J.2 Pre-Award Accounting System Checklist.pdf
PDF 292 KB Posted
- Attached to
- Technical Support Services Contract for Infrastructure Engineering Laboratories Federal contract opportunity
- Solicitation number
- 693JJ324R000007
About this file
This document is a Pre-Award Accounting System Checklist that is used to evaluate a contractor's accounting system prior to award of a government contract. The checklist covers a variety of questions related to the contractor's accounting system, including whether it has been audited by DCAA, whether it complies with Cost Accounting Standards (CAS), whether it is in full operation and in accordance with GAAP, whether it can segregate direct and indirect costs, accumulate costs by contract, provide for labor distribution, and generate financial information required for contract administration. The contractor must provide detailed narrative responses to each question. The checklist is generally required for contractors planning to bid on cost-type government contracts.
The related federal contract opportunity is for a Technical Support Services Contract for the Infrastructure Engineering Laboratories at the Turner-Fairbank Highway Research Center (TFHRC). This is a competitive small business set-aside solicitation using FAR Part 15 procedures to establish a multiple-award Indefinite Delivery Indefinite Quantity (IDIQ) contract. The services required include laboratory support with engineers, technicians, and other staff to complete requirements for one or more of the engineering laboratories at TFHRC.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SCA Wage Determination.pdf | ||
| RFP 693JJ324R000007 Q-A.pdf | ||
| 693JJ324R000007 0425.pdf | ||
| 693JJ324R000007 Amend 0002.pdf | ||
| SITE VISIT_LABS.pdf | ||
| 693JJ324R000007_Amend 0001.pdf | ||
| 693JJ324R000007.pdf | ||
| J.1 Labor Rates.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-AWARD SURVEY OF PROSPECTIVE CONTRACTOR ACCOUNTING SYSTEM CHECKLIST
PRE-AWARD SURVEY OF PROSPECTIVE CONTRACTOR ACCOUNTING SYSTEM
Date:
Company Name, Contract Number, and Full Address:
Commercial and Government Agency (CAGE) Code Number: (Found at https://cage.dla.mil/)
Cognizant Defense Contract Audit Agency (DCAA) office info (Address/phone number/E-mail) - (Found at http://www.dcaa.mil/Home/Locator)
Company Point of Contact:
(Name, Title, Phone Number, and E-mail address)
If the accounting books and records are located at a physical address other than the address provided above, please indicate address here:
Name, Title, and signature of Company Principal (President/VP/Controller, etc) responsible for the design of the Accounting System.
NAME
TITLE
E-MAIL ADDRESS
SIGNATURE
DATE
PLEASE ANSWER THE QUESTIONS BELOW:
1. HAVE YOU READ THE REQUIREMENTS IN THE SF1408?
2. HAVE YOU READ THE DCAA PUBLICATION DCAAM 7641.90 - "Information for Contractors"
DCAA'S WEBSITE at http:www.dcaa.mil/?
ALL questions must have explanatory narrative text entered in the boxes. Please provide sufficient detail to describe the process (Including Account Numbers/Process Flow etc.) Each Question must be complete. Do NOT refer to previous answers, (i.e. "See Question 3 Above").
YES
YES
NO
NO
http://www.dcaa.mil/Home/Locator)
Pre-award Survey of Prospective Contractor Accounting System Checklist
1. Has your organization's Accounting System ever been audited by DCAA?
YES (if Yes, the Offeror should attach a copy of their most recent DCAA audit report to this Modified Pre-Award Survey) or provide the DCAA Report number or DCAA POC info.
NO (if NO, answer N/A to Questions 1.A., 1.B., and 1.C. below)
1.A. If the answer is "Yes" to Question 1 above, when was the audit performed?
Within the past Year
Within the past 3 Years
Greater than 3 Years (PROVIDE THE YEAR THE AUDIT WAS PERFORMED HERE -
N/A (Answer to Question 1 is NO)
1.B. If the answer is "Yes" to Question 1 above, did DCAA determine the Accounting System acceptable for award of prospective contracts?
YES
NO (If NO provide an explanation in the box below)
N/A (Answer to Question 1 is NO)
1.C. If the answer is "Yes" to Question 1 above, have there been any changes to the Accounting System since the DCAA audit?
YES (If YES, describe the changes in the box below
N/A (Answer to Question 1 is NO)
2. Is your organization subject to CAS (48 CFR Chapter 99)?
YES (If YES, is it FULL or MODIFIED CAS?) FULL MODIFIED
(If YES (FULL or MODIFIED), the Offeror MUST attach a copy of their most recent audit reports/documentation regarding all CAS compliance or non-compliance issues to this Modified Pre-Award Survey)
NO (If NO provide an explanation in the box below why your organization is exempt and answer N/A to Questions 2.A., 2.B., and 2.C. below)
2.A. Has your organization submitted a CASB disclosure statement (CASB DS-1) to DCAA and has it been determined adequate?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (Answer to Question 2 is NO)
2.B. Has your organization been notified by DCAA that it is (or may be in) non-compliance with its disclosure statement or CAS?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (N/A, if the answer to Question 2 is NO)
2.c. Is any aspect of this proposal inconsistent with your organization’s disclosed practices or applicable CAS?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (N/A, if the answer to Question 2 is NO or if you have no current, active proposal being considered)
Instruction: If the Contractor is planning on bidding on Cost Type Contracts, the contractor MUST provide explanatory narrative for all of the following questions:
3. Has your organization's Accounting System been audited by an outside Certified Public Accountant/Consultant or other Cognizant Federal Agency other than DCAA?
YES (If YES, the Offeror MUST attach a copy of their most recent audit report to this Modified Pre-Award Survey) NOTE: Do not submit your Annual Financial Audit.
NO
4. Is your organization's Accounting System currently in full operation?
YES (If YES, provide an explanation that validates your answer in the box below).
NO (If NO, provide an explanation in the box below which portions are (1) in operation, (2) set up, but not yet in operation, (3) anticipated, or (4) non-existent)
N/A (If N/A, provide an explanation in the box below)
5. Is your organization's Accounting System in accord with Generally Accepted Accounting Principles (GAAP) Applicable in the Circumstances?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (N/A, provide an explanation in the box below)
6. Is your organization's Accounting System ready for a DCAA audit?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below as to when you will be ready for an audit)
N/A (N/A, provide an explanation in the box below)
7. Are the loaded hourly labor rates proposed consistent with your established estimating and accounting principles and procedures and FAR Part 31, Cost Principles? (Answer this Questions "N/A" if you do not have an active proposal)
YES (If YES, provide an explanation that validates your answer in the box below)
N/A (N/A, provide an explanation in the box below)
8. Does the Accounting System provide for the proper segregation of Direct Costs from Indirect Costs?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (N/A, provide an explanation in the box below)
9. Does the Accounting System provide for the identification and accumulation of Direct Costs by contract?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (N/A, provide an explanation in the box below)
10. Does the Accounting System provide for a logical and consistent method for the allocation of Indirect Costs to intermediate and final cost objectives? (A contract is a final cost objective.)
YES (If YES, provide an explanation that validates your answer in the box below)
11. Does the Accounting System Provide for the accumulation of costs under general ledger control?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (N/A, provide an explanation in the box below)
12. Does the Accounting System provide for a timekeeping system that identifies employees' labor by intermediate or final cost objectives?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (N/A, provide an explanation in the box below)
13. Does the Accounting System provide for a labor distribution system that charges Direct and Indirect labor to the appropriate cost objectives?
YES (If YES, provide an explanation that validates your answer in the box below)
14. Does the Accounting System provide for an interim (at least monthly) determination of costs charged to a contract through routine posting of books of account?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (N/A, provide an explanation in the box below)
15. Does the Accounting System provide for an exclusion of costs charged to government contracts of amounts which are not allowable in terms of FAR 31, Contract Cost Principles and Procedures, or other contract provisions?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (N/A, provide an explanation in the box below)
Pre-award Survey of Prospective Contractor Accounting System Checklist
16. Does the Accounting System provide for the identification of costs by contract line item and by units (as if each unit or line item were a separate contract) if required by the proposed contract?
YES (If YES, provide an explanation that validates your answer in the box below)
17. Does the Accounting System provide for the segregation of preproduction costs from production costs?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (N/A, provide an explanation in the box below)
18. Does the Accounting System provide financial information required by contract clauses concerning limitation of cost (FAR 52.232.20) or limitation on payments (FAR 52.216-16)?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (N/A, provide an explanation in the box below)
19. Does the Accounting System provide financial information required to support requests for Progress Payments?
YES (If YES, provide an explanation that validates your answer in the box below)
20. Is the Accounting System designed, and are the records maintained, in such manner that adequate, reliable data are developed for use in pricing follow-on acquisitions?
YES (If YES, provide an explanation that validates your answer in the box below)
NO (If NO provide an explanation in the box below)
N/A (N/A, provide an explanation in the box below)
21. Is your organization planning on submitting proposals on Cost-Type (FAR 16.3) contracts/task orders?
YES
NO (If NO provide an explanation in the box below)
N/A (N/A, provide an explanation in the box below)
22. Is your organization currently performing on Cost-Type (FAR 16.3) contracts/task orders?
YES
N/A
| PRE-AWARD SURVEY OF PROSPECTIVE CONTRACTOR ACCOUNTING SYSTEM CHECKLIST |
| 1. Has your organization's Accounting System ever been audited by DCAA? |
| 1.A. If the answer is "Yes" to Question 1 above, when was the audit performed? |
| 1.B. If the answer is "Yes" to Question 1 above, did DCAA determine the Accounting System acceptable for award of prospective contracts? |
| 1.C. If the answer is "Yes" to Question 1 above, have there been any changes to the Accounting System since the DCAA audit? |
| 2. Is your organization subject to CAS (48 CFR Chapter 99)? |
| 2.A. Has your organization submitted a CASB disclosure statement (CASB DS-1) to DCAA and has it been determined adequate? |
| 2.B. Has your organization been notified by DCAA that it is (or may be in) non-compliance with its disclosure statement or CAS? |
| 2.c. Is any aspect of this proposal inconsistent with your organization’s disclosed practices or applicable CAS? |
| 3. Has your organization's Accounting System been audited by an outside Certified Public Accountant/Consultant or other Cognizant Federal Agency other than DCAA? |
| 4. Is your organization's Accounting System currently in full operation? |
| 5. Is your organization's Accounting System in accord with Generally Accepted Accounting Principles (GAAP) Applicable in the Circumstances? |
| 7. Are the loaded hourly labor rates proposed consistent with your established estimating and accounting principles and procedures and FAR Part 31, Cost Principles? (Answer this Questions "N/A" if you do not have an active proposal) |
| 8. Does the Accounting System provide for the proper segregation of Direct Costs from Indirect Costs? |
| 9. Does the Accounting System provide for the identification and accumulation of Direct Costs by contract? |
| 10. Does the Accounting System provide for a logical and consistent method for the allocation of Indirect Costs to intermediate and final cost objectives? (A contract is a final cost objective.) |
| 11. Does the Accounting System Provide for the accumulation of costs under general ledger control? |
| 12. Does the Accounting System provide for a timekeeping system that identifies employees' labor by intermediate or final cost objectives? |
| 13. Does the Accounting System provide for a labor distribution system that charges Direct and Indirect labor to the appropriate cost objectives? |
| 14. Does the Accounting System provide for an interim (at least monthly) determination of costs charged to a contract through routine posting of books of account? |
| 15. Does the Accounting System provide for an exclusion of costs charged to government contracts of amounts which are not allowable in terms of FAR 31, Contract Cost Principles and Procedures, or other contract provisions? |
| Pre-award Survey of Prospective Contractor Accounting System Checklist |
| 16. Does the Accounting System provide for the identification of costs by contract line item and by units (as if each unit or line item were a separate contract) if required by the proposed contract? |
| 17. Does the Accounting System provide for the segregation of preproduction costs from production costs? |
| 19. Does the Accounting System provide financial information required to support requests for Progress Payments? |
| pricing follow-on acquisitions? |
| 21. Is your organization planning on submitting proposals on Cost-Type (FAR 16.3) contracts/task orders? |
| 22. Is your organization currently performing on Cost-Type (FAR 16.3) contracts/task orders? |
| NAME: |
| TITLE: |
| EMAIL ADDRESS: |
| NA Answer to Question 1 is NO: |
| NA Answer to Question 1 is NO_2: |
| NO If NO provide an explanation in the box below why your organization is exempt and answer NA to Questions 2A 2B and 2C below: |
| NA Answer to Question 2 is NO: |
| NA NA if the answer to Question 2 is NO: |
| NA NA if the answer to Question 2 is NO or if you have no current active proposal being considered: |
| NO: |
| NA If NA provide an explanation in the box below: |
| NA NA provide an explanation in the box below: |
| NA NA provide an explanation in the box below_2: |
| NA NA provide an explanation in the box below_3: |
| NA NA provide an explanation in the box below_4: |
| NA NA provide an explanation in the box below_5: |
| NA NA provide an explanation in the box below_6: |
| NA NA provide an explanation in the box below_7: |
| NA NA provide an explanation in the box below_8: |
| NA NA provide an explanation in the box below_9: |
| NA NA provide an explanation in the box below_10: |
| NA NA provide an explanation in the box below_11: |
| NA NA provide an explanation in the box below_12: |
| NA NA provide an explanation in the box below_13: |
| NA NA provide an explanation in the box below_14: |
| NA NA provide an explanation in the box below_15: |
| NA NA provide an explanation in the box below_16: |
| NA NA provide an explanation in the boxbelow: |
| undefined_2: |
| Date 1: |
| Group6: Off |
| Check Box7: Off |
| Check Box8: Off |
| Check Box9: Off |
| Check Box10: Off |
| DATE: |
| Check Box11: Off |
| Check Box12: Off |
| Check Box13: Off |
| Check Box14: Off |
| Check Box15: Off |
| Check Box16: Off |
| Check Box17: Off |
| Check Box18: Off |
| Check Box19: Off |
| Check Box20: Off |
| Check Box21: Off |
| Check Box22: Off |
| Check Box23: Off |
| Check Box24: Off |
| Check Box25: Off |
| Check Box26: Off |
| Check Box27: Off |
| Check Box28: Off |
| Check Box29: Off |
| Check Box30: Off |
| Check Box31: Off |
| Check Box32: Off |
| Check Box33: Off |
| Check Box34: Off |
| Check Box35: Off |
| Check Box36: Off |
| Check Box37: Off |
| Check Box40: Off |
| Check Box44: Off |
| Check Box45: Off |
| Check Box46: Off |
| Check Box47: Off |
| Check Box48: Off |
| Check Box49: Off |
| Check Box50: Off |
| Check Box51: Off |
| Check Box52: Off |
| Check Box53: Off |
| Check Box54: Off |
| Check Box55: Off |
| Check Box56: Off |
| Check Box57: Off |
| Check Box58: Off |
| Check Box59: Off |
| Check Box60: Off |
| Check Box61: Off |
| Check Box62: Off |
| Check Box63: Off |
| Check Box64: Off |
| Check Box65: Off |
| Check Box66: Off |
| Check Box67: Off |
| Check Box68: Off |
| Check Box69: Off |
| Check Box70: Off |
| Check Box71: Off |
| Check Box72: Off |
| Check Box73: Off |
| Check Box74: Off |
| Check Box75: Off |
| Check Box76: Off |
| Check Box77: Off |
| Check Box78: Off |
| Check Box79: Off |
| Check Box80: Off |
| Check Box81: Off |
| Check Box82: Off |
| Check Box83: Off |
| Check Box84: Off |
| Check Box85: Off |
| Check Box86: Off |
| Check Box87: Off |
| Check Box88: Off |
| Check Box89: Off |
| Check Box90: Off |
| Check Box91: Off |
| CAGE Code: |
| Cognizant DCAA Office: |
| Check Box39: Off |
| Check Box41: Off |
| Check Box42: Off |
| Check Box43: Off |
| Check Box1: Off |
| Check Box2: Off |
| Check Box3: Off |
| Check Box4: Off |
| Address: |
| POC: |
| If the accounting books and records are located: |
| Audit Year: |