J_7_Continuous_Maintenance_Planning_897_11_001_002_FY_22_06_16_21.pdf

PDF 1 MB Posted

Attached to
Pacific Northwest Carriers CVN IDIQ Maintenance/Repair
Solicitation number
N00024-24-R-4110
Issued by

About this file

The provided document is a Proposed Standard Work Template for a federal contract opportunity. It outlines the scope of work for two distinct task areas: Continuous Maintenance Planning and Program Management for Continuous Maintenance Availabilities.

The Continuous Maintenance Planning task requires the contractor to prepare 170 work items and 9 Continuous Maintenance/Windows of Opportunity work orders in accordance with the Joint Fleet Maintenance Manual. The work includes developing detailed cost estimates, conducting contractor ship checks, researching material availability, and providing quality planning services. The Program Management task requires the contractor to provide overall program management support for 5,000 man-days of continuous maintenance execution effort, including integrating repair activities, managing subcontractors, and providing cost reporting and technical document services. The contract opportunity is for maintenance, repair, and modernization efforts for CVN 68 Class and CVN 78 Class Aircraft Carriers home-ported in and visiting the Pacific Northwest region, and will be awarded as a competitive IDIQ contract with a 5-year base period and single option year.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROPOSED STANDARD WORK TEMPLATE

SHIP: N/A ITEM NO. 897-11-001

COAR: N/A PCN: NONE

SWT FILE NO: 897-11-001 CMP: N/A

REVISED: 16 JUNE 2021 PLANNER: N/A

1. SCOPE:

1.1 Title: Continuous Maintenance Planning; provide

1.2 Location of Work:

1.2.1 Not Applicable

1.3 Identification:

1.3.1 Not Applicable

2. REFERENCES:

2.1 Joint Fleet Maintenance Manual, Volume 7, Chapter 4

3. REQUIREMENTS:

3.1 Provide planning services to accomplish preparation of 170 work items and 9 CM/WOOs in accordance with 2.1 to accomplish the following:

3.1.1 Preparation of work items will be in accordance with Appendix 4-E of 2.1, utilizing the Navy Maintenance Database (NMD) program.

3.1.2 Preparation of detailed cost estimates to the paragraph and trade level for prepared work items utilizing NMDr.

3.1.3 Conduct contractor ship checks of Automated Work Requests (AWRs) for verification of work to be accomplished.

3.1.4 Research material availability and coordinate Long Lead Time Material and material requirements in support of planned work.

3.1.5 Provide quality planning services to support the identification of check points and required reports in work items, development of Test Inspection Plans (TIPs), schedules, and development of Process Control Procedures (PCPs).

Attachment J-7 N00024-24-R-4110 Proposed Standard Work Template 897-11

3.1.6 Provide Technical Document services in support of work item development.

3.1.6.1 The Technical Documents shall consist of technical drawings and manuals, general technical information including Military Specifications, Industry Standards, applicable Navy and Department of Defense (DoD) directives, Ship’s Information Booklets, Planned/Preventive Maintenance System (PMS), Engineering Operational Sequencing System (EOSS), and other documents.

4. NOTES:

4.1 Continuous Maintenance includes the following types of availabilities:

4.1.1 Schedule Continuous Maintenance Availabilities (CMAV)

4.1.2 Emergent Maintenance (EM)

4.1.3 Unscheduled Continuous Maintenance Availabilities - Windows of Opportunities

(WOO)

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

5.1 .1 None

5.2 PUSH MATERIAL:

5.2.1 None

5.3 KITTED MATERIAL:

5.3.1 None

Attachment J-7 N00024-24-R-4110

PROPOSED STANDARD WORK TEMPLATE (2)

SHIP: N/A ITEM NO. 897-11-002

COAR: N/A PCN: NONE

SWT FILE NO: 897-11-002 CMP: N/A

REVISED: 16 JUNE 2021 PLANNER: N/A

1. SCOPE:

1.1 Title: Program Management for Continuous Maintenance Availabilities; provide

1.2 Location of Work:

1.2.1 Not Applicable

1.3 Identification:

1.3.1 Not Applicable

2 REFERENCES:

2.1 Standard Items

3 REQUIREMENTS:

3.1 Provide overall Program Management, using 2.1 for guidance, to support 5,000 mandays of execution production effort of continuous maintenance and perform the following tasking:

3.1.1 Provide principal point of contact for all Continuous Maintenance

3.1.2 Integrate repair activities to include but not limited to: sub-contractors, AIT’s, I-level, Ship’s Force, etc.

3.1.2.1 Organize and lead daily Production Meetings

3.1.3 Provide program management support for identification and implementation of growth and/or new work contract changes.

3.1.4 Attend meetings such as monthly Planning Board for Maintenance (PB4M) meetings, planning progress meetings, and government review meetings.

Attachment J-7 N00024-24-R-4110

3.1.5 Develop, submit, and negotiate Cost proposals

3.1.6 Perform contract administration functions to include at a minimum contract modification processing, invoicing, and preparations for Award Fee Boards.

3.1.7 Perform subcontractor management to include placement of purchase orders for services and subsequent management of the purchased effort.

3.1.8 Provide cost reporting.

3.1.9 Provide Technical Document Services in support of authorized work under the contract.

3.1.9.1 The Technical Documents shall consist of technical drawings and manuals, general technical information including Military Specifications, Industry Standards, applicable Navy and Department of Defense (DoD) directives, Ship’s Information Booklets, Planned/Preventive Maintenance System (PMS), Engineering Operational Sequencing System (EOSS), and other documents.

4 NOTES:

4.1 Continuous Maintenance includes the following types of availabilities:

4.1.1 Schedule Continuous Maintenance Availabilities (CMAV)

4.1.2 Emergent Maintenance (EM)

4.1.3 Unscheduled Continuous Maintenance Availabilities - Windows of

Opportunities (WOO)

4.2 Execution effort is based on expected production man-days for the contract. This initial value is determined based on expected funding levels and historical data for emergent repairs.

5 GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

5.1 .1 None

5.2 PUSH MATERIAL:

5.2.1 None

5.3 KITTED MATERIAL:

Attachment J-7 N00024-23-R-4107

5.3.1 None

Attachment J-7 N00024-24-R-4110