ITB-2025-06_Russell_Harber_Dock_Replacement_-_Bid_Form.pdf
PDF 20 KB Posted
- Attached to
- Russell Harber Dock Replacement State and local contract opportunity
- Solicitation number
- ITB-2025-06
- Issued by
- Florida
About this file
This document is a Bid Form for the Russell Harber Landing Hurricane Sally Storm Damage Repairs project, issued by the City of Milton, Florida, and associated with FEMA Project 160536. The bid covers a comprehensive dock repair and replacement initiative involving the removal of existing 30-foot timber piles and installation of new infrastructure, including 6 new 50-foot by 13-inch diameter composite piles, a new floating dock measuring 6.5 feet wide by 60 feet long, 10 aluminum cleats, and associated site preparation and erosion control measures. The project requires mobilization, payment and performance bonds, removal of existing structures, clearing of driving lanes, installation of pile guides, and restoration of riprap and gangway elements.
The bid form is structured as an itemized cost breakdown with unit pricing for various project components, emphasizing in-place costs that include materials, hardware, shipping, fabrication, labor, equipment, insurance, bonds, permits, taxes, overhead, and profit. While no specific total project cost is listed, the detailed line items suggest a comprehensive marine infrastructure restoration effort. The project appears to be funded through FEMA and follows Florida Department of Transportation (FDOT) standard specifications, particularly for fill materials and riprap sizing. The document indicates a professional approach to storm damage repair, with careful consideration of environmental controls and precise technical specifications for dock reconstruction.
View the file
Other files for this state and local contract opportunity
Show all 34
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Russell Harber Landing Hurricane Sally Storm Damage Repairs City of Milton, Florida
FEMA PROJECT 160536
System Item Type Unit Qty Cost per Unit TOTAL COST
1.01 Mobilization / Demobilization Assumes barge equipment for installation of piles LS 1.00
1.02 Payment and Performance Bonds Payment and Performance Bonds LS 1.00
1.03 Erosion and Sediment Control Silt curtain, biologs, silt fence, straw and native seed LS 1.00
1.04 Removals Removal of existing 30 foot x 10-inch diameter timber piles EA 5.00
1.05 Clearing the Driving Lane Removing obstructions and riprap from driving lane for new piling. Includes EA 6.00
1.06 Dock Piles New 50 foot by 13-in diameter composite piles EA 6.00
1.07 Pile Guides New guide pockets for piles EA 6.00
1.08 Floating Dock New floating dock 6.5 feet wide by 60 feet long SF 390.00
1.09 Aluminum Cleats 14" aluminum dock cleats EA 10.00
1.10 Salvage and Reinstall Salvage and Reinstall existing riprap and gangway LS 1.00
1.11 Fill Materials - Bedding Stone Sizing per 2025 FDOT Standard Specifications Section 530-2.1.4 CY 45.00
1.12 Geotextile Fabric High Strength Non-Woven Geotextile Fabric SY 225.00
1.13 Riprap Sizing per 2025 FDOT Standard Specifications Section 530-2.1.3 CY 150.00
Highlighted lines indicate mitigation items -$
RUSSELL HARBER PARK DOCK REPAIR/REPLACMENT BID FORM
NOTE: All costs are to be considered in-place costs. Include cost for all materials, hardware, shipping, fabrication, labor, equipment, insurance, bonds, permits state and local taxes, overhead and profit to properly install items listed under each system.
FLOATING DOCK WITH COMPOSITE PILING (MITIGATION)
PROJECT TOTALS
CONSTRUCTION COST TOTAL
AMI Consulting Engineers PA Confidential 4/30/2025 Page 1