J-5 WORK PACKAGE REVIEW SUMMARY SHEET.pdf

PDF 453 KB Posted

Attached to
USNS MEDGAR EVERS ( T-AKE 13) ROH/DD
Solicitation number
N3220526R6120
Issued by

About this file

This is a Work Package Review Summary Sheet for USNS Medgar Evers, documenting a Regularized Overhaul/Depot (ROH/DD) availability scheduled for March 1 – July 28, 2027. The review was conducted on July 14, 2026, and assessed 153 work items comprising 386 Government Furnished Material (GFM) line items.

The summary identifies significant procurement challenges impacting project execution. A substantial number of work items require Material of Record (MOR) submissions and final solicitation pricing from contracting before purchase requisitions can be created, with examples including ship's whistle replacement components (WI 0103), propulsion motor pedestal bearing inspections (WI 0207), hose replacements (WI 0552), and fixed gas firefighting system components (WI 0565D). Several items show "awaiting program approval" status, including MHE battery chargers (WI 0308) and sea chest marine growth prevention chloropac cells (WI 0963). Certain GFM items have been received and are in the MSC warehouse, while others remain pending, with estimated delivery dates ranging through February 2027. Additionally, multiple work items related to sea valve overhauls (WI 0956), rudder and stern frame examinations (WI 0954), and CSI propeller shaft inspections (WI 0903) reference specific Small Purchase Solicitation (SPS) contract numbers with Required Delivery Dates (RDD) of January 27, 2027, and show "no update on award" status. Some items remain listed in work specifications with no MOR submitted. The review was conducted by Kevin Cabrera and noted by Port Engineer Joseph Fader.

View the file

Other files

File Type Posted
J-7 MSC Ship Repair Facility Survey.docx DOCX document
J-12 Past Perf Data.docx DOCX document
J-8-RFC(2022.12.28).docx DOCX document
J-3-Cat-B(2023.11.03).xlsx XLSX spreadsheet
Solicitation_N3220526R6120_RFP_MEV.pdf PDF
J-9-DisclosureofLobbyingActivities(1997.07).pdf PDF
J-13-PastPerfQuestionaire(2022.11.22).docx DOCX document
J-14-TechnicalNDA(2023.07.07).docx DOCX document
J-10-InterportDifferential(2026.04.10).docx DOCX document
J-2-Cat-A(2022.11 (version 1).xlsx XLSX spreadsheet
J-11 MSC Dry Dock Eval Form.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORK PACKAGE REVIEW SUMMARY SHEET

SHIPS NAME: USNS MEDGAR EVERS

AVAILABILITY TYPE: ROH/DD

AVAILABILITY DATES: 03/01/27 – 07/28/27

DATE REVIEW WAS CONDUCTED: 7/14/2026

NUMBER OF WORK ITEMS REVIEWED: 153

NUMBER OF GFM LINE ITEMS REVIEWED: 386

DESCREPANCIES IN WORK ITEM ORDER:

WI # WORK ITEM DESCRIPTION NOTE 4.0 GFM QTY GFM STATUS

0103 SHIPS WHISTLE

REPLACEMENT KPH-90 ELECTRIC PISTON HORN 2

PPE HAS SUBMITTED MOR-26-

003 ON 07/28/2025 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

0103 SHIPS WHISTLE

REPLACEMENT MOTOR STARTER 2

PPE HAS SUBMITTED MOR-26-

003 ON 07/28/2025 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

0103 SHIPS WHISTLE

REPLACEMENT M-522 SOUN D AND LIGHT CONTROL 1

PPE HAS SUBMITTED MOR-26-

003 ON 07/28/2025 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

0103 SHIPS WHISTLE

REPLACEMENT M-314 MILITARTY PUSHBUTTON,HORN MOMENTARY 2

PPE HAS SUBMITTED MOR-26-

003 ON 07/28/2025 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

LINER ZCA 35/315,BEARING SHELL IN HALVES E-ZCA

35 315 H7 MACHINED 1

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

TYPE 20 RIGID SEAL35/315 1

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

LINER ZCQ 28/300, BEARING SHELLS IN HALVES.

EZCQ 28 300 H7 MACHINED 1

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

TYPE 20 RIGID SEAL 28/315 (ALUMINUM) 1

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

RADIAL SHAFT SEAL 553 X 603 X 22 1

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

INSPECTION (5YR)

(SCSI)

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

RADIAL SHAFT SEAL 600 X 650 X 22 1

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

RIGID SEAL SC TYPE 22 IP 55 71-630 1

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

RIGID SEAL SC TYPE 22 IP 55 71-630 (OUTER SEAL) 1

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

FIXED OIL RING FOR SC 71-630 2

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

RIGID SEAL TYPE 22 IP 55 SC 63-600 1

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

RIGID SEAL TYPE 22 IP 55 SC 63-600 1

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

FIXED OIL RING SC 63/600 2

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

PIPING FOR HYDROSTATIC JACKING 37AL-05 X 730 1

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

HYDROSTATIC HOSE FC321-5350 1

PPE HAS SUBMITTED MOR-26-

101 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

CANNOT BE CREATED, PID

N32205-26-SIMACQ-DSM-PM6-

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

LINER ZCA 35/315 1

RECEIVED AT MSC

WAREHOUSE

PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

LINER ZCQ 28/300 NDE BEARING SHELL SET 1

RECEIVED AT MSC

WAREHOUSE

0207 PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

RING, SEALING 1

RECEIVED AT MSC

WAREHOUSE

0207 PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

RADIAL SHAFT SEAL 600 X 650 X 22 1

RECEIVED AT MSC

WAREHOUSE

0207 PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

DE BEARING SEALS 1

RECEIVED AT MSC

WAREHOUSE

0207 PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

NDE BEARING SEALS 1

RECEIVED AT MSC

WAREHOUSE

0207 PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

RIGID SEAL SC TYPE 22 IP 55 71-630 1

RECEIVED AT MSC

WAREHOUSE

0207 PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

RIGID SEAL SC TYPE 22 IP 55 71-630 (OUTER SEAL) 1

RECEIVED AT MSC

WAREHOUSE

0207 PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

FIXED OIL RING FOR SC 71-630 2

RECEIVED AT MSC

WAREHOUSE

0207 PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

RIGID SEAL TYPE 22 IP 55 SC 63-600 1

RECEIVED AT MSC

WAREHOUSE

0207 PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

RIGID SEAL TYPE 22 IP 55 SC 63-600 1

RECEIVED AT MSC

WAREHOUSE

0207 PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

FIXED OIL RING SC 63/600 2

RECEIVED AT MSC

WAREHOUSE

0207 PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

PIPING FOR HYDROSTATIC JACKING 37AL-05 X 730 1

RECEIVED AT MSC

WAREHOUSE

0207 PROPULSION

MOTOR PEDESTAL

BEARING

INSPECTION (5YR)

(SCSI)

HYDROSTATIC HOSE FC321-5350 1

RECEIVED AT MSC

WAREHOUSE

THRUST AND

LINESHAFT

BEARING

RING, SEALING 2

PPE HAS SUBMITTED MOR-26-

102 ON 04/21/2026 BUT UNTIL

INSPECTION (5 YR)

(SCSI)

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED "

THRUST AND

LINESHAFT

BEARING

INSPECTION (5 YR)

(SCSI)

SET OF THRUST PADS 2

PPE HAS SUBMITTED MOR-26-

102 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED "

MHE BATTERY

CHARGER

REPLACEMENT

CHARGER,BATTERY 12

PPE HAS SUBMITTED MOR-26-

103 ON 04/30/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS - NSN

MHE BATTERY

CHARGER

REPLACEMENT

CHARGER,BATTERY 12

PPE HAS SUBMITTED MOR-26-

103 ON 04/21/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS - SPS

0410 SAFER CCTV

INSTALL

WIRE ROPE ISOLATOR, WR16 SERIES, THRU-

BOLT TYPE 4 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

ABS 1YPE APPROVED, STEP

DOWN ISOLATION TRANSFORMER, UPS INPUT, 1PH

5KVA 240X480V-120/240V 60HZ CU

2 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

CABLE, LSDSGU-9, OR SIMILAR LOW SMOKE

TYPE, ZERO HALOGEN JACKET 28 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

CABLE, LSTSGU-9, OR

SIMILAR LOW SMOKE TYPE, ZERO HALOGEN JACKET 67 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

CABLE, LS3SJ-14, OR SIMILAR LOW SMOKE

TYPE, ZERO HALOGEN JACKET 322 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

INSTALL BREAKER, 15A FD35K TYPE 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL BREAKER, 15A, HFD TYPE 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

NEMA L6-20R FEMALE SOCKET,

20A 250VAC, COND. 10-16AWG, CABLE OD 0.385" TO O

780"

1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

IEC C320-C14 MALE PLUG, 10A 250VAC, COND.

UP TO 14AWG, MAX CABLE OD 9.2MM 10 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

IEC C320-C 13 LOCKING FEMALE CONNECTOR, 1OA

250VAC, COND. <1OAWG, CABLE OD <1OMM 10 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL PLUGLOCK INSERT, FOR C13/14 POWER PLUG 10 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

SMART-UPS ON-LINE, 3KVA, RACKMOUNT 2U, 208V,

2X L6-20R+ 1X L6-30R NEMA OUTLETS,

NETWORK CARD, EXTENDED RUNTIME

2 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL SMART-UPS SRT 96V 3KVA RM BATTERY PACK 2 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

APC NETSHELTER BASIC RACK PDU, 1U, 30A, 208V,

10 C13 OUTLETS 2 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL POWER CORD - 4FT, C14 TO LOCKING C13, 1OA 4 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL POWER CORD - 2FT, C14 TO LOCKING C13, 1OA 4 LISTED IN WORK SPEC, NO

INSTALL POWER CORD - 6FT, C14 TO LOCKING C13, 1OA 2 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

LSC60S-4, CAT-6A

CABLE, FOIL SHIELDED, BRAIDED SHIELD 240 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL LSCSOS-4, CAT-SE CABLE, FOIL SHIELDED 1295 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

RJ-45 PASSTHROUGH CONNECTOR, SHIELDED,

CAT5E/6/6A, MODULAR 67 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL PUNCHDOWN KEYSTONE JACK, SHIELDED, CATSE 55 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

DOUBLE SHIELDED INDUSTRIAL ETHERNET PATCH

CABLE, 5FT, CAT SE 55 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

SCREW COVER ENCLOSURE, 18" W X 18" H X

5" D, STEEL 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL CABLE GLAND, FOR O.D. 0.170-0.450 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

SCREEN COVER, 60%

LIGHT TRANSMITTENCE, FOR 15.6-16 9" SCREEN 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL LOUVER PLATE KIT, ANSI 61, MILD STEEL 2 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL SCREW, BUTTON HD: 8-32 UNC 1 /2 LNG 220 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL HEXNUT: 8-32, SLFLKG (NYLON INSERT) 220 LISTED IN WORK SPEC, NO

INSTALL WASHER, #8, OVERSIZED 220 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

24U RACK, 32" DEEP, TAA

COMPLIANT, SEISMIC RATED 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

VENTED FRONT DOOR, FOR 24RU

WRK RACKS, 64% OPEN 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL VENTED TOP, FOR 24RU WRK RACKS, 64% OPEN 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL HOLDDOWN BRACKETS, 24RU RACK 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL DOME CAMERA, SINGLE SENSOR, POE 10 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL PANORAMIC CAMERA, SINGLE SENSOR, POE 45 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

SERVER, NETWORK VIDEO RECORDER, WITH RAIDS

STORAGE, 12X 20TB HDD 2 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

20 PORT SWITCH, 16 X 10/100/1000T POE+ PORTS AND

4 X 100/1000X SFP PORTS, SINGLE PSU 2 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

28 PORT SWITCH, 24 X 10/100/1000T POE+ PORTS

AND 4 X 100/1000X SFP PORTS 5 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

SLIM 2U, WALL-MOUNT RACK, SWITCH ENCLOSURE

CABINET 5 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

15.6" ALL-IN-

ONE, WITH POE, WITH 2W INTERNAL SPEAKER,

WIN 11 IOT

1 LISTED IN WORK SPEC, NO

INSTALL

NETDIRECTOR CONSOLE, 8-PORT 1U RACK-MOUNT,

HDMI KVM SWITCH WITH 17 IN. LCD, DUAL RAIL,

TAA

1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

WAVE PROFESSIONAL LICENSE. ENABLES FORTY-

EIGHT (48) IP STREAM RECORDING 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

WAVE PROFESSIONAL LICENSE, ENABLES FIVE

(5) IP STREAM RECORDING 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

WAVE PROFESSIONAL LICENSE, ENABLES ONE (1) IP

STREAM RECORDING 2 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

PATCH PANEL, 110 PUNCHDOWN RJ45

ETHERNET, SHIELDED, RACK MOUNT, 1U 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL POE++ INJECTOR, 60 WATT 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

TM2000B NETWORK TIME SERVER,

NTP+PTP, IEEE1588, OXCO REF CLOCK 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL

SINGLE RACK MOUNT KIT,

FOR TIMESERVER TM2000 SERIES 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

0410 SAFER CCTV

INSTALL 10 AWG BONDING KIT 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

ANNUAL

INSPECTION OF

MANUALLY

OPERATED ALARMS

LOUDSPEAKER,PERMANENT MAGNET 2

RECEIVED AT MSC

WAREHOUSE

ANNUAL

INSPECTION OF

MANUALLY

OPERATED ALARMS

GENERAL ALARM BELL 5

ECHO DEPTH

SOUNDER

REPLACEMENT

IMO ECHO SOUNDER DISPLAY UNIT 1

LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE -

BEING PROVIDED BY N6?

ECHO DEPTH

SOUNDER

REPLACEMENT

IMO ECHO SOUNDER TRANSCEIVER UNIT 1

LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE -

BEING PROVIDED BY N6?

ECHO DEPTH

SOUNDER

REPLACEMENT

MATCHING BOX MB502 F/50B-6B 1

LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE -

BEING PROVIDED BY N6?

ECHO DEPTH

SOUNDER

REPLACEMENT

CHEST W/THT 50B6B STEEL HULL 1

LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE -

BEING PROVIDED BY N6?

ECHO DEPTH

SOUNDER

REPLACEMENT

TRANSDUCER W/ 30M CABLE 1

LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE -

BEING PROVIDED BY N6?

ECHO DEPTH

SOUNDER

REPLACEMENT

REMOTE DISPLAY UNIT WITH FLUSH MOUNT 3

LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE -

BEING PROVIDED BY N6?

REPLACE

CHLORAPAC

GENERATING TUBES

CHLOROPAC GENERATING CELLS

RECEIVED AT MSC

EDG STOP

SOLENOID VALVE

VALVE 1-1/2" BRONZE NO; 480/60, 480/60, E33GRV26-

OF1, E33GR26F1-DCVO

PPE HAS SUBMITTED MOR-26-

105 ON 04/21/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

CANNOT BE CREATED

LTFW COOLER

CLEANING AND

INSPECTION (2.5 YR)

OEM GASKETS EPDM TYPE; 1059 353 EA COOLER 1059

3/7/2025 (EMAIL) MATERIAL

ONBOARD PER PPE

BOW THRUSTER

LUBE OIL

FILTERING MODS

MODIFIED TT2200 BOW THRUSTER 1 LISTED IN WORK SPEC, NO

BOW THRUSTER

LUBE OIL

FILTERING MODS

CJC FILTRATION UNIT 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

BOW THRUSTER

LUBE OIL

FILTERING MODS

SEAL TANK 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

CARGO CRANE

CASUALTY MODE

MODIFICATIONS

CASUALTY HYDRAULIC POWER UNIT (CHPU)

HYDRAULIC POER UNIT 1

N2900261554082 -

RDD - 1/27/2027

NO UPDATE ON AWARD

MOR-26-107 ; ERP 1301378630

CARGO CRANE

CASUALTY MODE

MODIFICATIONS

IN-LINE CHECK VALVE BODY AND VALVE 4

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

1" QUICK DISCONNECT NIPPLE 4

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

1/2" QUICK DISCONNECT NIPPLE 4

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

SAE 1-1/2" CD62 FLANGE TO 1-1/2" NPTF 4

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

NPT PIPE REDUCER BUSHING 4

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

1/2" PIPE NIPPLE 4

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

1" PIPE NIPPLE 4

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

HHCS 5/8-11NC X 5.5 LG 16

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

LOCK WASHER 5/8 DIA 16

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

RIGHT ANGLE TEE REDUCER 1" TO 3/4" 4

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

1" TO 3/4" PIPE REDUCER 4

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

MALE CONNECTOR 4

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

MALE ELBOW 4

N2900261554082 -

RDD - 1/27/2027

CASUALTY MODE

MODIFICATIONS

HOSE ASSEMBLY 3/4" ID X 24" LG 4

N2900261554082 -

RDD - 1/27/2027

LTFW COOLER

OUTLET PIPING

MODIFICATION

BELZONA LTFW COOLER SW OUTLET PIPE WRAP KIT 1

MATERIAL IS CONSIDERED

HAZMAT. MSC WILL

ARRANGE TO PICK UP THE

MATERIAL FROM

CONTRACTOR FACILITY ONCE

READY. MSC

TRANSPORTATION COMPANY

IS REQUIRED TO CERTIFY THE

HAZMAT BELZONA ST HERO

REPAIR KIT, P/N: STPRK-1S,

PRICE: 2967.25

CHLOROPAC

CONTROL AND

POWER SUPPLY

PANEL

CONSOLIDATION

RELOCATION

POWER SUPPLY CONTROLLER 1

PPE HAS SUBMITTED MOR-26-

111 ON 04/23/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

CHLOROPAC

CONTROL AND

POWER SUPPLY

PANEL

HMI - PROGRAMMED 1

PPE HAS SUBMITTED MOR-26-

111 ON 04/23/2026 BUT UNTIL

PROVIDED THE FINAL

CONSOLIDATION

RELOCATION

SOLICITATION PRICING A PR

CANNOT BE CREATED

MAIN DIESEL

GENERATOR

PEDESTAL BEARING

INSPECTION (5 YR)

DE BEARING SHELL SET 4

PPE HAS SUBMITTED MOR-26-

108 ON 04/22/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

MAIN DIESEL

GENERATOR

PEDESTAL BEARING

INSPECTION (5 YR)

DE BEARING SEALS 4

PPE HAS SUBMITTED MOR-26-

108 ON 04/22/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

MAIN DIESEL

GENERATOR

PEDESTAL BEARING

INSPECTION (5 YR)

NDE BEARING SHELL SET 4

PPE HAS SUBMITTED MOR-26-

108 ON 04/22/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

MAIN DIESEL

GENERATOR

PEDESTAL BEARING

INSPECTION (5 YR)

NDE BEARING SEALS 4

PPE HAS SUBMITTED MOR-26-

108 ON 04/22/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

MAIN DIESEL

GENERATOR

PEDESTAL BEARING

INSPECTION (5 YR)

LINER ZCA 35/315 3

RECEIVED AT MSC

WAREHOUSE

MAIN DIESEL

GENERATOR

PEDESTAL BEARING

INSPECTION (5 YR)

LINER ZCQ 28/300 NDE BEARING SHELL SET 3

MAIN DIESEL

GENERATOR

PEDESTAL BEARING

INSPECTION (5 YR)

DE BEARING SEALS 4

RECEIVED AT MSC

WAREHOUSE

MAIN DIESEL

GENERATOR

PEDESTAL BEARING

INSPECTION (5 YR)

LINER ZCQ 28/300 NDE BEARING SHELL SET 1

RECEIVED AT MSC

WAREHOUSE

MAIN DIESEL

GENERATOR

PEDESTAL BEARING

INSPECTION (5 YR)

NDE BEARING SEALS 4

RECEIVED AT MSC

WAREHOUSE

MAIN DIESEL

GENERATOR

PEDESTAL BEARING

INSPECTION (5 YR)

DE BEARING SHELL SET 1

HOSE

REPLACEMENT (5

YR)

AFTER COOLER GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

AFTER COOLER GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

STARTING AIR GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

HOSE

REPLACEMENT (5

YR)

TURBO WATER GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

STARTING AIR GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

STARTING AIR GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

STARTING AIR GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

STARTING AIR GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

FUEL FILTER GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 2

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

REPLACEMENT (5

YR)

LUBRICATION GROUP HOSE ASSEMBLY 2

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

WATER GROUP FLEX CONNECTION 2

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

WATER GROUP FLEX CONNECTION 2

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

JACKET WATER HEATER HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

JACKET WATER HEATER HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

JACKET WATER HEATER HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

REPLACEMENT (5

YR)

JACKET WATER HEATER HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

AIR CLEANER GROUP HOSE ASSEMBLY 2

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

AIR CLEANER GROUP HOSE ASSEMBLY 2

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

FUEL FILTER GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

FUEL FILTER GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

FUEL SYSTEM HOSE ASSEMBLY 2

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

REPLACEMENT (5

YR)

FUEL SYSTEM HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

HOSE

REPLACEMENT (5

YR)

TURBO WATER GROUP HOSE ASSEMBLY 1

PPE HAS SUBMITTED MOR-26-

120 WI 552 ON 06/18/2026 BUT

UNTIL CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED

0565D

FIXED GAS

FIREFIGHTING

SYSTEM

INSPECTION AND

TEST

DISCHARGE HOSE 2"X31"(USE W/200-

395#CYLINDERS) 6

PPE HAS SUBMITTED MOR-26-

121 ON 06/25/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED;

PID: N32205-26-SIMACQ-DSM-

PM6-0336

0565D

FIXED GAS

FIREFIGHTING

SYSTEM

INSPECTION AND

TEST

HOSE DISCHARGE 1 1/2 INCH X 24 INCHFLEXIBLE 4

PPE HAS SUBMITTED MOR-26-

121 ON 06/25/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED;

PID: N32205-26-SIMACQ-DSM-

PM6-0336

0565D

FIXED GAS

FIREFIGHTING

SYSTEM

INSPECTION AND

TEST

3" S/S FLEX HOSE 37

PPE HAS SUBMITTED MOR-26-

121 ON 06/25/2026 BUT UNTIL

CONTRACTING HAS

PROVIDED THE FINAL

SOLICITATION PRICING A PR

CANNOT BE CREATED;

PID: N32205-26-SIMACQ-DSM-

PM6-0336

0903 CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

O-RING SEAL 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS

0903 CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

O-RING SEAL 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS

0903 CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

O-RING SEAL 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

COMPAC SEMI-FINISHED BEARING 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

KEY SET DWG F100168KY5 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

CAPSCREW, FLAT SOCKET HEAD 15

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

BULKHEAD SEAL OVERHAUL KIT 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

BEARING RETAINER T-AKE CLASS 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

1/8" GASKET STERN TUBE MOUNTING ADAPTOR 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

1/8" GREEN TAKE STERN TUBE SEAL MOUNTING

RING 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

JOINT 560 MOD 553 ND 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

ADHESIVE TAPE 50MM 4

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

VINYL TAPE, 1137081 9

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

BAILING SEAL W2T387640 6

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

PRESSURE TAPE W2T93058 3

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

SILVER BAND - 76" LONG W3T105 3

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

BRUSH W2T387820 12

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

STAINLESS STEEL HOUSING STRAP 9

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

O-RING 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

RING, COPPER SEALING 2

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

O-RING WITH VULCANIZED JOINT 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

O-RING 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

O-RING 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

HEXAGON HEAD SCREW 12

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

LOCKING WASHER M24 12

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

SCREW, HEX SOCKET HEAD CAP 12

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

O-RING SEAL 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

O-RING SEAL 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

O-RING SEAL 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

HCS M10X40X ASTM A480SS T-AKE STERN TUBE 14

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

CUP POINT, HEX SOCKET SET SCREW 2

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

PLUG, HEXAGON SOCKET COLLAR 2

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

DUBO RETAINING RING M10 24

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

DUBO RETAINING RING M12 52

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

DUBO RETAINING RING M16 84

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

MAJOR OVERHAUL KIT 712 MD/SERVICE KIT A 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

FACE CHANGE OUT KIT MD/SERVICE KIT B 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

SERVICE KIT A, 744 TYPE A8 SEAL/SERVICE KIT A 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

SEAT ASSY 712 MD 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

WALKERSELE M1/D7 650X714X25 2

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

TAKE RUDDER ORING OEM KITS 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

T-AKE RUDDER SEAL HOUSING 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

CSI PROPELLER

SHAFT AND STERN

TUBE INSPECTION

(5YR)(SCSI)

RUDDER BEARING 863.28OD X 80 1

PPE HAS SUBMITTED MOR-26-

109 ON 04/23/2026 BUT LTD IS

CURRENTLY WAITING FOR

PROGRAM APPROVAL TO

PROCESS ; PID N32205-26-

SIMACQ-DSM-PM6-0198 (MOR

CONTAINS MULTIPLE WIS,

0903,0904, 0954)

STERN TUBE SEAL

INSPECTION (FW

SYSTEM) (5 YR)

(SCSI)

SERVICE KIT A 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

STERN TUBE SEAL

INSPECTION (FW

SYSTEM) (5 YR)

(SCSI)

SERVICE KIT B 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

STERN TUBE SEAL

INSPECTION (FW

SYSTEM) (5 YR)

(SCSI)

SERVICE KIT A 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

STERN TUBE SEAL

INSPECTION (FW

SYSTEM) (5 YR)

(SCSI)

SERVICE KIT B 1 LISTED IN WORK SPEC, NO

MOR SUBMITTED BY THE PPE

RUDDER AND

STERN FRAME

EXAMIINATION

(5YR)

INTERNAL SEAL KIT 1

SPS N2900261324076

MOR-26-112

ERP: 1301369116

PID: N32205-26-SIMACQ-DSM-

PM6-0200

RDD – 1/27/2027

RUDDER AND

STERN FRAME

EXAMIINATION

(5YR)

SEAL KIT 1

SPS N2900261324076

MOR-26-112

ERP: 1301369116

PID: N32205-26-SIMACQ-DSM-

PM6-0200

STERN FRAME

EXAMIINATION

(5YR)

VALVES FOR SEAL PRESSURE 6

SPS N2900261324076

MOR-26-112

ERP: 1301369116

PID: N32205-26-SIMACQ-DSM-

PM6-0200

STERN FRAME

EXAMIINATION

(5YR)

COVER SEAL 1

SPS N2900261324076

MOR-26-112

ERP: 1301369116

PID: N32205-26-SIMACQ-DSM-

PM6-0200

STERN FRAME

EXAMIINATION

(5YR)

O-RINGS FOR HYDRAULIC NUT 1

SPS N2900261324076

MOR-26-112

ERP: 1301369116

PID: N32205-26-SIMACQ-DSM-

PM6-0200

STERN FRAME

EXAMIINATION

(5YR)

O-RINGS FOR HYDRAULIC NUT 1

SPS N2900261324076

MOR-26-112

ERP: 1301369116

PID: N32205-26-SIMACQ-DSM-

PM6-0200

STERN FRAME

EXAMIINATION

(5YR)

THRUST BEARING 1

SPS N2900261324076

MOR-26-112

ERP: 1301369116

PID: N32205-26-SIMACQ-DSM-

PM6-0200

STERN FRAME

EXAMIINATION

(5YR)

LOWER LINER 1

SPS N2900261324076

MOR-26-112

ERP: 1301369116

PID: N32205-26-SIMACQ-DSM-

PM6-0200

STERN FRAME

EXAMIINATION

(5YR)

UPPER LINER 1

SPS N2900261324076

MOR-26-112

ERP: 1301369116

PID: N32205-26-SIMACQ-DSM-

PM6-0200

STERN FRAME

EXAMIINATION

(5YR)

FILTER ELEMENT,AIR CONDITIONING

N2900261324077 – NSN

RDD- 1/27/2027

OVERHAULING SEA

VALVES (5YR)

CRANE

24" SERIES 200 LUG BUTTERFLY VALVE 3

RECEIVED AT MSC

WAREHOUSE

OVERHAULING SEA

VALVES (5YR)

CRANE

4" SERIES 225 LUG BUTTERFLY VALVE 1

RECEIVED AT MSC

WAREHOUSE

OVERHAULING SEA

VALVES (5YR)

CRANE

12" SERIES 225 LUG BUTTERFLY VALVE 1

RECEIVED AT MSC

WAREHOUSE

OVERHAULING SEA

VALVES (5YR)

CRANE

4" BRZ SWING CHECK REBUILD KIT 1

SPS N2900261254069

MOR-26-114;

ERP: 1301367021;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

RDD – 1/27/2027

NO UPDATE ON AWARD

OVERHAULING SEA

VALVES (5YR)

CRANE

6" BRZ SCUPPER W/CLOSING DEVICE REBUILD KIT 1

SPS N2900261254069

MOR-26-114;

ERP: 1301367021;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

RDD – 1/27/2027

NO UPDATE ON AWARD

OVERHAULING SEA

VALVES (5YR)

CRANE

3" BRZ SCUPPER W/CLOSING DEVICE 1

SPS N2900261254069

MOR-26-114;

ERP: 1301367021;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

VALVES (5YR)

CRANE

2" BRZ SCUPPER W/CLOSING DEVICE 6

SPS N2900261254069

MOR-26-114;

ERP: 1301367021;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

RDD – 1/27/2027

NO UPDATE ON AWARD

OVERHAULING SEA

VALVES (5YR)

CRANE

PIMA-MODEL 1626 BRZ, 2-INCH SWING CHECK

VALVE W/CLOSING DEVICE 6

SPS N2900261254069

MOR-26-114;

ERP: 1301367021;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

RDD – 1/27/2027

NO UPDATE ON AWARD

OVERHAULING SEA

VALVES (5YR)

CRANE

MILWAUKEE MODEL 5071, 3-INCH SWING CHECK

VALVE W/CLOSING DEVICE 1

SPS N2900261254069

MOR-26-114;

ERP: 1301367021;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

RDD – 1/27/2027

NO UPDATE ON AWARD

OVERHAULING SEA

VALVES (5YR)

CRANE

PIMA-MODEL 1626, BRZ, 6-INCH SCUPPER 1

SPS N2900261254069

MOR-26-114;

ERP: 1301367021;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

RDD – 1/27/2027

NO UPDATE ON AWARD

OVERHAULING SEA

VALVES (5YR)

CRANE

30" SERIES 200 LUG BUTTERFLY VALVE 4

SPS N2900261254070

MOR-26-113;

ERP: 1301367023;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

RDD - 1/27/2027

VALVES (5YR)

CRANE

24" SERIES 200 LUG BUTTERFLY VALVE 3

SPS N2900261254070

MOR-26-113;

ERP: 1301367023;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

VALVES (5YR)

CRANE

4" SERIES 225 LUG BUTTERFLY VALVE 2

SPS N2900261254070

MOR-26-113;

ERP: 1301367023;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

VALVES (5YR)

CRANE

4" SERIES 225 LUG BUTTERFLY VALVE 1

SPS N2900261254070

MOR-26-113;

ERP: 1301367023;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

VALVES (5YR)

CRANE

6" SERIES 225 LUG BUTTERFLY VALVE 1

SPS N2900261254070

MOR-26-113;

ERP: 1301367023;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

VALVES (5YR)

CRANE

2" SERIES 225 LUG BUTTERFLY VALVE 1

SPS N2900261254070

MOR-26-113;

ERP: 1301367023;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

VALVES (5YR)

CRANE

12" SERIES 225 LUG BUTTERFLY VALVE 1

SPS N2900261254070

MOR-26-113;

ERP: 1301367023;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

VALVES (5YR)

CRANE

16" SERIES 225 LUG BUTTERFLY VALVE 1

SPS N2900261254070

MOR-26-113;

ERP: 1301367023;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

VALVES (5YR)

CRANE

8" SERIES 225 LUG BUTTERFLY VALVE 2

SPS N2900261254070

MOR-26-113;

ERP: 1301367023;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

VALVES (5YR)

CRANE

VALVE,STOP-CHECK 4

N2900261264073

EDD - 12/30/2026

VALVES (5YR)

CRANE

VALVE,STOP-CHECK 2

N2900261264074

C2 STATUS - REJECTED.

FUNDS NOT AVAILABLE TO

PROCESS.

VALVES (5YR)

CRANE

VALVE,STOP-CHECK 2

N2900261264075

EDD - 12/30/2026

VALVES (5YR)

CRANE

LADISH- FIGURE 7275 SS, 1-INCH GLOBE STOP CHECK

VALVE 4

SPS N2900261484081

MOR-26-115;

ERP 1301373638;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

RDD – 1/27/2027

NO UPDATE ON AWARD

OVERHAULING SEA

VALVES (5YR)

CRANE

LADISH-FIGURE 7275 SS, 1.5 INCH GLOBE STOP

CHECK VALVE 2

SPS N2900261484081

MOR-26-115;

ERP 1301373638;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

RDD – 1/27/2027

NO UPDATE ON AWARD

OVERHAULING SEA

VALVES (5YR)

CRANE

LADISH-FIGURE 7275 SS, 2-INCH GLOBE STOP CHECK

VALVE 2

SPS N2900261484081

MOR-26-115;

ERP 1301373638;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

RDD – 1/27/2027

NO UPDATE ON AWARD

OVERHAULING SEA

VALVES (5YR)

CRANE

LADISH-FIGURE 8275 SS, 2-INCH GATE VALVE 7

SPS N2900261484081

MOR-26-115;

ERP 1301373638;

PID: N32205-26-SIMACQ-DSM-

PM6-0201

RDD – 1/27/2027

NO UPDATE ON AWARD

SEA CHEST MARINE

GROWTH

PREVENTION

SYSTEM (5 YR)

CHLOROPAC CELL 1/2LB NO TAPS 2

PPE HAS SUBMITTED MOR-26-

116 WI 963 ON 06/17/2026 BUT

LTD IS CURRENTLY WAITING

FOR PROGRAM APPROVAL TO

PROCESS

SEA CHEST MARINE

GROWTH

PREVENTION

SYSTEM (5 YR)

CHLOROPAC CELL 1/2LB 1 TAP 1

PPE HAS SUBMITTED MOR-26-

116 WI 963 ON 06/17/2026 BUT

LTD IS CURRENTLY WAITING

FOR PROGRAM APPROVAL TO

PROCESS

SEA CHEST MARINE

GROWTH

PREVENTION

SYSTEM (5 YR)

CHLOROPAC CELL 1LB NO TAPS 2

PPE HAS SUBMITTED MOR-26-

116 WI 963 ON 06/17/2026 BUT

LTD IS CURRENTLY WAITING

FOR PROGRAM APPROVAL TO

PROCESS

SEA CHEST MARINE

GROWTH

PREVENTION

SYSTEM (5 YR)

CHLOROPAC CELL 1LB 1 TAP 2

PPE HAS SUBMITTED MOR-26-

116 WI 963 ON 06/17/2026 BUT

LTD IS CURRENTLY WAITING

FOR PROGRAM APPROVAL TO

PROCESS

GYPSY WINCH

MASTER CONTROL

PEDESTAL;

REFURBISMENT

STAINLESS STEEL PLATE 13

RECEIVED AT MSC

WAREHOUSE

GYPSY WINCH

MASTER CONTROL

PEDESTAL;

REFURBISMENT

STUFFING TUBE 13

RECEIVED AT MSC

WAREHOUSE

GYPSY WINCH

MASTER CONTROL

PEDESTAL;

REFURBISMENT

BOLT, MACHINE 5/1618 X 3/4LG CRES 60

RECEIVED AT MSC

WAREHOUSE

GYPSY WINCH

MASTER CONTROL

PEDESTAL;

REFURBISMENT

NUT, SELFLOCKING 5/1618 CRES 60

RECEIVED AT MSC

WAREHOUSE

GYPSY WINCH

MASTER CONTROL

PEDESTAL;

REFURBISMENT

GARLOCK BLUEGARD 3000 1/8" THICK 4" 150# FULL

FACE GASKET, DIMENSIONS 41/2" ID X 9" OD WITH (8)

3/4" HOLES ON 71/2" BC

GYPSY WINCH

MASTER CONTROL

PEDESTAL;

REFURBISMENT

WEATHERRESISTANT EPDM RUBBER SHEET WITH

ADHESIVEBACK, 12" X 12", 1/8" THICK 13

RECEIVED AT MSC

WAREHOUSE

GYPSY WINCH

MASTER CONTROL

PEDESTAL;

REFURBISMENT

316 STAINLESS STEEL HEX HEAD SCREW 5/8"11

THREAD SIZE, 13/4" LONG 120

RECEIVED AT MSC

WAREHOUSE

GYPSY WINCH

MASTER CONTROL

PEDESTAL;

REFURBISMENT

ANTISEIZE COMPOUND 1

RECEIVED AT MSC

WAREHOUSE

GYPSY WINCH

MASTER CONTROL

PEDESTAL;

REFURBISMENT

GASKET SEALANT TYP 2 2

RECEIVED AT MSC

SLIDING BLOCK FAN

COWL AND BAFFLES

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

EXTERNAL FAN

BRACKET

SEAL PLAIN 80

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

LOCK WASHER 1/2 2

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

SCREW CAP HEX HD ½-13 X 1” 80

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

SCREW CAP HEX HD 5/8-11 X 1.5” 40

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

LOCK WASHER 5/8 1

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

GASKET 5

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

GASKET 5

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

PLUG, PIPE 40

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

SCREW CAP HEX HD ½-13 X.875” 5

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

WASHER, FLAT, COPPER 5

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

SCREW CAP HEX HD 25

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

WASHER, LOCK 5/16 1

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

RING, RETAINING 5

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

BREATHER 5

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

RECTIFIER, METALLIC 5

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

SEALING COMPOUND 2

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

WASHER, LOCK 1/4 2

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

ANTISEIZE COMPOUND 2

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

SEAL, LIP 5

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

SCREW CAP HEX HD ¼-20 X .5” 1

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

SCREW CAP HEX HD ¼-20 X .625” 1

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

SCREW CAP HEX HD ¼-20 X .75” 1

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

SCREW CAP HEX HD ½-13 X 1.25” 40

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

NUT, SELFLOCKING ¼-20 100

REPLACEMENT

WITH STAINLESS

STEEL

COMPONENTS AND

PRESERVATION OF

SCREW CAP, SOCKET HEAD ¼-20 X .5” 40

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

UNREP CHAIN, DOUBLE STRAND 1000

N2900261264072

MOR-26-117;

ERP: 1301373836;

PID: N32205-26-SIMACQ-DSM-

PM6-0203

RDD – 1/27/2027

NO UPDATE ON AWARD

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

CONNECTING LINK HOT DIPPED 10

N2900261264072

MOR-26-117;

ERP: 1301373836;

PID: N32205-26-SIMACQ-DSM-

PM6-0203

RDD – 1/27/2027

NO UPDATE ON AWARD

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

OFF SET LINK HOT DIPPED 4

N2900261264072

MOR-26-117;

ERP: 1301373836;

PID: N32205-26-SIMACQ-DSM-

PM6-0203

RDD – 1/27/2027

NO UPDATE ON AWARD

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SEAL 120

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

RETAINER, ROLLER,BEARING 120

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

RETAINER, ROLLER,NEEDLE 60

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

ROLLER,LINEAR-ROTARY MOTION 60

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

RING,RETAINING 40

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

WASHER,FLAT 40

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SET SCREW 40

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

FITTING,LUBRICATION 6

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SCREW CAP,HEXAGON HEAD 2

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

WASHER,LOCK 2

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SCREW CAP,HEXAGON HEAD 2

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

WASHER ,LOCK 2

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

BOLT,MACHINE 30

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

NUT,SELF-LOCKING,HEXAGON 10

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

VALVE,SAFETY RELIEF 10

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SEAL,PLAIN 5

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

RING,RETAINING 5

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

BEARING,ROLLER,CYLINDRICAL 5

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SEAL,PLAIN 5

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SCREW,CAP,HEXAGON HEAD 30

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SCREW,CAP,HEXAGON HEAD 60

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SCREW,CAP,HEXAGON HEAD 1

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SCREW,CAP,HEXAGON HEAD 30

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

WASHER, LOCK 30

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SCREW,CAP,HEXAGON HEAD 40

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

WASHER, LOCK 1

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SEAL,PLAIN 10

AAC - Y -TERMINAL ITEM - CJ

REJECTED STATUS

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

NUT,SELF-LOCKING,HEXAGON 40

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

BEARING,ROLLER,TAPERED 5

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SPACER,RING 25

EDD -

10/09/2026

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

CONE AND ROLLERS,TAPERED ROLLER BEARING 50

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

CUP,TAPERED ROLLER BEARING 10

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SCREW CAP,HEXAGON HEAD 50

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

WASHER, LOCK 1

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

WASHER, SPRING TENSION 120

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SEAL, PLAIN 10

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

CUP, TAPERED ROLLER BEARING 5

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

BEARING,ROLLER,TAPERED 5

EDD -

2/28/2027

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

WASHER, FLAT 10

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

NUT,SELF-LOCKING,HEXAGON 10

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SCREW,CAP,HEXAGON HEAD 10

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

BEARING UNIT,PLAIN 5

EDD – 11/30/2026

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

WASHER,FLAT 44

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

NUT,SELF-LOCKING,HEXAGON 50

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

SCREW,CAP,HEXAGON HEAD 25

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

WASHER,LOCK 1

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

PIN, COTTER 1

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SLIDING BLOCK

REFURBISHMENT

AND CHAIN

REPLACEMENT (5

YR)

PIN, COTTER 1

RECEIVED AT MSC

WAREHOUSE

TRANSFER HEAD

SL…