This document is a Price Proposal (Exhibit B) for ITB# OFN/250008, issued by the City of Ocala, Florida for an Underground Conduit Installation contract. The solicitation covers comprehensive conduit installation services, including trenching, hand digging, plowing, backhoe, missile-stitch bore, and directional boring techniques for 1.25", 2", and 3" conduit. The contract includes installation of various infrastructure components such as stub-ups, u-guards, fiber pedestals, flush vaults, fiber pulling, service drops, and related site restoration work. The estimated quantities range from 20 to 150,000 linear feet/units across different installation methods and equipment types, with a total of 42 distinct line items for pricing.
The price proposal template requires bidders to complete unit costs for each line item, which will then calculate the extended cost and total bid amount. While no specific pricing is filled in, the document provides a comprehensive framework for contractors to propose rates for underground conduit installation services. The contract appears designed to provide flexible infrastructure installation capabilities with multiple method options, allowing the City of Ocala to utilize the most appropriate technique for each specific project location and condition. The broad scope suggests the intent is to establish a comprehensive, multi-year contract for ongoing underground utility infrastructure development and maintenance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Exhibit B - PRICE PROPOSAL CONTRACT# OFN/250008
| Bidder name | Bidder Location |
| ENTER COMPANY NAME HERE | ENTER OFFICE LOCATION HERE |
| INITIAL CONTRACT TERM PRICING | |||||
| ITEM | DESCRIPTION | UOM | EST QTY | UNIT COST | EXTENDED COST |
| 1 | 1.25" conduit - Trenching | LF | 10,000 | $ - 0 | |
| 2 | 1.25" conduit - Hand dig | LF | 500 | $ - 0 | |
| 3 | 1.25" conduit - Plowed | LF | 50,000 | $ - 0 | |
| 4 | 1.25" conduit - Backhoe | LF | 500 | $ - 0 | |
| 5 | 1.25" conduit - Missile-Stitch Bore | LF | 150,000 | $ - 0 | |
| 6 | 1.25" conduit - Directional | LF | 10000 | $ - 0 | |
| 7 | 2" conduit - Trenching | LF | 1,000 | $ - 0 | |
| 8 | 2" conduit - Hand dig | LF | 500 | $ - 0 | |
| 9 | 2" conduit - Plowed | LF | 5,000 | $ - 0 | |
| 10 | 2" conduit - Backhoe | LF | 500 | $ - 0 | |
| 11 | 2" conduit - Missile-Stitch Bore | LF | 1,000 | $ - 0 | |
| 12 | 2" conduit - Directional | LF | 500 | $ - 0 | |
| 13 | 3" conduit - Trenching | LF | 500 | $ - 0 | |
| 14 | 3" conduit - Hand dig | LF | 500 | $ - 0 | |
| 15 | 3" conduit - Plowed | LF | 500 | $ - 0 | |
| 16 | 3" conduit - Backhoe | LF | 500 | $ - 0 | |
| 17 | 3" conduit - Missile-Stitch Bore | LF | 500 | $ - 0 | |
| 18 | 3" conduit - Directional | LF | 500 | $ - 0 | |
| 19 | 1.25" Stub-up | EA | 100 | $ - 0 | |
| 20 | 2" Stub-up | EA | 100 | $ - 0 | |
| 21 | 3” Stub-up | EA | 100 | $ - 0 | |
| 22 | Install U-Guard at Pole | EA | 500 | $ - 0 | |
| 23 | Fiber Pedestal placement | EA | 500 | $ - 0 | |
| 24 | 12X20 Flush Vault placement | EA | 1500 | $ - 0 | |
| 25 | 17X30 Flush Vault placement | EA | 250 | $ - 0 | |
| 26 | 24X36 Flush Vault placement | EA | 100 | $ - 0 | |
| 27 | Fiber Pedestal replacement | EA | 50 | $ - 0 | |
| 28 | 12x20 Flush Vault replacement | EA | 50 | $ - 0 | |
| 29 | 17x30 Flush Vault replacement | EA | 50 | $ - 0 | |
| 30 | 24x36 Flush Vault replacement | EA | 20 | $ - 0 | |
| 31 | Pulling fiber in conduit | LF | 200,000 | $ - 0 | |
| 32 | Pulling additional fibers in conduit simultaneously | LF | 50,000 | $ - 0 | |
| 33 | Pulling tracer in conduit | LF | 150,000 | $ - 0 | |
| 34 | Sod | SF | 500 | $ - 0 | |
| 35 | Asphalt remove/replacement (1” Thick) | SF | 500 | $ - 0 | |
| 36 | Cement remove/replacement (4” Thick) | SF | 500 | $ - 0 | |
| 37 | Miscellaneous installation of equipment (pole or pad mount) | HR | 100 | $ - 0 | |
| 38 | Labor Cost to Dig up/Search for Conduit | HR | 1,000 | $ - 0 | |
| 39 | Wall Fish fiber to Point of Service | EA | 1,600 | $ - 0 | |
| 40 | Install service drop up to 125' | EA | 500 | $ - 0 | |
| 41 | Install service drop over 125' | LF | 500 | $ - 0 | |
| 42 | Emergency Mobilization | HR | 500 | $ - 0 | |
| TOTAL BID AMOUNT | $ - 0 |