This document is a Statement of Work (SOW) for the corrective maintenance, replacement, and installation of water softener units at the Fermi National Accelerator Laboratory site. The SOW outlines the requirements for a subcontractor to perform this work, including providing all labor, materials, and supervision necessary. The subcontractor will be responsible for diagnosing issues, providing quotes, ordering parts, and completing repairs or replacements as needed. The SOW also covers the installation of new water softener units at locations determined by the Fermi Research Alliance (FRA). The contract period is a 2-year base with a 2-year option period.
The related federal contract opportunity is a solicitation for an Annual Water Softener Service Repairs and Replacements contract. FRA is seeking to establish a 4-year Service Time and Material Contract, with a base 2-year and 2-year option period, on a Lowest Price Technically Acceptable (LPTA) basis. The successful offeror must demonstrate the capabilities and resources to perform the required corrective maintenance, replacement, and installation of water softener units.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
J- 1 Water So�ener Statement of Work
Title: Correc�ve Maintenance, Replacement, and Installa�on of Site Water So�eners
1. Background: All domes�c water at the Fermi Na�onal Accelerator Laboratory (Fermilab) site is supplied by the City of Warrenville. The domes�c water then travels through nearly 21 miles of piping to reach its eventual des�na�on. The result is “hard” water that requires treatment by water so�ening units installed throughout the Fermilab property. A total of thirty-two (32) water so�eners (see Atachment 1, Water So�ener Loca�ons) are installed at mul�ple loca�ons to assist in so�ening the water to prepare it for a variety of applica�ons.
So� water is important to certain buildings and laboratories as it is used for humidifiers and cooling for computer centers. Hard water can calcify and clog orifices, causing damage to computer banks. So� water is also required for various processes in experiments, loop systems, regenera�on for LCW applica�ons, and dish washing.
Preventa�ve maintenance is performed by Fermi Research Alliance (FRA) site mechanics.
Correc�ve maintenance and/or replacement of these units is beyond the scope of site maintenance’s exper�se. FRA is in need of a subcontractor to be responsible for all correc�ve maintenance and/or replacement of the site’s water so�ener units as the needs are iden�fied. The subcontractor would also perform installa�on of new units in loca�ons determined appropriate by FRA.
2. Scope of Work
2.1. All work will be scheduled by FRA contac�ng the Subcontractor to set an agreeable �me and date.
2.2. All work will be performed at the Fermilab site in Batavia, Illinois.
2.3. The subcontractor shall provide all labor, material, and supervision necessary to perform correc�ve maintenance and replacement of all water so�ener units at the Fermilab site (see Atachment 1, Water So�ener Loca�ons).
2.3.1. Examples of correc�ve maintenance may include: broken / cracked tubes, malfunc�oning tank float, replacement or repair of check valves, repair of damage to external so�ener body, repair or replacement of flow valves, failure of electronic flowmeter or other electronic parts, and other maintenance items outside of the technical ability of in house maintenance technicians as determined by FRA.
2.3.2. Subcontractor will perform an inspec�on to diagnose issues and provide a quote prior to ordering parts and materials needed for repair.
2.4. The subcontractor shall provide all labor, material, and supervision necessary to perform installa�on of new water so�ener units as directed by FRA.
2.5. Subcontractor will replace water so�ener units when they cannot be repaired.
J- 1 Water So�ener Statement of Work
2.5.1. Replacement may be required due to end of life, gross failure of a unit, or when correc�ve maintenance costs would exceed the costs of a new unit.
2.5.2. Subcontractor will perform an inspec�on to diagnose issues and provide a quote prior to ordering parts and materials needed for replacement.
2.6. Subcontractor procure and install new water so�ener units at new loca�ons at Fermilab when requested by FRA personnel.
2.6.1. Subcontractor will provide a quote prior to ordering parts and materials needed for installa�on of new units.
3. Site Access
3.1. Subcontractor will need to meet FRA requirements to obtain a site access badge. These requirements include:
3.1.1. Possessing a Real ID or equivalent to access the site.
3.1.2. Comple�ng all required training modules.
3.2. Technicians must check in at the ISD Facili�es Management Opera�on Office / Shop prior to star�ng a task and again a�er task is complete.
4. Availability
4.1. All work is scheduled with the subcontractor.
4.2. There are certain loca�ons at Fermilab that will need to be scheduled dependent on the Lab’s opera�onal status and availability.
4.3. Work that affects compu�ng areas requires permission from each perspec�ve building manager or area facility manager.
5. Government Furnished Property
5.1. None.
6. Es�mated dura�on:
6.1. This contract period is two (2) year base and two (2 ) year op�on period.