J-1 Composite Work Package SOW CMAV SING-017-26_USS HIGGINS DDG-76.pdf
PDF 3 MB Posted
- Attached to
- USS HIGGINS (DDG 76) CMAV
- Solicitation number
- N6264926RR007
About this file
This is a Statement of Work (SOW) for ship repair work on USS HIGGINS (DDG 76) conducted at HMAS Kuttubal, Sydney Australia during the period of February 28 to March 19, 2026. The work is specified under specification number SING-017-26 and includes both standard Navy requirements and specific repair items organized into two categories: Category I comprises mandatory FY-26 standard items applicable to the job order without further reference (26 items covering general criteria, environmental compliance, quality management, safety protocols, and technical documentation), while Category II lists optional standard items that may be invoked within specific work items (12 items addressing specialized repairs such as insulation, welding, valve repair, and piping systems).
The executing work section details four specific repair items: Item 256-61-001 involves overhauling an 8-inch flanged seawater supply relief valve (Hunt Valve Co., MIL-DTL-24332) located in Engine Room Number Two, requiring disassembly, cleaning, component replacement, and multiple testing phases (hydrostatic test at 87 PSIG, seat tightness test at 58 PSIG, and operational test); Item 261-12-001 requires replacement of a 3-inch motor-operated fuel oil service pump suction valve in Engine Room Number 2 with installation, alignment, and adjustment of position indicators and torque limits; Item 320-10-001 involves installation of a Multi-Cable Transit (MCT) block in the Fan Room with neoprene insert blocks and Roxtec sealing systems; and additional work items address fuel oil system components, RHIB boat sling assemblies, and deck panel replacements. All work requires contractor submission of Test and Inspection Verification Sheets (TIVS) documenting material status, tag-out verification, test results, and compartment closeout inspections, with documentation due within three days of repair completion. Government-furnished materials are provided for major components, and the contractor must maintain system cleanliness levels, comply with Navy technical manuals and standards, and obtain Ship's Force verification and supervisor acceptance throughout the work performance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
SRF DET SINGAPORE (NMD)
USS HIGGINS (DDG 76)
SPECIFICATIONS FOR WORK TO BE ACCOMPLISHED
SPECIFICATION NUMBER: SING-017-26
Period of Performance: 28 February to 19 March 2026
Location: HMAS Kuttubal, Sydney Australia
INCLUDES ALL CHANGES THROUGH 1/29/2026
INDEX
SHIP: USS HIGGINS (DDG 76) SING-017-26
ITEMS THAT ARE STRUCK OUT IN THIS INDEX DO NOT APPLY TO THIS CONTRACT.
CATEGORY I. FY-26 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE.
ITEM_NO. TITLE CHANGE DATE CHANGE
009-001 General Criteria; accomplish 09/04/2024 Original
009-002 Environmental Compliance Report for Material Usage; accomplish 07/22/2024 Original
009-003 Toxic and Hazardous Substance; control 07/22/2024 Original
009-004 Quality Management System; provide 09/16/2024 Original
009-005 Temporary Access; accomplish 11/18/2024 CH-1
009-006 Maintaining Protection and Cleanliness from Non-Radioactive Operations;
accomplish
07/22/2024 Original
009-007 Confined Space Entry, and Certification; accomplish 09/04/2024 Original
009-008 Shipboard Fire Protection and Fire Prevention; accomplish 09/30/2024 Original
009-010 Asbestos-Containing Material (ACM); control 09/16/2024 Original
009-018 Mine Warfare Ships Magnetic Material; control 09/04/2024 Original
009-019 Provisioning Technical Documentation (PTD); provide 07/22/2024 Original
009-020 Government Property; control 07/22/2024 Original
009-021 Alteration Verification, Logistic and Technical Data; provide 07/22/2024 Original
009-023 Interference; remove and install 11/18/2024 CH-1
009-024 Authorization, Control, Isolation, Blanking, Tagging, and Cleanliness; accomplish 09/16/2024 Original
009-034 Fire Protection of Unmanned Vessel at Contractor Facility; accomplish 07/22/2024 Original
009-039 Technical Manual Contract Requirement (TMCR) for a New Technical Manual for
Commercial Equipment/Component; accomplish
07/22/2024 Original
009-040 Contractor Crane, Multi-Purpose Machine and Material Handling Equipment at a
Naval Facility; provide
07/22/2024 Original
009-060 Schedule and Associated Report for CNO Availability; provide and manage 09/16/2024 Original
009-061 Shipboard Use of Fluorocarbons; control 09/16/2024 Original
009-067 Integrated Total Ship Testing; manage 09/16/2024 Original
009-068 Availability Work Certification (AWC) Data for Chief of Naval Operations (CNO)
Availabilities; provide
09/16/2024 Original
009-069 Heavy Weather/Mooring Plan; provide 09/16/2024 Original
009-070 Confined Space Entry, Certification, Fire Protection, Fire Prevention and
Housekeeping for Unmanned Vessels; accomplish
09/16/2024 Original
009-072 Physical Security at a Private Contractor Facility; accomplish 09/16/2024 Original
009-073 Shipboard Electrical/Electronic Cable Procedure; inspect, test, install, remove, and repair
09/16/2024 Original
009-074 Occupational, Safety and Health Plan; accomplish 09/16/2024 Original
009-080 Ship Facility; maintain 09/16/2024 Original
009-081 Compartment Closeout; accomplish 09/16/2024 Original
009-082 Installation of Equal Component Vice Specified Component; report 07/22/2024 Original
009-084 Threaded Fastener Requirement; accomplish 07/22/2024 Original
009-088 Collection, Holding and Transfer (CHT) and Motor Gasoline (MOGAS) Tank, Space, and Piping, including Sewage or MOGAS-Contaminated Tank, Space, and Piping; certify
09/16/2024 Original
009-093 Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution
Prevention Act (PPA) Information; provide
07/22/2024 Original
Page 1 of 4 EXECUTING WORK
ITEM_NO. TITLE CHANGE DATE CHANGE
009-099 Ship Departure Report; provide 09/16/2024 Original
009-100 Ship's Stability; maintain 09/16/2024 Original
009-101 Ship Transit and Berthing; accomplish 09/16/2024 Original
009-106 Work Authorization Form Coordinator (WAFCOR); provide 09/16/2024 Original
009-109 Non-SUBSAFE Work on SUBSAFE-Certified Vessel; accomplish 07/22/2024 Original
009-110 Non-Nuclear Work on a Nuclear Vessel; accomplish 07/22/2024 Original
009-111 Schedule and Associated Report for Non-CNO Availability; provide and manage 09/16/2024 Original
009-117 Combat Systems, Light-Off Suport; provide 09/17/2024 Original
009-118 CG Deck Loading; accomplish 07/22/2024 Original
009-120 Fact Finding and Critique of Unplanned Event; manage 09/17/2024 Original
009-122 Temporary Padeye; install and remove 11/18/2024 CH-1
009-125 Boat 65 Feet (20meters) Long and Less; accomplish 11/18/2024 CH-1
009-126 Schedule Model Review (SMR); accomplish 09/17/2024 Original
Page 2 of 4 EXECUTING WORK
CATEGORY II. FY-26 STANDARD ITEMS WHICH MAY BE INVOKED IN THE WORK ITEMS OF THIS JOB ORDER.
TITLE CHANGE DATEITEM NO. CHANGE
009-011 Insulation and Lagging; accomplish 09/16/2024 Original
009-012 Weld, Fabricate, and Inspect; accomplish 09/16/2024 Original
009-025 Structural Boundary Test; accomplish 09/04/2024 Original
009-026 Deck Covering; accomplish 09/25/2024 Original
009-032 Cleaning and Painting Requirements; accomplish 09/25/2024 Original
009-037 General Procedure for Woodwork; accomplish 09/16/2024 Original
009-047 Gate Valve; repair 07/22/2024 Original
009-052 Relief Valve; repair 07/22/2024 Original
009-071 Piping System; test 09/16/2024 Original
009-107 Piping System Cleanliness Restoration and Flushing
(Non-Nuclear); accomplish
09/16/2024 Original
Page 3 of 4 EXECUTING WORK
ITEM NO. TITLE
Seawater Supply Relief Valve; overhaul256-61-001
Fuel Oil Service Pump Suction Valve; replace261-12-001
Multiple Cable Transit (MCT) Block; install320-10-001
Electrical Cable Replacement; accomplish320-11-001
No. One Oil Distribution Box Prairie Air Flexible Hose Fabricate;
accomplish
551-62-001
7 Meter Rigid Hull Inflatable Boat (RHIB) Boat Sling Assembly Weight
Test; accomplish
583-11-001
Large Pulper Left Side Frame Guard; fabricate and install593-32-001
J-Bar Davit weight test; accomplish611-11-001
Access Trunk Safety Net; replace612-21-001
Dressing Line, Forward and Aft; fabricate613-00-001
Nomex Deck Panel; replace622-12-001
Cosmetic Polymeric (PRC) Deck Covering; replace634-11-001
Insulation and Lagging; replace635-11-001
Self-contained Breathing Apparatus Breathing Air Charging System
(SCBA BACS) Air Booster Pump Assembly Relief Valves; test
664-11-001
Temporary Service, provide992-21-001
Page 4 of 4 EXECUTING WORK
SHIP: USS HIGGINS (DDG 76) ITEM NO: 256-61-001
COAR: 26 PCN: EM02-L053
CSWT FILE NO: 256-014 (DDG 51) CMP: NONE
REVISED: 28 MAY 2025 PLANNER: GRAY, CHARLES
BAUSER, BRANDON
TOILOLO, JESMOND
SSP: SING-017-26 1 of 7 ITEM NO: 256-61-001
1. SCOPE:
1.1 Title: Seawater Supply Relief Valve; overhaul
1.2 Location of Work:
1.2.1 Engine Room Number Two (4-254-0-E)
1.3 Identification:
1.3.1 Quantity (One EA), 8-Inch Flanged Relief Valve, SW-V-088/SWC- V0269; MIL-DTL-24332 , MFG: Hunt Valve Co., INC.; MFG Part No.:
R10AQ2Q2AT-BM3; Set Pres: 64PSIG, Max Accum Press: 74PSIG; APL:
883119536
2. REFERENCES:
2.1 NAVSEA Standard Items , (FY26)
2.2 S0400-AD-URM-010 Rev 8, Tag-out Users Manual
2.3 256-6218410 Rev R, Seawater Cooling System Diagram
2.4 S9086-RJ-STM-010 Rev 7, Naval Ship's Technical Manual, Chapter 504, Pressure, Temperature and Other Mechanical and Electromechanical Measuring Instruments
2.5 S9086-RK-STM-010/CH-505 Rev 6, Naval Ship's Technical Manual, Chapter 505, Piping Systems
2.6 802-5959353 Rev BT, Schedule of Piping, Valves, Fittings, and Associated Piping Components
2.7 BIW_D50959 Rev A, Valve, 8-Inch Flanged Relief Valve
2.8 804-5284201, Reinforced Rubber Gasket Material for Pipeline Joints
2.9 256-6218410 BK Rev R, DDG-51 Class Seawater Cooling System Engineering Data Booklet
3. REQUIREMENTS:
3.1 Procure and provide the following materials:
TOTAL
QUANTITY
REQUIRED NAME OF PART PIECE NO. REF. NO.
FIGURE/DRAWING
NO. PART NO.
28 EA Bolt, 2-inch x 0.625-inch, QQ-N-
N/A 2.6 N/A MIL-DTL-
1222, Grade
28 EA Nut, 0.625-inch
N/A 2.6 N/A MIL-DTL-
1222, Grade
2 EA Gasket, 12.375-inch
N/A 2.8 N/A NIR,
Type I
SHIP: USS HIGGINS (DDG 76)
SSP: SING-017-26 2 of 7 ITEM NO: 256-61-001 x 0.0625 inch or 2
3.2 Submit one legible copy, in approved transferrable media, of a report listing Contractor Furnished Material (CFM) used in accomplishing this work item. The report must include status of materials not already on-hand, description of material, quantity, and delivery date. Document on Enclosure (One).
(V)(G) "TAG-OUT VERIFICATION"
3.3 Prior to commencement of work, contractor must obtain Ship's Force signature on Enclosure (One) as verification of tag out and record tag out serial number using 2.2 and 2.5 for guidance. Document on Enclosure (One). See Note 4.2.
3.4 Remove existing valve listed in 1.3 and located in 1.2, using 2.3 and 2.5 for guidance. System cleanliness shall be maintained during repair. Place caps or temporary blind covers over open piping to prevent entry of debris. Remove all foreign material such as paint, heavy scale, grease, or other contaminants for at least 6 inches on each side of the repair area. It is not necessary to polish the piping. The piping should be clean, dry, and free of solvents and flammable vapors.
3.4.1 Matchmark each valve part.
3.4.2 Drain and dispose of system fluids.
3.4.3 Disassemble, clean each internal and external surface free of foreign matter (including paint), and inspect each parts for defect.
3.4.3.1 Retain all serviceable fasteners and hardware for re-use.
3.5 Repair valve per 009-052 of 2.1, as follows using GFM provided in
5.1 and using 2.7 for guidance:
3.5.1 Remove existing and install new lifting stem provided in
5.1.2. Ensure stem is polished to a 32 Root-Mean-Square finish and free of raised edges and foreign matter.
3.5.2 Remove existing and install new metallic disc provided in
5.1.1. Machine, grind, or lap and spot-in metallic disc to seat to obtain a 360-degree continuous contact.
3.5.2.1 Inspect contact using blueing method. Transfer line must not exceed 1/16-inch in width.
3.5.3 Dress and true each gasket mating surface.
3.5.4 Chase and tap each exposed threaded area.
3.5.5 Assemble valve installing new each packing, each soft seat, each gasket, and each fastener for those removed in 3.4.3.
3.5.6 Set valve to lifting pressure 64 psig.
(I)(G) "HYDROSTATIC TEST (SHOP)"
3.6 Accomplish a hydrostatic test using clean fresh water at 87 PSIG for a minimum of 10 minutes, for the equipment listed in 1.3.1, using 2.4 and
2.9 for guidance. Allowable leakage: None. Document in Enclosure (One).
See Note 4.2.
3.6.1 Submit one legible copy, in hard copy or approved
SSP: SING-017-26 3 of 7 ITEM NO: 256-61-001 transferrable media, a report listing calibration certification of all gauges used for hydrostatic testing. Report must contain gauge serial number, gauge test range, and expiration date of certification. Document in Enclosure (One). See Note 4.2.
3.6.2 Master and backup test gauges with gauge range and graduation in accordance with Table 504-6-1 of 2.4. The backup gauge must be cross-checked to the master hydrostatic test gauge up to the maximum test pressure just prior to start of testing. Master and backup gauges must track within 2 percent of each other.
(I)(G) "SEAT TIGHTNESS TEST (SHOP)"
3.7 Accomplish seat tightness testing for a minimum of 3 minutes.
Allowable leakage: None. Purge valve of test medium, Install wire and lead lock seals following testing. Document on Enclosure (One).
3.7.1 Ensure the seat tightness test pressure is 58 PSIG for the valve listed in 1.3.1.
3.7.2 Master and backup test gauges with gauge range and graduation in accordance with Table 504-6-1 of 2.4. The backup gauge must be cross-checked to the master hydrostatic test gauge up to the maximum test pressure just prior to start of testing. Master and backup gauges must track within 2 percent of each other.
3.8 Install each wire and leadlock seal after setting each relief valve.
Attach metal tag to each valve stamped with ship name and hull number, valve number or identification, valve lifting pressure, date valve tested and set and name of repair facility.
(I)(G) "OPERATIONAL TEST (SHOP)"
3.9 Accomplish an operational test using clean fresh water for the equipment listed in 1.3.1 and using 2.4 for guidance. Document in Enclosure (One).
3.9.1 Master and backup test gauges with gauge range and graduation in accordance with Table 504-6-1 of 2.4. The backup gauge must be cross-checked to the master hydrostatic test gauge up to the maximum test pressure just prior to start of testing. Master and backup gauges must track within 2 percent of each other.
3.10 Install valve listed in 1.3 and located in 1.2, using 2.3 and 2.5 for guidance.
(V)(G) "VERIFY CLEANLINESS"
3.11 Verify existing cleanliness Level III was maintained throughout the performance of this work item. Level III cleanliness is a degree of cleanliness that results in a surface that is reasonably free of contamination and any remaining residue on the surface does not interfere with system operations or damage system components. Document in Enclosure (One). See Note 4.2.
3.12 Accomplish the requirements of 009-032 of 2.1 for each new and disturbed surface.
(V)(G) "FINAL VISUAL INSPECTION"
3.13 Accomplish final visual inspection with the SUPERVISOR and designated Ship's Force Representative of the repaired and installed
SSP: SING-017-26 4 of 7 ITEM NO: 256-61-001 valve. Document in Enclosure (One). See Note 4.2.
3.14 Submit one legible copy, in hard copy or approved transferrable media, of Enclosure (One) to the SUPERVISOR within 3 days of repair.
4. NOTES:
4.1 NAVSEA Standard Items (NSIs) are located at:
https://www.navsea.navy.mil/Home/RMC/CNRMC/Our-Programs/SSRAC/
4.2 Enclosure (One) is a Test and Inspection Verification Sheet (TIVS).
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
TOTAL
QUANTITY
PROVIDED NAME Of PART
PIECE
NO.
REF
NO.
NATIONAL
STOCK
NO.
REQ
PARA NO.
1. 1 EA DISC ASSEMBLY
B50810MF
D
4820-01- 326-1513 3.5.2
2. 1 EA
LIFTING STEM,
MONEL, QQ-N-288
B49432MF
D 2.7
4820-01- 326-3087 3.5.1
3. 1 EA
SEAT RING,
MONEL, QQ-N-288
B50809MF
D 2.7
4820-01- 260-6982 3.5
4. 3 EA
PREFORMED
PACKING, TEFLON
A49366MR
K 2.7
5330-01- 151-8359 3.5.5
5. 1 EA
O-RING,
FLUOROCARBON
RUBBER, SAE-AMS-
M83248/1 -219 2.7
5331-00- 166-8406 3.5.5
6. 1 EA
O-RING,
FLUOROCARBON
RUBBER, SAE-AMS
M83248/1 -242 2.7
5331-00- 165-1960 3.5.5
7. 1 EA
O-RING,
FLUOROCARBON
RUBBER, SAE-AMS
M83248/1 -269 2.7
5331-00- 167-5150 3.5.5
8. 1 EA
O-RING,
FLUOROCARBON
RUBBER, SAE-AMS
M83248/1 -273 2.7
5331-01- 361-4786 3.5.5
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
SSP: SING-017-26 5 of 7 ITEM NO: 256-61-001
ENCLOSURE (ONE)
TEST AND INSPECTION VERIFICATION SHEET (TIVS)
REV/
PARA
REQUIREMENTS / COMPONENT
IDENTIFICATION RESULTS ACTIVITY SIGNATURE/PRINTED
NAME
KTR
3.2
Submit one legible copy, in approved transferrable media, of a report listing Contractor Furnished Material
(CFM) used in accomplishing this work item. The report must include status of materials not already on-hand, description of material, quantity, and delivery date.
Date Submitted:
Report Serial#:
SRF
KTR
S / F3.3
(V)(G) “TAG-OUT VERIFICATION”
Prior to commencement of work, contractor must obtain Ship's Force signature on Enclosure (One) as verification of tag out and record tag out serial number using 2.2 and 2.5 for guidance.
SAT / UNSAT
Tag-Out Serial #:
Date Verified:
____________________ SRF
KTR
3.6
(I)(G) "HYDROSTATIC TEST (SHOP)"
Accomplish a hydrostatic test using clean fresh water at 87 PSIG for a minimum of 10 minutes, for the equipment listed in 1.3.1, using 2.4 and 2.9 for guidance. Allowable leakage: None.
SAT / UNSAT
Date/Time:
_________________ SRF
SSP: SING-017-26 6 of 7 ITEM NO: 256-61-001
KTR
3.6.1
Submit one legible copy, in hard copy or approved transferrable media, a report listing calibration certification of all gauges used for hydrostatic testing.
Report must contain gauge serial number, gauge test range, and expiration date of certification.
Date Submitted:
Report Serial#:
SRF
KTR
3.7
(I)(G) "SEAT TIGHTNESS TEST" (SHOP)
Accomplish seat tightness testing for a minimum of 3 minutes. Allowable leakage: None.
Ensure the seat tightness test pressure is 58 PSIG
SAT / UNSAT
Date/Time:
_________________ SRF
KTR
3.9
(I)(G) “OPERATIONAL TEST (SHOP)”
Accomplish an operational test using clean fresh water for the equipment listed in 1.3.1 and using 2.4 for guidance.
SAT / UNSAT
Date/Time:
SRF
KTR
3.10
(V)(G) “VERIFY CLEANLINESS”
Verify existing cleanliness Level III was maintained throughout the performance of this work item. Level III cleanliness is a degree of cleanliness that results in a surface that is reasonably free of contamination and any remaining residue on the surface does not interfere with system operations or damage system components.
SAT / UNSAT
Date/Time:
SRF
3.13
(V)(G) “FINAL VISUAL INSPECTION”
Accomplish final visual inspection with the SUPERVISOR and designated Ship's Force
Representative of the repaired valve.
SAT / UNSAT
DATE/TIME:__________________
KTR
SSP: SING-017-26 7 of 7 ITEM NO: 256-61-001
Work Completed:
Sign: _____________________________ Print: _____________________________Date: __________
PROJECT MANAGER
S / F
SRF
SHIP: USS HIGGINS (DDG 76) ITEM NO: 261-12-001
COAR: 26 PCN: EB14-L010
CMP: NONE
PLANNER: CARPIO, EDWIN
BAUSER, BRANDON
SSP: SING-017-26 1 of 7 ITEM NO: 261-12-001
1. SCOPE:
1.1 Title: Fuel Oil Service Pump Suction Valve; replace
1.2 Location of Work:
1.2.1 Engine Room Number 2 (4-254-0-E)
1.3 Identification:
1.3.1 Quantity (One EA), Motor Operated Fuel Oil Gate Valve, Size:
3.00 IPS, 150 PSI FLGE., Mfr: Morpac Industries Inc., Mfr ID: 10017- 2, Equipment Spec: MIL-V-18110, Capacity: 72 GPM, NSN:4810-01-658- 7068, APL: 883041370, Valve No.: 2-FS-V-2B for 2B F/O Service Tank.
1.3.1.1 Quantity (One EA), Gate Valve, 3.00 IPS 150 PSI, Flange, Stainless Steel, Mfr ID/Part Number: S15F2316MP 3" DDG 870110, NSN: 4820-01-327-7736, APL: 883041233
2. REFERENCES:
2.1 NAVSEA Standard Items, (FY26)
2.2 S0400-AD-URM-010 Rev 8, Tag-Out Users Manual
2.3 S6435-SZ-MMA-010 Rev 1, Electric Motor Operated Valves
2.4 261-6218469 Rev J, PRPLN GTRB and Gas Turbine Gen Fuel Service System Diagram
2.5 505-6596813 Rev Y, Instl Mchry & Pp Hold Fr 254 to 300 (Stbd)
2.6 802-5959353 Rev BT, MIL-STD-777D Modified for DDG-51 Class, Schedule of Piping, Valves, Fittings and Associated Piping Components for Naval Surface Ships
2.7 10017 Rev M, Valve Assembly 3 IN Gate
3. REQUIREMENTS:
(V)(G) "TAG-OUT VERIFICATION"
3.1 In accordance with 2.3, prior to commencement of work, contractor must obtain Ship's Force signature on Enclosure (One) as verification of tag out and record tag out serial number for equipment identified in
1.3.1 and located in 1.2, using 2.2 for guidance. Allowable discrepancy None. Annotate tag-out serial number. Document on Enclosure (One).
3.2 Remove and dispose of each system fluid from the equipment listed in 1.3.1.
3.3 Disconnect electrically and mechanically and remove the valve listed in 1.3, using paragraph 6-6.8 of 2.3 and 2.4 for guidance. Record and retain electrical hook-up data.
3.3.1 Remove existing and install new material provided in 5.1, and listed in 1.3, using 2.3 through 2.6 for guidance.
TOTAL
QUANTITY
NAME OF
PART PIECE NO. REF. NO.
FIGURE/DRAWING
NO. PART NO.
SSP: SING-017-26 2 of 7 ITEM NO: 261-12-001
REQUIRED
1 SH Gasket, 3" Valve, (Bluegard 3000 or equal)
5 2.3/2.6 Table 7-12, page 69/154
Commercial
4 EA Screw, Cap, Hex Head, 3/8- 16 X 1", Monel
4 2.3 Table 7-12 Commercial
4 EA Screw, Cap, Hex Head, 3/4- 10 X 1- 1/8", Monel
5 2.3 Table 7-12 Commercial
3.3.2 Restore piping flange mating surfaces exposed by disassembly of piping system. Repair by removing high spots, burrs, abrasions, and foreign matter, where removal can be accomplished by hand tools.
Take precautions to maintain phonographic finish on flanges that have it.
3.3.3 Chase and tap each exposed threaded area.
3.3.4 Each new material must conform to 2.6, including Category and Group E-5.
3.4 Assemble valve and install actuator using paragraph 6-6.8.4 of 2.3 for guidance and material requirements.
3.4.1 Install new gaskets, o-rings, pins, keys, studs, bolts, and nuts. Material shall conform to specifications in Chapter 7 of 2.3.
(V)(G) "STRAIN FREE"
3.5 Align piping to the valve. Piping shall be supported independently and shall not impose a strain. Accomplishment of alignment by adjustment of the first adjacent hanger is to be considered within the scope of the work. Document results on Enclosure (One).
(V)(G) "POSITION INDICATOR ASSEMBLY ADJUSTMENT"
3.6 Accomplish valve position indicator adjustment using paragraph 6-2 of 2.3 for guidance. Document results on Enclosure (One).
3.6.1 Adjust 1/4 and 1/2 turn valve position indicator using Table 6-2, pinion to switch matrix and Figure 6-1 of 2.3.
(V)(G) "STOP SCREW ADJUSTMENT"
3.7 Accomplish turn assemblies stop screw adjustment using paragraph 6-3 of 2.3 for guidance. Document results on Enclosure (One).
3.7.1 Adjust stop screws using paragraph 6-3.1 of 2.3 for guidance.
(V)(G) "MECHANICAL INDICATOR ADJUSTMENT"
3.8 Accomplish mechanical indicator adjustment using paragraph 6-4.1 of
2.3 for guidance. Acceptance criteria: Mechanical Indicator Open/Close
SSP: SING-017-26 3 of 7 ITEM NO: 261-12-001 position: Satisfactory. Document results on Enclosure (One).
(V)(G) "TORQUE LIMIT ADJUSTMENT"
3.9 Accomplish torque limit adjustment in accordance with Paragraph 6.5, and Figure 6-4 of 2.3. Allowable over torque: None. Document results on Enclosure (One)
3.9.1 Set torque barrel adjustment using paragraph 6-5.1 of 2.3 for guidance.
3.9.2 Adjust torque arm using paragraph 6-5.2 of 2.3.
3.9.3 Accomplish torque adjustment:
3.9.3.1 Back off the torque barrel nut (1) until there is no
tension on the torque spring (10).
3.9.3.2 Turn the torque barrel nut (1) in 1/2 turn increments until actuator operates through a full cycle.
(V)(G) "OPERATIONAL TEST"
3.10 Accomplish an operational test of the motor operated valve listed in 1.3, locally and remotely using shipboard procedures and Chapter 2 of
2.3 for guidance. Allowable external leakage or deformation: None.
Document results in Enclosure (One).
3.10.1 Cycle the valve from full closed to full open to full closed 3 times once manually, once locally and once remotely from fuel oil console verifying valve position open/closed each time. Allowable binding: None.
3.11 Accomplish the requirements of 009-032 of 2.1 for disturbed surfaces.
3.12 Install new aluminized cloth spray shields on fuel oil piping and valve flanges and components in accordance with ASTM-F-1138.
(V)(G) "COMPARTMENT CLOSEOUT"
3.13 Accomplish a joint inspection with the SUPERVISOR upon completion, inspection, and acceptance, by the contractor, of work within each compartment. Acceptance criteria is completion of all contractor work within the compartment inclusive of associated Work Items, and settled changes to associated Work Items. Document results on Enclosure (One).
3.14 Submit one legible copy, in hard copy or approved transferrable media, of Enclosure (One) to the SUPERVISOR within 3 days from completion of repair. Document results on Enclosure (One).
4. NOTES:
4.1 NAVSEA Standard Items are available at:
https://www.navsea.navy.mil/Home/RMC/CNRMC/Our-Programs/SSRAC/
4.2 Enclosure (One) is a Test and Inspection Verification Sheet (TIVS).
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
TOTAL
QUANTITY
PROVIDED NAME Of PART
PIECE
NO.
REF
NO.
NATIONAL
STOCK
NO.
REQ
PARA NO.
SSP: SING-017-26 4 of 7 ITEM NO: 261-12-001
1. 1 EA
Actuator Assembly, Stainless Steel Gate Valve, 3", Integral Controller, P/N:
10017-2
Table 7- 12, 6-15 2.3
4810-01- 658-7068 3.3
5.2 PUSH MATERIAL:
1. None.
SSP: SING-017-26 5 of 7 ITEM NO: 261-12-001
Enclosure (One)
TEST AND INSPECTION VERIFICATION SHEET (TIVS)
REV/
PARA
REQUIREMENTS / COMPONENT
IDENTIFICATION RESULTS ACTIVITY SIGNATURE/PRINTED NAME
KTR
3.1
(V)(G) "TAG-OUT VERIFICATION"
In accordance with 2.3, prior to commencement of work, contractor must obtain Ship’s Force signature on Enclosure (One) as verification of tag-out and record tag-out serial number for equipment identified in 1.3.1 and located in 1.2, using 2.2 for guidance.
Allowable discrepancy: None
Annotate tag-out serial #: _____________
SAT / UNSAT
Date/Time_____________________
SRF DET SG
KTR
3.5
(V)(G) “STRAIN FREE”
Align piping to the valve. Piping shall be supported independently and shall not impose a strain.
Accomplishment of alignment by adjustment of the first adjacent hanger is to be considered within the scope of the work.
SAT / UNSAT
Date/Time_____________________
SRF DET SG
KTR
3.6
(V)(G) “POSITION INDICATOR
ASSEMBLY ADJUSTMENT”
Accomplish valve position indicator adjustment using paragraph 6-2 of 2.3 for guidance.
SAT / UNSAT
Date/Time_____________________
SRF DET SG
KTR
3.7
(V)(G) “STOP SCREW ADJUSTMENT”
Accomplish turn assemblies stop screw adjustment using paragraph
6-3 of 2.3 for guidance.
Date/Time_____________________ SRF DET SG
SSP: SING-017-26 6 of 7 ITEM NO: 261-12-001
Work Completed:
KTR
3.8
(V)(G) “MECHANICAL INDICATOR
ADJUSTMENT”
Accomplish mechanical indicator adjustment using paragraph 6-4.1 of 2.3 for guidance.
Date/Time_____________________
SRF DET SG
KTR
3.9
(V)(G) “TORQUE LIMIT ADJUSTMENT”
Accomplish torque limit adjustment in accordance paragraph 6.5 and
Figure 6-4 of 2.3.
SAT / UNSAT
Date/Time_____________________ SRF DET SG
KTR
3.10
(V)(G) “OPERATIONAL TEST”
Accomplish an operational test of the motor operated valve listed in 1.3, locally and remotely using shipboard procedures and Chapter 2 of 2.3 for guidance.
SAT / UNSAT
Date/Time_____________________
SRF DET SG
KTR
3.13
(V)(G) “COMPARTMENT CLOSEOUT”
Accomplish a joint inspection with the SUPERVISOR upon completion, inspection, and acceptance by the contractor, of work within each compartment. Acceptance criteria is completion of all contractor work within the compartment inclusive of associated Work Items, and settled changes to associated Work Items.
Date/Time_____________________
SRF DET SG
KTR
3.14
Submit one legible copy, in hard copy or approved transferrable media, of Enclosure (One) to the SUPERVISOR within 3 days from completion of repair.
Enclosure (One) Submitted
YES / NO
Date:______________ SRF DET SG
SSP: SING-017-26 7 of 7 ITEM NO: 261-12-001
Sign: _______________________Print:___________________Date:________________________
SHIP: USS HIGGINS (DDG 76) ITEM NO: 320-10-001
COAR: 26 PCN: CM02-L011
BWST FILE NO: 000-001 CMP: NONE
REVISED: 05 APR 2019 PLANNER: CANLAS, CHRISTIAN
BALDOVINO, ROMMEL
BAUSER, BRANDON
GRAY, CHARLES
SSP: SING-017-26 1 of 15 ITEM NO: 320-10-001
1. SCOPE:
1.1 Title: Multiple Cable Transit (MCT) Block; install
1.2 Location of Work:
1.2.1 Fan Room (1-78-2-Q)
1.3 Identification:
1.3.1 Quantity (One EA), Multi-Cable Transit, Steel, Hole No. 1450- E-745, Penetration No. ETR-SR-44104, Checkpoint No. T016 (18'-0" OFF
CL, PORT, 0'-5" AFT OF FR 78, 5" BELOW 01 LVL).
2. REFERENCES:
2.1 NAVSEA Standard Items, (FY 26)
2.2 MIL-STD-2003-3B Rev 3B, Electric Plant Installation Standard Methods for Surface Ships and Submarines (Penetrations)
2.3 S1005506, Roxtec R Frames Information Drawing
2.4 ASS2005002501, Roxtec Installation Instructions
3. REQUIREMENTS:
(V)(G) "RECEIPT INSPECTION"
3.1 Accomplish receipt inspection of each equipment listed in 1.3. and provided in 5.2 with the SUPERVISOR to ensure equipment is suitable to existing vessel configuration. Allowable damage or deformation: None.
Documents results in Enclosure (One).See Note 4.2.
3.2 Install new each missing or defective MCT neoprene insert block for the equipment listed in 1.3 and located in 1.2, as designated by the SUPERVISOR, in accordance with Section 4 of 2.2, using 2.3 and 2.4 for guidance.
3.2.1 Template exact size, location and configuration from existing shipboard condition.
(V)(G) "AIR TEST"
3.3 Accomplish the requirements of 009-025 of 2.1 for air hose test of the restored MCT listed in 1.3 and located in 1.2, to include each sealing block and compression plate. Allowable leakage: None.
3.3.1 Air hose nozzle must be placed at less than 3 inches, but greater than zero inches, from the area to be tested and pressure directed at the structure under test in a manner most likely to disclose leaks. The minimum nozzle diameter must be 3/8 inch and the nozzle pressure must be 90 plus or minus 5 PSIG as monitored at the nozzle.
3.3.1.1 Apply a soapy solution to the opposite side of the
structure and inspect for leaks.
SSP: SING-017-26 2 of 15 ITEM NO: 320-10-001
3.3.1.2 Inspect joint or fitting for leakage by observing for formation of bubbles. Allowable leakage: None.
3.3.2 Submit one legible copy, in hard copy or electronic media, of a report listing results of the requirements of 3.3 to the SUPERVISOR. Document in Enclosure (One).
3.4 Accomplish the requirements of 009-032 of 2.1 for new and disturbed surfaces.
(V)(G) "COMPARTMENT CLOSE-OUT"
3.5 Accomplish a joint inspection with the SUPERVISOR upon completion, inspection, and acceptance, by the contractor, of work within each compartment. Acceptance criteria is completion of all contractor work within the compartment inclusive of associated Work Items, and settled changes to associated Work Items. Document on Enclosure (One).
3.6 Submit one legible copy, in hard copy or approved transferrable media, of Enclosure (One) to the SUPERVISOR within 3 days of repair completion. Document in Enclosure (One)
4. NOTES:
4.1 NAVSEA Standard Items are available at:
https://www.navsea.navy.mil/Home/RMC/CNRMC/Our-Programs/SSRAC/
4.2 Enclosure (One) - Test and Inspection Verification Sheet.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
TOTAL
QUANTITY
PROVIDED NAME Of PART
PIECE
NO.
REF
NO.
NATIONAL
STOCK
NO.
REQ
PARA NO.
1. 4 EA
RM 20W40 3.5-
16.5 2 2.4
RM001204
01000 3.2
2. 2 EA RM30 10-25 3 2.4
RM001003
01000 3.2
3. 2 EA RM20 4-14.5 4 2.4
RM001002
01000 3.2
4. 1 BX RM 10/0 x 12 5 2.4
RM003101
21000 3.2
SSP: SING-017-26 3 of 15 ITEM NO: 320-10-001
SSP: SING-017-26 4 of 15 ITEM NO: 320-10-001
Installation Instructions
Project:
Location:
Transit:
Solution:
Print date:
HIG
Fan Room (1-78-2-Q), LCL WW Hole
No. 1450-E-745
R 125 AISI316 WITH
NET 2026-01-21
SSP: SING-017-26 5 of 15 ITEM NO: 320-10-001
SSP: SING-017-26 6 of 15 ITEM NO: 320-10-001
SSP: SING-017-26 7 of 15 ITEM NO: 320-10-001
Installation instructions Roxtec R frame
Installation
Remove any dirt from the sleeve/ hole.
Lubricate the frame sparsely on the outside with Roxtec Lubricant.
Insert the frame into the sleeve/ hole. Please see table “Aperture dimensions”.
If pipes/cables are pre-routed, an R frame can be cut open with a sharp tool. Cut the longside open between screws.
For R100, cut between screw and corner.
5 6 7
Push the front fittings to the sides. Lubricate the inside of the frame thoroughly, especially into the corners.
If the frame is provided with a net, cut or bend the net with a sharp tool, or your fingers, to enable cables/pipes to pass through at their position in the frame.
Pull the cables through. Please see note on reverse page.
1 2 3 4
SSP: SING-017-26 8 of 15 ITEM NO: 320-10-001
8 9 0.1–1.0 mm 0.004- 0.039”
Adapt modules which are to seal cables or pipes by peeling off layers until you reach the gap seen in pic. 9. The halves may not differ by more than one layer.
Achieve a 0.1-1.0 mm gap between the two halves when held against the cable/pipe.
Lubricate all modules for the frame thoroughly, both the inside and the outside surfaces.
SSP: SING-017-26 9 of 15 ITEM NO: 320-10-001
Insert the modules and cables/ pipes according to your installation plan (transit plan).
Push the front fittings back towards the center.
Tighten the nuts crosswise. The frame will compress until it is sealed. Please see recommended torque in the table.
Torque settings
R 70-R 127 6-7
* The recommended torque depends on several things, e.g cable or pipe size, amount of used lubricant, sleeve size or material in the cable sheath, etc.
R 150-R 200 9-11
Aperture dimensions Type: Aperture
Ø (mm) Clearance depth (mm) Packing space (mm)
R 70 70-71 75 40 x 40
R 75 75-76 75 40 x 40
R 100 100-102 80 60 x 60
R 125 125-127 75 80 x 80
R 127 127-129 75 80 x 80
R 150 150-152 75 90 x 90
R 200 200-202 75 120 x 120
Disassembly Reverse order
Note
■ For optimum reliability, wait 24 hours or longer after installation before exposing the cables/pipes to strain or pressure.
■ To be used with: RM modules.
■ Cables/pipes shall be parallel to the sleevehole.
■ Cable/pipe with a considerable weight needs to be supported to prevent damage or subsidence to the seal.
DIsclaImer ”The Roxtec cable entry sealing system (”the Roxtec system”) is a modular-based system of sealing products consisting of different components. Each and every one of the components is necessary for the best performance of the Roxtec system. The Roxtec system has been certified to resist a number of different hazards. Any such certification, and the ability of the Roxtec system to resist such hazards, is dependent on all components that are installed as a part of the Roxtec system. Thus, the certification is not valid and does not apply unless all components installed as part of the Roxtec system are manufactured by or under license from Roxtec (“authorized manufacturer”). Roxtec gives no performance guarantee with respect to the Roxtec system, unless (I) all compo-nents installed as part of the Roxtec system are manufactured by an authorized manufacturer and (II) the purchaser is in compliance with (a), and (b), below.
Type: Rec. torque* (Nm)
A S
S ver_1.8
/G B
/1235/stsa n
R oxtec ® and M ultidiam eter ® are registered tradem arks of R oxtec in S w eden and/or other countries.
SSP: SING-017-26 10 of 15 ITEM NO: 320-10-001
(a)During storage, the Roxtec system or part thereof, shall be kept indoors in its original packaging at room temperature.
(b) Installation shall be carried out in accordance with Roxtec installation in-structions in effect from time to time.
The product information provided by Roxtec does not release the purchaser of the Roxtec system, or part thereof, from the obligation to independently determine the suitability of the products for the intended process, installation and/or use.
Roxtec gives no guarantee for the Roxtec system or any part thereof and assumes no liability for any loss or damage whatsoever, whether direct, in-direct, consequential, loss of profit or otherwise, occurred or caused by the Roxtec systems or installations containing components not manufactured by an authorized manufacturer.
Roxtec expressly excludes any implied warranties of merchantability and fitness for a particular purpose and all other express or implied representations and warranties provided by statute or common law.
User determines suitability of the Roxtec system for intended use and assumes all risk and liability in con-nection therewith. In no event shall Roxtec be liable for consequential, punitive, special, exemplary or incidental damages.”
Roxtec International AB Box 540, 371 23 Karlskrona, SWEDEN
PHONE +46 455 36 67 00, FAX +46 455 820 12
EMAIL info@roxtec.com, www.roxtec.com mailto:info@roxtec.com http://www.roxtec.com/
SSP: SING-017-26 11 of 15 ITEM NO: 320-10-001
NTS I I Hole No. 1450-E-745 D<awingnumbor
1/1
SSP: SING-017-26 12 of 15 ITEM NO: 320-10-001
RTD Version No: 4.41.14.0
Respo,,S<ble Created Date
SSP: SING-017-26 13 of 15 ITEM NO: 320-10-001
Enclosure (One)
TEST AND INSPECTION VERIFICATION SHEET (TIVS)
PARAGRAPH
REQUIREMENT/COMPONENT
IDENTIFICATION RESULTS ACTIVITY SIGNATURE/PRINTED NAME
KTR
3.1
(V)(G) "RECEIPT INSPECTION"
Accomplish receipt inspection of each equipment listed in
1.3 and provided in 5.2 with the SUPERVISOR to ensure equipment is suitable to existing vessel configuration. Allowable damage or deformation: None.
SAT / UNSAT
DATE/TIME:________________
SRF DET SG
KTR
3.3
(V)(G) "AIR TEST"
Accomplish the requirements of 009-025 of 2.1 for air hose test of the restored MCT listed in 1.3 and located in 1.2, to include each sealing block and compression plate.
Allowable leakage: None.
SAT / UNSAT
DATE/TIME:
SRF DET SG
3.3.2
Submit one legible copy, in hard copy or electronic media, of a report listing results of the requirements of 3.3 through 3.3.1.2 to the
SUPERVISOR.
Report submitted:
YES / NO
DATE/TIME:_________________
KTR
SSP: SING-017-26 14 of 15 ITEM NO: 320-10-001
SRF DET SG
KTR
3.5
(V)(G) "COMPARTMENT CLOSE-
OUT"
Accomplish a joint inspection with the SUPERVISOR upon completion, inspection, and acceptance, by the contractor, of work within each compartment. Acceptance criteria is completion of all contractor work within the compartment inclusive of associated Work Items, and settled changes to associated
Work Items. Document on Enclosure (One).
Report submitted:
YES / NO
DATE/TIME: ______________
SRF DET SG
KTR
3.6
Submit one legible copy, in hard copy or approved transferrable media, of Enclosure (One) to the
SUPERVISOR within 3 days of repair completion.
Report submitted:
YES / NO
DATE/TIME:_______________
SSP: SING-017-26 15 of 15 ITEM NO: 320-10-001
Work Completed:
Sign: Print: Date:
SHIP: USS HIGGINS (DDG 76) ITEM NO: 320-11-001
COAR: 26 PCN: EE02-L007
CSWT FILE NO: 320-002 (DDG 51) CMP: NONE
REVISED: 30 SEP 2024 PLANNER: BALDOVINO, ROMMEL
CANLAS, CHRISTIAN
CARPENTER,
DAVID.SING
GRAY, CHARLES
SSP: SING-017-26 1 of 7 ITEM NO: 320-11-001
1. SCOPE:
1.1 Title: Electrical Cable Replacement; accomplish
1.2 Location of Work:
1.2.1 Passage (1-338-1-L)
1.2.2 AFFF Stowage Room (1-338-3-A)
1.2.3 AFFF Station No. 2 (1-330-1-Q)
1.2.4 Service Interface Room (1-330-0-Q)
1.2.5 Security Station (1-330-2-Q)
1.2.6 Passage (1-318-2-L)
1.2.7 Stateroom (1-330-2-L)
1.2.8 Stateroom (1-314-2-L)
1.2.9 Damage Control Locker (1-304-2-A)
1.2.10 Passage (1-300-01-L)
1.3 Identification:
1.3.1 Quantity (175 LF), Cable Power, Electrical, Circuit: (1-344- 3)-4P-G(1), Cable Type: TXW-4, NSN: 6145-01-225-2151
1.3.2 Quantity (One), Power Panel, 1-344-3, Class Z Vent Zone 3- Panel 2
1.3.3 Quantity (3), Power Transformer, 1-300-2, 3kVA, 450V/120V
2. REFERENCES:
2.1 NAVSEA Standard Items, (FY26)
2.2 320-6218728 Rev AL, One Line Diagram Power System - 60HZ
2.3 321-6220410 Rev AR, Main Cableway - Routing by Checkpoint
2.4 301-6221038 Rev W, DDG-51 Class Installation Electrical Local Wireway Design Zone 3250, Main Deck FR 338-370
2.5 301-6221033 Rev Y, DDG-51 Class Installation Electrical Local Wireway Design Zone 3150, Main Deck FR 300-338
2.6 MIL-STD-2003-3B, Electric Plant Installation Standard Methods for Surface Ships and Submarines
2.7 MIL-STD-1310H, Shipboard Bonding, Grounding and Other Techniques for Electromagnetic Pulse (EMP) Mitigation and Safety
2.8 S9086-KC-STM-010/300 Rev 11, ELECTRIC PLANT - GENERAL
3. REQUIREMENTS:
3.1 Ensure only Qualified Personnel prepare electrical cable endings to
SSP: SING-017-26 2 of 7 ITEM NO: 320-11-001 receive connectors, assemble connector parts on the cable endings, attach the connectors to the cable endings, supervise, and inspect the execution of the process.
3.1.1 Submit one legible copy, in hard copy or approved
transferrable media, of the credentials of the Qualified Personnel accomplishing connector fabrication, Supervision, and QA Inspection to the SUPERVISOR prior to the start or continuation of work. Submit any change as it occurs. Document in Enclosure (One)
(V)(G) "RECEIPT INSPECTION"
3.2 Accomplish receipt inspection with the SUPERVISOR of the materials provided in 5.1 to accomplish required repairs for the equipment listed in 1.3.1 and located in 1.2.2. Allowable deformation or damage: None.
Documents results in Enclosure (One). See Note 4.2.
(V)(G) "TAG-OUT VERIFICATION"
3.3 Prior to commencement of work, contractor shall obtain Ship's Force signature on Enclosure (One) as verification of tag out and record tag-out serial number using 2.2 for guidance. Document results in Enclosure (One).
3.4 Accomplish an insulation resistance test of each electric cable conductor using the appropriate direct current megger using Table 300-3-4 of 2.8 for guidance prior to disconnecting cable.
3.4.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.3 to the SUPERVISOR within 24 hours of testing. Document in Enclosure (One).
3.5 Disconnect and remove cable listed in 1.3 in the location listed in
1.2 from Power Panel 1-344-3 to Power Transformer 1-300-2 using sheet 163A of 2.2 for guidance. Record electrical hook-up data.
3.5.1 Accomplish a visual inspection of the equipment listed in 1.3 at the location listed in 1.2 for any signs of burns, cracks, or fraying of insulation..
3.5.1.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.5.1 to the SUPERVISOR. Document in Enclosure (One)
3.6 Install new cable identified in 1.3 in the location listed in 1.2, installing new terminal lugs, fasteners and nuts conforming to MIL-DTL- 1222, Type I or II, Grade 5, zinc coated inside void and 316 CRES fasteners and nuts.
3.6.1 Electrically connect equipment listed in 1.3 using 2.6 and hook-up data of 3.5 for guidance.
3.6.2 Bond and ground equipment listed in 1.3 in accordance with 2.7.
3.7 Accomplish an insulation resistance test of each electric cable conductor using the appropriate direct current megger using Table 300-3-4 of 2.8 for guidance after reconnecting cable.
3.7.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements
SSP: SING-017-26 3 of 7 ITEM NO: 320-11-001 of 3.7 to the SUPERVISOR within 24 hours of testing. Document in Enclosure One
(V)(G) "LOCAL AIR HOSE TEST"
3.8 Accomplish the requirements of 009-025 of 2.1 for a local air hose test on each bulkhead penetration using 2.3 through 2.5 for guidance.
Allowable leakage: None. Document in Enclosure (One)
3.8.1 The minimum nozzle diameter must be 3/8 inch and the nozzle pressure must be 90 plus or minus 5 PSIG as monitored at the nozzle.
3.8.2 Apply a soapy solution to the opposite side of the structure and inspect for leaks.
3.8.3 Air hose nozzle must be placed at less than 3 inches, but greater than zero inches, from the area to be tested and pressure directed at the structure under test in a manner most likely to disclose leaks.
3.8.4 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of Local Air Hose Test on each bulkhead penetration to the SUPERVISOR. Document in Enclosure (One).
3.9 Accomplish the requirements of 009-032 of 2.1 for each new and disturbed surface.
(V)(G) "COMPARTMENT CLOSE-OUT"
3.10 Accomplish a joint inspection with the SUPERVISOR upon completion, inspection, and acceptance, by the contractor, of work within each compartment. Acceptance criteria is completion of all contractor work within the compartment inclusive of associated Work Items, and settled changes to associated Work Items. Document on Enclosure (One).
3.11 Submit one legible copy, in hard copy or approved transferrable media, of Enclosure (One) to the SUPERVISOR within 3 days of repair completion.
4. NOTES:
4.1 NAVSEA Standard Items (NSIs) are located at:
https://www.navsea.navy.mil/Home/RMC/CNRMC/Our-Programs/SSRAC/
4.2 Enclosure (One) is a Test and Inspection Verification Sheet (TIVS).
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
TOTAL
QUANTITY
PROVIDED NAME Of PART
PIECE
NO.
REF
NO.
NATIONAL
STOCK
NO.
REQ
PARA NO.
1. 250 FT
Cable, Power, Electrical N/A 2.2
61450122 52151 3.6
5.2 PUSH MATERIAL:
1. None.
SSP: SING-017-26 4 of 7 ITEM NO: 320-11-001
Enclosure (One)
TEST AND INSPECTION VERIFICATION SHEET (TIVS)
PARAGRAPH
REQUIREMENT/COMPONENT
IDENTIFICATION RESULTS ACTIVITY SIGNATURE/PRINTED NAME
KTR
3.1.1
Submit one legible copy, in hard copy or approved transferrable media, of the credentials of the Qualified Personnel accomplishing connector fabrication, Supervision, and QA Inspection to the
SUPERVISOR prior to the start or continuation of work. Submit any change as it occurs.
Report submitted:
YES / NO
DATE/TIME:_________________
SRF DET SG
KTR
3.2
(V)(G) "RECEIPT INSPECTION"
Accomplish receipt inspection with the SUPERVISOR of the materials provided in
5.1 to accomplish required repairs for the equipment listed in 1.3.1 and located in 1.2.2. Allowable deformation or damage: None.
Acceptable Criteria: Allowable deformation or damage: None.
SAT / UNSAT
DATE/TIME:________________
SSP: SING-017-26 5 of 7 ITEM NO: 320-11-001
KTR
S / F3.3
(V)(G) “TAG-OUT VERIFICATION”
Prior to commencement of work, contractor shall obtain Ship's Force signature on Enclosure (One) as verification of tag out and record tag-out serial number using 2.2 for guidance.
Tag-out No. _____________
SAT / UNSAT
DATE/TIME:__________________
SRF DET SG
KTR
3.4.1 Submit one legible copy, in hard copy or
approved transferrable media, of a report listing results of the requirements of 3.4 to the SUPERVISOR within 24 hours of testing.
Report submitted:
YES / NO
DATE/TIME:_________________
SRF DET SG
KTR
3.5.1.1
Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of 3.5.1 to the SUPERVISOR.
Report submitted:
YES / NO
SSP: SING-017-26 6 of 7 ITEM NO: 320-11-001
KTR
3.7.1
Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of 3.7 to the SUPERVISOR within 24 hours of testing
Report submitted:
YES / NO
DATE/TIME:_________________
SRF DET SG
KTR
3.8
(V)(G) "LOCAL AIR HOSE TEST”
Accomplish the requirements of 009-025 of 2.1 for a local air hose test on each bulkhead penetration using 2.3 through
2.5 for guidance.
Acceptable Criteria: Allowable leakage:
None.
SAT / UNSAT
DATE/TIME:
SRF DET SG
KTR
3.8.4 Submit one legible copy, in hard copy or
approved transferrable media, of a report listing results of Local Air Hose Test on each bulkhead penetration to the
SUPERVISOR.
Report submitted:
YES / NO
SSP: SING-017-26 7 of 7 ITEM NO: 320-11-001
S/F
KTR
3.10
(V)(G) "COMPARTMENT CLOSE-OUT"
Accomplish a joint inspection with the SUPERVISOR upon completion, inspection, and acceptance, by the contractor, of work within each compartment. Acceptance criteria is completion of all contractor work within the compartment inclusive of associated Work Items, and settled changes to associated Work Items.
Acceptable Criteria:
SAT / UNSAT
DATE/TIME:
SRF DET SG
KTR
3.11
Submit one legible copy, in hard copy or approved transferrable media, of
Enclosure (One) to the SUPERVISOR within 3 days of repair completion.
report submitted:
YES / NO
DATE/TIME:_________________
SRF DET SG
Work Completed:
SHIP: USS HIGGINS (DDG 76) ITEM NO: 551-62-001
COAR: 26 PCN: EM01-3347
CMP: NONE
PLANNER: MARCOS, FRANK SRFDS
BARTOLOME, LUCIANO
BAUSER, BRANDON
SSP: SING-017-26 1 of 6 ITEM NO: 551-62-001
1. SCOPE:
1.1 Title: No. One Oil Distribution Box Prairie Air Flexible Hose Fabricate; accomplish
1.2 Location of Work:
1.2.1 Ship to Shop
1.3 Identification:
1.3.1 Quantity (One EA), Prairie Air Supply Flexible Hose to O.D.
Box, 1 1/2 Inch NPS, 150 PSI, Flanged, Bronze, Hose Number: 1-PA-F-1, MIL-H-24135-10 Aeroquip 2651 or Equal, Sheet 3A, Plan 3A-4A, Zone 8E of 2.2 and Sheet 19A of 2.3
2. REFERENCES:
2.1 NAVSEA Standard Items, (FY26)
2.2 551-6218461 Rev N, GTRB Bleed, Starting Anti-Icing & Prairie/Masker Air Sys Diag
2.3 551-6218461BK Rev N, GTRB Bleed, Starting, Anti-Icing & Prairie/Masker Air System Diagram Engineering Data Booklet
2.4 S6430-AE-TED-010 Rev 8, Piping Devices and Flexible Hose Assemblies
3. REQUIREMENTS:
3.1 Obtain from SUPERVISOR the equipment identified in 1.3 and take to contractor facility.
3.2 Fabricate new Flexible Hose Assembly using Government Furnish Material (GFM) listed in 5.2. Template from existing size and configuration of the Flexible Hose Assembly obtained in 3.1, using 2.2 through 2.4 for guidance.
3.2.1 Inspect existing flexible hose end fittings in accordance with paragraph 5-2 of 2.4., and reuse where found acceptable. Allowable damaged: None
3.2.2 Inspect new flexible hose in accordance with paragraph 5-1 of
2.4. Allowable damaged: None
3.2.3 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.2.1 and 3.2.2 to the SUPERVISOR. Document on Enclosure (One).
(I)(G) "HYDROSTATIC TEST"
3.3 Accomplish hydrostatic test in accordance with paragraph 7-2 of 2.4 of the new flexible hose assembly. Acceptance criteria: Hose shall not burst, leak, or show signs of fitting separation. Document results on Enclosure (One).
3.3.1 Draw a chalk line around the circumference of the hose next to each fitting attachment in accordance with 7-2.a of 2.4. Measure distance from the lines to fitting edges radially at four places that
SSP: SING-017-26 2 of 6 ITEM NO: 551-62-001 are 90° apart, record measurement.
3.3.2 Using freshwater or other appropriate liquid, apply a proof pressure (300 PSIG) equivalent to twice the rated hose working pressure. Hold this pressure for 1 to 5 minutes.
3.3.2.1 Use two pressure gauges when performing hydrostatic
tests. Use a master gauge having a scale range greater than the maximum test pressure, but not exceeding 200 percent of maximum test pressure.
3.3.2.2 Each master and backup test gage shall conform to gage range and graduation shown on Table 504-6-1 of 2.4. The backup gage shall be cross-checked to the master hydrostatic test gage up to the maximum test pressure just prior to start of testing.
Master and backup gages shall track within 2 percent of each other. Record serial number, range, and calibration due date for each gauge used on Enclosure (One).
(I)(G) "HOSE MEASUREMENT"
3.3.3 Upon completion of test, measure the distance from the chalk lines to the fittings in accordance with paragraph 7-2.d of 2.4.
Allowable change in measured distance from chalk line to fitting:
None. Document results on Enclosure (One).
3.4 Upon satisfactory hydrostatic test install on new CRES
identification tag on each flexible hose assembly engraved in accordance with Paragraph 7-4 of 2.4.
3.4.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing the identification tag test data for each hose assembly tested to the SUPERVISOR. Document on Enclosure (One).
(I)(G) "HOSE CLEANLINESS INSPECTION"
3.5 Inspect new flexible hose assembly for cleanliness prior to delivery. Surface shall be visually free of grease, oil, flux, scale, dirt, loose particles and any other foreign contamination. Document result on Enclosure (One).
3.6 Deliver new flexible hose assembly to the SUPERVISOR.
3.7 Submit one legible copy, in hard copy or approved transferrable media, of Enclosure (One) to the SUPERVISOR within 3 days from completion of repair. Document results on Enclosure (One).
4. NOTES:
4.1 NAVSEA Standard Items (NSI) are available at:
https://www.navsea.navy.mil/Home/RMC/CNRMC/Our-Programs/SSRAC.
4.2 Enclosure (One) is a Test and Inspection Verification Sheet (TIVS).
5. GOVERNMENT…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .