/Lookup?uid=123457005033 http://www.specagent.com/Lookup?uid=123457005036 http://www.specagent.com/Lookup?ulid=5139 http://www.specagent.com/Lookup?uid=123457235340 http://www.specagent.com/Lookup?uid=123457235331 http://www.specagent.com/Lookup?uid=123457235332 http://www.specagent.com/Lookup?uid=123457235333 http://www.specagent.com/Lookup?uid=123457235334 http://www.specagent.com/Lookup?uid=123457235339 http://www.specagent.com/Lookup?uid=123457235335 http://www.specagent.com/Lookup?uid=123457235336

STANDING-SEAM METAL ROOF PANELS 074113.16 -5

Provide manufacturer's standard sections as required for support and alignment of metal panel system.

B. Panel Accessories: Provide components required for a complete, weathertight panel system including trim, copings, fascia, mullions, sills, corner units, clips, flashings, sealants, gaskets, fillers, closure strips, and similar items. Match material and finish of metal panels unless otherwise indicated.

1. Closures: Provide closures at eaves and ridges, fabricated of same metal as metal panels.

2. Backing Plates: Provide metal backing plates at panel end splices, fabricated from material recommended by manufacturer.

3. Closure Strips: Closed-cell, expanded, cellular, rubber or crosslinked, polyolefin-foam or closed-cell laminated polyethylene; minimum 1-inch- thick, flexible closure strips; cut or premolded to match metal panel profile. Provide closure strips where indicated or necessary to ensure weathertight construction.

C. Flashing and Trim: Provide flashing and trim formed from same material as metal panels as required to seal against weather and to provide finished appearance. Locations include, but are not limited to, eaves, rakes, corners, bases, framed openings, ridges, fascia, and fillers. Finish flashing and trim with same finish system as adjacent metal panels.

D. Gutters and Downspouts: NOT APPLICABLE

E. Panel Fasteners: Self-tapping screws designed to withstand design loads.

F. Panel Sealants: Provide sealant type recommended by manufacturer that are compatible with panel materials, are nonstaining, and do not damage panel finish.

1. Sealant Tape: Pressure-sensitive, 100 percent solids, gray polyisobutylene compound sealant tape with release-paper backing; 1/2 inch wide and 1/8 inch thick.

2. Joint Sealant: ASTM C920; as recommended in writing by metal panel manufacturer.

3. Butyl-Rubber-Based, Solvent-Release Sealant: ASTM C1311.

2.5 FABRICATION

A. Fabricate and finish metal panels and accessories at the factory, by manufacturer's standard procedures and processes, as necessary to fulfill indicated performance requirements demonstrated by laboratory testing. Comply with indicated profiles and with dimensional and structural requirements.

B. Provide panel profile, including major ribs and intermediate stiffening ribs, if any, for full length of panel.

C. Fabricate metal panel joints with factory-installed captive gaskets or separator strips that provide a weathertight seal and prevent metal-to-metal contact, and that minimize noise from movements.

STANDING-SEAM METAL ROOF PANELS 074113.16 -6

D. Sheet Metal Flashing and Trim: Fabricate flashing and trim to comply with manufacturer's recommendations and recommendations in SMACNA's "Architectural Sheet Metal Manual" that apply to design, dimensions, metal, and other characteristics of item indicated.

2.6 FINISHES

A. Panels and Accessories:

1. Two-Coat Fluoropolymer: AAMA 621. Fluoropolymer finish containing not less than 70 percent polyvinylidene fluoride (PVDF) resin by weight in color coat.

2. Concealed Finish: White or light-colored acrylic or polyester backer finish.

PART 3 - EXECUTION

3.1 PREPARATION

A. Miscellaneous Supports: Install subframing, furring, and other miscellaneous panel support members and anchorages according to ASTM C754 and metal panel manufacturer's written recommendations.

3.2 INSTALLATION OF UNDERLAYMENT

A. Self-Adhering Sheet Underlayment: Apply primer if required by manufacturer. Comply with temperature restrictions of underlayment manufacturer for installation. Apply at locations indicated on Drawings, wrinkle free, in shingle fashion to shed water, and with end laps of not less than 6 inches staggered 24 inches between courses. Overlap side edges not less than 3-1/2 inches. Roll laps with roller. Cover underlayment within 14 days.

B. Slip Sheet: Apply slip sheet over underlayment before installing metal roof panels.

C. Flashings: Install flashings to cover underlayment to comply with requirements specified in Section 076200 "Sheet Metal Flashing and Trim."

3.3 INSTALLATION OF STANDING-SEAM METAL ROOF PANELS

A. Standing-Seam Metal Roof Panel Installation: Fasten metal roof panels to supports with concealed clips at each standing-seam joint at location, spacing, and with fasteners recommended in writing by manufacturer.

1. Install clips to supports with self-tapping fasteners.

2. Install pressure plates at locations indicated in manufacturer's written installation instructions.

3. Snap Joint: Nest standing seams and fasten together by interlocking and completely engaging factory-applied sealant.

B. Accessory Installation: Install accessories with positive anchorage to building and weathertight mounting and provide for thermal expansion. Coordinate installation with flashings and other components.

STANDING-SEAM METAL ROOF PANELS 074113.16 -7

C. Flashing and Trim: Comply with performance requirements, manufacturer's written installation instructions, and SMACNA's "Architectural Sheet Metal Manual." Provide concealed fasteners where possible and set units true to line and level as indicated. Install work with laps, joints, and seams that will be permanently watertight and weather resistant.

3.4 CLEANING AND…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .