ITB_04-25_Bid_Tab.pdf
PDF 25 KB Posted
- Attached to
- ITB 04-25 Lift Station 14 Electric Improvements
- Solicitation number
- ITB 04-25
- Issued by
- Volusia County, Florida
About this file
The document is a bid tabulation (ITB 04-25) for Lift Station 14 Electric Improvements issued by New Smyrna Beach Utilities in Volusia County, Florida. The project involves furnishing and installing electrical, instrumentation, and control panels and systems, with comprehensive site improvements including general requirements, mobilization, demolition, surveying, and final restoration. The bid includes a project allowance and bypass pumping, with four contractors submitting proposals: Accurate Power & Technology, C&R Technical LLC, Clearwater Solutions, and Powerserve Tech. The project has a proposed completion timeline of 210 consecutive calendar days, with sealed proposals originally due electronically via VendorLink.
The bid prices range from $385,722.94 to $495,150.00, with a consistent $20,000 project allowance across all bidders. The lowest bid was submitted by Accurate Power & Technology at $385,722.94, while the highest was from C&R Technical LLC at $495,150.00. The scope includes replacing existing electrical infrastructure, with specific line items for electrical panel installation, site improvements, and bypass pumping. The project involves upgrading a lift station with KSB model KRTK200-400/646X pumps, and includes potential liquidated damages of $1,000 per consecutive calendar day for incomplete work, with additional penalties for wastewater overflows.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Accurate Power & Technology C&R Technical LLC Clearwater Solutions Powerserve Tech
Description QTY UOM Unit Price Unit Price Unit Price Unit Price Furnish and Install Electrical, Instrumentation and Control Panels, and Systems 1 LS $247,272.94 $334,750.00 $308,794.22 $340,000.00
Site Improvements (to also include General Requirements, Mobilization, Demo, Survey, As- Built and Final Restoration, etc.) 1 LS $82,450.00 $98,150.00 $44,731.60 $45,000.00
Project Allowance 1 LS $20,000.00 $20,000.00 $20,000.00 $20,000.00
Bypass Pumping 1 LS $36,000.00 $42,250.00 18244.77 $50,000.00
$385,722.94 $495,150.00 $391,770.59 $455,000.00
ITB 04-25 Lift Station 14 Electric Improvements
TOTAL BID PRICE
Sheet1
File details come from the government source that posted it. Updated .