J-4 Price Proposal Spreadsheet.xlsx
XLSX spreadsheet 14 KB Posted
- Solicitation number
- 697DCK-26-R-00034
About this file
The document is a Price Proposal Spreadsheet for the GFK Airport Traffic Control Tower (ATCT) Replacement Project located in Grand Forks, North Dakota. The spreadsheet provides a detailed pricing breakdown by construction division, with a total allowance of $325,000 covering materials, labor, overhead, profit, and bonding. The line items span typical construction categories including general requirements, concrete, masonry, structural steel, architectural elements, mechanical systems, electrical work, site preparation, and utilities.
This pricing document corresponds to FAA Solicitation Number 697DCK-26-R-00034, which seeks construction of a new Airport Traffic Control Tower and Base Building at Grand Forks International Airport. The Federal Aviation Administration's Southwestern Region is managing the procurement, with the solicitation posted under FAA Acquisition Management Policy. Potential bidders are required to review all attachments and can request additional documentation by contacting Erin M. Crabtree via email. The government emphasizes that this announcement does not guarantee procurement and will not reimburse vendors for proposal preparation costs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 697DCK-26-R-00034 -003.pdf | ||
| GFK Questions and Answers Final.xlsx | XLSX spreadsheet | |
| 697DCK-26-R-00034 - 0002.pdf | ||
| 697DCK-26-R-00034 - 01.pdf | ||
| GFK Site Visit Sign-In Sheet.pdf | ||
| J-3 Wage Determination ND20250014.pdf | ||
| J-5 Past Performance Questionnaire.pdf | ||
| 697DCK-26-R-00034 - Final.pdf | ||
| J-6 Master Subcontracting Plan.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE PROPOSAL SPREADSHEET
| GFK ATCT Replacment Project |
| Grand Forks, North Dakota |
| Pricing Breakdown Form |
| The Contractor must furnish all materials, labor, supervision, equipment and everything else whatsoever to construct an Airport Traffic Control Tower located at the Grand Forks International Airport (GFK) in strict conformance with the solicitation/contract at the following prices (including OH & P): | ||||||
| ATCT Costs | ||||||
| Item | Division | Description | $ Materials | $ Labor | $ Material & Labor | |
| 1 | 01 | General Requirements | ||||
| 2 | 01 | Permits | ||||
| 3 | 03 | Concrete - Cast In Place | ||||
| 4 | 03 | Concrete - Pre-Cast | ||||
| 5 | 04 | Masonry | ||||
| 6 | 05 | Structural Steel | ||||
| 7 | 05 | Cold Form Metal Framing | ||||
| 8 | 05 | Misc. Metals | ||||
| 9 | 06 | Rough Carpentry | ||||
| 10 | 07 | Waterproofing Dampproofing Sealants | ||||
| 11 | 07 | Cladding/Composite Panels | ||||
| 12 | 07 | Roofing | ||||
| 13 | 07 | Fire Proofing | ||||
| 14 | 08 | Doors Frames Hardware | ||||
| 15 | 08 | Entrances Storefronts | ||||
| 16 | 08 | Windows | ||||
| 17 | 08 | Louvers And Vents | ||||
| 18 | 09 | Drywall | ||||
| 19 | 09 | Tile & Stone | ||||
| 20 | 09 | Acoustical Ceilings | ||||
| 21 | 09 | Carpet Resilient Flooring | ||||
| 22 | 09 | Wall Finishes | ||||
| 23 | 09 | Painting And Wallcovering | ||||
| 24 | 10 | Misc. Specialties Signage | ||||
| 25 | 10 | Specialties | ||||
| 26 | 10 | Lockers | ||||
| 27 | 11 | Equipment | ||||
| 28 | 12 | Window Treatment | ||||
| 29 | 12 | Casework | ||||
| 30 | 12 | Furnishings | - | - | $325,000 | * Allowance |
| 31 | 14 | Elevators Conveying | ||||
| 32 | 21 | Fire Protection | ||||
| 33 | 22 | Plumbing | ||||
| 34 | 23 | HVAC | ||||
| 35 | 26 | Electrical | ||||
| 36 | 26 | Security | ||||
| 37 | 31 | Site Prep | ||||
| 38 | 32 | Site Improvements | ||||
| 39 | 32 | Ductbank | ||||
| 40 | 33 | Site Utilities |
| Subtotal | $ 325,000.00 |
| Overhead | |
| Profit | |
| Bond | |
| Total |