ITB_04-25_Bid_Tab.pdf

PDF 25 KB Posted

Attached to
ITB 04-25 Lift Station 14 Electric Improvements
Solicitation number
ITB 04-25
Issued by
Volusia County, Florida

About this file

The document is a bid tabulation (ITB 04-25) for Lift Station 14 Electric Improvements issued by New Smyrna Beach Utilities in Volusia County, Florida. The project involves furnishing and installing electrical, instrumentation, and control panels and systems, with comprehensive site improvements including general requirements, mobilization, demolition, surveying, and final restoration. The bid includes a project allowance and bypass pumping, with four contractors submitting proposals: Accurate Power & Technology, C&R Technical LLC, Clearwater Solutions, and Powerserve Tech. The project has a proposed completion timeline of 210 consecutive calendar days, with sealed proposals originally due electronically via VendorLink.

The bid prices range from $385,722.94 to $495,150.00, with a consistent $20,000 project allowance across all bidders. The lowest bid was submitted by Accurate Power & Technology at $385,722.94, while the highest was from C&R Technical LLC at $495,150.00. The scope includes replacing existing electrical infrastructure, with specific line items for electrical panel installation, site improvements, and bypass pumping. The project involves upgrading a lift station with KSB model KRTK200-400/646X pumps, and includes potential liquidated damages of $1,000 per consecutive calendar day for incomplete work, with additional penalties for wastewater overflows.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Accurate Power & Technology C&R Technical LLC Clearwater Solutions Powerserve Tech

Description QTY UOM Unit Price Unit Price Unit Price Unit Price Furnish and Install Electrical, Instrumentation and Control Panels, and Systems 1 LS $247,272.94 $334,750.00 $308,794.22 $340,000.00

Site Improvements (to also include General Requirements, Mobilization, Demo, Survey, As- Built and Final Restoration, etc.) 1 LS $82,450.00 $98,150.00 $44,731.60 $45,000.00

Project Allowance 1 LS $20,000.00 $20,000.00 $20,000.00 $20,000.00

Bypass Pumping 1 LS $36,000.00 $42,250.00 18244.77 $50,000.00

$385,722.94 $495,150.00 $391,770.59 $455,000.00

ITB 04-25 Lift Station 14 Electric Improvements

TOTAL BID PRICE

Sheet1

File details come from the government source that posted it. Updated .