This document outlines the deliverables schedule for the Part A/Part B Medicare Administrative Contractor (MAC) Jurisdiction L contract. The contractor will provide Medicare claims processing and payment services for Delaware, Maryland, New Jersey, Pennsylvania, Washington D.C., and parts of Virginia.

Key deliverables include project plans for implementation, risk management, workload closeout, and testing. The contractor must also submit monthly status reports, an operational productivity report, and a final estimated cost proposal. Other deliverables encompass provider enrollment appeals reports, medical review documentation, improper payment reduction strategies, and joint operating agreements with entities such as QICs, RACs, and BCRCs. Due dates vary from monthly to annual, with initial deliverables due 30 days after contract award or cutover. The Centers for Medicare and Medicaid Services will oversee the contract and associated deliverables.

View the file

Other files

File Type Posted
J.23 Government Provided Proposal Assumptions (GPPA) redline Amend 2.docx DOCX document
J.23 Government Provided Proposal Assumptions (GPPA) clean Amend 2.docx DOCX document
75FCMC20R0008 Amend 2.pdf PDF
JL Solicitation 75FCMC20R0008 Sections B-M CLEAN Amend 1.pdf PDF
Q and A RFP 75FCMC20R00008.xlsx XLSX spreadsheet
J.34 CLIN 0001 Cost Proposal Template - Implementation clean Amend 1.xlsx XLSX spreadsheet
J.37 CLIN 0004 Cost Proposal Template - Option Year 2 (PM, MIP, RAC) clean Amend 1.xlsx XLSX spreadsheet
J.23 Government Provided Proposal Assumptions (GPPA) redline Amend 1.docx DOCX document
J.48 CLIN 0015 Cost Proposal Template - Option Year 5 (MPIP) clean Amend 1.xlsx XLSX spreadsheet
J.43 CLIN 0010 Cost Proposal Template - Base Year (MPIP) clean Amend 1.xlsx XLSX spreadsheet
J.22 Basis of Estimate redline Amend 1.xlsx XLSX spreadsheet
J.22.A Historic & Proposed FTE, Hours & Gross Cost Instructions & Narrative redline Amend 1.docx DOCX document
J.46 CLIN 0013 Cost Proposal Template - Option Year 3 (MPIP) clean Amend 1.xlsx XLSX spreadsheet
J.1 Statement of Work (SOW) clean Amend 1.docx DOCX document
J.33 Cost Template Summary Sheet clean Amend 1.xlsx XLSX spreadsheet
J.21 Proposal Self-Check Tool clean Amend 1.xlsx XLSX spreadsheet
J.49 CLIN 0016 Cost Proposal Template - Option Year 6 (MPIP) clean Amend 1.xlsx XLSX spreadsheet
J.22.A Historic & Proposed FTE, Hours & Gross Cost Instructions & Narrative clean Amend 1.docx DOCX document
JL Solicitation 75FCMC20R0008 Sections B-M REDLINE Amend 1.pdf PDF
J.45 CLIN 0012 Cost Proposal Template - Option Year 2 (MPIP) clean Amend 1.xlsx XLSX spreadsheet
J.40 CLIN 0007 Cost Proposal Template - Option Year 5 (PM, MIP, RAC) clean Amend 1.xlsx XLSX spreadsheet
J.41 CLIN 0008 Cost Proposal Template - Option Year 6 (PM, MIP, RAC) clean Amend 1.xlsx XLSX spreadsheet
J.22 Basis of Estimate clean Amend 1.xlsx XLSX spreadsheet
J.38 CLIN 0005 Cost Proposal Template - Option Year 3 (PM, MIP, RAC) clean Amend 1.xlsx XLSX spreadsheet
J.42 CLIN 0009 Cost Proposal Template - Outgoing Contractor Workload Transition Activities clean Amend 1.xlsx XLSX spreadsheet
J.36 CLIN 0003 Cost Proposal Template - Option Year 1 (PM, MIP, RAC) clean Amend 1.xlsx XLSX spreadsheet
J.1 Statement of Work (SOW) redline Amend 1.docx DOCX document
J.47 CLIN 0014 Cost Proposal Template - Option Year 4 (MPIP) clean Amend 1.xlsx XLSX spreadsheet
J.35 CLIN 0002 Cost Proposal Template - Base Year (PM, MIP, RAC) clean Amend 1.xlsx XLSX spreadsheet
J.23 Government Provided Proposal Assumptions (GPPA) clean Amend 1.docx DOCX document
J.21 Proposal Self-Check Tool redline Amend 1.xlsx XLSX spreadsheet
J.39 CLIN 0006 Cost Proposal Template - Option Year 4 (PM, MIP, RAC) clean Amend 1.xlsx XLSX spreadsheet
J.44 CLIN 0011 Cost Proposal Template - Option Year 1 (MPIP) clean Amend 1.xlsx XLSX spreadsheet
75FCMC20R0008.pdf PDF
J.37 CLIN 0004 Cost Proposal Template - Option Year 2 (PM, MIP, RAC).xlsx XLSX spreadsheet
J.22.A Historic & Proposed FTE, Hours & Gross Cost Instructions & Narrative.docx DOCX document
J.24 Attestations.docx DOCX document
J.45 CLIN 0012 Cost Proposal Template - Option Year 2 (MPIP).xlsx XLSX spreadsheet
J.10 Contractor Business Ethics COI and Compliance Program Requirements.docx DOCX document
J.1.B List of Key Acronyms.docx DOCX document
J.33 Cost Template Summary Sheet.xlsx XLSX spreadsheet
J.35 CLIN 0002 Cost Proposal Template - Base Year (PM, MIP, RAC).xlsx XLSX spreadsheet
J.23.A GPPA Audit & Reimbursement Tables.xlsx XLSX spreadsheet
J.42 CLIN 0009 Cost Proposal Template - Outgoing Contractor Workload Transition Activites.xlsx XLSX spreadsheet
J.1 Statement of Work (SOW) - Jurisdiction L.docx DOCX document
J.7 AB MAC Award Fee Plan and Self Assessment Template.docx DOCX document
J.9 Non-Disclosure Statement.docx DOCX document
J.40 CLIN 0007 Cost Proposal Template - Option Year 5 (PM, MIP, RAC).xlsx XLSX spreadsheet
J.43 CLIN 0010 Cost Proposal Template - Base Year (MPIP).xlsx XLSX spreadsheet
J.1.A List of Key Definitions.docx DOCX document
Show 40 more

Latest 50 of 79 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP # 75FCMC20R0008

Attachment J.2 – A/B MAC Deliverable Schedule Jurisdiction L V.11.0

RFP/SOW WBS #
Related SOW Requirement Name
Deliverable Name
Deliverable Description
Deliver to
Deliverable Due Date
Frequency
CMS Business Owner Functional Area
C.5.1.1
Jurisdiction Implementation Project Plan
Jurisdiction Implementation Project Plan
A detailed description of all activities required to transfer all Medicare operations from the outgoing contractor to the incoming contractor.
Contracting Officer's Representative and/or Designees
Baseline due within 30 days of the jurisdiction kickoff meeting, unless otherwise directed by the COR.
Once
Center for Medicare Management (CM) / Medicare Contractor Management Group (MCMG) / Division of Medicare Administrative Contractor (MAC) Program Management (DMPM)
C.5.1.3
Risk Management Plan
Risk Management Plan
Identifies the jurisdiction wide as well as segment specific risks, mitigation strategies, and maintenance process for the risks associated with the contractor’s segment workload transition
Contracting Officer's Representative and/or Designees
Due within 30 calendar days of kickoff meeting.
Once
CMM / MCMG/ DMPM
C.5.1.4
Cutover Plans
Part A Cutover Plan; Part B Cutover Plan
An expanded part of the Jurisdiction Implementation Project Plan that contain the day by day activities and procedures, some of which may be detailed to the hour, that the contractor will follow during the cutover period to ensure a successful cutover of a Part A and Part B workload.
Contracting Officer's Representative and/or Designees
Initial at least 45 calendar days prior to the Part A and Part B cutover date contained in the Jurisdiction Implementation Project Plan
Once
CMM / MCMG/ DMPM
C.5.1.5
Test Plan
Test Plan
A plan to identify the approach to testing, types of tests, schedule, and progress for the implementation.
Contracting Officer's Representative and/or Designees
Initial within 30 calendar days after kickoff meeting.
Once
CMM / MCMG/ DMPM
C.5.1.6
Lessons Learned Documentation
Lessons-Learned Document Regarding Implementation Activities
Identifies the lessons learned during the implementation.
Contracting Officer's Representative and/or Designees
Within 40 calendar days after the final Part A/Part B cutover
Once
CMM / MCMG/ DMPM
C.5.1.7
Accounts Receivable Reconciliation
Receipt of Accounts Receivable Transmittal Document
Certifies receipt of transmittal document that describes the total amounts and counts of the accounts receivables of the outgoing contractor.
Contracting Officer's Representative and/or Designees
Due within 10 calendar days after receipt of the Accounts Receivable Transmittal Document
Once
CMM / MCMG and OFM/AMG/DFOIC
C.5.1.9
Implementation Stakeholder Communication
Communications Plan
Identifies the processes and procedures the contractor will follow to ensure that all transition stakeholders are informed of the transition and its progress.
Contracting Officer's Representative and/or Designees
Due within 30 calendar days after contract award date.
Once
CMM / MCMG/ DMPM
C.5.2.1
Workload Closeout Project Plan (Option that may be exercised at the End of the Contract)
Workload Closeout Project Plan
Describes the outgoing contractor’s plan for the transfer of Medicare functions and the closeout of operations at contract end.
Contracting Officer's Representative and/or Designees
Due 15 calendar days of jurisdiction kickoff meeting
Once
CMM / MCMG/ DMPM
C.5.2.3
Workload Closeout Risk Management Plan (Option that may be exercised at the End of the Contract)
Workload Closeout Risk Management Plan
Includes a periodic assessment of new risks and mitigation and contingency planning where appropriate.
Contracting Officer's Representative and/or Designees
Initial Due within 30 calendar days of replacement contractor kickoff meeting
Once
CMM / MCMG/ DMPM
C.5.2.4
Accounts Receivable Transmittal Document
Accounts Receivable Transmittal Document
Describes the total amounts and counts of the accounts receivables of the outgoing contractor.
Contracting Officer's Representative and/or Designees
60 calendar days prior to the effective date of the transfer
Once
CMM / MCMG and OFM/DFRP
C.5.2.5
Cost Accounting/Audit (Option that may be exercised at the End of the Contract)
Financial Audit Supporting Documentation
Describes the details to support the post-cutover financial activities of the outgoing contractor.
Contracting Officer's Representative and/or Designees
Within 30 calendar days after closeout end
Once
CM / MCMG / DMPM
C.5.4.3
Security
Information Technology Systems Contingency Plan Report
Information Technology (IT) Systems Contingency Plan (See BPSSM Table 3.1 Planning Table, for 3.4)
Contracting Officer's Representative and/or Designees and CMS Business Owner
Initial within 90 days prior to the first segment cutover date and annually thereafter
Annually
OIS/MCMG/DMSSOO
C.5.4.3
Security
IT Security Tests And Reports
Contractor conducted or any other independent IT evaluation
Contracting Officer's Representative and/or Designees
10 business days after conducted
As required
OIS/MCMG/DMSSOO
C.5.4.3
Security
Risk Assessment Report
Risk Assessment (See BPSSM Table 3.1 Planning Table, for 3.2)
Contracting Officer's Representative and/or Designees
Initial within 90 days prior to making AB payments under the contract and annually thereafter
Annually
OIS/MCMG/DMSSOO
C.5.4.3
Security
Statement of Security Compliance
Annual certification (See BPSSM Table 3.1 Planning Table, for 3.3)
Contracting Officer's Representative and/or Designees
In accordance with BPSSM
Annually
OIS/MCMG/DMSSOO
C.5.4.3
Security
Systems Security Plan
Systems Security Plan (SSP) (See BPSSM Table 3.1 Planning Table, for 3.1)
Contracting Officer's Representative and/or Designees
Initial within 90 days prior to making AB payments under the contract and annually thereafter
Annually
OIS/MCMG/DMSSOO
C.5.4.3
Security
Systems Security Profile Documentation
Systems Security Profile (See BPSSM Table 3.1 Planning Table, for 3.7)
Contracting Officer's Representative and/or Designees
Consistent with frequency
As required
OIS/MCMG/DMSSOO
C.5.4.3.2
Administer Security Program
Corrective Action Management Process Report
Report progress in correcting deficiencies or findings identified by audits, reviews, etc. in accordance with guidance provided by the BPSSM and other CMS guidance.
Contracting Officer's Representative and/or Designees
In accordance with BPSSM or as requested by CMS (Corrective Action Plans for findings identified in Section 912 Evaluations must be remedied prior to making payments).
Monthly
OIS/MCMG/DMSSOO
C.5.4.3.4
Correct Deficiencies
Incident Reporting and Responses Report
Incident Reporting and Response (See BPSSM Table 3.1 Planning Table, for 3.6)
Contracting Officer's Representative and/or Designees
As required by the CMS Incident Handling & Breach Notification Handbook, RMH Vol. III 7-1. Incidents involving individually identifiable information must be reported within one hour
Monthly and As required
OIS/MCMG/DMSSOO
C.5.4.3.5
Security Review and Verification
FISMA Assessment
Contractor will examine and analyze implemented security safeguards to provide evidence of compliance with applicable laws, regulations and requirements.
Contracting Officer's Representative and/or Designees
As part of the May 1st POA&M submission
Annually
CM/MCMG/DMSSOO
C.5.4.3.5
Security Review and Verification
FISMA Compliance
Any FISMA Compliance evidence to CMS (See H.26- FEDERAL INFORMATION SECURITY MANAGEMENT ACT (FISMA)) on completed and current CMS contracts
Contracting Officer's Representative and/or Designees
As requested by CMS
As requested
CM/MCMG/DMSSOO
C.5.4.4.1
Quality Control Program
Quality Control Plan (QCP)
Specifies the procedures and resources applied to ensure services meet contract performance requirements.
Contracting Officer's Representative and/or Designees and CMS Business Owner
The QCP shall be submitted into the CMS ART 45 calendar days prior to the start of each contract period and within 30 calendar days of any substantive changes in the MAC's quality operations. A courtesy copy of the QCP deliverable shall be sent to CMS's QCP Mailbox at QCP@cms.hhs.gov when submitting the QCP deliverable to CMS ART. Both redlined and clean copies should be submitted.
Prior to start of base operational period; prior to start of each subsequent contract year; and when substantive changes occur in quality operations.
CM/MCMG/DPA
C.5.4.5
Public Relations (Implementation-only deliverable)
Public Relations Plan - Implementation Deliverable
Describes the contractor’s plans for managing the programs public relations.
Contracting Officer's Representative and/or Designees
Initial within 30 calendar days of contract award.
One month after contract award.
CM/MCMG
C.5.4.5.3.3
Review Written Responses for Reading Level (Fogging) Accuracy and Timeliness
Readability Attestation for Beneficiary Appeals Correspondence
Contractors are required to attest that they are issuing correspondence that satisfies the readability requirements outlined in the Federal Register. This attestation should include how contractors ensure that this requirement is being met (e.g., software programs, quality reviews, etc.). Additional information regarding the readability requirements is in IOM 100-04, Chapter 29, Section 290.3.2 -- Reading Levels.
Contracting Officer's Representative and/or Designees and CMS Business Owner
Within 30 days after cutover
Annual
CPC/MEAG/DAO
C.5.4.6.1
Responses to Congressional Inquiries
Responses to Congressional Inquiries Report
Describes a summary of the congressional inquiry responses
Contracting Officer's Representative and/or Designees
Within 7 calendar days of month end
Monthly
OBIS/CMS
C.5.4.8.3
Successful Implementation of Change Requests
Change Request Implementation Report
Describes the Change Requests (CRs) that the contractor has implemented in the quarterly period.
Contracting Officer's Representative and/or Designees
The due dates for the Change Request Implementation Report are as follows, per the IOM:

Quarter 1 - Oct Nov Dec (report due no later than February 28th) Quarter 2 - Jan Feb Mar (report due no later than May 28th) Quarter 3 - Apr May Jun (report due no later than August 28th) Quarter 4 - Jul Aug Sep (report due no later than November 28th)

Quarterly
CM/MCMG/ Division of Change and Operations Management (DCOM)
C.5.4.8.3
Successful Implementation of Technical Direction Letters
Technical Direction Letter (TDL) Compliance Report (TCR)
Describes the Technical Direction Letters that the contractor has implemented during the quarterly period.
This information shall be submitted electronically to CR_IMPL_REPORTS@cms.hhs.gov. These deliverables must also be delivered concurrently to the COR in accord with CMS technical direction regarding the contract deliverable process.
The due dates for the TCR are as follows, per the IOM: Quarter 1 - Oct Nov Dec (report due no later than February 28th)

Quarter 2 - Jan Feb Mar (report due no later than May 28th) Quarter 3 - Apr May Jun (report due no later than August 28th) Quarter 4 - Jul Aug Sep (report due no later than November 28th)

Quarterly
CM/MCMG/ Division of Change and Operations Management (DCOM)
C.5.4.9
Business Continuity Planning and Disaster Recovery
Comprehensive Continuity of Operations (COOP) Plan
Describes the Contractor’s policies and procedures to ensure that essential business functions continue during a disaster. The COOP plan elements include protection of physical infrastructure, IT disaster recovery, business continuity (with or without system availability), and other topics
Contracting Officer's Representative and/or Designees
Initial is due 60 calendar days prior to cutover, thereafter annually as requested by CMS
Once, then Annually
OIS/MCMG/DMSSOO
C.5.4.10.2
Self Assessment Process for Internal Controls
Certification Package for Internal Controls (CPIC) Report
Attestation and documentation of the adequacy of the internal controls.
Contracting Officer's Representative and/or Designees. CPIC should also be delivered to CMS internalcontrols@cms.hhs.gov.
Initial is due within 15 business days after June 30. Update is due 5 business days after September 30.
Annually
OFM/ Accounting Management Group (AMG)/ Division of Financial Oversight & Internal Controls (DFOIC)
C.5.4.10.3
Correcting Internal Control Deficiencies – CAP process
Corrective Action Plan (CAP)
Describes a plan of action to correct weaknesses, findings, gaps, or other deficiencies.
Contracting Officer's Representative and/or Designees. CAP reports should also be delivered to CMS CAPS@cms.hhs.gov.
Initial CAP reports are due within 45 calendar days of receiving a final audit report or after discovery of a material weakness; thereafter 30 calendar days form quarter end
Within 45 calendar days after discovery of material weakness, and quarterly
OIT and OFM/AMG/DFRPO
C.5.4.11
Compliance Program
Compliance Documents
Position Description for the Compliance Officer and other members of the Compliance Department
Contracting Officer's Representative and/or Designees
Initial 30 calendar days after contract award and annually thereafter
Annually - End of Period of Performance/Contract Year
OAGM
C.5.4.11
Compliance Program
Compliance Documents
Code of Conduct
Contracting Officer's Representative and/or Designees
Initial 30 calendar days after contract award and annually thereafter
Annually - End of Period of Performance/Contract Year
OAGM
C.5.4.11
Compliance Program
Compliance Documents
Written compliance policies and procedures
Contracting Officer's Representative and/or Designees
Initial 30 calendar days after contract award and annually thereafter
Annually - End of Period of Performance/Contract Year
OAGM
C.5.4.11
Compliance Program
Compliance Documents
Compliance training materials used or developed in the last year
Contracting Officer's Representative and/or Designees
Initial 30 calendar days after contract award and annually thereafter
Annually - End of Period of Performance/Contract Year
OAGM
C.5.4.11
Compliance Program
Compliance Documents
Names and positions of the Board of Directors and/or Compliance Committee members charged with oversight of the compliance program
Contracting Officer's Representative and/or Designees
Initial 30 calendar days after contract award and annually thereafter
Annually - End of Period of Performance/Contract Year
OAGM
C.5.4.11
Compliance Program
Compliance Documents
Charters for the Board and/or Executive Compliance Committees
Contracting Officer's Representative and/or Designees
Initial 30 calendar days after contract award and annually thereafter
Annually - End of Period of Performance/Contract Year
OAGM
C.5.4.11
Compliance Program
Compliance Documents
Conflict of interest questionnaire(s) that are completed by employees, managers, officers and Board members
Contracting Officer's Representative and/or Designees
Initial 30 calendar days after contract award and annually thereafter
Annually - End of Period of Performance/Contract Year
OAGM
C.5.4.11
Compliance Program
Compliance Documents
Risk assessment protocol(s) developed by the Compliance Department
Contracting Officer's Representative and/or Designees
Initial 30 calendar days after contract award and annually thereafter
Annually - End of Period of Performance/Contract Year
OAGM
C.5.4.11
Compliance Program
Compliance Documents
Internal audit plan
Contracting Officer's Representative and/or Designees
Initial 30 calendar days after contract award and annually thereafter
Annually - End of Period of Performance/Contract Year
OAGM
C.5.4.11
Compliance Program
Compliance Documents
Any reportable events to CMS (See H.21- Reportable Events) on completed and current CMS contracts
Contracting Officer's Representative and/or Designees
Initial 30 calendar days after contract award and annually thereafter
Annually - End of Period of Performance/Contract Year
OAGM
C.5.5.4
Provider Enrollment Appeals
Monthly Rebuttal Report
A monthly status report of every rebuttal submission received by the contractor in response to an enrollment deactivation utilizing the template provided in IOM Pub. 100-08, Chapter 15, Section 15.27.5.
This report should be sent electronically to the Contractor Officer’s Representative and ProviderEnrollmentAppeals@cms.hhs.gov.
On the 15th of each month.
Monthly with the initial report due on October 15, 2019.
CPI / PEOG / DCA
C.5.5.4.1
Provider Enrollment Appeals
Monthly Appeals Report
A monthly status report of every appeal (CAP and reconsideration request) submission received by the contract in response to an initial determination utilizing the template provided in IOM Pub. 100-08, Chapter 15, Section 15.25.4.
This report should be sent electronically to the Contracting Officer’s Representative and ProviderEnrollmentAppeals@cms.hhs.gov.
On the 15th of each month.
Monthly
CPI / PEOG / DCA
C.5.7.1.7
Provider Service Plan
Provider Service Plan (PSP)
Describes the strategies, project activities, efforts, and approaches the contractor will use throughout the duration of its contract.
Contracting Officer's Representative and/or Designees and mailbox ProviderServices@cms.hhs.gov
By the last day of the first month of the first year of the contract
One Time
CMM/PCG/DCPC
C.5.7.1.8
Provider Customer Service Program (PCSP) Activity Report
Provider Customer Service Program (PCSP) Activity Report
Summarizes and recounts the contractor's PCSP activities, process improvements, and best practices during the reporting period.
Contracting Officer's Representative and/or Designees and mailbox ProviderServices@cms.hhs.gov
First report due on the 30th calendar day after the first 6 months of the contract year; second report due 30 calendar days after the last day of the contract year. If the contract period is six months or less, the contractor should only submit one report 30 calendar days after the last day of the contract period.
Semiannually
CMM/PCG/DCPC
C.5.7.2.1
Telephone Inquiries
Disaster Recovery Plan
Plan describing how the Medicare provider telecommunications operations will be maintained or continued in event of natural or manmade disaster
Contracting Officer's Representative and/or Designees and mailbox ServiceReports@cms.hhs.gov
End of third month of contract year
Annual
CM/PCG/DCPC
C.5.7.3.2
Web Technology
Website Attestation statement
Statement by contractor attesting that CMS contractor website guidelines have been followed See IOM Pub. 100-9, Chapter 6, Section 50.2.2.
Contracting Officer's Representative and/or Designees and mailbox ProviderServices@cms.hhs.gov
Within 30 calendar days after cutover; thereafter, by the end of the sixth month of the contract year.
Annual
CMM/PCG/DCPC
C.5.7.3.2
Web Technology
Website Attestation statement-- Current Procedural Terminology (CPT) usage
Statement by contractor attesting whether website adheres to requirements in IOM Pub 100-4, Chapter 23, section 20.7.
Contracting Officer's Representative and/or Designees and mailbox ProviderServices@cms.hhs.gov
Within 30 calendar days after cutover; thereafter, by the end of the sixth month of the contract year.
Annually
CMM/PCG/DCPC
C.5.8
Claims Processing
Social Security Number Removal Initiative (SSNRI) Status Report
A status report of the progress of MAC systems and non-systems changes for the SSNRI project, including dates of completion for each task milestone.
FFS_SSNRI@cms.hhs.gov with copy to Contracting Officer's Representative
Due by the 5th day of each month, August 2017 through April 2018
Monthly
CM/MCMG/DCOM
C.5.8.2.5
Payment of Claims Outside Common Working File
Workload Report for Payment of Claims Outside Common Working File
Workload Report for Payment of Claims Outside Common Working File
Contracting Officer's Representative and/or Designees
Within 20 calendar days of the month end.
Monthly
CMM/MCMG
C.5.8.4.4
The Do Not Forward Initiative
Do-Not-Forward (DNF) Initiative Report
Describes the Medicare checks and payments for professional claims returned or held to the contractor thru the DNF initiative.
Contracting Officer's Representative and/or Designees
Within 15 calendar days of quarter end
Quarterly
CMM/PBG
C.5.10.1.9
Conduct and Notice of the Redetermination
Readability Attestation for Beneficiary Appeals Correspondence and/or Medicare Redetermination Notices
Contractors are required to attest that they are issuing correspondence that satisfies the readability requirements outlined in the Federal Register. This attestation should include how contractors ensure that this requirement is being met (e.g., software programs, quality reviews, etc.). Additional information regarding the readability requirements is found in IOM 100-04, Chapter 29, Section 290.3, How to Establish Reading Level.
Contracting Officer's Representative and/or Designees and CMS Business Owner
Within 30 days after cutover, as applicable, and annually, thereafter.
Annual
CPC/MEAG/DAO
C.5.11.2
Banking Relations
Copy of Tripartite Agreement
Describes the agreement between CMS, the contractor and its bank.
Contracting Officer's Representative and/or Designees
Upon initiation
Once
OFM / Financial Services Group (FSG)
C.5.11.2.3
Contractor Monthly Bank Reconciliation Worksheet
CMBRW
Bank reconciliation
Contracting Officer's Representative, CMS Business Owner, and mailbox higlasbankrecon@cms.hhs.gov
On or before the 15th of the month
Monthly
OFM/AMG/DFOIC
C.5.11.2.3.1
Cash Collection Worksheet
Cash Collection Worksheet
Reconciles the cash balance
Contracting Officer's Representative, CMS Business Owner, and mailbox
On the 15th of the month
Monthly
OFM/AMG/DFOIC
C.5.11.2.3.2
Estimated Allowance for Uncollectible Accounts
Allowance Matrix
Calculates the allowance percentage of receivable
Contracting Officer's Representative, CMS Business Owner, and mailbox
HIGLAS Contractors: 5 business days after month end
HIGLAS Contractors: Monthly Non-HIGLAS Contractors: March and September
OFM/AMG/DFOIC
C.5.11.2.4
Letter-of-Credit Limitation
Letter of Credit Limitation Change Request
Written requests for changes to the monthly letter-of-credit limitation.
Contracting Officer's Representative and/or Designees
Consistent with frequency
As required
OFM / Financial Services Group (FSG)
C.5.11.3.2.5
Audit Plan
Audit Plan
The audit plan identifies each cost report selected for an audit (in-house or field.) The audit plan lists each provider’s name, provider #, cost reporting period, issues selected for audit, and an explanation as to why the provider was chosen for an audit.
Contracting Officer's Representative and/or Designees
Initial within 30 calendar days after the cutover date; thereafter within 30 calendar days prior to the annual period end
Annually
OFM/FSG
C.5.11.4.2
Applications for Extended Schedule
Extended Repayment Plan (ERS) Extension Report
In Excel format, this report identifies providers who have requested an ERS and identifies those requests that have been approved, denied, and pending.
Contracting Officer's Representative and/or Designees
Within 15 calendar days of quarter end
Quarterly
OFM / FSG / Division of Medicare Overpayments (DMO)
C.5.11.7.1
Unsolicited/Voluntary Refunds
Unsolicited/Voluntary Refund Check Summary Report
Describes a summary of the unsolicited/voluntary refund checks.
Contracting Officer's Representative and/or Designees
Upon Request
Upon Request
OFM / Program Integrity Group (PIG)
C.5.11.8.1
Administrative Freeze Payments
Provider Overpayment Referral Checklist
Describes summary of overpayment information for a Provider in bankruptcy.
Contracting Officer's Representative and/or Designees
Consistent with frequency
As required
OFM / AMG / DFO
C.5.11.8.2
Closed Bankruptcy Case
Quarterly Bankruptcy Tracking Report
Describes the status of the discharge of bankruptcy proceedings. Builds on the information contained in the summary of detailed underpayment and overpayment information for a Provider in bankruptcy.
Contracting Officer's Representative and/or Designees
Quarterly
As required
OFM / AMG / DFO
C.5.11.9.1
Accounts Receivable Trend Analyses
Accounts Receivable Trend Analysis Reports
Describes the results of accounts receivable trend analyses.
Contracting Officer's Representative and/or Designees
On or before January 22, April 22, July 22, and October 22. (The third and fourth quarter due dates may change due to the accelerated time periods. Medicare contractors will be notified of these changes by a Technical Direction Letter (TDL)
Quarterly
OFM/AMG/DFOIC
C.5.12.1
Development of Improper Payment Reduction Strategy (IPRS)
IPRS
Describes the operational plan for how the contractor will evaluate data and address program vulnerabilities throughout the year.

See PIM 100-08, Chapter 7.

Contracting Officer's Representative and/or Designees and in CMS ART
The Initial strategy is due after contract award no less than 30 calendar days prior to first claims cutover date even if there are multiple cutover dates. Thereafter the strategy is due no less than 45 calendar days prior to start of each option year. If a major revision is needed to the MRS, notify the COR and MR BFL to determine if a revised strategy is required. See PIM 100-08 Chapter 7.
Annually
OFM/Provider Compliance Group (PICG)/ Division of Medical Review and Education (DMRE)
C.5.12.1
Development of Improper Payment Reduction Strategy (IPRS)
Strategy Analysis Report (SAR)
An annual update to the IPRS that describes progress towards goals as defined in the strategy and any changes that need to be made to the strategy. See PIM 100-08, Chapter 7.
Contracting Officer's Representative and/or Designees and in CMS ART
The SAR is due within 14 calendar days after final cutover date and 7.5 months after option year starts.

Where the initial SAR and Option year strategy would be due within 60 calendar days of each other the contractor shall inform the Contracting Officer's Representative of this occurrence, to address on a case by case basis

Annually
OFM/PCG/DMRE
C.5.12.1.6.1
Defending MR Decisions at ALJ Hearings - Coordination
OMHA Contacts
Level 1 appeals contact information
Contracting Officer's Representative and Lynnsie.Doty@cms.hhs.gov
The contractor shall ensure that CMS has the most up-to-date contact information for Level 1 appeals in order to support the successful coordination of the appeals process with Levels 2, 3, and 4. The contractor shall provide updated contact information via email using the template provided under TDL-150507 if there are changes to any pertinent contact information (e.g., fax numbers, addresses, and telephone numbers). Send all emails to the CMS contact, Lynnsie Doty, at Lynnsie.Doty@cms.hhs.gov, and copy the Contracting Officer’s Representatives (CORs).
When contact information changes
CPC/MEAG/DAO
C.5.12.2.19
Monthly Reporting of Medical Review Savings
Medical Review Savings Report
Financial savings to the Trust Fund that result from performing Medical Review. Calculated as denials minus reversals. See PIM 100-8 Chapter 7.
CMS ART
Due the 20th day of every month
Monthly
OFM/PCG/DMRE
C.5.12.2.21
Medical Review/Prior Authorization
Prior Authorization of Certain OPD Services Activity Reporting
The Contractor will report all activities and metrics related to the prior authorization program for certain OPD services. The content and format of this report will be determined by CMS and shall be submitted to CMS ART
Contracting Officer's Representative, MR/PA BFL, and the OPD mailbox (OPD_PA@cms.hhs.gov)
Due on the 20th of each month
Monthly
CPI/PCG/DPMS
C.5.12.2.21
Medical Review/Prior Authorization
Prior Authorization of Certain OPD Services Activity Reporting
The Contractor will report all activities related to the prior authorization program for certain OPD services. The content and format of this report will be determined by CMS and shall be submitted to CMS ART
Contracting Officer's Representative, MR/PA BFL, and the OPD mailbox (OPD_PA@cms.hhs.gov)
November 30
Annually
CPI/PCG/DPMS
C.5.13.2
Support of Comprehensive Error Rate Testing
Comprehensive Error Rate Testing (CERT) Program: Medicare Administrative Contractor

Certification

MACs shall submit a certification that all required information has been completely and accurately entered on the CERT Claims Status website. The MAC's Certifying Official shall sign the certification and submit it to CMS via CMS ART.
Contracting Officer's Representative and/or Designees
October 15th
Annually
Office of Financial Management (OFM) / Payment Accuracy & Reporting Group (PARG)
C.5.14.2
Electronic Correspondence Referral System Status Inquiries
Number of ECRS request submitted to the BCRC
Provides the number of MSP prepay ECRS Requests by category (Inquiries and CWF Assistance Requests) sent to the BCRC each month.
Contracting Officer's Representative and/or Designees
Last business day of the following month
Monthly
OFM/FSG/ Division of Medicare Secondary Payer Operations (DMPO) - MSP Prepay
C.5.14.3
Identification and Adjudication of Medicare Secondary Payer Claims and Application of Benefits and Processing Formula
Number of MSP claims processed
Provides the number of MSP claims processed during the given month including the number of claims processed, rejected, adjusted and denied.
Contracting Officer's Representative and/or Designees
Last business day of the following month
Monthly
OFM/FSG/ Division of Medicare Secondary Payer Operations (DMPO) - MSP Prepay
C.5.14.3.3
Medicare Secondary Payer Claims Inquiries
The number of inquiries and documentation received and responded to.
The number of inquiries and documentation the Contractor responded to from insurers and other interested parties (e.g., attorneys and/or beneficiaries, etc.) on MSP billing requirements to assist with resolving claims inquiries accurately, timely, and responsively.
Contracting Officer's Representative and/or Designees
Last business day of the following month
Monthly
OFM/FSG/ Division of Medicare Secondary Payer Operations (DMPO) - MSP Prepay
C.5.14.4
Transfer of Documentation and Phone Calls to the Benefits Coordination and Recovery Center
Number of phone calls and documentation transferred to the BCRC
Number of phone calls and documentation transferred to the BCRC
Contracting Officer's Representative and/or Designees
Last business day of the following month
Monthly
OFM/FSG/ Division of Medicare Secondary Payer Operations (DMPO) - MSP Prepay
C.5.14.5
Medicare Secondary Payer Hospital Audits
Hospital Audit Report
Describes the results of hospital audits and reviews for Medicare Secondary Payer hospitals.
Contracting Officer's Representative and/or Designees
Within 30 calendar days after each hospital audit is completed
Annually
OFM/FSG/ Division of Medicare Secondary Payer Operations (DMPO) - MSP Prepay
C.5.14.6.1
Duplicate Primary Payments
Unsolicited/Voluntary MSP Posted Checks Status Report (identifying associated vs. not associated with a known debt) vs. NO ECRS needed but NO A/R has been established yet)
Provides a listing of all Posted Provider, Physician, or Other Supplier MSP Unsolicited/Voluntary Refund Checks (identifying each entry as (1) associated to a known debt vs. (2) NOT associated to a known debt and ECRS entry required) vs. NO ECRS needed but NO A/R has been established yet) received by the MAC Contractor.
Contracting Officer's Representative and/or Designees
Last business day of the following month
Monthly
OFM/FSG/Division of Medicare Secondary Payer Operations (DMPO) MSP Post-Pay
C.5.14.6.2
Inquiries Specific to Debt Collection Efforts for Providers, Physicians, and other Suppliers
MSP Pending Correspondence Report
Provides a listing of all pending MSP correspondence.
Contracting Officer's Representative and/or Designees
Last business day of the following month
Monthly
OFM/FSG/Division of Medicare Secondary Payer Operations (DMPO) - MSP Postpay
C.5.14.6.5
Misrouted Benefits Coordination and Recovery Center Medicare Secondary Payer Recovery Checks (Non-GHP checks) and/or Misrouted Commercial Repayment Center MSP Recovery Checks (GHP Checks)
Medicare Secondary Payer (MSP) Misrouted Recovery Checks (and Associated Correspondence) (Non-GHP = BCRC and GHP=CRC)
Provides a listing of all misrouted MSP - GHP or Non-GHP - checks either transferred to the BCRC for Non-GHP checks only; and/or transferred to the Commercial Repayment Center (CRC) for GHP checks only (broken down by where sent - BCRC or CRC).
Contracting Officer's Representative and/or Designees
Last business day of the following month
Monthly
OFM/FSG/Division of Medicare Secondary Payer Operations (DMPO) - MSP Postpay
C.5.14.6.6
Misrouted Benefits Coordination and Recovery Center MSP Recovery Correspondence (Non-GHP) and/or Misrouted Commercial Repayment Center MSP Recovery Correspondence (GHP)
Medicare Secondary Payer (MSP) Misrouted Recovery Correspondence (Non-GHP=BCRC and GHP=CRC)
Provides a listing of all misrouted MSP -GHP or Non-GHP -correspondence that was either transferred to the Medicare Secondary Payer Recovery Contractor (MSPRC) - Non-GHP correspondence only and/or either transferred to the Commercial Repayment Center (CRC) - GHP correspondence only (broken down by where sent - MSPRC or CRC).
Contracting Officer's Representative and/or Designees
Last business day of the following month
Monthly
OFM/FSG/Division of Medicare Secondary Payer Operations (DMPO) - MSP Postpay
C.5.15.2
Review of Comprehensive Outpatient Rehabilitation Facility Billing Records
Aberrant Billing Practices Notification
Immediate written notification whenever aberrant billing practices are discovered
Contracting Officer's Representative and/or Designees
Consistent with Frequency
As required
CMSO/SCG/DCCP
C.5.15.3
Review of Inpatient Rehabilitation Facilities and Critical Access Hospitals’ Rehabilitation Distinct Part Units (DPU)
Written Report of the Applicable Calculated Compliance Percentage
Written report of the applicable calculated compliance percentage attained by the IRF or a provider attempting to be classified as an IRF within the contractor's jurisdiction. The contractor must determine each IRF's applicable compliance percentage prior to the start of each IRF's next cost reporting period, and include the most current information for all IRFs within the contractor's jurisdiction in the written report.
Contracting Officer's Representative, CMS Business Owner, and the RO responsible for the geographic area where the IRF is located, and, if appropriate, to the appropriate ROs involved with the administration of the MAC contract.
On or before the 15th of each month
Monthly
CMM/ Chronic Care Policy Group (CCPG)/ Division of Institutional Post Acute Care (DIPC)
C.5.18.1
Education Materials
Rural Health Clinic (RHC) Education Materials
The Contractor is encouraged to use CMS-created national education materials when training RHCs.
Contracting Officer's Representative and/or Designees
Six weeks prior to the intended use of the education materials
As required
CMM / MCMG/ DMPM
C.5.19.1
Education Materials
Federally Qualified Health Center Education Materials
The Contractor is encouraged to use CMS-created national education materials when training FQHCs.
Contracting Officer's Representative and/or Designees
Six weeks prior to the intended use of the education materials
As required
CMM / MCMG/ DMPM
C.5.23.1
Post-Award Meeting
Post-Award Meeting Minutes
Describes the results of the Post-Award meeting conducted.
Contracting Officer's Representative and/or Designees
Within 3 business days of the Post-Award meeting
Once
CMM/MCMG
C.5.23.2
Project Management Plan -Implementation Deliverable
Project Management Plan
Describes the plan for overall management of the program.
Contracting Officer's Representative and/or Designees
Initial within 30 business days after contract award, updates within 15 calendar days after quarter end
Quarterly
CMM/MCMG
C.5.23.4
Monthly Status Report (MSR)
Monthly Status Report (MSR)
Describes the monthly status of the program through a report. This deliverable is comprised of both the narrative Monthly Status Report Word document and the Monthly Status Report Excel (MSRE) document. Please include in the file name the jurisdiction number, the MAC Name, and the month for which you are reporting.
Contracting Officer's Representative and/or Designees
Within 20 calendar days after month end.
Monthly
CMM/MCMG
C.5.23.5
Ad Hoc Reporting
Estimate At Completion (EAC) Report
Provides monthly estimate of total contract costs to be expended, by SLIN, and includes the MAC Project Manager’s cost estimation of all operational changes/impacts throughout the contract year. MAC is to use the EAC Report spreadsheet template and accompanying instructions provided by the Contracting Officer at contract modification.
Contracting Officer, Contracting Specialist, COR, and designees as determined by COR.
Monthly EAC Reports are due into CMS ART no later than 30 calendar days after the end of the reporting month. In addition to submittal to CMS ARTS, the MAC will send an electronic copy to the CO, CS, COR and others as directed by the COR.
Monthly
OAGM/MCMG
C.5.23.6
Voucher/Financial Management System
Monthly Cost Report
Submit a monthly cost report to the CMS ART System in accordance with the work breakdown structure (WBS) schedule instructions. In addition, submit a statement to the Contracting Officer's Representative via the deliverable mailbox indicating that this action has been completed.
Contracting Officer's Representative and/or Designees
Monthly cost reports are due into CMS ART no later than 30 calendar days after the end of the reporting month
Monthly
CMM/MCMG
C.5.23.6
Voucher/Financial Management System
Final Estimated Cost Proposal
The contractor shall submit the final estimated cost proposal into CMS ART once contract estimated costs have been negotiated, and a subsequent modification has been executed by the CO. For new contract awards, CMS will notify the contractors when CMS ART is available for final estimated cost proposal entry and the date that submission is due. With respect to change orders, once the change order has been definitized, the contractor shall submit the final estimated cost proposal into CMS ART. In addition, the contractor shall submit a statement to the Contracting Officer's Representative via the deliverable mailbox indicating that this action has been completed.
Contracting Officer's Representative and/or Designees
For new contract awards, CMS will notify contractors when CMS ART is available for final estimated cost proposal entry and the date that submission is due. The final estimated cost proposal shall be entered into CMS ART no later than 5 business days after the contract modification has been executed. With respect to change orders, once change order has been definitized, the contractor shall submit the final estimated cost proposal into CMS ART. In addition, the contractor shall submit a statement to the Contracting Officer's Representative via the deliverable mailbox indicating that this action has been completed.
As required
CMM/MCMG
C.5.23.11
Operational Productivity Report (OPR)
Operational Productivity Report (OPR)
The Contractor shall prepare and upload the OPR into the CMS-ART system. An electronic version in excel form should also be sent via email to the Contracting Officer's Representative (COR) and Contracting Officer (CO)/Contracting Specialist (CS) on the contract.
Contracting Officer's Representative, Contracting Officer/Contracting Specialist, and/or Designees
Monthly OPRs are due into CMS-ART no later than 30 calendar days after the end of the reporting month
Monthly
CM/MCMG
C.5.26
Support of RAC Program Operations
Updated RAC Joint Operating Agreement
The updated JOA defines any updates to the roles and responsibilities of a mutually agreed upon methods to work with and support CMS’ mission with the RAC.
Contracting Officer's Representative and/or Designees
Consistent with frequency updates: By January 15th, April 15th, July 15th, and October 15th.
First Year Quarterly; Subsequent Years Annually
OAGM
C.6.1
Joint Operating Agreements
Initial Joint Operating Agreement (JOA)
The initial JOA defines roles and responsibilities of a mutually agreed upon methods to work with and support CMS’ mission—with each of the following parties: Unified Program Integrity Contractors (UPICs); Qualified Independent Contractors (QICs); Administrative Qualified Independent Contractors (AdQICs); Quality Improvement Organizations (QIOs); Recovery Audit Contractors (RACs); Cost Report Appeals Support Contractor; Benefits Recovery and Coordination Center (BCRC); Commercial Repayment Center (CRC); Call Center Operations (CCO); Virtual Data Center (VDC); and Supplemental Medical Review Contractor (SMRC).
Contracting Officer's Representative and/or Designees
30 calendar days prior to cutover
Once
Office of Acquisitions and Grants Management (OAGM)
C.6.1
Joint Operating Agreements
Updated Joint Operating Agreement
The updated JOA defines any updates to the roles and responsibilities of a mutually agreed upon methods to work with and support CMS’ mission—with each of the following parties: UPICs; Cost Report Appeals Support Contractor; QIOs; VDC; CCO; BCRC; CRC; and SMRC.
Contracting Officer's Representative and/or Designees
Consistent with frequency updates: By January 15th, April 15th, July 15th, and October 15th.
First Year Quarterly; Subsequent Years Semiannually
OAGM
C.6.1.1.1
Referrals to Quality Improvement Organization
Quality Improvement Organization Referrals
Describes the referrals to the QIO for quality of health care determinations.
Contracting Officer's Representative and/or Designees
Consistent with frequency
Every 6 months due January 1 & July 1
Center for Clinical Standards and Quality (CCSQ)
C.6.1.2
Joint Operating Agreement: Qualified Independent Contractor (QIC) and Administrative Qualified Independent Contractor (AdQIC)
Updated Joint Operating Agreement
The updated JOA defines any updates to the roles and responsibilities of a mutually agreed upon methods to work with and support CMS’ mission—with each of the following parties: QICs, and the AdQIC.
Contracting Officer's Representative and/or Designees
Consistent with frequency updates: on January 1st (or a mutually agreeably time between the respective parties).
Annual basis or more frequently if significant changes warrant an interim update.
OAGM
C.6.2.1
State Agencies Responsible for Licensing Institutional Providers (e.g., Survey and Certification, Licensing Authorities)
Health Insurance Benefits Agreement, Provider-Based Determination, or Other Institutional Provider Information
The Health Insurance Benefits Agreement, Provider-Based Determination, or Other Institutional Provider Information is provided in the format requested to state agencies with a copy to CMS.
Contracting Officer's Representative and/or Designees
Consistent with frequency
As required
CMSO/SCG/DACS

06/02/2020