This Invitation to Bid (ITB-20-2026) is issued by the City of Murfreesboro, Tennessee, for comprehensive roof structure and interior repairs at 519 E. State Street, a 1912-built residential property that sustained prior fire damage. The scope of work includes complete removal and replacement of the roof structure (excluding interior ceiling joists), installation of new roofing materials, soffit and overhang work, electrical service reworking, drywall patching, flooring installation, insulation upgrades to R-30, bathroom and kitchen renovations, exterior door replacement, plumbing modifications, and final finishing work. The project is a single lump-sum bid item with all-inclusive pricing covering labor, materials, equipment, services, and accessories. A mandatory pre-bid meeting is scheduled for January 27, 2026, at 2:00 p.m. at the project site. Sealed bids must be received electronically by 2:00 p.m. Central Time on February 4, 2026, with public opening and reading via Zoom. The contract term is 45 calendar days from the Notice to Proceed, with liquidated damages of one percent of the total contract value assessed per day for work not substantially completed by day 46. Written questions must be submitted by January 28, 2026 (five business days prior to bid opening).
This project is funded through a Community Development Block Grant (CDBG) utilizing federal funds, requiring compliance with applicable federal clauses including Davis-Bacon Act prevailing wage requirements, debarment verification through SAM, anti-lobbying certifications, and domestic preference for U.S.-produced materials. Bidders must be properly licensed Tennessee contractors as required by law for projects exceeding $25,000, and must provide names and descriptions of any proposed subcontractors, all subject to City approval. The bid form requires a single total price for all work specified. The contract specifies a maximum of one progress payment up to 55 percent of the contract amount upon at least 60 percent project completion and City inspection approval, with final payment upon City completion inspection and homeowner acceptance. Pricing shall be effective for six months from the date of bid award. Lead-based paint hazards were identified in a November 17, 2025, risk assessment on the front columns and bent metal exterior trim; contractors must employ professionally trained, experienced, and licensed lead workers for any required abatement. All work must comply with the International Building Code 2018, locally adopted codes, and applicable federal compliance requirements. City Council approval is required before any contract becomes effective.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID
This Invitation to Bid (ITB) is subject to the instructions, conditions, specifications, addenda, and any other elements of this ITB, including those incorporated by reference.
DATE ISSUED: January 20, 2026
BID TITLE: ITB-20-2026 – 519 E. State Street Rehab- Roof Structure and Interior Repairs
CITY CONTACT
PERSON:
Cathy Smith, Purchasing Director
TELEPHONE NUMBER: 615-849-2629
EMAIL: purchasing@murfreesborotn.gov
All bid responses must be received and acknowledged by the Purchasing Department on or before the day and time listed below, at which time all bids will be publicly opened and read aloud via Zoom. A link will be provided to all those registered as following this bid. Only electronic bids will be accepted.
BID OPENING DATE: February 4, 2026
BID OPENING TIME: 2:00pm
1. Instructions and Conditions
1.1. Bid Submission to the City of Murfreesboro
The City is seeking Bids for “ITB-20-2026 – 519 E. State Street Rehab- Roof Structure and Interior Repairs for the Community Development Department as set forth in the specifications listed within Section 2 of this ITB. Electronic Bids will be received by the City of Murfreesboro until 2:00 p.m. CT on February 4, 2026, at which time the bids will be opened via Zoom. A Zoom link will be provided and listed on OpenGov, to all those following this solicitation. A pre-bid meeting will be held on January 27, 2026, at 2:00pm at 519 E. State Street, Murfreesboro.
1.2. Background
This project is a Community Development Block Grant (CDBG) project that utilizes federal funds. This project will be contracted using a CDBG Contract for Rehab. Due to this project utilizing federal funds, the applicable clauses located in Attachment A are hereby incorporated into this Invitation to Bid, as well as any contract or work order entered into between the City, the homeowner, and Contractor. A sample agreement is included in the Attachments section of the OpenGov post.
1.3. Deadline and Late Responses
No Bids received after Bid opening date and time will be accepted. The City will accept Bids submitted electronically via our procurement portal, OpenGov.
1.4. Organization and Completeness
It shall be the sole responsibility of the bidder to have completed the electronic form(s) and uploaded the required documents to the City before the Bid deadline. Partial or incomplete Bids may be rejected. All Bids should be typewritten or written in ink and clearly legible, and numbers must be expressed in both words and figures. Erasures, whiteouts, and other modifications should be initialed. Bidders are cautioned to verify their Bid prior to submission.
1.5. Preparation; Lump Sum
The ITB should be prepared simply and economically, providing a straightforward, concise description of bidder’s capabilities to satisfy the requirements of the ITB.
Emphasis should be on completeness and clarity of content. Bids will be considered on the basis of a lump-sum Bid for all work described in Section 2, below.
1.6. Subcontracting
If any part of the work is, or is to be, subcontracted, the bidder shall provide within the ITB response submittal a description of the subcontracting organization and the contractual arrangements made therewith. All subcontractors will be subject to approval by the City.
The successful bidder will also furnish, at the request of the City, the corporate or company name and the names of the officers or principals of said companies proposed as subcontractors by the bidder.
1.7. Signature
All Bids must be signed by a duly authorized officer of the company empowered with the legal right to bind the company. A typed name will not be acceptable without the person’s written signature as well. Signatures are required where indicated; failure to comply with this requirement shall be cause for rejection of Bid.
1.8. Completeness of Invitation to Bid (“ITB”).
These documents, and those listed on OpenGov, constitute the complete set of specification requirements and ITB. The bidder is responsible for ensuring that all pages and all addenda are received. The City advises all bidders to closely examine this ITB package and immediately direct any questions regarding the completeness of this ITB package and any addenda thereto to the City’s Contact Person via the Question/Answer tab on OpenGov. Bidders must register with OpenGov to ensure that all relevant written communications are available to them in the preparation of their proposal. Registration can be accomplished through the website:
https://procurement.opengov.com/portal/murfreesborotn
Bidders must satisfy themselves as to the accuracy of the estimated quantities in the Bid Schedule. After Bids have been submitted, the Bidder shall not assert that there was a misunderstanding concerning the quantities of work or the natures of the work to be done.
1.9. Bid Interpretation. Communication with the Purchasing Department.
Cathy Smith is the City’s contact for coordinating communications between the department and firms submitting bids. If additional information is required in order to make an interpretation of items in this ITB, written questions (including e-mails) will be accepted until five (5) business days prior (01/28/2026) to the bid opening date. All questions regarding the ITB should be addressed via the OpenGov Question/Answer Tab or to purchasing@murfreesborotn.gov.
The City specifically requests that no contact concerning this ITB be made with any other City personnel until the selection process has been completed. Failure to honor this requirement will be viewed negatively in the selection process and may result in the disqualification of a bid.
1.10. Discrepancies, Errors, and Omissions
Any discrepancies, errors, omissions, or ambiguities in this ITB, the specifications or addenda (if any) should be reported to the contact person for the City. If necessary, a written addendum will be issued on OpenGov, notification made to firms on record, and the addendum will be incorporated into the ITB and will become part of the contract. The City will NOT be responsible for any oral instructions, clarifications, or other communications and no such oral communication may be relied on by any bidder.
The City of Murfreesboro is not responsible for technical errors or omissions made by prospective bidders during the bid submission process that may result in a bid not https://procurement.opengov.com/portal/murfreesborotn being submitted, being submitted incompletely, or being submitted incorrectly. In the case of technical issues that are verified to be a City error, the Purchasing Department will take reasonable steps to resolve the issue so that the process remains fair to all bidders.
1.11. Errors
Certain mistakes may be corrected so long as the intended correct bid response is clearly evident. In the event of a disagreement between unit price and extended price, the unit price will control.
1.12. Further Negotiation
The City reserves the right to further negotiate, after the ITBs are opened, with any potential vendor if such is deemed necessary at the discretion of the City.
1.13. Bid Modification
Bids may be modified, withdrawn, and/or resubmitted in writing to the City prior to the deadline for bid submission via the procurement portal. After this deadline, no withdrawals or resubmissions may be made for any reason. Bidders must register with OpenGov to ensure that all relevant written communications are available to them in the preparation of their proposal. Registration can be accomplished through the website:
https://procurement.opengov.com/portal/murfreesborotn.
1.14. Tax Exempt
The City is exempt from federal and state taxes. Upon request, the City will provide a sales tax exemption certificate to the awarded firm. Contractors doing business with the City shall not be exempted from paying sales tax to their suppliers for materials to fulfill contractual obligations to the City, nor shall any vendor be authorized to use the City’s Tax Exemption Number in securing such materials.
1.15. Contract Term
If an award is made, any contract resulting from this ITB will be effective on the date the contract is signed. The contract shall not be effective until approved by the City Council and signed by all required parties. The term shall be 45 calendar days from the Notice to Proceed.
1.16. Liquidated Damages
If the work is not completed and the property made move-in ready in 45 calendar days from the Notice to Proceed, then the successful bidder will be assessed liquidated damages in an amount equal to ONE PERCENT (1%) of the total Contract value per day beginning on the 46th day and running until the work is completed and the property is move-in ready.
1.17. Pricing Effective for Six (6) Months
https://procurement.opengov.com/portal/murfreesborotn
The successful bidder shall provide in the bid price the cost for the goods or services rendered. Pricing shall be effective for six months from date of bid award. If, in the bidder’s opinion, additional equipment or services are necessary, this shall be included with explanation in the bid. It is requested that bidders raise any such questions in advance of submitting a bid to the City. To submit a bid implies consent to the terms set forth in this ITB.
1.18. Approval Required
No award or acquisition can be made until approved by the City Council. The City will not be obligated to bidders for equipment and/or services until the completion of a signed contract approved by authorized officials of the City. This solicitation in no manner obligates the City to the eventual rental, lease, or purchase of any equipment or services described, implied, or which may be proposed, until confirmed by a written contract.
Progress towards this end is solely at the discretion of the City and may be terminated at any time prior to the signing of a contract.
1.19. Terms and Conditions
The City reserves the right to reject any and all bids, to waive any irregularities in a bid, to make awards to more than one bidder, to accept any part or all of a bid, or to accept the bid (or bids) which, in the judgement of the governing body, is in the best interest of the City. The City also reserves the right to make revisions to any quantity shown on the bid form dependent upon bid prices and available funding. Prices bid on each item shall be firm regardless of the actual quantity of item(s) purchased.
1.20. Withdrawal of Bid
No bidder may withdraw its bid for a period of ninety (90) calendar days after the date and time set for the opening of the responses. In the event the City awards a contract to a bidder and during such ninety (90) day period determines that such bidder will be unable to properly perform the contract, the City reserves the right to terminate the contract and award the contract to the next best offer without being required to re-advertise the project.
1.21. Cost of Response
The City will not be liable for any costs incurred by the bidders in preparing a response to this solicitation. Bidders will submit responses at their own risk and expense. The City makes no guarantee that any equipment or services will be purchased as a result of the solicitation and reserves the right to reject any and all responses. All responses and their accompanying documentation will become the property of the City.
1.22. Contract
The successful bidder’s responses to this ITB shall be included as an addendum to the contract. Should any conflict or discrepancy arise between the ITB and the contract, the contract shall control. All bidders who are awarded contracts pursuant to this ITB agree to be bound by the terms and conditions set forth in the sample City Contract provided. If the bidder objects to any contract terms or proposes any additional terms such objections and terms must be set forth in the bid. Rejection of any proposed City Contract terms may be a basis for rejection of the bid.
1.23. Contract Termination
The City reserves the right to cancel the contract for the work without cost or penalty to the City if, in the City’s opinion, there is a failure at any time by the contractor to adequately perform the contract, or if there is any attempt to willfully impose upon the City a material or product or workmanship which is, in the opinion of the City, of an unacceptable quality. Cancellation of the contract shall not impair any rights or claim of the City to damages for the breach of any covenants of the contract by the contractor. The contract awarded may be terminated upon any of, but not limited to, the following occurrences:
1.23.1. Bankruptcy or insolvency of the bidder or one or more of the bidder’s principal owners;
1.23.2. Failure of the bidder to provide satisfactory services or failure to comply with the specifications;
1.23.3. Unauthorized substitution of products other than those identified in the specifications or specifically approved by the City as a substitute prior to award of the contract;
1.23.4. Unsatisfactory performance of products supplied by the bidder or services provided by the bidder;
1.23.5. Fraud; or
1.23.6. Any other breach of the terms of the ITB specifications or contract.
1.24. Contract Modification
The contract may be modified only by written amendment executed by all parties and their signatories hereto.
1.25. Replacement or Repair
No waiver of any provision of the contract shall affect the right of any party thereafter to enforce such provision or to exercise any right or remedy available to it in the event of any other default. The City, at its option and in lieu of immediate termination, may request the awarded bidder replace or repair any defective goods or correct performance by written notice to the contractor. In that event, the contractor shall take correct action within the amount of time specified by the City in the written notice. Exercise of this option shall not relieve the contractor of any liability to the City for damages for the breach of any covenants of the contract by the contractor.
1.26. Expense of Legal Action
Awarded bidder agrees that, in the event either party deems it necessary to take legal action to enforce any provision of the contract, and in the event the City prevails, awarded bidder shall pay all expenses of such action including the City’s attorney fees and costs at all stages of the legal action.
1.27. Governing Laws and Venue
The validity, construction, and effect of the contract, and any and all extensions and/or modifications thereof shall be governed by the laws of the State of Tennessee. Any action between the parties arising from this agreement shall be maintained in the courts of Rutherford County, Tennessee.
1.28. Severability
Should any provision of the contract be declared to be invalid by any court of competent jurisdiction, such provision shall be severed and shall not affect the validity of the remaining provisions of the contract.
1.29. Indemnification and Hold Harmless
1.29.1. Contractor must indemnify, defend, and hold harmless the City, its officers, agents and employees from any claims, penalties, damages, costs and attorney fees (“Expenses”) arising from injuries or damages resulting from, in part or in whole, the negligent or intentional acts or omissions of contractor, its officers, employees and/or agents, including its subcontractors or independent contractors, in connection with the performance of this Agreement, and, Expenses arising from any failure of Contractor, its officers, employees and/or agents, including its subcontractors or independent contractors, to observe applicable laws, including, but not limited to, labor laws and minimum wage laws.
1.29.2. Pursuant to Tennessee Attorney General Opinion 93-01, the City will not indemnify, defend or hold harmless in any fashion Contractor from any claims arising from any failure, regardless of any language in any attachment or other document that Contractor may provide.
1.30. Statutory Disqualification
By submitting a response, it is represented that neither Contractor nor any of its officers, directors, shareholders, member, or partners has been convicted or plead guilty or nolo contender to any violation of the Sherman Anti-Trust Act, mail fraud, or other state or federal criminal violation in connection with a contract let by the City of Murfreesboro or any political subdivision of the State of Tennessee.
1.31. Contractor’s Employment Practices
Bidder, after being first duly sworn, affirms that by its employment policy, standards and practices, it does not subscribe to any personnel policy which permits or allows for the promotion, demotion, employment, dismissal or laying off of any individual due to the individual’s race, creed, color, national origin, age or sex and it is not in violation of and will not violate any applicable laws concerning the employment of individuals with disabilities.
1.32. City’s Employment Practices
It is the policy of the City not to discriminate on the basis of age, race, sex, color, national origin, or disability in its hiring and employment practices, or in admission to, access to, or operation of its programs, services, and activities. With regard to all aspects of this contract, Bidder certifies and warrants it will comply with this policy.
Bidder must affirm that under its employment policies, standards and practices, it does not subscribe to any personnel policy which permits or allows for the promotion, demotion, employment, dismissal or laying off of any individual due to the individual’s race, creed, color, national origin, age or sex and that it is not in violation of and will not violate any applicable laws concerning the employment of individuals with disabilities.
1.33. Conflict of Interest
By submitting a response, it is represented that no officer, committee member, or director of the City or other persons whose duty is to vote for, let out, overlook, or in any manner supervise any work on any contract for the City has a “direct interest”, as defined by T.C.A. §12-4-101, in the bidder or in the work which is subject to this ITB.
1.34. Ethical Standards
Bidder understands that it shall be a breach of ethical standards for any person to offer, give or agree to give any employee or former employee, or for any employee or former employee to solicit, demand, accept or agree to accept from another person, a gratuity or an offer of employment in connection with any decision, approval, disapproval, recommendation, preparation of any part of a program requirement or a purchase request, influencing the content of any specification or procurement standard, rendering of advice, investigation, auditing or in any other advisory capacity in any proceeding or application, request for ruling, determination, claim or controversy or other particular matter, pertaining to any program requirement of a contract or subcontract or to any solicitation or bid therefore.
1.35. Breach of Ethical Standards
A breach of ethical standards could result in civil/or criminal sanctions and/or debarment or suspension from being a contractor or subcontractor under City contracts.
1.36. Payments
Payments under the contract shall be made upon submittal of an invoice after performance of the portion of the services which each payment represents. The final payment shall not be made until after the performance is complete.
1.37. Codes & Regulation
All services and work to be done must comply with city, county, state, and federal laws, rules, codes and regulations. All work shall be in accordance with the specifications as described in Section 2 and the International Building Code 2018. The contractor will obtain and pay for all permits, if any, necessary to complete the work.
1.38. Iran Divestment Act of Tennessee
By submission of this bid, each bidder and each person signing on behalf of any bidder certifies, and in the case of a joint bid each party thereto certifies as to its own organization, under penalty of perjury, that to the best of its knowledge and belief that each bidder is not on the list created pursuant to §12-12-106. Bids not conforming with this provision shall not be opened. Failure of any bidder to comply therewith shall void such bid and such bid shall not be considered.
1.39. Non-Boycott of Israel
By submission of this bid, each bidder and each person signing on behalf of any bidder certifies, and in the case of a joint bid each party thereto certifies as to its own organization, under penalty of perjury, that to the best of its knowledge and belief that each supplier is not boycotting Israel pursuant to T.C.A. § 12-4-119 and will not boycott Israel during the term of contract. This applies to contracts of $250,000 or more and to contractors with ten (10) or more employees.
1.40. Evaluation of Bid
1.40.1. The ability of the bidder to perform the contract or to provide the material for service required;
1.40.2. Whether the bidder can perform the contract and provide the material or service promptly or within the time specified without delay or interference;
1.40.3. The character, integrity, reputation, experience, and efficiency of the bidder;
1.40.4. The previous and existing compliance by the bidder with laws and ordinances relating to the contract or service;
1.40.5. The ability of the bidder to provide future maintenance and service for the use of the subject contract;
1.40.6. Terms and conditions stated in the bid;
1.40.7. Compliance with specifications or the ITB;
1.40.8. Utilization of the format set forth in this ITB for submittal of a bid; and,
1.40.9. Bidder’s past performance with the City.
1.41. Bidder’s Compliance
The City will evaluate proposals for compliance and completeness.
1.42. Contractor’s License
Pursuant to Tennessee Code Annotated Title 62, Chapter 6, Part 1, if a bid is $25,000 or above, bidder must be a licensed contractor as required by the Contractor’s Licensing Act of 1976, Public Chapter No. 822 of the General Assembly of the State of Tennessee as amended. In accordance with T.C.A. §62-6-119, Bidder shall place their bid in an envelope or provide within the electronic bid document: (1) the bidder’s name, license number, expiration date thereof, and license classification of the contractor applying to bid for the prime contract; (2) The name, license number, expiration date thereof, and license classification of the contractor applying to bid for the masonry contract (if applicable) where the total cost of the materials and labor for the masonry portion of the construction project exceeds one hundred thousand dollars ($100,000); (3) The name, license number, expiration date thereof, and license classification of the contractor applying to bid for the electrical, plumbing, heating, ventilation, or air conditioning contracts except when such contractor's portion of the construction project is less than twenty-five thousand dollars ($25,000); (4) For each vertical closed loop geothermal heating and cooling project, the company name, department of environment and conservation license number, classification (G, L or G,L) and the expiration date, except when the geothermal portion of the construction project is in an amount less than twenty-five thousand dollars ($25,000); (5) Prime contractor bidders who are to perform the masonry portion of the construction project which exceeds one hundred thousand dollars ($100,000), materials and labor, the electrical, plumbing, heating, ventilation or air conditioning or the geothermal heating and cooling must be so designated; and (6) Only one (1) contractor in each of the classifications listed above shall be written on the bid envelope or provided within the electronic bid document. Bids not conforming with this provision shall not be opened. Failure of any bidder to comply therewith shall void such bid and such bid shall not be considered.
2. Technical Specifications
2.1. Scope of Work
The house at 519 E. State Street was built in 1912, and at some time in the past had a fire that was contained within the attic. With the combination of fire damage and age of the home/date of original construction, the entire roof structure (except interior ceiling joists) must be removed and replaced. New soffit/overhang on all edges of roof must be installed.
The contractor shall take necessary precautions prior to allowing workers to demolish the roof. The purpose of the work is to provide a complete, weathertight roof structure and miscellaneous work on the interior. It is the intent to provide the homeowner with a complete and finished project. The scope shall include the following:
2.1.1. Repairs of the roof structure will include removal of all metal roofing, rafters, gable end framing, porch rack beams, rafters/ceiling joists above porch. The roof structure over the laundry room consists of only rafters, which must be removed.
The contractor will be responsible for protecting the interior from weather-related damage when replacing the roof structure and shingles. The contractor shall use tarps and other means and methods to protect the interior of the home. The Contractor is responsible for protecting electrical wiring in attic from damage.
2.1.2. Rework existing electrical service to extend straight up vertically in lieu of running in the soffit. Purchase and install new panel cover and label all circuits. Replace wiring in panel that has twist lock connectors inside panel. See Section 3.14 for additional work items
2.1.3. Provide additional bracing where existing studs extend into attic. See Section “A” and Roof Framing Plan.
2.1.4. Install new roof structure, gable ends, overhang/soffit and porch framing and roof deck as shown on Attachment B- Roof Framing Plan, Section “A” & “B”. Roof slopes shall match existing slopes.
2.1.5. Install synthetic felt, asphalt shingles, ridge vent, metal fascia, break metals, gutters and downspouts.
2.1.6. Install new vinyl siding over gable ends and front porch gable. Install perforated soffit all around including front porch. Install flashing where gable wall meets the brick and other locations as needed to make exterior water tight.
2.1.7. Reinsulate attic to an R-30 blown-in type insulation.
2.1.8. Replace the existing subfloor in the bathroom (except under tub) and entry hallway.
2.1.9. Remove the existing flooring in the living room, bathroom, laundry room and front entry. The flooring may have several layers of sub floor and finish flooring. Remove all down to original subfloor prior to installation of new flooring.
2.1.10. Install new vanity, sink faucet, water supply lines, stop valves and trap in bathroom.
2.1.11. Install new laminate flooring in the bathroom, hallway, HVAC closet, kitchen, laundry room, living room, and front entry. Install new shoe mold; prep and paint base and new shoe mold.
2.1.12. Patch holes in sheetrock walls in the two bedrooms, front entry, and hallway.
Patch ceiling in closet off hallway.
2.1.13. Replace all duct work and install new 6” duct with wall register into laundry room.
A framed and finished fur-down will be required in the kitchen to hide the duct.
Have the existing unit serviced and cleaned.
2.1.14. Install new batt insulation in rafters above laundry room and install ½” sheetrock ceiling. Provide baffles to aid in ventilation. Install trim between sheetrock ceiling and wood paneling on walls. Paint new sheetrock ceiling.
2.1.15. Install 2 x 4 framed half wall in laundry room behind washer/dryer. Relocate laundry tray and plumb lines into new half wall to protect from freezing. Insulate wall with R-13 batt insulation. Wall shall be finished with ½” sheetrock, finished, and painted. Install and paint base molding.
2.1.16. Remove existing countertops in kitchen and replace them with new laminate tops.
Provide integral backsplash, rolled front edge and precut end splashes. Install new kitchen sink, faucet, supply lines, stops and trap. Install new 2 x 4 fluorescent light fixture.
2.1.17. Patch new sheetrock in kitchen around wall cabinets. This will require removal of the wall cabinets.
2.1.18. Paint kitchen, hallway, entry, bathroom and living room walls and ceilings, trim, and doors.
2.1.19. Replace front and rear exterior doors, frames, and hardware with new insulated metal door/frame and hardware (lockset and deadbolt). Paint door and trim.
2.1.20. Add additional insulation in the attic to obtain R-30. Install R-19 batts between rafters in laundry room.
2.1.21. Install interconnected smoke detectors with battery back-up.
2.2. Completion
The owner will move out for 45 calendar days. In addition, the owner will remove pictures, items in upper kitchen cabinets and other loose items on countertops and tables. The contractor will be required to relocate furniture and appliances as required to complete the work. All work must be substantially complete so that the owner can occupy the house on the 46th day after Notice to Proceed is issued.
3. Materials and Execution of Work
3.1. All materials and installation of materials shall be in accordance with locally adopted codes. Materials not specifically specified shall comply with local codes.
3.2. Lumber
3.2.1. Rafters #2 SPF (Spruce, Pine or Fur) 2 x 6
3.2.2. Decking & Sheathing ½” OSB
3.2.3. Ridge & Fascia Board #2 SPF
3.2.4. Miscellaneous framing and blocking #3 or better SPF
3.2.5. Gable Framing #2 or better SPF 2 x 4
3.2.6. 2 x 2 attached to bottom of laundry room rafters #3 SPF or better
3.2.7. Subfloor shall be 5/8” tongue and groove exterior rated plywood or OSB
3.2.8. Installation of lumber shall be straight, plumb, and attached with appropriate fasteners. Walls shall be plumb and straight.
3.3. Roof Shingles
3.3.1. Shingles shall be Architectural Style shingles with 30-year warranty in accordance with the shingle manufacturer’s instructions. Approved manufacturers are:
• GAF Timberline Architectural Shingle,
• Owens Corning Duration Architectural Singles,
• CertainTeed Landmark Architectural Style Shingles.
3.3.2. Furnish and install synthetic felt over entire roof.
3.3.3. Other manufacturers can be considered if submitted to the City for approval prior to ordering or starting the work.
3.3.4. Furnish and install synthetic felt over entire roof.
3.3.5. Install felt and shingles in accordance with manufacturers’ requirements and locally adopted codes.
3.4. Ridge Vents
3.4.1. Install ridge vents on all ridges. Cut roof shall provide a minimum of 18” net free area per lineal foot.
3.4.2. Patch holes in roof deck with OSB and 2x framing where existing roof vents were removed.
3.4.3. Install ridge vent to roof deck with appropriate fasteners.
3.5. Aluminum Gutters and Downspouts
3.5.1. Remove gutters and downspouts and install new 5” continuous and seamless gutters. Downspouts shall extend to within 6” of the ground. Manufacturer’s standard color will be used. Minimum 0.027 aluminum must be used. Install metal type screen guards, secure to gutters.
3.6. Gypsum Board Ceiling and Walls
3.6.1. Shall be ½” gypsum board. Tape and mud all joints. Sand to a smooth and even finish. Install gypsum board with appropriate fasteners and required by manufacturer.
3.6.2. Patch the following holes as listed below:
• Front Bedroom: Patch 32” x 32” hole in wall that abuts ceiling and wall corner.
• Front Entry: Patch 32” x 32” hole in wall.
• Rear Hallway: Patch 48” x 24” hole in wall.
• Closet off rear hallway: Patch 16” x 16” hole in ceiling.
• Rear Bedroom: Patch two 32” x 32” holes, repair all corner drywall crack both vertical and horizontal. Corner shall be made smooth, filled with drywall mud and sanded. In some cases, existing tape will need to be removed and replaced.
3.7. Insulation
3.7.1. Blown-in type insulation to ab R-30. Batt insulation shall be R-30. Roof above laundry room shall be insulated to the highest R Value possible with the installation of baffles with baffles above laundry room. Install 2 x 2’s on bottom of laundry room rafters to provide additional room for insulation/baffles. Install insulation using a friction fit.
3.8. Kitchen Countertop
3.8.1. Install new plastic laminate countertop with integral back splash and rolled front edge. Furnish and install matching end piece back splashes. Caulk backsplash to wall intersection.
3.9. Bathroom Vanity
3.9.1. Furnish and install new 30” wide bathroom vanity with cultured marble top with sink and backsplash. Provide escutcheons plates at plumbing penetrations.
Secure vanity to the wall and caulk vanity/wall & vanity top/wall intersections.
3.10. Painting
3.10.1. Paint all new and/or patched sheetrock. New drywall shall be primed before finish coat is installed. Existing holes and blemishes shall be patched in all sheetrock prior to painting.
3.10.2. Paint two new exterior doors and frame with exterior grade paint.
3.10.3. All surfaces to be painted will be prepped before painting and receive a minimum two coats. The finished product will be free from drips and runs. Protect all surfaces that are not to be painted from drips and spills.
3.10.4. Paint all drywall patches to match existing. Paint all walls in rear bedroom.
3.10.5. Colors to be selected by the owner.
3.11. Flooring
3.11.1. New laminate flooring shall 10 mm thick laminate flooring plus attached pad.
Approved manufacturers are:
• Pergo Elements original
• Mohawk Rev Wood Plus
• Stainmaster Laminate Flooring
3.11.2. Other manufacturers will be considered after submission of technical data and review by the City. The Owner shall select flooring pattern and color from manufacturer’s standard options.
3.11.3. Install flooring as required by manufacturers.
3.12. New Exterior Doors
3.12.1. The new front exterior door shall be insulated with a metal door with half glass, and the new rear exterior door shall be insulated with metal with no glass. Install new doorknob and deadbolt and new door trim. Front and rear door locks shall be keyed the same.
3.12.2. Install doors plumb and weather tight. Caulk threshold prior to installation; fill gaps with caulk, insulation, or other approved material.
3.13. Plumbing
3.13.1. Install new kitchen sink with new stop valves, supply lines, and trap. Install new bathroom faucet with new stops, supply lines and trap. Rework laundry tray plumbing to be relocated out of exterior wall into new half wall to prevent freezing.
3.14. Electrical Work
3.14.1. All electric work shall be in accordance with locally adopted NEC code and MTE requirements.
3.14.2. Electrician licensed by the City of Murfreesboro must perform all electrical work.
3.14.3. Rework existing electrical service to extend straight up in lieu of running in soffit.
Coordinate this work with MTE prior to beginning work.
3.14.4. Install interconnected hard wired smoke detectors with battery back up in each bedroom, front entry and rear hallway.
3.14.5. Install new 2 x 4 fluorescent light fixture in kitchen.
3.14.6. Replace the existing 4 exterior security lights. Lights shall be motion activated.
3.14.7. Install new electrical panel cover over panel in rear bedroom.
3.14.8. Replace wiring in electrical panel that has twist lock connectors.
3.15. Miscellaneous Items
3.15.1. The contractor shall provide all materials, equipment, tools, fasteners, and labor for a complete and finished project. All debris generated from this work shall be removed from the property and disposed of legally. Any damage to the existing structure caused by the Contractor shall be repaired at the Contractor’s expense.
Items to remain such as casework, cabinets, fixtures, and finishes shall be protected from damage. The Contractor shall coordinate all work, especially removal and replacement of roof structure to prevent weather-related damage to items within the house. The structure shall be secured prior to completing the day’s work. Contractor to provide onsite toilet facilities.
3.15.2. The Contractor shall be responsible for obtaining all permits and inspections.
3.15.3. Contractor shall provide a final cleaning of the house prior to the homeowner moving back into the house.
3.15.4. Contractor must provide dust barrier walls especially at opening to reduce the spread of dust.
Attachments- Attachment A- Federal Clauses Attachment B- Roof Framing Plan Attachment C- Lead Based and Risk Assessment Report for 519 E. State Street
PURCHASING
DEPARTMENT BID FORM
NAME OF BID: ITB-20-2026
519 E. State Street Rehab- Roof Structure and Interior Repairs
Name of Bidder:
Date:
INSTRUCTIONS:
All prices must include all costs. Costs included in the bid prices shall include services rendered and parts, labor, accessories, freight, and any other standard equipment necessary to provide this service. The City is not subject to sales tax. PROVIDE WITH YOUR BID RESPONSE THE NAMES OF ANY SUBCONTRACTORS THAT WILL BE USED TO PERFORM
SERVICES FOR THIS BID.
ITEM
NO.
QUANTITY
DESCRIPTION
TOTAL PRICE
ITB-20-2026- 519 E. State Street Rehab- Roof Structure and Interior Repairs per Specifications
Total Project
All bid responses must be received and acknowledged by the Purchasing Department on or before the day and time listed below, at which time all bids will be publicly opened and read aloud via Zoom. A link will be provided to all those registered as fol...
File details come from the government source that posted it. Updated .